QUEENS BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137, Fetter Lane, London, EC4A 1HD | ||
B e f o r e :
____________________
J. T. MACKLEY & COMPANY LIMITED | Claimant | |
- and - | ||
GOSPORT MARINA LIMITED | Defendant |
____________________
Geoffrey Hawker (instructed by Blake Lapthorn for the Defendant)
____________________
Crown Copyright ©
H.H. Judge Richard Seymour Q. C. :
Introduction
The Contract
The Arbitration Clause
“(1) Except as otherwise provided in these Conditions if a dispute of any kind whatsoever arises between the Employer [that is to say, Gosport] and the Contractor [that is to say, Mackley] in connection with or arising out of the Contract or the carrying out of the Works including any dispute as to any decision opinion instruction direction certificate or valuation of the Engineer (whether during the progress of the Works or after their completion and whether before or after the determination abandonment or breach of the Contract) it shall be settled in accordance with the following provisions.
(2) For the purpose of sub-clauses (2) to (6) inclusive of this Clause a dispute shall be deemed to arise when one party serves on the Engineer a notice in writing (hereinafter called the Notice of Dispute) stating the nature of the dispute…
(3) Every dispute notified under sub-clause (2) of this Clause shall be settled by the Engineer who shall state his decision in writing and give notice of the same to the Employer and the Contractor within the time limits set out in sub-clause (6) of this Clause.
(4) Unless the Contract has already been determined or abandoned the Contractor shall in every case continue to proceed with the Works with all due diligence and the Contractor and the Employer shall both give effect forthwith to every such decision of the Engineer. Such decisions shall be final and binding upon the Contractor and the Employer unless and until as hereinafter provided either
(a) the recommendation of a conciliator has been accepted by both parties or
(b) the decision of the Engineer is revised by an arbitrator and an award made and published…
(6) (a) Where a Certificate of Substantial Completion of the whole of the Works has not been issued and either
(i) the Employer or the Contractor is dissatisfied with any decision of the Engineer given under sub-clause (3) of this Clause or
(ii) the Engineer fails to give such decision for a period of one calendar month after the service of the Notice of Dispute or
(iii) the Employer or the Contractor is dissatisfied with any recommendation of a conciliator appointed under sub-clause (5) of this Clause
then either the Employer or the Contractor may within 3 calendar months after receiving notice of such decision or within 3 calendar months after the expiry of the said period of one month or within one calendar month of receipt of the conciliator’s recommendation (as the case may be) refer the dispute to the arbitration of a person to be agreed upon by the parties by serving on the other party a written Notice to Refer.
(b) Where a Certificate of Substantial Completion of the whole of the Works has been issued the foregoing provisions shall apply save that the said period of one calendar month referred to in (a)(ii) above shall be read as 3 calendar months…
(8) (a) Any reference to arbitration under this Clause shall be deemed to be a submission to arbitration within the meaning of the Arbitration Acts 1950 to 1979 or any statutory re-enactment or amendment thereof for the time being in force. The reference shall be conducted in accordance with the Institution of Civil Engineers’ Arbitration Procedure (1983) or any amendment or modification thereof being in force at the time of the appointment of the arbitrator. Such arbitrator shall have full power to open up review and revise any decision opinion instruction direction certificate or valuation of the Engineer.
(b) Neither party shall be limited in the proceedings before such arbitrator to the evidence or arguments put before the Engineer for the purpose of obtaining his decision under sub-clause (3) of this Clause.
(c) The award of the arbitrator shall be binding on all parties… ”
No provision for adjudication
Substantial Completion of the Works
The Adjudications
The Reference to the Engineer
“Gosport Marina Land Reclamation
We refer to Clause 66(2) of the ICE Conditions of Contract (Sixth Edition) as amended, and to the Schedule of Loss and Expense accompanying the Joint Notice of Dispute and Notice to Refer served today on behalf of our Client, Gosport Marina Ltd upon the Contractor, J. T. Mackley & Co. Ltd, and yourselves as Consulting Engineer.
