QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
B e f o r e :
____________________
(1) SAMUEL HENRY PAYNE (2) JILLIAN SCOTNEY (3) GARY MARK PAYNE |
Claimants |
|
AND |
||
JOHN SETCHELL LIMITED |
Defendant |
____________________
Neutral Citation Number: [2001] EWHC 457 (TCC)
IN THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Date: 16 March 2001
Before:
HIS HONOUR JUDGE HUMPHREY LLOYD QC
- - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - -
BETWEEN:
(1) SAMUEL HENRY PAYNE
(2) JILLIAN SCOTNEY
(3) GARY MARK PAYNE
Claimants
AND
JOHN SETCHELL LIMITED
Defendant
- - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - -
Nicola Shaldon appeared for the claimants, instructed by Kenneth Bush, King's Lynn.
Owain Thomas appeared for the defendant, instructed by Hill Dickinson.
- - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - -
JUDGMENT
____________________
Crown Copyright ©
"Ground Investigation at Fair View Cottage, Engine Road, Ten Mile Bank, Downham Market
Thank you for your Instruction of 14 June 1988, to carry out the above.
We hope to visit the site week ending 17 June 1988 and carry out ground investigation consisting of hand augured 150mm diameter borehole in vicinity of extension and inspection of formation level of existing foundations.
Further to our telephone conversation today we have spoken with your Designer, Mike Hastings, and arranged for copies of his drawings to be forwarded to us direct.
On the basis of this, we shall prepare a report of the findings, together with recommendations for proposed foundations. Should you require more comprehensive site investigation, we would be pleased to offer names of Firms who specialise in this type of work.
Whilst the report and recommendations are intended for your advice and use. Copyright will be retained by John Setchell Limited and these should not be relied upon by any third party.
Fees will be related to the number of engineer hours occupied on the investigation, interpretations and preparation of report, however we estimate that our invoice will be in the order of £100.00 plus travelling at £0.25 per mile, laboratory analysis charges and VAT."
"Thank you for your instruction to carry out Ground Investigation at the above.
As you are aware we visited the site on Tuesday 21 June 1988 and excavated a hand augured 150mm diameter borehole.
For reference the plot fronts eastwards onto Engine Road.
Borehole was excavated by ourselves central to rear footing of proposed extension and revealed the following soil series:-
Topsoil and fill to 0.6 metres, over
Medium grey silt containing fragments indicating made ground to 1.7 metres, over
Organic peat material containing bog oak and fibrous material to 2.8 metres, over
Soft grey sand to borehole end at 3.0 metres
Water table stood at 2.2 metres below ground level.
Inspection of surrounding excavated trenches revealed brown silt layer which suggested that borehole had been excavated in old cesspit or soak-away.
From the findings of this investigation we conclude that ground at this site consists of silty soils overlying peat at 1.7 metres. Organic peat continues to 2.8 metres overlying soft running sand of unknown thickness.
The existing cottage is constructed at the foot of the bank of the River Ouse and is in a poor structural condition.
Building tilts westwards and walls are approximately 150mm out of plumb in this direction. Rear wall is propped by large buttress and front wall is severely bowed. Additionally water washing down bank has removed soil to front wall leaving voids under footings.
Trial pits to front of dwelling and new excavations to rear revealed that cottage has no footings and is constructed directly off silt material with walls approximately 3 courses below ground level.
Although a full survey was not carried out to the existing building, it clearly is in a poor state of disrepair.
In our opinion, traditional unreinforced concrete strip footings founded at approximate depth 0.9 metres at this site could not be depended upon to provide satisfactory long-term support for the proposed extension, as peat layer beneath may experience compaction due to increased load on foundations and additionally any seasonal variations in water table may cause shrinking and dwelling of peat resulting in unacceptable distortion and cracking of superstructure.
These recommendations are based on the findings of our site investigation. We point out that other conditions may exist elsewhere on the site of which we have no knowledge, and accept no responsibility.
We recommend that any extension to building should be constructed on independent raft foundation capable of distributing load over entire raft area with movement joints between new and existing structure.
However, due to leaning of building and position of buttress to rear wall we do not envisage that construction of raft foundation could be undertaken to extension without undermining existing structure.
Formation under raft would require excavation of approximately 700mm topsoil adjacent existing wall and removal of buttress. This would severely undermine existing foundation and may cause collapse or further distortion of wall.
In our opinion, construction of extension as shown on Mike Hastings drawing is not feasible for the following reasons:-
1. That new foundations unless piled, would undermine existing.
2. Plans show no provisions for existing buttress to rear wall and its removal is likely to cause damage to existing structure.
3. New internal party wall is required to existing structure which presents foundation problems.
4. Although a full survey was not undertaken the existing building is clearly in a poor state of disrepair and no guarantee that future movement will occur can be given. Due to peat layer beneath and high water table, underpinning of walls is impracticable.
Whilst not strictly in accordance with our Brief, it is our opinion that long-term structural stability of the existing structure could not be guaranteed without strengthening of existing foundations. This would involve costly underpinning works and we recommend that you give serious consideration to demolishing the structure.
We recommend that new dwelling on this site be provided with reinforced concrete raft foundation, capable of distributing superstructure load over the entire ground floor area, thus reducing imposed ground pressure, and additionally giving structural stiffness. We would recommend that such a foundation be designed by a Chartered Structural Engineer, and that construction of the foundation be carried out by a Contractor having proven experience of this type of work.
I trust that this is satisfactory, however, should you have any queries please do not hesitate to contact me."
"Thank you for your recent telephone message, following which we understand that the original cottage is to be demolished, with a new dwelling to be constructed at the site.
We would be pleased to design structural raft foundation for the new dwelling as recommended in our letter of 23 June 1988 and in order that we may proceed, will you please arrange for a copy of the Architectural drawings to be forwarded to us.
We would also visit the site during construction to inspect excavated ground ready for raft formation, and fixed steel reinforcement prior to concreting. Upon successful completion of these items we would provide a letter Certifying that this work had been carried out to our satisfaction.
Regarding our Fees, I suggest that these be calculated as outlined on the enclosed Conditions, and to assist your budgeting, I estimate that Fees will amount to approximately £500.00 plus expenses and VAT. Should it become apparent that this is going to vary significantly we will let you know.
In the past there have been some instances of misunderstanding regarding Instructions and we have adopted a policy of confirming Instructions in writing. Would you therefore be good enough to countersign the enclosed copy of this letter and return it in the envelope provided signifying that you find these Conditions acceptable and are responsible for settlement of our account.
The Conditions referred to in that letter included: -
"4. OWNERSHIP OF DOCUMENTS, COPYRIGHT AND RESPONSIBILITIES:
The Copyright in all drawings, reports, specifications, bills of quantities, calculations and other documents provided by the Consultant in connection with the Project shall remain vested in the Consultant, the Client having licence to copy and use such documents and to reproduce the designs contained in them for any purpose related to the Project.
The Consultant is responsible to carry out work as Briefed by the Client, exercising reasonable skill and care expected from a competent Engineer.
5. THIRD-PARTY APPROVALS:
When Applications is made to the Local Authority, N.H.B.C. etc., for Approvals to carry out works, any works commenced, materials ordered or abortive designs carried out prior to Approval shall be entirely at the Client's risk.
6. SUPERVISION AND CONSTRUCTION:
Civil and Structural work designed by the Firm, by its necessity often dictates a departure from traditional building practice. The Clients should therefore satisfy themselves that those who carry out constructions are competent and familiar with the type of work required.
Those carrying out construction are responsible for checking all dimensions prior to setting out or ordering materials. Any anomalies should be brought to the attention of the Engineers.
We recommend that a firm of Chartered Civil or Structural Engineers be engaged to inspect and advice at stages during constructions.
We accept no responsibility for items of construction not supervised by ourselves."
"As you are aware we visited site on Thursday 15th September 1988 to discuss and inspect raft formation with your Builder, Mr Payne.
Please find enclosed two copies of sketch SK1 showing increase in depth of hoggin where trench footings had previously been excavated for extension to existing building.
All back-fill material in trench should be removed and replaced with imported hoggin compacted in minimum 150mm layers. Sides from trench should be graded at 45o.
