QUEENS BENCH DIVISION
TECHNOLOGY & CONSTRUCTION COURT
133-137 Fetter Lane London EC4A 1HD |
||
B e f o r e :
____________________
JOHNSON CONTROL SYSTEMS LIMITED |
Claimant |
|
- and - |
||
TECHNI-TRACK EUROPA LIMITED (In administrative receivership) |
Defendant |
____________________
Mr Graham Eklund QC (instructed by Kennedys) for the Defendant
____________________
Crown Copyright ©
His Honour Judge David Wilcox:
PART I – THE COUNTERCLAIMS
"He would investigate a proposed contract, produce a price based on the specification. On large contracts I would then go through the final figures carefully with him. I was ultimately responsible for the price at which he tendered for a contract.
All project costings were entered using a computer software package called "Pegasus". Over the years the company accounts department had imputted information into this programme relating to materials, labour etc., This information was then correlated within the programme providing feed-back on the project costs. I treated this information as a safety net in that it reassured me that the price we were suggesting for a contract was realistic based on previous project costs. I found the information to be accurate in general to within 5-10% of job pricing. This programme was used when pricing the contracts with Johnson.
In 1992 the company had tendered for work on four buildings in the Glaxo project at Stevenage. We had been successful in three of those tenders, the Chemistry Building (the first tender we won, and the first job we started working on), the Biology Building and C.R.S.F."
The Contractual Regime
"Any notice, approval, agreement, request, or other communication required or permitted pursuant to the Sub-contract shall be in writing and sequentially serialised and shall be deemed property given when delivered by hand or, if mailed, upon the earlier of actual receipt or three (3) days after being deposited in the mail as registered post or recorded delivery, first class postage pre-paid except during the subsistence of an industrial dispute effecting the postal service in which case service of notices by post shall not be as effective as follows…..".
"Sub-contract price – the total awarded value of the sub-contract as indicated in the sub-contract agreement plus any increase and/or decrease authorised by Change Order.
"Clause 4 – Sub-Contract Period goes on to state:
If during the course of the Sub-contract Work the Sub-contractor shall consider that by reason of …. a delay caused by the Contractor, or the Employer or anyone for whom they are responsible but not by reason of default by the Sub-Contractor, his Sub-sub-contractors or Suppliers, it is unable to complete any Section or Sections according to the Schedule subject to Clause 4.1 hereof, the Sub-contractor shall forthwith give written notice to the Contractor of the cause of delay and the effect such is likely to have upon the completion of any such Section in accordance with the Schedule.
Failure of the Sub-contractor to provide such written notice may be deemed by the Contractor to be a waiver by the Sub-contractor to its entitlement to an extension of time. The Sub-contractor shall use his best endeavours to provide the Contractor within the shortest practicable time, an estimate of the probable effect on the progress of the Sub-contract Work. If the Contractor agrees that an extension of time is valid under certain circumstances and that the Sub-contractor has used his best endeavours to avoid or minimise the effect of such, it shall issue an extension of time in respect of the relevant Section. Where in its opinion the delay is likely to effect the completion of the said Section adversely and is beyond the reasonable control of the Sub-contractors and/or shall issue variations to the Schedule if in its opinion the delay is likely to effect the progress of any Section of the Sub-contract Works in accordance with the Schedule adversely and is beyond the reasonable control of the Sub-contractor.
Without prejudice to the generality of the foregoing, the Contractor may at any time whatsoever, make such extension of time in respect of the relevant Section or such amendment to the Schedule as in all the circumstances may be reasonable, including having regard to any act, omission, default and/or any other breach on this Agreement by the Contractor or the Employer, or anyone for whom they are responsible".
The Contract Works
Secondly, there were Laboratory Pressurisation Panels (LPP's). These were small panels located outside the laboratories, which provided the controls for each laboratory and were intelligent panels which did not distribute power. They were used and supplied by Dudley Bower on a site-wide basis, including the Biology Building and the CRSF Building. TTEL's obligation was to wire from the field equipment by way of example, from the VAV box controllers and sensors to the LPP panel.
Thirdly the Room Control Panels (RCP). These were the same as LPP's except that they were used for non-laboratory rooms. In the Chemistry Building there were a number of non-laboratory rooms on the first floor. These panels were supplied by Dudley Bower to the Chemistry Building and TTEL's obligation under the contract was to wire the field equipment to the RCP panels.