The said Schedule summarises our Client’s claims against both the Contractor and Engineer. Some of these claims have already been referred to you as the Engineer pursuant to Clause 66(2) of the ICE Conditions of Contract; others, for example Item 5 in the Schedule, have not.
Accordingly, and for the avoidance of doubt, each and every Item in the Schedule is hereby referred to you as the Engineer pursuant to the said Clause 66(2) insofar as they concern the Contractor. Insofar as they concern yourselves, no such reference is, of course, necessary.
We await your decision(s) in these matters pursuant to Clause 66(3) of the ICE Conditions of Contract at your early convenience. Where and to the extent that you may already have given a Clause 66(3) decision, please supply copies of the relevant decision letters.”
The Notice to Refer
“1. On 7th February 2000 the Gosport Marina Limited, the issuing party herein, entered into a contract (the “Contract”) whereby J T Mackley & Co Ltd (the “Contractor”) agreed to carry out land reclamation works for the Gosport Marina Ltd (the “Employer”) at its site in Mumby Road, Gosport, Hampshire.
2. The form of that contract was the ICE 6th edition (January 1991) with corrigenda (August 1993) and Guidance Notes (March 1995) and Amendments (reference: ICE 6th edition tax/February 1998).
3. By a Contract made on the 26th June 1998, Posford Haskoning Ltd (then Posford Duvivier) (the “Consulting Engineer”) contracted to provide professional services as detailed and described in the Agreement.
4. The Respondents agreed to exercise reasonable skill, care and diligence in the performance of the services set out in their respective agreements.
1. [sic] This notice, as to the Contractor, is issued under clause 66 of the Contract and in accordance with the ICE Arbitration Procedure (1983) as amended, and as to Consulting Engineer under clause 9 of the Association of Consulting Engineers Conditions of Engagement, 1995 and in accordance with the Chartered Institute of Arbitrators rules and procedures.
2. The Contract involved land reclamation using dredged fill. It required a programme of controlled and staged filling in 0.5 m layers over soft unstable silt seabed, and the installation of sheet pile walls and wick drains at various stages in that programme. The Consulting Engineer, as part of its professional services, was responsible for the design and construction supervision of, inter alia that area of land reclamation which was to be used for car parking.
3. During the initial phase of reclamation filling significant silt slippage and ground movements occurred within and beyond the toe of the reclamation, necessitating extensive additional dredging works to re-establish water depths. The slippage caused physical damage, delays, and consequential losses, and necessitated extensive remedial works. Additional costs were incurred by the Issuing Party as a consequence of the slippage and ground movements.
4. The displacement of the very soft unstable silt seabed that occurred during initial placement of Phase 1 reclamation was an inevitable consequence of the design and method of construction of the Consulting Engineer. Further this seabed ground failure, which occurred almost from the commencement of the work, was known to the Contractor, who despite the failure continued work, without adequate supervision, causing the ground failure to worsen over time.
5. Insufficient consideration was given by either of the Respondents as to the likely implications of the displacement on the existing Marina facilities, or the need to subsequently remove the material from site, even though the Respondents were aware of the importance of the Marina continuing to function throughout the construction period.
6. The Issuing Party has suffered loss and expense as a consequence of the Respondents’ breaches of contract and duties owed, full details whereof are set out in the schedule annexed hereto. The Issuing Party’s claim will also include a claim for interest and costs.
7. Given the complexities of the dispute and the specialised nature of the works, the Issuing Party is of the view that an arbitrator with substantial experience of marine work should be appointed by the appropriate Appointing Authorities.”
Mackley’s objections to the Notice to Refer
The relevant provisions of Arbitration Act 1996
“(1) The Court may, on the application of a party to arbitral proceedings (upon notice to the other parties) determine any question as to the substantive jurisdiction of the tribunal…
(2) An application under this section shall not be considered unless -
(a) it is made with the agreement in writing of all the other parties to the proceedings, or
(b) it is made with the permission of the tribunal and the court is satisfied –
(i) that the determination of the question is likely to produce substantial saving in costs,
(ii) that the application was made without delay, and
(iii) that there is good reason why the matter should be decided by the court.”