Elsewhere site has been stripped of topsoil revealing medium brown silts which will be satisfactory for raft formation.
We confirm that you will forward copy of sketch to your Builder.
Should any further problems arise on site we will be pleased to advise but in the meantime our next visit will be scheduled for inspection of fixed reinforcement to raft."
In that letter Mr Payne was described as Mr Wright's builder. When Mr Payne came to give evidence he was somewhat reticent about his involvement but his daughter, the second claimant, said that he was the builder and I have little doubt that for all practical purposes he should be regarded as the builder of the foundations, at least.
"I confirm that we visited the site during construction on 15 September and 11 October 1988 to inspect site stripped ready for construction, and fixed steel reinforcement ready for casting concrete.
I hereby certify that construction has been satisfactorily carried out to our design and as shown on drawing no. 3731/01A.
I trust that this is satisfactory. However, should you have any queries please do not hesitate to contact me."
"As discussed, you intend to construct a pair of dwellings as shown on Mike Hasting's building design services drawing 3259, foundation being shown on our drawing 3731/01A.
I confirm that we are happy with this arrangement, and that we will visit the site to inspect stripped ground, prior to placing hoggin fill, and also to inspect the fixed reinforcement prior to concrete casting. On satisfactory completion of this we will provide a Letter of Certification."
Mr Setchell duly inspected the site on 30 July and 16 August to examine the ground and the reinforcement respectively. For his own comfort Mr Setchell also investigated the ground with a hand auger which revealed silt and clay overlying peat at 1.2m adjacent to the foundation. He recorded this in his letter of 21 August 1990 in which he also said:-
"I hereby certify that the foundation constructed is as shown on our design drawing 3731/01A is to our satisfaction, and we believe is suitable for support of dwelling on ground conditions at the above site".
An identical letter was issued in respect of both Nos. 3 and 4 Fair View Cottages (as they have become).
"W H E R E A S
(1) The owner is desirous of building a semi-detached dwelling house on certain land situate at Engine Road, Ten Mile bank, Downham Market, in the County of Norfolk, and has caused drawings and specification setting forth the work to be done to be prepared.
(2) The builder has agreed to execute and carry out the said works in accordance with the said drawings and specifications for the sum of £20,000.00.
N O W I T I S H E R E B Y A G R E E D as follows:-
(1) The builder for the consideration of £20,000.00 (twenty thousand pounds) shall at his own proper costs and charges forthwith erect and build in a substantial and workmanlike manner upon the land of the owner outlined blue on the plan annexed hereto one semi detached dwelling house with outbuildings according to the several plans, elevations and specifications agreed by both parties, a copy of the plan being hereto annexed and subject to the directions of the said owner. The specification shall be as near as possible the same as for 1 and 2 Fair View Cottages, Engine Road, aforesaid excepting internal decoration and the supply of the storage heaters themselves.
(2) The plans detail drawings and specification shall be and remain the property of the owner but during the progress of the work the same shall be in the custody of the builder who shall deliver them to the owner when the contract shall have been performed. Should there be any discrepancy between the plans detail drawings and specification the specification shall prevail and be deemed to be correct and binding notwithstanding the drawings, subject however to any deviation, if any, stipulated by the owner.
(3) The owner shall give to the builder vacant possession of the site on or before the end of April 1991 and the builder shall complete the said dwelling houses with outbuildings so as to be fit for occupation and remove all surplus material, plant and rubbish from the site on or before that date. The builder will pay to the owner the sum of £200.00 per week for each week or part thereof that elapses from 30 April 1991 without the said buildings and works having been completed. In the event of monies being payable to the owner hereunder they shall be payable on completion of the said works and shall carry interest thereafter at 17% per annum.
(4) The builder shall provide all materials and scaffolding plant tools and tackle necessary for the purpose of completing the said dwelling houses and outbuildings. All such materials shall be the best of their respective kinds and shall be approved by the owner.
...
(6) The builder shall conform to the provisions of every Act of Parliament statutory instrument by-law or regulation for the time being in force affecting the said building or buildings and will give all necessary notices and obtain every requisite sanction in respect of the said works under every such statute instrument by-law or regulation and will keep the owner indemnified against all fines, penalties and loss incurred by reason of any breach of any such statute instrument by-law or regulation.
(7) If the owner shall require any deviation from the said plans, drawings and specification or any additional or other work to be done the builder will carry out the work according to such requirement and do the additional or other work in a substantial and workmanlike manner within the time prescribed by and to the satisfaction of any architect employed by the owner. No variation or deviation shall vitiate this agreement.
(8) In any of the following cases namely where delay is caused by (i) strike or lock-out of workmen (ii) accident to the works for which the builder is not responsible (iii) extras or variations or other reasonable cause the owner shall grant such extension of time for completion of the works as shall appear to him to be reasonable (and shall grant such an extension even though the date specified in clause 3 hereof has passed or the works have in fact been completed if in the circumstances of the case it shall appear reasonable to him to do so).
...
(10) The builder shall indemnify the owner against any liability, loss, claim or proceedings whatsoever whether arising by common law or by statute in respect of personal injury to or to the death of any person whom so ever arising out of or in the course of or caused by the execution of work unless due to any act or default of the owner or for any person for whom the owner is responsible under this contract and against all actions, claims and demands whatsoever to any third person arising out of or occasioned by the negligent, imperfect or improper performance of this contract by the builder, his workmen, servants or agents.
(11) In case of any dispute or difference shall arise between the parties hereto touching or relating either to the said buildings or works or to any other matter or thing arising under this contract the same shall be referred to an arbitrator to be nominated on the request of either parties or failing agreement between the parties by the President or the Vice-President for the time being of the Fellows of the Royal Institute of Chartered Surveyors whose aware shall be final and binding upon both the said parties. Such reference shall be deemed to be an arbitration pursuant to the Arbitration Act 1950 and or any statutory modification or re-enactment thereof for the time being in force.
(12) The Builder will cause the said works to be supervised by a qualified architect or chartered surveyor and any structural foundations by a structural engineer and will comply with their requirements and will provide with them that they shall issue appropriate certificates of completion and supervision and these certificates will be handed over to the owner and completion shall not be deemed to take place until these certificates are handed over to the owner.
The decision to buy No 3 preceded this contract so I do not accept that Mr Payne relied on the defendant's letter certificate of 21 August 1990 when deciding to buy, nor do I accept that in some way the prospect of obtaining such a certificate was influential since Mr Payne undertook in clause (12) that it would be obtained by him as a condition of his contract with Mr Wright, for the latter's benefit. The defendant was unaware of the terms of the contract, including clause (12). (I shall return to the terms of the building contract.)
"11A. At all material times Mr Wright and/or Mrs Gotobed relied upon the advice, drawings and certification of the Defendant as to the type of foundations, the design of the foundations, and adequacy of their construction and their suitability to provide adequate support for numbers 1, 2, 3 and 4.
12. At all material times, the Defendant knew or ought to have known that the foundations were to be for dwelling houses for occupation. When certifying that the concrete raft foundations were suitable for use as set out at Paragraphs 7 and 11 above, the Defendant thereby assumed responsibility for the suitability of the foundations to Mr Wright and/or Mrs Gotobed and to future owners of numbers 1, 2, 3 and 4.
12A. At all material times when acquiring the freeholds of numbers 1, 2 and 3 the claimants relied upon the said certification provided by the Defendant.
13. The Defendant owed a duty pursuant to Section 1 of the Defective Premises Act 1972 to all those thereafter acquiring an interest in the properties, which includes the claimants, to ensure that the work which they took on was done in a professional manner, and so that, as regards that work the dwellings would be fit for habitation when completed.
14. Further or alternatively, the Defendant owed the claimants a common law duty of care to act with reasonable care and skill and/or the claimants will rely on Section 3 of the Latent Damage Act 1986 in support of the contention that the claimants' causes of action against the Defendant (accrued under Section 3(1) of the 1986 Act) shall be treated as if based on a breach of a duty of care at common law owed by the Defendant to the claimants.