"5. Further Requirements:-
a) the installation of the BMS will be of a non-continuous nature requiring continuation of activities and/or areas of the works in sequence, to be agreed with the Contractor, to facilitate installation of associated components by others.
………..
The sub-Contractor shall allow for all costs associated with the requirements within the "lump sum tender price". The contract came to an end on 9th February 1994 and circumstances are set out below.
Unpaid Valuations to 18th January 1994
Unpaid Work after 18th January 1994
THE LOSS AND EXPENSE CLAIM
"The Contractor may at any time, but not unreasonably, issue to the Sub-contractor a request to accelerate the carrying out of or to alter the sequence or timing of the Sub-contract Work or any Section or Sections thereof (an 'acceleration request').
Within ten(10) Working Days of the date of the Acceleration Request (or within such other period as may be agreed between the Contract and the Sub-contractor, the Sub-contractor shall provide the Contractor with:-
"The Sub-contractor's explanation as to why it is unable to apply with the proposed revised programme date;
or
In addition to the details under Clause 7.1, full details of measures the Sub-contractor deems necessary to comply with the Acceleration Request.
The Sub-contractor shall not take any further action until the Contractor issues an instruction requiring a Change.
Any Change Order issued under this provision in accordance with the procedures set out in Clause 7.1 shall incorporate a revised Schedule and the Sub-contract shall be read and construed accordingly.
The Sub-contractors may, at any time, submit to the Contractor proposals for early completion of the Sub-contract Works or any Section or Sections thereof or any amendment thereto. If such proposals are acceptable, the Contractor shall issue a Change Order in accordance with Clause 7.1 and this clause".
"No Overtime other than Casual Overtime shall be worked without the prior written approval of the Contractor. The request to work such Overtime shall be made in writing at least four (4) Working Days in advance of the planned performance of such Overtime. Additional payment for such approved Overtime will only be made on the prior written agreement of the Contractor.
Casual Overtime by the Sub-contractor or all Sub-sub-contractors shall be the Sub-contractors responsibility and may be performed without prior notification to the Contract or within the Working Day solely at the Sub-contractors expense.
"We have undertaken the controls electrical installation as sub contractor to Johnson Control on the CRSF building, the Glaxo site in Stevenage. We have, during the contract, experienced delays, disruption and uneconomical working which has resulted in us incurring substantial additional costs, which we are seeking to recover.
The purpose of this document is to provide further details and substantiation in respect of our additional costs in order that they may be accessed and agreed in a fast and efficient manner. In order to maintain the site progress, it is essential that we are able to quickly resolve the claim situation to enable additional funds to become available against the project."
"Delays and Disruptions
We believe that during the course of the contract we have experienced severe delays and disruption to our works, which could not have been foreseen or envisaged at the tender stage. We have progressed diligently with our first and second fix activities and have suffered in terms of productivity as a direct result of site conditions. We are currently experiencing severe delays of our final terminations as a direct result of our of sequence work in respect of late delivery of control panels and controllers and the non-completion of works by other trades, including trunking, duct work and fume cupboards.
We have provided a comprehensive schedule of completion of our electrical installation and have detailed areas that are being delayed although work is outstanding by others causing disruption and associated uneconomical working. We also highlighted WERE (sic) possible cover up dates in respect of our first fix and wiring works which we believe clearly demonstrate that we have been delayed in completing our works for several weeks. It should be noted that the schedules provided are not fully complete and that additional work is being added on a number on an ongoing basis and will be updated in due course.
We believe that the procedures associated with the cover up notices were not highlighted within the specification at tender stage and we are still of the opinion that they are not clearly identified in the specification now. The associated administration disruption and substantial loss of productivity associated with these procedures are significant and we feel entitled to recover costs in respect of lost productivity.
We believe we have demonstrated from the enclosed schedules that the majority of our work has revolved return visits, out of sequence working and a significant degree of disruption in order for us to complete out works., Wee feel justified in claiming the lost productivity associated with the out of sequence working and the associated disruption. We have highlighted the cost in the next section associated with lost production man hours."
LATE DELIVERY OF CONTROL PANELS
It confirms that some panels were late delivered.
