QUEENS BENCH DIVISION
BIRMINGHAM DISTRICT REGISTRY
TECHNOLOGY AND CONSTRUCTION COURT
Birmingham Civil Justice Centre 33 Bull Street Birmingham B4 6DS | ||
B e f o r e :
____________________
COWLIN CONSTRUCTION LIMITED | Claimant | |
- and - | ||
CFW ARCHITECTS (a firm) | Defendant |
____________________
Ms Nerys Jefford of Counsel (instructed by Hugh James Jones Simey) for the Defendant
____________________
Crown Copyright ©
Background
"Further to our telephone call yesterday I am pleased and relieved that we have reached agreement regarding our appointment details. I will prepare the appointment documents and forward them to you for signature. I confirm the following basic points agreed:Lump sum fee of £277,000.
CFW to propose the payment instalment.
Form of appointment to be SFA/99.
Appointment to include up to 40 site visits.
The instalment breakdown will be subject to the programme of design information, the details of which will no doubt become clearer at the meeting on Tuesday. It is therefore probable that I won't be able to issue the appointment document to you until week commencing 19 June 2000 as I am on leave next week."
"Further to my fax to Ian Natt of 8 June, I have now liaised with the team in our office who will be producing the drawing information to suit your building programme, and have prepared a draft Architect's Appointment document which I will forward to you for signature. However we are still to agree the instalment schedule for our stage payments which will be recorded in the Appointment document. I therefore propose the following …"
The document then lists 24 months, beginning June 2000, with staged payment amounts against each month.
"I confirm that we will discuss/agree the milestone payments at our meeting tomorrow, however I propose the following which perhaps you could give some thought to prior to tomorrow: …."
Insert the date of the building contract on page A
Execute as a deed on page G
Initial the foot of each page adjacent to my initial."
"copies of our proposed contract for amendment, particularly with regard to the pages in which a 'yellow' sticker is attached. We would also suggest that the document be amended to incorporate a clause to the effect that "where this document contradicts the requirements of the main contract the conditions of the main contract are to apply."
"Re CFW SFA/99 appointment document. We are trying to complete the above document which was returned by Mr Natt on 7 August 2000. Mr Natt indicated some changes required to the schedule of stage payments but now that our payment No.3 has slipped by at least three weeks, further changes will be required to complete this section of the document. Have you prepared a revised milestone payment schedule, and if so how does this affect our schedule? Your response will enable us to revise our cash flow forecast for the forthcoming months…."
"Further to your letter dated 7 August 2000, I am enclosing two copies of our revised SFA/99. We have revised the payment schedule and programme broadly in line with the actual progress that has been made to date and to accord with our reported completion dates sent by fax today … The schedule also now includes reference to the requirement to fully comply with building regulations and the schedule has been initialled. I look forward to receiving one completed copy of the signed Form of Agreement in due course."
"We consider the [unpaid] invoices to be outstanding to the point that you are at default under Clause 5.10 under SFA/99.
We also draw to your attention that we have received no written notice under Clause 5.12 of the Agreement of your reasons for withholding payment…
In accordance with Clause 8.7 copies of … will be supplied to Cowlin in due course…"
"There is currently a dispute between our clients regarding two matters, namely (i) payment of [identified] invoices and (ii) the present contractual position between our clients. The RIBA currently prescribes as the standard form of agreement for the appointment of an Architect in a Design and Build situation the use of SFA/99 coupled with the amendment applicable to a Design and Build contract namely amendment DB2/99. [I refer to the latter as DB2/99.] This is precisely the form of agreement which has been tendered to your clients and accepted in writing by Ian Natt in a fax of 9 June 2000. The form of contract submitted for execution by your clients has not been withdrawn by our clients. The document was handed back to them some six weeks ago when our clients indicated that it was scarcely possible to require the redrafting of a contract both agreed in writing by your clients and acted upon by both sides for a period of upwards of 12 months. It is not in dispute that your clients have not signed the contractual documents handed to them. Nonetheless they are bound by SFA/99 / DB2/99 which they have accepted in writing albeit not by signing the actual contractual document. Our client's authorship of the fax of 20 June 2000 is not in dispute nor is the applicability of the milestones there enlisted [sic]. Our clients are puzzled that you now raise matters alleged to be outstanding in relation to the payments due at milestones 3, 4 and 5….