15. In the circumstances, the Defendant owed, and/or is to be taken to have owed, a duty at common law and/or under the Defective Premises Act to:-
(a) Ensure that the foundations would be good and sufficient to support the house without subsidence;
(b) Undertake sufficient investigations of the first site, and in particular, of the soil conditions, to enable them to make a proper informed decision as to the best form of foundations:
(c) Undertake sufficient investigations of the second site, and in particular, of the soil conditions, to ensure that the design used in the first construction was appropriate.
(d) Adequately supervise the construction of the foundation in order to ensure both that the structure was built in accordance with the design, and that the design was in fact appropriate.
(e) Exercise reasonable skill and care when certifying the adequacy of the foundations.
16. The Defendant was in breach of its statutory duty and/or duty of care in that the foundations were not designed/supervised in a professional manner and/or the dwelling houses were not fit for human habitation.
PARTICULARS
(a) Failing to make adequate enquiry; failing to carry out adequate borehole investigations of the first site: the Defendant carried out only one borehole investigation; this was contrary to good practice, particularly when it was in an area suspected to be a cesspit or soakaway;
(b) Failing to carry out adequate borehole investigation of the second site: the Defendant carried out two borehole investigations, but both were after the site had been stripped and neither established the thickness of the peat;
(c) Failing to realise the implications of the presence of peat in close proximity to the underside of the rafts - namely the risk of the peat compacting and consequent subsidence; the Defendant failed to heed the very poor bearing strata of the fibrous peat which existed immediately beneath the rafts;
(d) Failing to consider the removal of the peat and its replacement with compact hoggin;
(e) Failing to consider the use of pile and reinforced concrete beams;
(f) Failing to act in accordance with good practice and, in particular, Codes of Practice BS 8004 (Foundation), BS 6031 (Earthworks) and CP 2001 (Site Investigation);
(g) Failing to design a foundation adequate for its purpose; the raft foundations designed by the Defendant were not suitable and sufficient for their purposes, namely to support the properties without subsidence;
(h) Failing to observe or heed the inadequacy of the designs proposed for both the first and second sites.
(i) Certifying that the foundations were satisfactorily constructed and suitable for use when they were not.
17. By reason of the aforesaid the claimants have suffered loss and damage.
18. The claimants also claim interest pursuant to Section 35(A) of the Supreme Court Act 1981.
THE CLAIMANTS THEREFORE CLAIM AS FOLLOWS:-
(i) But for the Defendant's breach of statutory duty and/or negligence, the 1st claimant would have owned the freehold in a property worth £50,000. In the event, because of the tilting of the raft, number 1 requires piling. The remedial work required will also extend to the costs of making good the property by, inter alia, repairing the floor screeds and plaster work disturbed by the remedial work, and repairing damage to brickwork and external drains, plus the costing of gaining co-operation of the owners of the adjoining properties. In consequence of the above, the 1st claimant has suffered a diminution in value of number 1 of £25,000. Further and/or alternatively, the full cost of implementing the remedial works is likely to be in or about £25,000.
(ii) The loss to the 2nd claimant, calculated on the basis stated in paragraph (i) above, is £25,000
(iii) The loss caused to the 3rd claimant calculated on the basis stated in paragraph (i) above, is £25,000
(iv) Further each of numbers 1, 2 and 3 constitutes a risk of danger to its adjacent property, numbers 2, 3 and 4 respectively, and the claimants are entitled to an indemnity from the Defendant in respect of their liabilities to the owners of each adjacent property for the cost of rendering their properties safe:
(v) Further the 1st and 3rd claimants have suffered loss by reason of abortive attempts to sell their houses. Both sales fell through as a result of the tilting caused by the defendant's negligence.
(vi) Further, such of the claimants as are residing in the properties will suffer physical discomfort and inconvenience arising from the remedial works and claim damages in respect thereof.
(vii) Further the claimants are entitled to claim interest on the sum found to be due to him pursuant to S.35A of the Supreme Court Act 1981 for such period and at such rate as the Court deems fit."
"On the facts found in relation to the issues arising out of the matters pleaded at Paragraphs 1 to 15 of the Amended Particulars of Claim, the preliminary issues shall be as follows:-
1. Assuming that the defendant acted or did not act in the respects pleaded in the particulars in Paragraph 16 of the Amended Particulars of Claim and that the claimants suffered the losses claimed in Paragraph 17 of the Amended Particulars of Claim and the prayer, did the defendant owe a duty of care in negligence to any of the claimants in respect of his performance of the retainer[s] (including certification) described in the Amended Particulars of Claim? This issue is to include the following sub-issues:
(a) Did the defendant owe a duty of care to Mr Wright and/or Mrs Gotobed as alleged at Paragraph 15 of the Amended Particulars of Claim?
(b) If so, what were the nature and scope of the duties owed?
(c) Were the duties such as to ground causes of action for the losses set out at Paragraph 17 of the Amended Particulars of Claim and paragraphs (i) to (iii), (iv), (v) and (vi) of the prayer, namely
(i) damages in respect of the cost of the remedial work at, and/or diminution in value of, the properties of the claimants;
(ii) an indemnity from the defendant in respect of any contingent liability (to make the properties safe) owed to their neighbour(s);
(iii) damages in respect of the abortives sales;
(iv) damages in respect of any physical discomfort and/or inconvenience suffered as a result of any remedial works to the properties.
(d) When did the causes of action of Mr Wright and/or Mrs Gotobed against the defendant accrue?
(e) Did fresh causes of action against the defendant accrue to each of the claimants on the date of their acquisition of interests in the properties pursuant to section 3(1) of the Latent Damages Act?
(f) Did the defendant owe a duty of care to the claimants as alleged at Paragraph 15 of the Amended Particulars of Claim?
(g) If so, what were the nature and scope of the duties owed?
(h) Were the duties such as to ground causes of action for the losses set out at Paragraph 17 of the Amended Particulars of Claim and paragraphs (i) to (iii), (iv), (v) and (vi) of the prayer, namely
(i) damages in respect of the cost of the remedial work at, and/or diminution in value of, the properties of the claimants;
(ii) an indemnity from the defendant in respect of any contingent liability (to make the properties safe) owed to their neighbour(s);
(iii) damages in respect of the abortive sales;
(iv) damages in respect of any physical discomfort and/or inconvenience suffered as a result of any remedial works to the properties.
(i) Are the causes of action of the claimants referred to above time barred?
(j) Do the claimants fall within section 14A of the Limitation Act 1980 and/or section 3 of the Latent Damage Act 1986?
2. Are the claimants' causes of action under the Defective Premises Act time barred?"
"The issues raised in this case are difficult. The difficulties have been recognised for many years and, despite the efforts of the Law Commission, of the legislature and of the appellate courts, the difficulties have not been resolved. The complaint was made in Mr Duncan Wallace's article of January 1989 in the Law Quarterly Review, mentioned above, that:
"it is an astonishing and disturbing fact that litigants and their advisers still do not know in 1988 whether, in a typical foundations claim in tort brought against a negligent builder by a subsequent owner, there is, as a matter of law, liability for anticipatory repairs where the damage, as in both Dutton and Anns, is superficial and limited to the building itself".
The complaint seems to me justified and calls for urgent action."
Faced with such a formidable list of issues I echo the feelings of both Mr I.N.Duncan Wallace QC and Ralph Gibson LJ. Ironically Mr Duncan Wallace wrote in the year when the first two cottages were built. Over ten years later and despite at least two further decisions of the House of Lords about liability in such situations the answers to the issues raised by these typical claims are still not clear (or not as clear as they should be).
Nos 1 and 2 Fair View Cottages
Duty of care concurrent with duty in contract
"My own belief is that, in the present context, the common law is not antipathetic to concurrent liability, and that there is no sound basis for a rule which automatically restricts the claimant to either a tortious or a contractual remedy. The result may be untidy; but, given that the tortious duty is imposed by the general law, and the contractual duty is attributable to the will of the parties, I do not find it objectionable that the claimant may be entitled to take advantage of the remedy which is the most advantageous to him, subject only to ascertaining whether the tortious remedy is so inconsistent with the applicable contract that, in accordance with ordinary principle, the parties must be taken to have agreed that the tortious remedy is to be limited or excluded."
...