“(1) Unless otherwise agreed by the parties, the arbitral tribunal may rule on its own substantive jurisdiction, that is, as to –
(a) whether there is a valid arbitration agreement,
(b) whether the tribunal is properly constituted, and
(c) what matters have been submitted to arbitration in accordance with the arbitration agreement.
(2) Any such ruling may be challenged by any available arbitral process of appeal or review or in accordance with the provisions of this Part.”
“The provisions of this Part are founded on the following principles, and shall be construed accordingly –
(a) the object of arbitration is to obtain the fair resolution of disputes by an impartial tribunal without unnecessary delay or expense;
(b) the parties should be free to agree how their disputes are resolved, subject only to such safeguards as are necessary in the public interest;
(c) in matters governed by this Part the court should not intervene except as provided by this Part.”
The case on behalf of Gosport as to the jurisdiction of the Court
The case on behalf of Mackley as to the jurisdiction of the Court
Whether to exercise the jurisdiction of the Court
“44. Section 30 of the 1996 Act provides that the tribunal may rule on its own substantive jurisdiction. It is clear from the Report of the Departmental Advisory Committee on the Arbitration Bill, February 1996 (DAC Report), that s. 30 was intended to state the doctrine of “kompetenz-kompetenz”. It was the intention that the basic rule was to be that the tribunal would make the rulings on jurisdiction in the first instance rather than recourse being had to the courts.
45. Section 32 provides an exception to this basic rule; under s. 32(1) the court may determine questions as to the substantive jurisdiction of the tribunal on the application of a party to arbitral proceedings. A restriction on that right is imposed by s. 32(2)…
Section 32 was therefore intended to provide that an application to the court would only be made in strictly limited circumstances; recourse to the court would be very much the exception. Paragraph 147 of the DAC Report states:
“….this Clause provides for exceptional cases only: it is not intended to detract from the basic rule as set out in Clause 30. Hence the restrictions in Clause 32(2), and the procedure in Clause 32(3). It will be noted that we have required either the agreement of the parties, or that the Court is satisfied that this is, in effect, the proper course to take. It is anticipated that the Courts will take care to prevent this exceptional provision from becoming the normal route for challenging jurisdiction.
46. In ABB Lummus Global Ltd. v. Keppel Fells Ltd. (formerly Far East Levington Shipbuilding Ltd) [1999] 2 Lloyd’s Rep 24 Clarke J declined to consider an arbitration application for a declaration that an arbitration application was still on foot because the requirements of s 32(2) were not satisfied. He observed that the purpose of the Act was to restrict the role of the court at an early stage of the arbitration.
47. The issue raised by the application to the court in the arbitration claim form in these proceedings is clearly a question as to the substantive jurisdiction of the arbitrators within the meaning of s 30 (see the definition in s 82(1)). If the owners had appointed an arbitrator, it is also clear, as was accepted by the owners, that the court would not have had jurisdiction to determine the issue, as the conditions in s 32(2) were not satisfied. The owners, however, contended that the conditions contained in s 32(2) were not applicable to these proceedings because they have not appointed and arbitrator and they are not a party to arbitral proceedings. They are therefore entitled to bring the arbitration application.
48. I do not accept the submission. The court is given guidance as to the circumstance in which it should intervene in relation to arbitration by the terms of s 1 in Pt 1 of the 1996 Act. This provides:
“The provisions of this Part are founded on the following principles, and shall be construed accordingly…(c) in matters governed by this Part the court should not intervene except as provided by this Part.”
49. It is clear from the DAC Report that this principle was included because of international criticism that the courts of England and Wales intervened more than it was thought they should in the arbitral process, and this was a discouragement to the selection of London as a forum for arbitration.
50. The provisions of Pt 1 of the 1996 Act regulate all matters not only after constitution of the tribunal by the appointment of an arbitrator but prior to that; see for example s 9, s12 and s 44(5) which all relate to powers that can be exercised prior to the appointment of the arbitral tribunal.
51. In my view therefore the present application for the determination of whether there is an arbitral agreement is a matter regulated by Pt 1 of the 1996 Act and in accordance with s 1(c), the court must approach the application on the basis it should not intervene except in the circumstances specified in that part of the 1996 Act.