Mr Whitehead in his evidence in relation to Outstation panels accepted that there was some delay in the supply of these because the supplier, Paul Carter and Associates, went into liquidation. In consequence 10-15% had to be completed and recovered through the liquidator. It was TTEL's responsibility to wire field equipment and interconnections with the MCC's to the Outstations and to position and fix the Outstation panels, which were two to three metres wide and two metres high.
"Q. They are delivered later than the anticipated programme, are they not?
A. I think what you are trying to make me say here is that they were late on site and it caused a problem. I personally believe they were later than we thought, but that, you know, there were other things to do and those things would have to be installed later".
"Q. You also said that you were 'extremely concerned with regard to the recent request for us to carry out final connections and terminations at …….the late… delivery of control panels'. Do you recall what was the concern about that?
A. Because we wanted to connect both ends at the same time.
Q. Why did you want to do that?
A. Because it was convenient for us, that is all
Q. Otherwise out of sequence working?
A. No it would not have been because if you are only connecting on end, one end is about 30-40 metres away to hook on the other and so it would not have made any difference.
Q. It was more convenient for you?
Y. Yes.
Q. You've got to come back; instead of going up to it and doing it, you'd have to come back some time later and do it?
A. No. The two items are not close to each other.
Q. What was the concern then?
A. From my point of view?
Q. Yes.
Q. I was identifying so that if at a later date the panels were not completed on time. It was stated in a letter that we could not do them at the same time. I was contractually covering ourselves."
It is clear that some panels were delivered late. The consequence of late delivery was some interference with the continuity of TTEL's programme of working. Such delays may have given rise to loss and expense by TTEL.
TTEL's difficulty is that it cannot demonstrate that any particular delay did cause loss and expense. Neither can it demonstrate that any particular delay was critical or in breach of any agreed programme.
Within the scope of the original contract, as Mr Theaker confirmed, there is always a necessity to revisit. TTEL contend that the level of re-visiting went beyond that which was acceptable and therefore led to loss of profitability and loss of expense. I accept that on occasions, tradesman were unable to terminate connections and had to leave wiring coiled at the location that a panel or item of field equipment was later to be fitted at. This had the advantage of expensive pieces of equipment not being exposed to the risk of damage by other trades during the course of work within later fixes.
No excessive margin of re-visit over and above contractual scope has been proved in this case. Furthermore, as to loss of productivity there is no evidence that tradesman were standing around with nothing to do. The evidence of those on site, employed by TTEL Mr Lewis and Mr Hassell is to the contrary.
CEILING GRID ERECTION
"Q. Just help me with what the problem about the ceiling tiles was. I know you were writing about it. Tell me what the problem was about.
A. The problem is that if ceiling tiles went up then somebody would have to take the ceiling tiles down.
Q. Yes.
A. Our point on that was as to if there was any damage or anything to the ceiling tiles, we would not accept any responsibility because the controllers were not there at the right time.
Q. Did it limit accessibility?
A. No.
Q. Did not limit accessibility?
A. They could work through it.
Q. There was complaint because there was more work involved?
A. The complaint was to cover ourselves if there was any damage or anything like that.
Q. Also, because there was more work involved to take the tiles down?
A. We would not take the tiles down.
Q. You would not?
A. No. The ceiling fixers take them down.
Q. You'd have to wait until somebody came along and took them down?
A. We just identified which ones we wanted and they would take them down.
COVER UP NOTICES
SITE SECURITY
LABORATORY FURNITURE
TOOL BOX TALKS
THE EXPERT EVIDENCE
He said in his report:
"The calculation of the actual man-hours was based both on the record and time spent on various buildings, as recorded on TTEL's time-sheets and backed up by the daily records of labour on each element of the project as provided to LMK and via JCS by TTL. The calculation of recovered hours is deduced from the gross values of agreed applications made by TTL, having made allowance for materials content of the application, and using, the tendered labour rate, the hours are calculated.
TTL then calculate the apparent losses on labour committed to the contract by using the lost man-hours calculation, price and the rate included within the tenderers/sub-contract orders for the projects. In addition they projected the probable losses in terms of man hours to complete the contracts, in order to indicate to JCS the possible total costs:
"In addition to the calculation for loss of productivity/man-hours, TTL included some additional costs on the chemistry project due to changes in drawings from tender stage when compared to actual construction drawings issued to them. Arguably these additional costs would not necessarily form part of the loss and expense claim, but would be recovered as a variation item to the various projects. However, it must be remembered the impact of such variation may lead to prolongation of the contract, to a claim by TTL for such prolongation.