Our clients consider that your clients have repudiated the contract… Your clients have put forward a claim for set-off which is firstly excluded by the terms of the contract…"
Hugh James go on to say that CFW, subject to some provisos, are prepared to submit the existing dispute or differences to the decision of an agreed adjudicator.
"4.1 That the contract entered into between Cowlin and CFW was the RIBA form4.2 That Cowlin had not by their actions or omissions or in any way repudiated the contract between Cowlin and CFW
4.3 That by accepting the alleged repudiation by Cowlin, CFW had wrongfully repudiated the contract between Cowlin and CFW
4.4 That CFW be liable for the fees and expenses of the adjudicator
4.5 That CFW meet the costs of Cowlin in this adjudication."
On 11 September 2001, Hugh James sent Lee Crowder a document which all have described as a Counter Notice to Cowlin's notice to refer the dispute to adjudication. In the Counter Notice, CFW admit the matters contained in Cowlin's introduction to the notice to refer and they confirm that CFW's contentions as to the nature of the contract are as stated in sub-paragraph 2.2 of the notice to refer. CFW state that in the adjudication they "seek a decision from the adjudicator as follows:
4.1 That the contract entered into between Cowlin and CFW was SFA/99 together with DB2/99.4.2 That Cowlin have repudiated the contract between Cowlin and CFW by failing to make payment of the sum of £30,000 due from Cowlin…
4.3 That CFW have fairly and reasonably repudiated the contract between Cowlin and them on the following grounds.
4.4 That Cowlin forthwith pay the sum of £30,000 plus VAT…
4.5 (not used)
4.6 That Cowlin be liable for the fees and expenses of the adjudicator.
4.7 That Cowlin pay the costs of CFW of the adjudication."
"We note that you are seeking to introduce an additional point to be decided by the adjudicator under clause 4.4 of your Counter Notice. This additional point is clearly not included in our client's notice of adjudication and is therefore outside the ambit of the current adjudication. Accordingly any adjudicator which is appointed in accordance with the RIBA appointment procedure will be directed to ignore clause 4.4 of your Counter Notice for the purpose of this adjudication. Should your clients wish to raise this additional point, they will need to initiate their own separate adjudication proceedings."
"We entirely agree with you that the adjudicator has misunderstood the nature of the contract under which he has been appointed and we entirely concur with the remarks in the third paragraph of your letter of 19 September. However there is a difficulty that arises upon which you have not touched in your correspondence. Cowlin seek a decision in the nature of a declaration that the binding contract between Cowlin and CFW was the RIBA form … whereas our clients contend for SFA/99 with DB2/99. We do not believe that it is within the powers of an adjudicator to make a declaration as to which is the form of contract under which his appointment has purportedly been made. An adjudicator is a creature of the contract under which he is appointed. If it is not clear whether he has been appointed under contract A or contract B then it is doubtful whether he has been appointed validly at all and we cannot accept that he has the power to decide that issue… Consequently we cannot accept that the adjudicator has the power to decide which of the forms of contract contended for is that applicable to the relationship between Cowlin and CFW. Since a decision as to that seems to be a necessary pre-condition to deciding the other matters contended for we are dubious as to whether this adjudication can proceed at all as at presently constituted. Subject to that issue…" Hugh James go on to deal with procedural matters.
"We are not satisfied that you have jurisdiction to decide the issue raised by Cowlin in 4.1 of their notice to refer which would require you to decide that the contract entered into between the parties was the RIBA form rather than SFA/99 together with DB2/99."
"Irrespective of its status, it seeks a decision from the adjudicator over the nature and form of the contract between the parties. At its simplest level, therefore, it can be stated that both parties are interested in having resolved the issue of the nature and form of the contract…. I invite the parties to agree that I have jurisdiction to decide the nature and form of the contract, such decision to have the usual force and effect accorded to an adjudicator's decision. If the parties cannot agree upon this, then my initial view is that the adjudicator must form a view on whether there is, or is not, a contract in the form contended for by the referring party…. I direct that the parties advise me, unequivocally, whether they agree to the Counter Notice … proceeding as a conjoined matter for my decision…If agreement is reached then that agreement, together with an agreed timetable for dealing with the Counter Notice, is to be sent to me… If the parties do not agree, they should advise me in writing of their respective positions…"
"We confirm that there is no consensus to the joinder of paragraph 4.4 of the Counter Notice with the current adjudication. Accordingly, we confirm that you are to take into account the Counter Notice but not Clause 4.4 thereof."