52. I accept the owners’ submission that the use of the word “should” as opposed to the word “shall” shows that an absolute prohibition on intervention by the court in circumstances other than those specified in Pt 1 was not intended. That submission seems to me to have force as the view is expressed in the DAC Report that a mandatory prohibition of intervention in terms similar to art 5 of the United Nations Commission on International Trade Model Law on International Commercial Arbitration (21 June 1985) (the Model Law) was inapposite. However, it is clear that the general intention was that the courts should usually not intervene outside the general circumstances specified in Pt 1 of the 1996 Act.
53. The circumstances in this case which the owners say are ones in which the court should intervene cannot have been unanticipated by the draftsmen of the 1996 Act. It is very common for . a person who is alleged to be party to an arbitration agreement but denies that he is to make his position clear before an arbitrator is appointed by the person contending that there is a binding arbitration agreement. Thus the argument of the owners must be premised on the assumption that the draftsmen of the 1996 Act intended to allow a party to an arbitration agreement recourse to the courts without any conditions, if he took that step prior to the appointment of an arbitrator, but imposed the conditions in s 32 if he had appointed an arbitrator. If the owners are right, then a party to an arbitration agreement which is disputed can obtain the decision of the courts Without being subject to the restrictions by the simple step of not appointing an arbitrator.
54. I do not consider that this can have been the intention. The 1996 Act sets out in very clear terms the steps that a party who contends that there is another party to an arbitration agreement should take. First, he should appoint an arbitrator. If the other party appoints an arbitrator, then s 31 (1) makes it clear that his appointment of an arbitrator does not prevent him challenging the substantive jurisdiction of the tribunal. If the other party appoints an arbitrator, then s 31(1) makes it clear that his appointment of an arbitrator does not prevent him challenging the substantive jurisdiction of the tribunal. If the other party does not appoint an arbitrator, then the default provisions (s 17) or failure of appointment procedures (s 18) apply. Once the arbitral tribunal is constituted, then in accordance with the policy of the 1996 Act it is for that tribunal to rule on its own jurisdiction, save in the circumstances specified in s 32. Any award made can then be challenged under s 67. The rights of the party who challenges the existence of the arbitration agreement and takes no part are protected by s 72; he is given the right of recourse to the courts in the circumstances set out. Those provisions, in my view, provide a clear and workable set of rules which the owners should have followed in this case. I can see no reason which would justify the court intervening in the circumstances of this particular case, as it is no different from many others.
55. The owners contended that it would be in the overall interests of justice for the court to hear this application because it would generally be convenient to do so and that the argument over the validity of the arbitration agreement was bound to arise at a later stage. However, this argument fails to take into account one of the underlying principles of the Act, that the parties should resolve their dispute by the methods they have chosen and the court’s intervention should be limited.”
“That rule provides:
Once his appointment is completed the Arbitrator shall have jurisdiction over any issue connected with and necessary to the determination of any dispute or difference already referred to him whether or not any condition precedent to referring the matter to arbitration had been complied with.
The submission of the appellants is that if a matter has been referred to arbitration then it is open to the arbitrator to consider decisions of the Engineer on other matters even if those decisions have become final and binding because they were not challenged in accordance with the procedure under Clause 66. So in the instant case after receipt of the final certificate which quantified those claims left unquantified by the Engineer’s decision, the appellants gave notice to the Engineer of a dispute in relation to quantification. The Engineer having resolved that dispute, the appellants then gave notice for an arbitration to take place on those items. It is plain that the object of the appellants in commencing the arbitration was to try and give jurisdiction to the arbitrator to resolve those matters which were previously the subject of the Engineer’s decision and in relation to which Clause 66(4) prima facie applies.