These methods of calculating loss productivity are often used in the mechanical services section of the Construction Industry for the calculation of additional costs due to delays etc. Had the Contract not been repudiated, I would assume that JCS and TTL would have negotiated some form of settlement around the information provided by TTL, possibly with JCS taking such information forward as part of their claim for delay, destruction etc, against their employer ELMK:
"I see no flaw in the method and calculation used by TTL, but would note that ultimately a settlement figure for such claim for delay, destruction etc.., would probably be lower than the figures included by TTL in their documentation….."
"Taking the non weighted percentage…above it would seem that 52% of responsibility lies with JCS. Whilst 47% seems to lie with unknown parties and only 1% lies with TTL, I will assume that the 47% should be split between TTL and JCS. If all 47% falls to JCS then virtually all the responsibility and therefore the majority of acceptable costs lies with JCS. If all 47% falls to TTL then something approaching an equal split of responsibility exists, with some 50% plus of the acceptable cost due to TTL. However the probable level of split lies between these two extremes, and if I take the half-way mark of equal split of responsibility of my unknown items, then I believe this would give an outcome of moneys due to TTL of some 75% of acceptable cost claimed under the document of January 1994.
"Whilst this calculation cannot be completed this time given the number of assumptions I have used, I am mindful that TTL's directors would have performed such analysis which may have led them to report to their Bankers an overall recovery of approximately half of the claim figure that TTL had submitted to JCS". (Emphasis supplied).
"39. We had a meeting with Johnson in early December when we explained to them that the situation on the site was beginning to have cash flow implications. In order to assist us, Johnson had provided prompt payment against our October valuation and had agreed to reduce the period for paying from 60 days to 45 days. They had also agreed to the release of retentions. With that letter I summarised for Johnson our concerns and highlighted where we considered that additional costs were being incurred by us. Their letter in response seemed to us to be not unsympathetic and asked us to particularise where we considered our losses were.
40. Following this challenge by Johnson to prove the variations we submitted in the week preceding Christmas 1993, the company produced a detailed document setting out the specifics of each individual variation claim, in comparison with the original tender, and the reason for the difference. The document was submitted to Johnson under cover of a letter dated 6th January 1994. These variations were perfectly normal and properly related back to the initial tender.
41. At no point had there been any dispute on site as to the fact that the work for these variations had been properly carried out. We were not even seeking full payment for them at that time, simply part payment in recognition of the extra work performed. There were literally hundreds of variations totalling around £350,000 in value. These changes in the work were required by Johnson. The original tender was not under-priced and were it not for the conduct of Johnson and other external hindrances beyond the control of the company, I believe the contract could have been completed on time at the price quoted….".
"The original tender document supplied by Johnson's clearly identified the systems and associated points in respect of land, office and plant room areas. We are currently doing detailed comparisons between the tender documents and the construction issued drawings and schedules in order to highlight any changes or discrepancies. When this process has been completed a full and final comprehensive schedule of all additional works will be provided along with the associated cost…..".
(my emphasis)
"7.1 The Contractor shall have the right at any time to require any alteration in, addition to, and/or deduction from the Sub-contract Work (a Change) without rendering the Sub-contract void. In such circumstances the Contractor shall issue a preliminary instruction for a Change Order to the Sub-contractor indicating the Change and the Sub-contractor shall forthwith consult with any of its sub-sub-contractors and Suppliers whose work would be effected by the said Change to ascertain any adjustments to their Sub-sub-contract sums and extensions of their sub-contract periods consequent upon such a Change.
If following such consultations the Sub-contractor and the Contractor can agree upon such matters, the Contractor shall issue a Change Order to the Sub-contractor adjusting the Sub-contract Price and/or Schedule and may provide Drawings and Specifications describing the Change. Each Change Order will be incorporated in the Sub-contract….All Changes in the Sub-Contract Work shall be completed within the time schedule set forth in the Sub-contract or the Change Order and shall be performed in accordance with the provisions of the Sub-Contract and the Change Order. The adjustments resulting from a Change in the Sub-contract Work shall be based on proposals and schedules prepared by the Sub-contractor properly itemised and supported by sufficient substantiated data to permit evaluation and approval by the Contractor. Proposal for the said adjustment shall be accompanied by a sufficient breakdown and supporting details to permit evaluation and approval by the Contractor. Said adjustment shall be consistent with a bid submitted by the Sub-contractor for that portion of the Sub-contract Work. Notwithstanding the foregoing, the Contractor shall be entitled to issue a construction to the Sub-contractor at any time requiring a change and the Sub-contractor shall comply with the Instructions.