"But, for the present purposes more important, in the present case liability can, and in my opinion should, be founded squarely on the principle established in Hedley Byrne itself, from which it follows that an assumption of responsibility coupled with the concomitant reliance may give rise to a tortious duty of care irrespective of whether there is a contractual relationship between the parties, and in consequence, unless his contract precludes him from doing so, the plaintiff, who has available to him concurrent remedies in contract and tort, may choose that remedy which appears to him to be the most advantageous."
"The defendants there had in relation to the design been in contractual relations with the plaintiffs, but it was common ground that a claim in contract was time barred. If the plaintiffs happen to discover the defect before any damage had occurred there would seem to be no good reason for holding that they would not have had a cause of action in tort at that stage, without having to wait until some damage had occurred. They would have suffered economic loss through having a defective chimney upon which they required to expend money for the purpose of removing the defects. It would seem that in a case such as Pirelli, where the tortious liability arose out of a contractual relationship with professional people, the duty extended to take reasonable care not to cause economic loss to the client by the advice given. The plaintiffs built the chimney as they did on reliance on that advice. The case would accordingly fall within the principle of Hedley Byrne -v- Heller & Partners Ltd [1964] AC 465. I regard Junior Books Ltd v Veitchi Co. Ltd [1983] 1 AC 520 as being an application of that principle."
Many find great difficulty in accepting this analysis (as there are difficulties in seeing how on its facts Junior Books v The Veitchi Co [1983] 1 AC 520 can be justified by Hedley Byrne v Heller). Clerk & Lindsell on Torts, para 33-11, say that the observations are mysterious (see also Jackson & Powell on Professional Negligence, 4th ed., para 2-61). Liability for a negligent mis-statement stems from a voluntary assumption of responsibility towards the claimant which creates the special relationship. It is thus generally not found when the parties' relationship is governed by contract, especially if there is anything other than the simplest arrangement. That is not the case here, as the defendant's conditions show, although I do not accept Mr Thomas's argument that they exclude liability towards third parties. The provisions relied on (see paragraph 3 above) are standard provisions designed to define and to limit the use to be made of the defendant's products and services. The effect of Hedley Byrne has been re-stated on numerous occasions. For present purposes it is convenient to refer to part of the speech of Lord Browne-Wilkinson in White v Jones [1995] AC 207 at page 274:
"Let me now seek to bring together these various strands so far as is necessary for the purposes of this case: I am not purporting to give any comprehensive statement of this aspect of the law. The law of England does not impose any general duty of care to avoid negligent misstatements or to avoid causing pure economic loss even if economic damage to the plaintiff was foreseeable. However, such a duty of care will arise if there is a special relationship between the parties. Although the categories of cases in which such a special relationship can be held to exist are not closed, as yet only two categories have been identified, viz (1) where there is a fiduciary relationship and (2) where the defendant has voluntarily answered a question or tenders skilled advice or services in circumstances where he knows or ought to know that an identified plaintiff will rely on his answers or advice. In both these categories the special relationship is created by the defendant voluntarily assuming to act in the matter by involving himself in the plaintiff's affairs or by choosing to speak. If he does so assume to act or speak he is said to have assumed responsibility for carrying through the matter he has entered upon. In the words of Lord Reid in Hedley Byrne v Heller [1964] AC 465 at 486, he has 'accepted a relationship... which requires him to exercise such care as the circumstances require,' ie although the extent of the duty will vary from category to category, some duty of care arises from the special relationship. Such relationship can arise even though the defendant has acted in the plaintiff's affairs pursuant to a contract with a third party."
On the other hand there are a number of decisions where a liability akin to Hedley Byrne (perhaps justified by Donoghue v Stevenson) has been held to exist in circumstances comparable to those in Pirelli so Lord Keith's opinion about Pirelli may be valid, even though the facts do not obviously attract Hedley Byrne. The point is not academic although it might only have assisted the defendant's clients to avoid the period of limitation applicable to the primary case for breach of contract, as it is a necessary prelude to the consideration of the claimants' position. There is much less doubt about Pirelli as authority that the cause of action will arise at the date when the client decided to go ahead with the project in reliance on the advice and not when the damage was discovered. Neither Mr Wright nor Mrs Gotobed Wright appear to have suffered any damage in relation to Nos 1 and 2 at any date as a result of acting on that advice and would therefore have had no cause of action. (Mr Wright may have suffered damage in relation to No 4 but that is not directly the subject of this action; I deal later with his position in the context of No 3.)
"He who was responsible for the defect - and it will be convenient to refer to him compendiously as "the builder" - is, by the reasonable foreseeability of that injury, in a proximate neighbour relationship with the injured person on ordinary Donoghue v Stevenson principles".
"The foundation of the plaintiff's case is Anns -v- Merton London Borough Council [1978] AC 728. That decision was concerned directly only with the liability in negligence of a local authority in respect of its functions in regard to securing compliance with building bylaws and regulations. The position of the builder as regards liability towards a remote purchaser of a building which suffered from defects due to carelessness in construction was touched on very briefly. However, it has since been generally accepted that similar principles govern the liability both of the local authority and of the builder.
It has been held by this House in Murphy -v- Brentwood District Council [1991] 1 AC 398 that Anns was wrongly decided and should be departed from, by reason of the erroneous views there expressed as to the scope of any duty of care owed to purchasers of houses by local authorities when exercising the powers conferred upon them for the purpose of securing compliance with building regulations. The process of reasoning by which the House reached its conclusion necessarily included close examination of the position of the builder who was primarily responsible, through lack of care in the construction process, for the presence of defects in the building. It was the unanimous view that, while the builder would be liable under the principle of Donoghue -v- Stevenson [1932] AC 562 in the event of the defect, before it had been discovered, causing physical injury to persons or damage to property other than the building itself, there was no sound basis in principle for holding him liable for the pure economic loss suffered by a purchaser who discovered the defect, however such discovery might come about, and required to expend money in order to make the building safe and suitable for its intended purpose.
In the present case it is clear that the loss suffered by the Plaintiffs is pure economic loss. At the time the Plaintiffs carried out the remedial work on the concrete pillars the building was not unsafe by reason of the defective construction of these pillars. It did, however, suffer from a defect of quality which made the Plaintiffs' lease less valuable than it would otherwise have been, in respect that the building could not be loaded up to its design capacity unless any occupier who wished so to load it had incurred the expenditure necessary for the strengthening of the pillars. It was wholly uncertain whether during the currency of their lease the Plaintiffs themselves would ever be likely to require to load the building up to its design capacity, but a purchaser from them might well have wanted to do so. Such a purchaser, faced with the need to strengthen the pillars, would obviously have paid less for the lease than if they had been sound. This underlines the purely economic character of the Plaintiffs' loss. To hold in favour of the Plaintiffs would involve a very significant extension of the doctrine of Anns so as to cover the situation where there existed no damage to the building and no imminent danger to personal safety or health. If Anns were correctly decided, such an extension could reasonably be replaced as entirely logical. The undesirability of such an extension, for the reasons stated in Murphy -v- Brentwood District Council, formed an important part of the grounds which led to the conclusion that Anns was not correctly decided. That conclusion must lead inevitably to the result that Plaintiffs' claim fails."
"23. On this point Mr Wilkinson relies on Lancashire and Cheshire Association of Baptist Churches -v- Howard and Seddon Partnership [1993] All ER 467. In that case, the Defendant architects designed a new sanctuary for the Defendants' church and then, as the judge held, became 'for all practical purposes the contractor' under a special temporary employment programme operated by the Manpower Services Commission. There was a trial of two preliminary issues: (i) was the Plaintiffs' claim in contract statute-barred, and (ii) did the defendants owe to the Plaintiffs a concurrent duty in tort? At that trial, it was accepted that the claim in contract was barred.
In his judgment on the second issue Judge Michael Kershaw QC, sitting in the Queen's Bench Division at Manchester on official referees' business, held that, although there could be a concurrent duty in tort, the Defendant owed no duty of care to the Plaintiffs to prevent purely economic loss. His reasons can, I think, be summarised in the following propositions:
1. As a general rule, there is no liability in tort for economic loss (p.478c).
2. The relationship between the parties was not of the 'unique' or 'exceptional' kind exemplified in Junior Books Limited -v- Veitchi Company Limited [1982] 1 AC 520, which provides an exception to that general rule (p.479j).