"From the attitude of [Cowlin's] solicitors it would appear that [Cowlin] is not prepared to allow [CFW's] fee dispute (although it is inextricably linked into the claim) to be dealt with in a single consolidated adjudication procedure. This means that we have now been instructed by CFW to seek an institutional appointment of an adjudicator from the RIBA…"
"It is my view that I cannot adjudicate over any aspect of the Counter Notice without the agreement of the parties or unless I am properly appointed by the RIBA. For the avoidance of doubt, Lee Crowder's fax of 27 September does not, in my view, unequivocally record agreement to the Counter Notice being conjoined. Unless the RIBA appoints me to deal with the Counter Notice, I will not deal with it."
"For the avoidance of doubt, therefore, I confirm my view that the parties have agreed that I may decide in this adjudication either in favour of the decisions sought at clause 4 of the notice of adjudication or in accordance with the decisions sought in the Counter Notice at clause 4 (but not resolving the issue at 4.4). It is understood that in deciding either way or the other in accordance with the notice of adjudication or the Counter Notice, I will resolve the decisions sought in each notice."
"I take the view that the issues referred to me are those set out in the notice of adjudication and Counter Notice (save for 4.4 of the Counter Notice) and indeed that the parties have agreed that this is the case."
Cost of completing drawings and dealing with health and safety issues:£107,453.70An additional 14 weeks of preliminary costs as a result of delay: £97,720.06
Additional costs of winter working resulting from delay: £174,797.20
Additional concrete and hard core used as a result of the delayed start and winter working conditions: £106,227.68
Abortive costs due to incorrect scheduling and detailing: £34,862.88
Inflationary features: £130,460.15
Finance charges: £20,873.62
This totalled £672,395.29 excluding liquidated damages which were to be advised separately.
"You have not suggested a date for such a meeting but have indicated that you could need a week or ten days, or possibly several weeks, to consider the issues. Such a vague proposition is quite unacceptable to us. Some comments made by you concerning CFW's attitude suggest that CFW are dismissive of our claim and are not likely to make a serious offer to settle. Notwithstanding this, Cowlin are prepared to give you until 10.00 am on Friday, May 17 2002 to make a satisfactory offer in settlement of our claim before taking immediate and substantive action. Cowlin have already been fully reasonable in giving CFW (or if they so decided their insurers) every opportunity to meet with us over the last two months and give you this final opportunity."
"I refer to our recent meeting in connection with this matter and confirm, that in view of the various complexities of your allegations, it has been necessary for us to obtain and review all the files held by CFW, following our meeting with them, which unfortunately is taking longer than anticipated. Please be assured it is our intention to return to you as soon as possible and I would ask you to bear with us for the time being."
Mr Harris' jurisdiction
Was there a construction contract between the parties?
As at 18 May 2002, was there a dispute between the parties?
"Was there any dispute or difference arising between the contractors and the engineer? It is accepted that, in order that a dispute or difference can arise on this contract, there must in the first place be a claim by the contractor. Until that claim is rejected, you cannot say that there is a dispute or difference. There must be both a claim and a rejection of it in order to constitute a dispute or difference."
"A dispute can only arise once the subject-matter of the claim, issue or other matter has been brought to the attention of the opposing party and that party has had an opportunity of considering and admitting, modifying or rejecting the claim or assertion."
"A dispute is not lightly to be inferred. Nevertheless, there must come a time when a dispute will arise, usually, where a claim or assertion is rejected in clear language without the possibility of further discussion, and such a rejection might conceivably be by way of an obvious and outright refusal to consider a particular claim at all."
"for there to be a dispute for the purposes of exercising the statutory right of adjudication, it must be clear that a point has emerged from the process of discussion or negotiation has ended and that there is something which needs to be decided."
"In my judgment a dispute is something different from a claim… While a dispute can be about a claim, there is more to a dispute than simply a claim which has not been accepted…. For there to be a dispute, there must have been an opportunity for the protagonists each to consider the position adopted by the other and to formulate arguments of a reasoned kind… The construction of the word "dispute" for the purposes of the 1996 Act … is not simply a matter of semantics, but a question of practical policy… The whole concept underlying adjudication is that the parties to an adjudication should first themselves have attempted to resolve their differences by open exchange of views and, if they are unable to, they should submit to an independent third party for decision the facts and arguments they have previously rehearsed among themselves. If adjudication does not work in that way, there is a risk of premature and unnecessary adjudications in cases in which, if only one party had had a proper opportunity to consider the arguments of the other, accommodation might have been possible."
VAT
Conclusion