In the event the Contractor and the Sub-contractor are unable to agree the value of an Instruction for Change then the Contractor shall determine a fair valuation of such instruction and such valuation shall be binding until Practical Completion of the whole of the Sub-contract Work.
7.2 Should the Sub-contractor or its Sub-sub-contractor perform any sub-contract work or proceed in any manner which the Sub-contractor may subsequently allege has caused the Contractor or its Sub-sub-contractor increased costs, damage or loss purporting in each case to have acted upon oral instruction or with a tacit consent acceptance or approval of the Contractor or any other direction other than by a properly executed Change Order pursuant to Clause 7.1 the Sub-contractor or its Sub-Sub-Contractors shall be held to have done so at their own risk, the Sub-Contractor and its Sub-Sub-Contractor shall have no claim against the Contractor or Employer on account of any alleged increased costs, damage or loss.
7.3 If the Sub-contractor believes that any interpretation, decision or act or omission of the Contractor causes a change in cost or time and should be considered as an instruction or a Change, it shall immediately notify the Contractor. The Contractor shall determine if it agrees then either issue an instruction for Change or a Change Order or notify the Sub-Contractor that it disagreed. In the latter event the Sub-Contractor shall continue to prosecute the Sub-contract work including the matters which are the subject of the said disagreement notwithstanding the said disagreement.
7.4 No Change Order or instruction for a Change shall be issued where
7.4.3 the Sub-Contractors or its Sub-Sub-Contractors proceed with any section of the Sub Contract Work without giving notices as required under the Sub-Contract.
Needless to say in respect of work and variations neither Johnson nor TTEL seem to have followed the strict contractual regime. Mr Quigley rightly observes that the parties had adopted a more informal approach to matters of notices and formalities under the Contract and accordingly is not surprised that there are no formal notices complying with the rigor of Clause 7 served and counter-served.
The experts in their joint report conclude:
Chemistry Building Initial Works Claim
The experts agree that five of the six items of work claimed were 'estimates' representing £38,730.25 out of £53,310.69 claimed.
GNA's Report (Paragraphs 6.53 to 6.59) relies on paragraph 62-66 of Mr Whitehead's Witness Statement.
KLJKQ (paragraph 4.5 of his report) cannot comment on the validity of the quantities claimed but he said that the rates used in the calculations appear to coincide with those used in the build-up of earlier variation prices.
The experts agree that they were unable to comment on the extent of the work actually carried out on the six items claimed".
Mr Ian Milner who compiled the claim document was not available to help. There was no other direct evidence, save that of Mr Bull. Mr Quigley in his report would only go so far as to say
"….If the differences between the numbers of these specific items have increased during the project, then the variation should be allowed to the account of TTEL" (Emphasis added).
THE TERMINATION OF THE CONTRACT
"Re Glaxo Group Research Campus: Stevenage
Chemistry/Biology/CRSF
With regard to your sub-contracts on the three packages referred to above, we wish to advise given the mandatory notice that you are failing to execute the works with due diligence and expedition.
Your failure is with regards to not employing sufficient labour to ensure the execution of the works in an expedient manner to facilitate the available work faces on all three contracts required by Clause 3.2 of the Sub-contract document. Therefore should you fail to remedy the situation in compliance with this notice by 8am on Friday 11th February 1994 then we will take the works wholly out of your hands. In this event we will have the free use of all the tools, tackle, stores and other things that may be on site in connection with the works.
The balance will be re-claimed. All the costs of executing the remaining works if they exceed the value of the balance. Such costs you will have to pay.
Yours faithfully,
G. Fitchett".
It is apparent that on 8th or at latest 9th February, Johnson also decided to sue TTEL for the recovery of moneys allegedly overpaid represented in part by the sum of £150,000, the payment of which was advised by Mr Theaker and was in fact paid on 28th January in the light of the information of cash flow difficulties, candidly revealed to Johnson by TTEL. The effect of the letter of determination was reinforced by the active decision to commence proceedings and to obtain a Mareva Injunction.