The primary submission of Mr. Elliott Q.C. is that rule 5.2 does not allow an arbitrator to have jurisdiction over any issue which has been determined by the Engineer and which is final and binding by virtue of the provisions of Clause 66(4). He submits, (and this was a submission accepted by the judge), that once the decision of the Engineer has become final and binding in relation to any matter, there simply is not an “issue” which could be said to be connected with and necessary to the determination of any dispute or difference. Albeit at one time I did wonder whether some assistance was given to Mr. Bowdery by the final sentence of Clause 66(8) in his argument that even decisions of the Engineer unchallenged were reviewable provided they could be said to be “connected with and necessary to the determination of any dispute or difference already referred to (the arbitrator)”, I was very much persuaded by Mr. Elliott that there was no force in that point. Mr. Elliott pointed out that there are decisions which are taken by the Engineer with a small “d” which are to be distinguished from a decision with a capital “D”. The decisions with a capital “D” being those taken under Clause 66.
It seems to me that the construction of rule 5.2 suggested by Mr. Elliott is the correct construction and accords with commercial common sense. It seems unlikely that a contract would provide for decisions of the Engineer being “final and binding” and then leave the whole matter uncertain once the final certificate had been produced.”
It seems to me that the passage upon which Mr. Coulson relied does indeed support his submission.
The Submissions on behalf of Gosport in relation to the Notice to Refer
“19. Where an Engineer’s Clause 66(3) Decision has not been sought, it would appear that there is no limit to the time during which a valid Notice to Refer may be issued. However, if and to the extent that the obtaining of a Clause 66(3) Decision is a condition precedent to arbitration, the proper view is that the arbitration (once commenced) cannot proceed with regard to that dispute until the Engineer has given his Decision or the time for its delivery has expired. Needless to say, other disputes in the same arbitration which are not so caught may proceed, since there is no stay on the arbitration as a whole. Rule 5.2 of the I.C.E. Arbitration Procedure 1997 may here be relevant, in that the condition precedent on one issue may be over-ridden provided that that issue is “connected with and necessary to the determination of” any dispute or difference already referred to the arbitrator and not so caught.
20. In its unamended form, the I.C.E. Sixth Edition has no provision for adjudication, which therefore falls to be governed by the Housing Grants, Construction and Regeneration Act 1996 and the Scheme for Construction Contracts promulgated thereunder. S. 108(3) of the Act provides that:-
“…the decision of the adjudicator is binding until the dispute is finally determined by ….arbitration…”
but neither in the Act itself nor in the Scheme for Construction Contracts is there any time limit (measured from the date of the adjudicator’s decision) within which the relevant dispute must be referred to arbitration. I.C.E. Clause 66(6) does not, therefore, apply. Nor can the condition precedent in Clauses 66(2) and (3) affect the position, since s. 108(2)(a) of the Act enables a party to give notice at any time of his intention to refer a dispute to adjudication, thereby by-passing the unamended I.C.E. Sixth Edition.”
“…Gosport did seek the appointment of the same person as Arbitrator in both arbitrations. Faced with two different appointing authorities (Mackley having ignored the Notice to Concur), Gosport issued Notices of Dispute, to Refer and to Concur covering both arbitrations in “joint” form so that each appointing authority and both Mackley and Posford would know what was afoot. Inevitably, these Notices covered issues in both arbitrations and thus were, perforce, generic rather than specific. Fortunately, Gosport’s aim succeeded in that Mr. Morris is now appointed in both arbitrations. However, from here on it is Gosport’s intention to keep the two references rigidly separate so far as paperwork is concerned, although should both Respondents so agree, Gosport would not oppose joinder.”
The validity of the Notice to Refer
“The contract shall –
(a) enable a party to give notice at any time of his intention to refer a dispute to adjudication,”
but I cannot see what that has to do with any subsequent arbitration in which the correctness of the decision of the adjudicator is sought to be disputed. Contrary to the impression given by Mr. Hawker in his written skeleton argument, it is not the case that the only permissible remedy of a party to an adjudication who is aggrieved by the outcome is arbitration. What s. 108(3) actually provides is:-
“The contract shall provide that the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement.”
That form of words makes it plain, in my judgment, that arbitration is only available as a means of challenging the decision of an adjudicator if the relevant contract so provides or an ad hoc arbitration agreement is made. Where it is sought to rely on an arbitration clause in the relevant contract, it seems to me to be obvious that the ability to do so, and the terms upon which such may be done, fall to be determined under the relevant arbitration clause.
Conclusion