3. What was said by Lord Keith in Murphy in the passage quoted in paragraph 22 above should be understood as providing an explanation for the result in the Junior Books case, rather than as stating doctrines of law to be derived from or supported by the Junior Books case (p.480h).
24. The difficulty which I have about that reasoning is that it treats the contractual relationship between the parties as irrelevant to the scope of the tort duty. Thus, proposition (1), however accurate a statement of the position when there is no contract between the parties, does not seem to me to be adequate when there is. As to (2), Junior Books was a non-contractual case, and indeed one of the ways in which it was 'unique' or 'exceptional' is commonly explained in later cases as lying precisely in the fact that the relationship between the parties was 'sufficiently akin' to contract to introduce the element of reliance (for example by Lord Bridge in Murphy at page 481D). As to (3), I do not understand Lord Keith to be concerned primarily with Junior Books, to which he devotes only a passing reference, and there is certainly no need to ascribe to him the intention of stating any doctrine of law as derived from or supported by it. What is clear, I think, is that he regarded Pirelli as a case in which a duty in tort to take reasonable care not to cause economic loss to the client arose out of a contractual relationship.
25. I do not, therefore, find myself able to follow the Lancashire and Cheshire Association case on this point. On the basis of the considerations and authorities canvassed in paragraphs 21 and 22 above I consider that, where there are concurrent duties in contract and tort to use due care and skill, the scope of the duty in tort is normally coterminous with that in contract. Whether or not I am right in believing that there is such a general principle, I conclude in particular that a designer's concurrent duty in tort to use due care and skill extends to taking care not to cause economic loss unless the contractual duty is more limited.
26. That being the responsibility of a professional designer, question (iv) asks whether the position of a builder who also designs is different. Mr Wilkinson submits that the effect of Murphy is that builders are in no circumstances under any non-contractual duty to safeguard against economic loss. It is therefore necessary to consider what were the facts and decision in that case. It was an action against a local authority for negligence in approving badly designed foundations, but the decision of the House of Lords proceeds on the basis that there cannot be a duty on the part of the local authority in such circumstances, unless the builder has a similar duty (see, for example, Lord Keith at page 469A, Lord Bridge at page 479C-F and Lord Oliver at page 483G). So far, therefore, there is no material distinction between the situations in that case and this. Moreover, the decision of the House of Lords was that there was no such duty in that instance.
27. In three respects, however, the facts were different from those in this case. In the first place, the builder in Murphy was not the designer of the defective foundations (see page 458B). Secondly, Mr Murphy had no contract with the designers, who, although defendants to the writ, were never served (see page 405B). Thirdly, although he bought his house from the builder, he bought it as a completed house and was not a party to a building contract (see page 404D). In the face of those distinctions, I do not see how Murphy can be a binding authority on the presence or absence of a concurrent common law duty on the part of a contractor designer-builder to use due care and skill to prevent economic loss from defective design.
28. Nor, apart from the question of direct authority, do I find anything in the reasoning which suggests the denial of such a duty. Both Lord Keity, at page 469A, and Lord Bridge, at page 475A, compare the position of a builder with that of the manufacturer of a chattel. In both cases (implicitly in that of Lord Keith, explicitly in that of Lord Bridge), it is clear that the obligations of the manufacturer are being considered in relation to an ultimate user with whom there is no contractual relationship. Lord Bridge, at page 480F, summarises the earlier decision of the House in D & F Estates Limited -v- Church Commissioners [1989] 1 AC 177 as being that a builder 'in the absence of any contractual duty or of a special relationship of proximity' owes no duty of care in tort in respect of the quality of his work. Lord Oliver, at page 489B, says that he is 'able to see no circumstances from which there can be deduced a relationship of proximity such as to render the builder liable in tort for pure pecuniary damage sustained by a derivative owner with whom he has no contractual or other relationship'. These passages all leave issues as to the existence and extent of any concurrent liability on the part of a contractor untouched.
29. There remains the question whether in principle a distinction should be drawn between the duty of a designer who is an independent professional and that of one who also builds. I can see no reason for such a distinction, which would introduce unnecessary and unacceptable anomalies between the position of employers who engaged architects and that of those who relied on builders who produced their own designs. It is true that a line must be drawn somewhere if builders are not to be concurrently liable in tort for all their contractual obligations, including workmanship as well as design, and including those which amount to warranties as well as those which can be expressed in terms of a duty of care, and that there may be apparent anomalies between cases on each side of that line, but that is inherent in the recognition of concurrent duties in tort matching some, but not all, contractual obligations. What is neither inherent nor justified is to create distinctions turning not on the content of the duty, but on the trade or profession of the person undertaking it.
30. I reach that conclusion on principle, because no authority bearing directly on this particular point was cited to me. I observe, however, that it is in accord with the judgment of Megaw LJ in Batty -v- Metropolitan Property Realisations [1978] 2 All ER 445, at page 453d-j, with which the other members of the Court of Appeal agreed, and which does not seem to be affected by the doubts cast on other aspects of that case in D & F Estates and Murphy; on the contrary, it is referred to by Lord Goff in Henderson (page 783B) without any suggestion of disapproval as one of the cases illustrating the development of concurrent liability.
31. I conclude that the concurrent duty in tort of a contractual designer to use due care and skill not to use economic loss is not displaced by the fact that the design is created by the builder.
32. Mr Wilkinson finally submitted that the decision as to the depth of the foundations was not a design decision. His reason was that it was one taken, not in the design department of the defendant, which apparently specified merely 'size and depth of foundation to suit site conditions', but by the site agent. There is nothing in this point. Specification of the type, size and depth of foundations is clearly a design decision and the design responsibility was that of the defendant company, regardless of its internal arrangements for the discharge of that responsibility..... .
"it would be remarkable to find that a similar obligation in the nature of a transmissible warranty of quality, applicable to buildings of every kind and subject to no such limitations or exclusions as are imposed by the Act of 1972 could be derived from the builder's common law duty of care...".
There is therefore in my judgment nothing in the speeches in either case which on their Lordships' reasoning justifies a distinction being made between the "designer" and the "builder", nor is there any operational, practical or social reason to do so.
"Although the judge held that the builders owed a duty to subsequent owners to take reasonable care to safeguard them from damage to the contents of the dairy, he held that they did not owe any duty to take reasonable care to safeguard them from damage to the dairy itself. I confess my instinctive reaction to that finding was one of unease and a desire to discover what policy considerations could lead to such a result. It seemed odd to exempt a builder for damage to the building which he had seen but fix him with liability for damage for the contents which he had not seen."
Schiemann LJ continued at page 102:
"In substance the judge applied a control device so as to achieve the result that the builders were not liable to subsequent owners for damage to the building itself. There being no evidence of any contractual exclusion cause which sought to exclude liability in tort, the case has proceeded on the basis that, had there been no change in ownership, the builders would have been liable to the original owners both in contract and in tort (Henderson -v- Merrett Syndicates Ltd [1995] 2 AC 145). Contract is irrelevant for present purposes but it is significant that the builders are assumed liable to the original owners in tort for damage to the building. The result of the judge's holding is that, although the builders were under a duty owed to the original owners to build the wall in such a way that it contained any fire for a certain period and although they broke that duty, the original owners cannot sue because they have suffered no damage and the subsequent owners cannot sue because the duty owed to them only extends to chattels in the building and not to the building itself. Whatever the justification is for coming to that result it cannot be either a desire not to increase the degree of care which the builders would need to exercise when building the wall or a desire not to increase the exposure of the builders to damages greater than those to which they would have been exposed had there been no change in ownership. As I have already indicated, had there been no change of ownership the builders would have been liable in tort for the damage to the building. Mr Stow was not in a position to indicate any consideration of policy which argued in favour of the judge's conclusion but submitted that that conclusion was one to which the judge rightly recognised that he was compelled to come by reason of the speeches in Murphy -v- Brentwood".