THE MAREVA INJUNCTION – THE ENQUIRY
"I therefore had to ask that the Company reduces overdraft with the bank as quickly as possible with a view to the account being in credit from the end of February and that thereafter we would have to re-negotiate the overdraft facility. I needed full information about the problems on the contract".
"….I anticipate that the company would have continued to trade. I accept that we may not have recovered everything we considered we were owed by Johnsons. In the construction industry one does not bank on receiving full payment, and it is well known in the industry that Johnson in particular regularly pays smaller contractors less than the value of the work done. As stated in paragraph 15 above, both Tony Ball and I were always conservative when producing figures for claims in our management accounts. I do however believe that we would have recovered a minimum of £100,000 out of our claim for £372,000.
Even had we not recovered anything, although this would have made a serious debt in our profits for February, one of the proposals that I was going to discuss with Johnson was that the Company withdraw from the contract so as to stop our losses. I appreciate that I may have had difficulty in persuading the bank to support us any more than they were already doing, but I believe that the bank would have continued its support"
Mr Bull gave evidence on Day 8 that the labour element of the sub-contract was of the order of 70/75%, the rest being materials; he explained however, in relation to the labour element that the real cost incurred was in the order of one third of that charge.
"I can say that the imposition of the Mareva injunction was a defining moment in the relationship between the Bank and the Company. It was the event which left me with no confidence in the company's ability to trade and which made me decide that the facility should be called in. Prior to then, I had the concerns that I have previously expressed in the light of the percentage of the Company's turnover that the Johnson contract represented. If the Mareva Injunction had not been taken out, I may well have required the Company to produce its cash flow on a weekly basis. Had the company reorganised its balance sheet as described…above..in those circumstances I believe that the Bank's support would have been forthcoming…." .
"I'll crush you, you'll be finished! You play by my rules or not at all!"
I reject that submission. I hold that I have no discretion in the matter since an enquiry was ordered by HHJ Malcolm Lee QC and that order was never appealed. He had discharged the injunction concluding that it was wrongfully sought. That decision was appealed and the appeal rejected. The decision to discharge an injunction and the decision to enforce an undertaking as to damages given to the court, are two separate matters. It may be that the decision to enforce an undertaking in many cases is best left to the trial judge. In this case it was not.
"(1) Save in special cases an undertaking as to damages is the price that the person asking for an interlocutory injunction has to pay for its grant….
(2) The undertaking there described as an undertaking as to damages, does not found any cause of action. It does, however, enable the party enjoined to apply to the court for compensation if it is subsequently established that the interlocutory injunction should not have been granted.
(3) The undertaking is not given to the enjoined but to the court.
(4) In a case where it is determined that the injunction should not have been granted, the undertaking is likely to be enforced, though the court retains discretion not to do so.
(5) The time at which the court shall determine whether or not the interlocutory injunction should have been granted will vary from case to case. It is important to underline the fact that the question whether the undertaking shall be enforced is a separate question on the question of whether the injunction should be discharged or continued.
(6) In many cases injunctions will remain in being until the trial and in such cases the propriety of its original grant and the question of the enforcement of the undertaking will not be considered before the conclusion of the trial…..
(7) Where an interlocutory injunction is discharged before the trial the court at the time of discharge is faced with a number of possibilities:
(a) the court can determine forthwith that the undertakings to damages should be enforced and can proceed at once to make an assessment of damages. It seems probable that it will only be in rare cases that the court can take this course because the relevant evidence of damages is unlikely to be available…….
(b) The court may determine that the undertaking should be enforced but then direct an enquiry as to the damages in which issues of causation and quantum will have to be considered…….in the light of the decision of the Court of Appeal in Norwest Holst Civil Engineering Ltd. v Polysius Ltd Transcript No.644 of 1967, the court should not order an enquiry as to damages and at the same time leave open for the tribunal at the enquiry to determine whether or not the undertaking should be in force. A decision that the undertaking should be enforced is a pre-condition for the making of an order of an enquiry as to damages.
(c) the court can adjourn the application for the enforcement of the undertaking to the trial or further order.
(d) the court can determine forthwith the undertaking is not to be enforced.
8. It seems that the damages are awarded on a similar basis to that on which damages are awarded for breach of contract. This matter has not been fully explored in the English cases though it is to be noted that in Air Express Ltd., v Ansett Transport Industries (Operations) Pty Ltd [1979] 146C.L.R. 249, 267 Aickin J. in the High Court of Australia expressed the view that it would be seldom that it would be just and equitable that the unsuccessful plaintiff 'should bare the burden of damages which were not foreseeable from circumstances near to him at the time'. This passage suggests that the court in exercising its equitable jurisdiction should adopt similar principles to those relevant in a claim for breach of contract."
I hold that I have no discretion as to whether I proceed or not with the enquiry as to the appropriate compensation in this case. Had it been open for me to consider such an exercise of discretion, I would have found little difficulty in concluding that the undertaking should have been enforced by the court and that an enquiry into the measure of compensation should be undertaken.
"I do not think the conduct of the defendant presents so meritorious a state of facts as compels me to grant the enquiry asked."
In Modern Transport Co. Ltd. v Duneric Steamship Co. [1917] 1 KB.370, 380, Swinfen Eady L.J. said that inequitable conduct by the defendant constituted special circumstances such that no enquiry as to damages was to be granted, even if the claim for an injunction could not be sustained at the trial; but that was a case where he held that the plaintiffs were justified in applying for an interlocutory injunction. In Upper Canada College v City of Toronto [1917] 40 O.L.R. 483, the court in refusing to order an enquiry as to damage on an undertaking given on the grant of an interlocutory injunction discharged at the trial, had regard to a number of circumstances including the good faith of the plaintiffs and the fact that no costs were awarded against them when the action was dismissed. In Attorney General for Ontario v Harry [1982] 25 C.P.C.67, a factor taken into account by the court in refuting to enforce an undertaking as to damages, notwithstanding the discharge at the trial of the interlocutory injunction, was the inequitable conduct of the defendant. These cases support the general words of Turner L.J. in Newby v Harrison [1861] 3 De G.F. and J. 287, 290:
"There may be cases in which the court will not consider it just to enforce an undertaking, though the jurisdiction to do so exists".
TTEL's PROFIT AND LOSS ACCOUNT FOR THE YEAR ENDED 30TH APRIL 1993.
TTEL'S TURNOVER AND TTEEL'S TURNOVER AND EXPENSES DURING THE 8 MONTHS ENDED 31ST DECEMBER 1993.
Q. …you have assumed a gross profit in Engineering of 30%, not the 19.7% which you knew to be disclosed by the audited accounts.
A. that is true. I would like to caveat that on two fronts, if I may. One is, my Lord, that I had not fully absorbed the nature of the journal entries between the different sets of management accounts by the time I had prepared this report, and a lot of that came through to me during my discussions with Mr Granger. Secondly it is only recently in fact that I developed some thoughts on that. I accept that point. I accept that I made the initial assumption of gross profit margin of 30% but I would not say that this is my view at this point. (My emphasis).
Q. You've made an assumption. You have not referred at all comparing that assumption to the actual accounts which you had which revealed a gross profit margin in engineering of 19.5?
A. Is that correct?
Q. That is correct. I would like to expand on that if I may. That was simply because I could not relate the cost of sales at that time within the statutory accounts of engineering to the charge from TTEL to engineering but I was able to do so subsequently. In other words, I did not have the link. I did not want to make an assumption simply because it was there.
Judge Wilcox: But you had the accounts
A. That is true my Lord
Q. They are staring you in the face and you say they are statutory accounts and that you give them face value. Then you make an assumption that is very much elevated from that. I cannot understand that.
A. OK let me explain my Lord. There are two issues there. One is if we look at the statutory accounts. I was unable to pinpoint that the turnover into statutory cuts was linked with the turnover of Europa. However, at that time when I prepared my report, I accept that I was not able to link the cost of sales with the management charge that was made by Europa. I made an assumption because I was not sure. I did not sufficiently explore my thought processes on the gross profit margin that was used in the statutory accounts; that is the point I am really making. In other words I made the assumption on the basis that if they are both roughly in the same type of business, is 30% a reasonable assumption because Europa had made a gross profit margin of 30. I will assume 30.