Schiemann LJ examined all the leading authorities. In the course of doing so he said (at page 104):-
"7. The whole of the discussion in the speeches about complex structures is premised on the assumption that it matters in cases where actual damage has been caused whether that damage is to the very defective article or building or whether it is to something or someone else - see especially the speech [in Murphy] of Lord Bridge between pages 476 and 479 and that of Lord Jauncey between pages 496B and 497D."
"It is these difficulties which I think justify the policy which prevents recovery in tort against the builder in this case for defects in the building which have caused damage to it. I do not think it is an answer to say that the original contracting party may be owed a concurrent duty in tort and so why should the same duty not be owed to his successor in title? This is still an undeveloped area of the law and in practice the builder may well be able to exclude such liability by his contract."
Schiemann LJ concluded his judgment:-
"However in the present case the whole of the dairy was built at the same time by the builders, marketed as a unit, bought as a unit to be used as a unit and was used as a unit. I have no doubt that any holding either that (1) the rooms on one side of the wall should be treated for present purposes as constituting a different building from the rooms on the other side of the wall or that (2) the walls should be treated as constituting a different building from the rooms on one side of it, would be a thoroughly undesirable approach to the issues before us".
In my judgment Bellefield provides a useful and powerful illustration of the effect of Murphy in that a builder (in the sense that I have used) although responsible for a matter of design was not liable for defects in the building itself.
(a) No; the defendant owed Mr Wright or Mrs Gotobed Wright a duty at common law to exercise reasonable professional skill and care and judgment:
(i) in carrying out in June 1988 the site investigation and in reporting on the proposal to extend Fair View Cottage; such a duty was to avoid causing loss and damage to either resulting from reliance on that investigation and report;
(ii) in designing in July 1988 a foundation which would be reasonably suitable for Mr Wright's proposed design for two new cottages on the site of Fair View Cottages;
(iii) in inspecting in September and October 1988 the excavated ground ready for the raft foundation and the fixed steel reinforcement prior to concreting;
(iv) on completion of the formation and the fixing of reinforcement, in issuing the letter of 20 October 1988 certifying that such work had been carried out to the defendant's satisfaction;
but the duties in (ii) to (iv) were to avoid causing physical injury or loss and damage to other property that might result from failure to carry out the duty properly.
(b) See above.
(d) On the assumptions to be made, and if there had been a cause of action: (i) and (ii) in July 1988, (iii) in September or October 1988; (iv) October 1988.
"If the same principle applies in this field of real property to the liability of the builder of a permanent structure which is dangerously defective, that liability can only arise if the defect remains hidden until the defective structure causes personal injury or damage to property other than the structure itself. If the defect is discovered before any damage is done, the loss sustained by the owner of the structure, who has to repair or demolish it to avoid a potential source of danger to third parties, would seem to be purely economic. Thus, if I acquire a property with a dangerously defective garden wall which is attributable to the bad workmanship of the original builder, it is difficult to see any basis in principle on which I can sustain an action in tort against the builder for the cost of either repairing or demolishing the wall. No physical damage has been caused. All that has happened is that the defect in the wall has been discovered in time to prevent damage occurring. I do not find it necessary for the purpose of deciding the present appeal to express my concluded view as to how far, if at all, the ratio decidendi of Anns -v- Merton London Borough Council [1978] AC 728 involves a departure from this principle establishing a new cause of action in negligence against a builder when the only damage alleged to have been suffered by the Plaintiff is the discovery of a defect in the very structure which the builder erected.
My example of the garden wall, however, is that of a very simple structure. I can see that more difficult questions may arise in relation to a more complex structure like a dwelling-house. One view would be that such a structure should be treated in law as a single indivisible unit. On this basis, if the unit becomes a potential source of danger when a hitherto hidden defect in construction manifests itself, the builder, as in the case of the garden wall, should not in principle be liable for the cost of remedying the defect. It is for this reason that I now question the result, as against the builder, of the decision in Batty -v- Metropolitan Property Realisations Ltd [1978] QB 554.
However, I can see that it may well be arguable that in the case of complex structures, as indeed possibly in the case of complex chattels, one element of the structure should be regarded for the purpose of the application of the principles under discussion as distinct from another element, so that damage to one part of the structure caused by a hidden defect in another part may qualify to be treated as damage to "other property", and whether the argument should prevail may depend on the circumstances of the case. It would be unwise and it is unnecessary for the purpose of deciding the present appeal to attempt to offer authoritative solutions to these difficult problems in the abstract. I should wish to hear fuller argument before reaching any conclusion as to how far the decision of the New Zealand Court of Appeal in Bowen -v- Paramount Builders (Hamilton) Ltd should be followed as a matter of English law. I do not regard Anns -v- Merton London Borough Council as resolving that issue".
Lord Oliver in his speech agreed that that was the possible basis upon which a builder might be liable at common law for negligence which caused damage to personal property (see page 214 B-D). In Warner v Basildon Corporation (1990) 6 Const LJ 146 Ralph Gibson LJ (who gave the leading judgment) said:
"Guided by the sense of the speeches in D & F Estates, as I understand them, I would apply the first principles there explained by Lord Bridge. The theory of complex structures - and, I would add, of complex chattels - as a general concept forms, in my judgment, no part of those principles".
"If a builder erects a structure containing a latent defect which renders it dangerous to persons or properties, he will be liable in tort for injury to persons or damage to property resulting from that dangerous defect. But if the defect becomes apparent before any injury or damage has been caused, the loss sustained by the building owner is purely economic. If the defect can be repaired at an economic cost, that is the measure of the loss. If the building cannot be repaired, it may have to be abandoned as unfit for occupation therefore valueless. These economic losses are recoverable if they flow from breach of a relevant contractual duty, but, here again, in the absence of a special relationship or proximity they are not recoverable in tort. The only qualification I would make to this is that, if a building stands so close to the boundary of the building owner's land that after discovery of the dangerous defect it remains a potential source of injury to persons or property on neighbouring land or on the highway, the building owner ought, in principle, to be entitled to recover in tort from the negligent builder the cost of obviating the danger, whether by repair or demolition, so far as the cost is necessarily incurred in order to protect himself from potential liability to third parties."
"For these reasons, the complex structure theory offers no escape from the conclusion that damage to a house itself which is attributable to a defect in the structure of the house is not recoverable in tort on Donoghue -v- Stevenson principles, but represents purely economic loss which is only recoverable in contract or in tort by reason of some special relationship of proximity which imposes on the tort feasor a duty of care to protect against the economic loss."
Lord Oliver also disavowed the complex structure theory - see page 484D-485B. Later in his speech Lord Oliver said (at page 490E):
"Take the simple case of the builder who built a house within adequate foundations and presents it to his son and daughter-in-law as a wedding present. It would be manifestly absurd, if the son spends money on rectifying the defect which has come to light, to hold him entitled to recover the expenditure from his father because the gift turns out to be less advantageous than he at first supposed."
However Lord Keith, Lord Bridge, and Lord Jauncey left open the possibility of liability for "another part" of the building. For example Lord Jauncey said at page 497:-
"My Lords, I agree with the views of my noble and learned friend, Lord Bridge of Harwich, in this appeal that to apply the complex structure theory to a house so that each part of the entire structure is treated as a separate piece of property is quite unrealistic. A builder who builds a house from foundations upwards is creating a single integrated unit of which the individual components are interdependent. To treat the foundations as a piece of property separate from the walls or the floors is a wholly artificial exercise. If the foundations are inadequate the whole house is affected. Furthermore, if the complex structure theory is tenable there is no reason in principle why it should not also be applied to chattels consisting of integrated parts such as a ship or a piece of machinery. The consequences of such application would be far reaching. It seems to me that the only context for the complex structure theory in the case of the building would be where one integral component of the structure was built by a separate contractor and where a defect in such a component had caused damage to other parts of the structure, eg, a steel frame erected by a specialist contractor which failed to give adequate support to floors or walls. Defects in such ancillary equipment - such as central heating boilers or electrical installations would be subject to the normal Donoghue and Stevenson principle if such defects gave rise to the damage in other parts of the building."
Latent Damage Act
Accrual of cause of action to successive owners in respect of latent damage to property.