Q. I can understand you were making an informed assumption, but why was it not on the basis of 19.7%?
A. Simply
Q As was shown in the statutory accounts.
A. Because my Lord I could not support the cost of sales figures in the statutory accounts in relation to the records of Europa, that is the reason.
Q. You know the duty of an expert to draw to the attention of the court matters which are adverse to the case of the party which you are called to give evidence on behalf of?
A. Absolutely.
Q. In making an assumption about the gross profit margin of engineering, you have material….namely the audited accounts in engineering which were adverse to that assumption, did you not?
A. I had statutory accounts which were adverse to that assumption; I accept that, although I would like to add, as I keep saying, that I wanted to link the transactions that I could identify in Europa's books with their statutory accounts and I have now been able to do that. My Lord I am very……I have been conscious of this before the start of my evidence, that this has been a moving scenario in three stages. One is I identified a lot more about the relationships between the companies during my meeting with Mr Granger and I have identified more since then, because I have been undertaking further analyses. I do not have any…in other words, I have developed my though processes.
Judge Wilcox But you have not drawn the change brought about by your thought processes to the attention of the court until it has been enquired into, have you?
A. They have been drawn to
Q. Have you?
A. I have to the extent that it is covered in the single joint report, which is a later document.
Q. Yes Mr Eklund
Mr Eklund In the joint report you repeat the assumption that engineering could have achieved a gross profit of the order of 30% do you not? Page 139.
A I repeat that assumption, but I also highlight in paragraph 7.2 the existence of the two separate sets of management charges. At that stage, I had not quite come to grips with why there were two separate sets of figures; I accept that point. The reason I did draw to the attention of the court the fact that I had other information at hand
Q. What you have not done is drawn to the attention of the court what you now accept, namely the gross profit margin engineering should be taken at less than 20%
A. At around 20% yes.
Q. When you prepared your report, you had for your information and to enquire into a substantial number of documents including various versions of the management accounts and general entries did you not?
A. I did.
Q. Yes. Please turn to page 133
Judge Wilcox Is that 133 Mr Eklund
A. Yes that is a page from the joint statement which you set out in paragraph 3.3 'for the avoidance of doubt we have set out the various documents referred to in the Chapel report with copies of identified documents being designated as document 1 etc in manuscript at the right-hand side of each copy.
A. Yes.
A. One of the primary sets of instructions that I had apart from looking at the valuation of the company was to review Mr Granger's report. The document supporting Mr Granger's report included only one version of those set of management accounts. I then received separately papers from the administrative receiver's files, which had a whole set of various management accounts all co- mingled. In order to establish a sort of audit trail if I can call it that is an exercise which has been going on since I was instructed essentially and I accept that at that time I had not fully absorbed that audit trail. It had come through to some extent from my discussions with Mr Granger.
Q. Since your discussions with Mr Granger and the signing of the joint report signed on 6th February 2002, have you prepared any further report clarifying your view as a result of your understanding of the documents which you are now referring to?
A. I have prepared analyses for conferences with counsel but no reports.
TTEL'S ACCOUNTING TREATMENT OF CLAIMS & VARIATIONS IN RESPECT OF THE GLAXO CONTRACT
ADMINISTRATION SERVICE CHARGE PAID BY TTEL TO WARWICKSHIRE PROPERTIES LTD
TTEL'S ADDITIONAL MOTOR EXPENSES
TTEL'S CZECHOSLOVAKIAN COSTS
TTEL'S ADDITIONAL REPAIR COSTS
TTEL'S FINANCIAL POSITION PRIOR TO THE MAREVA INJUNCTION
THE VALUATION OF TTEL
Turnover £1,899,556
Cost of Sales (£1,381,211)
Gross Profit £518,343
Administrative Expenses (£460,131)
Other Operating Income £1,073
Interest Payable £17,271)
£42,016
Claims and Variations £86,190
Administration Service Charge (£45,000)
Maintainable before Tax £83,206
CONCLUSIONS
A: The Claim
B: The Counterclaim
a) £13,385.80 )
£12,703.89 )
£12,633.85 ) (para 53)
b) £25,972.00 (para 61.)
C: Enquiry into damages
Judgment:
i) £1,847.00 (para 150)
ii) £225,000.00 (para 211)
_________________
TOTAL £291,542.54