3. (1) Subject to the following provisions of this section, where -
(a) a cause of action ("the original cause of action") has accrued to any person in respect of any negligence to which damage to any property in which he has an interest is attributable (in whole or in part); and
(b) another person acquires an interest in that property after the date on which the original cause of action accrued but before the material facts about the damage have become known to any person who, at the time when he first has knowledge of those facts, has any interest in the property;
a fresh cause of action in respect of that negligence shall accrue to that other person on the date on which he acquires his interest in the property.
(2) A cause of action accruing to any person by virtue of subsection (1) above-
(a) shall be treated as if based on a duty of care at common law owed to the person to whom it accrues; and
(b) shall be treated for the purposes of section 14A of the 1980 Act (special time limit for negligence actions where facts relevant to cause of action are not known at date of accrual) as having accrued on the date on which the original cause of action accrued.
(3) Section 28 of the 1980 Act (extension of limitation period in case of disability) shall not apply in relation to any such cause of action.
(4) Subsection (1) above shall not apply in any case where the person acquiring an interest in the damage property is either -
(a) a person in whom the original cause of action vests by operation of law; or
(b) a person in whom the interest in that property vest by virtue of any order made by a court under section 538 of the Companies Act 1985 (vesting of company property in liquidator).
(5) For the purposes of subsection (1)(b) above, the material facts about the damage as would lead a reasonable person who has an interest in the damaged property at the time when those facts become known to him to consider it sufficiently serious to justify his instituting proceedings for damages against a defendant who did not dispute liability and was able to satisfy a judgment.
(6) For the purpose of this section a person's knowledge includes knowledge which he might reasonably have been expected to acquire-
(a) from facts observable or ascertainable by him; or
(b) from facts ascertained by him with the help of appropriate expert advice which
but a person shall not be taken by virtue of this subsection to have knowledge of a fact ascertainable by him only with the help of expert advice so long as he has taken all reasonable steps to obtain (and, where appropriate, to act on) that advice.
...."
"The statutory development enacted by the Defective Premises Act 1972 effected clear and precise changes in the law imposing certain specific statutory duties subject to carefully defined limitations and exceptions. This change did not, of course, operate retrospectively. The common law developments have effected changes in the law which inevitably lack the kind of precision attainable by statute though limits have had to be and are still being worked out by decisions of the courts in a spate of ensuing litigation, including the instant case, and since our jurisprudence knows nothing of the American doctrine of "prospective overruling" and the law once pronounced authoritatively by the courts here is deemed always to have been the law, the changes have full retrospective operation".
Direct Duty of Care
(1) The purpose for which the statement was made;
(2) The purpose for which the statement was communicated;
(3) The advisee and any relevant third party;
(4) The size of any class to which the advisee belongs;
(5) The state and knowledge of the advisor;
(6) Reliance by the advisee.
In my view these factors are important but do not adversely affect the claimant's case. In the case of (1) Neill LJ pointed out that "in many cases, however, the statement will have been prepared or made, or primarily prepared or made, for a different purpose and for the benefit of someone other than the advisee. In such cases it will be necessary to look carefully at the precise purpose for which the statement was communicated to the advisee."
"I see the force of the argument that Mrs Adams was likely to show the letter to a third person. If she had wanted to know about the progress of the works only for her own information she could have asked her husband. But in my judgment it does not follow, even if one postulates that the classes of person to whom the letter might be shown included the purchaser and the purchaser's advisers as well as the bank or other institution which was supplying funds to Mrs Adam, that Mr Bannister had "undertaken a responsibility" towards the purchaser in the sense in which that phrase was used by Lord Goff in Henderson -v- Merrett Syndicates Ltd [1995] 2 AC 145 at page 180. It is to be remembered that Mr Bannister knew nothing of the reference to him in the supplemental contract of 30 December 1992.
I would start with the general proposition that if an adviser to one party to a transaction gives advice to that party his duty is prima facie to that party alone. But this general proposition has to be considered in the light of the recent authorities. First, it is clear that if the adviser to one party to a transaction makes a careless misrepresentation which that party communicates to the other party in circumstances which would make the first party liable for its accuracy to the other party, the adviser may be liable as well as his principal: cf Hobhouse LJ in McCullagh -v- Lane Fox [1996] 1 EGLR 35 at page 44. Secondly, the words "assumption of responsibility" must be understood in the sense of a conscious assumption of responsibility for the task rather than a conscious assumption of legal liability to the plaintiff for the careful performance of the task: see Lord Browne-Wilkinson in White -v- Jones [1995] 2 AC 207 at page 273. The court must therefore examine all the circumstances of the case. Thus, in my judgment, in order to establish liability against the adviser in a case such as the present the advisee must show some connecting thread between the task the adviser has undertaken to perform and the course of action upon which the advisee can be foreseen to be likely to embark.
Of course in some cases an adviser will provide information to his client in the knowledge that a third party will learn of and rely on that advice and in reliance on it will take an anticipated course of action. The adviser knows the purpose of the advice and the purpose for which it will be used by the third party. The knowledge may be actual or inferential. The mortgage cases fall into this category. But in order for the adviser to be liable to the advisee it seems to me that, if one applies Lord Oliver's criteria, he must have actual or inferential knowledge not only that the advice will be communicated to the advisee but also knowledge of the purpose for which the information is required by the advisee. It is only such circumstances that there is room for a finding that the adviser has undertaken responsibility to the advisee in respect of some foreseeable loss.
In the present case Mr Bannister was not giving advice as to whether a particular course of action should be taken. At its highest his duty was to supply information for the purpose of enabling someone else to decide upon a course of action. Accordingly, in order to determine the scope, and indeed the existence, of any duty owed by him to Mrs Machin, it is necessary to look closely at the consequences for which in the circumstances Mr Bannister could properly be held responsible if the information provided by him proved to be inaccurate.
By 13 January Mr Bannister knew that the property was to be sold. Let it be assumed that he also knew or should have foreseen that the letter might be shown to the purchaser. But against what harm was Mr Bannister to be regarded as having undertaken to guard Mrs Machin? Was the letter a signal on which she could rely to go ahead with the purchase without any further enquiry? The fact that Mr Bannister was due to carry out another inspection with a view to providing a final certificate puts the answer to the second question beyond doubt. But even without the additional and overwhelming factor of the impending final certificate I would hold that on the facts of this case Mr Bannister owed no duty of care to Mrs Machin in relation to the letter of 13 January 1993".
(f) The defendant owed a duty of care to the claimants (and any person likely to lend money secured on the house) as described under (g) below. The defendant also owed a duty of care under the Defective Premises Act 1972 in respect of the duties undertaken by him as set out in answer to (a) above.
(g) A duty to take care that the statements made in the letter certificate were reliable; that the design had been prepared with reasonable care and, in so far as the designer had investigated the ground conditions, that reasonable care had been taken in the investigation and that the design was reasonably based on it.
Limitation
Issue 2: The Defective Premises Act 1972
"Duty to build dwellings properly
(1) A person taking on work for or in connection with the provision of a dwelling (whether the dwelling is provided by the erection or by the conversion or enlargement of a building) owes a duty -
(a) if the dwelling is provided to the order of any person, to that person;
and
(b) without prejudice to paragraph (a) above, to every person who acquires an interest (whether legal or equitable) in the dwelling;
to see that the work which he takes on is done in a workmanlike or, as the case may be, professional manner, with proper materials and so that as regards that work the dwelling will be fit for habitation when completed.
(2) A person who takes on any such work for another on terms that he is to do it in accordance with instructions given by or on behalf of that other shall, to the extent to which he does it properly in accordance with those instructions, be treated for the purposes of this section as discharging the duty imposed on him by subsection (1) above except where he owes a duty to that other to warn him of any defects in the instructions and fails to discharge that duty.
(3) A person shall not be treated for the purposes of subsection (2) above as having given instructions for the doing of work merely because he has agreed to the work being done in a specified manner, with specified materials or to a specified design.
(4) A person who -
(a) in the course of a business which consists of or includes providing or arranging for the provision of dwellings or installations in dwellings;
or
(b) in the exercise of a power of making such provision or arrangements conferred by or by virtue of any enactment;
arranges for another to take on work for or in connection with the provision of a dwelling shall be treated for the purposes of this section as included among the persons who have taken on the work.
(5) Any cause of action in respect of a breach of the duty imposed by this section shall be deemed, for the purposes of the Limitation Act 1939, the Law Reform (Limitation of Actions, &c) Act 1954 and the Limitation Act 1963, to have accrued at the time when the dwelling was completed, but if after that time a person who has done work for or in connection with the provision of the dwelling does further work to rectify the work he has already done, any such cause of action in respect of that further work shall be deemed for those purposes to have accrued at the time when the further work was finished".
"It was submitted - and it seems to be correct although surprising - that the time is not extended by section 14(A) of the 1980 Act (inserted by the Latent Damage Act 1986) because the claim under the Defective Premises Act 1972 is not an "action for damages for negligence"."
In Société Commerciale de Réassurance v ERAS (International) and Others [1992] 2 All ER 82 the Court of Appeal had to consider the ambit of section 14A. Mustill LJ said at page 85:-
"This question whether s14A applies to contractual claims is by no means straightforward. The different treatment for limitation purposes of claims in contract and in tort is already unsatisfactory because: (1) whatever the legal logic, the fact that claims in contract and in tort between the same parties arising out of the same facts become time-barred on dates which may well be years apart offends common sense; (2) the existence of different rules for what may really be the same claims forces the law into unnatural complications. Whatever the historical justification for holding that there are concurrent rights of action in contract and tort, nobody we believe would trouble nowadays to insist on the difference, but for the fact that one form of claim (usually the one in tort) offers procedural advantages. This is not a sound basis for the development of a practical and self-consistent law of negligence; (3) so far as limitation is concerned, the rules regarding the accrual of the cause of action tend to push the evolution of substantive law in the wrong direction. In most if not all cases a plaintiff will be better off by framing his action in tort, whereas, in our judgment, if a contract is in existence this is the natural vehicle for recourse.
Whilst these features are firmly embedded in the law, at least so far as this court is concerned, we have no enthusiasm for attributing to s14A a meaning which, if the respondents are right, will enhance the practical attraction of a claim in tort. Nevertheless, we find it impossible to resist the conclusion, in company with the learned judge and also with Mr Kenneth Rokison QC, sitting as a deputy judge of the High Court in Iron Trade Mutual Insurance Co Ltd v J.K. Buckenham Ltd [1990] 1 All ER 808, that as a matter of language s14A cannot be applied to actions in contract. Even when the section is read in isolation, the words 'any action for damages in negligence' denote to our minds an action asserting that the defendant has committed the tort of negligence, and are not wide enough to comprise what is often (albeit inaccurately) called 'contractual negligence'. This reading is reinforced by the express overriding of the ordinary provision for tort claims in s2, coupled with the absence of any overriding of the provision for the contractual claim in s5.
The position becomes even clearer when reference is made to s11 of the 1980 Act. The special regime thereby created for personal injury claims is expressed to apply -
'(1) .... to any action for damages for negligence, nuisance or breach of duty (whatever the duty exists by virtue of a contract or of provision made by or under a statute or independently of any contract or any such provision)....'
We find it impossible to accept that, when the draftsman of the 1986 Act came to prepare the new s14A for insertion in the 1980 Act, he ignored the precedent supplied by s11, and assumed that the naked word 'negligence' would suffice to denote a breach of contractual duty, of a kind which in s11 had been thought worthy of special mention. The contrast in language must, as it seems to us, reflect a distinction in the kinds of claim to which the different methods of enlarging time are to apply.
This conclusion was resisted by Clarksons principally on the ground that it is based too narrowly on the words of the statute, and pays insufficient regard to the mischief which s14A was designed to correct, namely the barring of claims before the injured party knows that he has a claim to assert. We cannot agree, for Clarkson's proposition states the mischief in terms which are too wide. The insertion of s14A stemmed from the Law Reform Committee's 24th Report (Latent Damage) (Cmnd 9390), which took up again the question of latent damage which had been left unresolved in the committee's 21st Report of 1977 (Final report on Limitation of Actions) (Cmnd 6923). Whilst this work was in progress there were a number of important decisions in this field, notably Pirelli General Cable Works Ltd v Oscar Faber & Partners (a firm) [1983] 2 AC 1, and this led to the canvassing of various possible solutions. It is quite plain, on reading the report as a whole (and in particular para 4.4) that with the exception of one solution considered and rejected at para 3.17(b) the committee was occupied solely with claims arising in tort. We do not find this surprising. In latent damage claims, the claim in tort will either be equal or superior to that in contract from a limitation point of view. If faced with a time bar, the plaintiff will concentrate on his cause of action in tort, and will have nothing to gain by deploying a claim in contract as well (if indeed he has a contract with the defendant, which he often will not); so that it would be natural for the committee to focus its attention accordingly.
Thus, if the words of the section had been sufficiently ambiguous to require recourse to its origins, we should have held that such recourse did not assist the appellants. In the event however we are content to rest on the words themselves, which are quite clear."
Nos 3 Fair View Cottages
58,. The nature and scope of the duties owed by the defendant to Mr Payne were thus essentially the same as those which the defendant had undertaken for Mr Wright or Mrs Gotobed Wright except that, of course, the defendant was specifically required not to carry out a site investigation (although he did so for his own purposes) and therefore was to assume, vis a vis Mr Payne, that the site conditions were those which had been discovered originally. There was therefore no reliance on the defendant, no assumption of responsibility, and no liability to Mr Payne (or Mr Wright) of the kind previously described in answer to issue 1(a). The defendant's liability under the Defective Premises Act 1972 is thus not as extensive in relation to No 3 as it is or may be in relation to Nos 1 and 2. The defendant's duty to take care in the preparation of the design may, thus be attenuated if it were to appear that had the additional fee been paid the defendant would have carried out a more extensive site investigation than was ultimately done, voluntarily, and that such a site investigation would have revealed conditions which would have led a prudent engineer not to continue with the proposal to use the same raft foundation design. The defendant's contractual duties towards Mr Payne in relation to the inspection of the ground and of the reinforcement and in providing a certificate were however identical to those undertaken for Nos 1 and 2. The answer to sub-issue (a) in relation to No 3 Fair View Cottage is: No, but the defendant owed Mr Payne the duties set out in (a)(ii)-(iv).
"But if the sub-contracted work or materials do not in the result conform to the required standard, it will not ordinarily be open to the building owner to sue the sub-contractor or supplier direct under the Hedley Byrne principle. Claiming damages from him on the basis that he has been negligent in relation to the performance of his functions. For there is generally no assumption of responsibility by the sub-contractor or supplier direct to the building owner, the parties having so structured their relationship that it is inconsistent with any such assumption of responsibility."
Answers to Issues
1. The defendant owed a duty of care to each claimant in respect of the performance of his retainer to issue a certificate on completion of the foundations as set out in (g) below.
The answers to the sub-issues are:
In relation to Nos 1 and 2 and the claims of the first and second claimant:
(a) No; the defendant owed Mr Wright or Mrs Gotobed Wright a duty at common law to exercise reasonable professional skill and care and judgment:
(i) in carrying out in June 1988 the site investigation and in reporting on the proposal to extend Fair View Cottage; such a duty was to avoid causing loss and damage to either resulting from reliance on that investigation and report;
(ii) in designing in July 1988 a foundation which would be reasonably suitable for Mr Wright's proposed design for two new cottages on the site of Fair View Cottages;
(iii) in inspecting in September and October 1988 the excavated ground ready for the raft foundation and the fixed steel reinforcement prior to concreting;
(iv) on completion of the formation and the fixing of reinforcement, in issuing the letter of 20 October 1988 certifying that such work had been carried out to the defendant's satisfaction;
but the duties in (ii) to (iv) were to avoid causing physical injury or loss and damage to other property that might result from failure to carry out the duty properly.
In relation to No 3 and the claim of the third claimant:
(a) No, but the defendant owed Mr Payne the duties set out in (a)(ii)-(iv).
(b) See above.
(c) No, except in relation to the duty set out in answer to issue 1(a)(i).
(d) In relation to Nos 1 and 2: On the assumptions to be made, and if there had been a cause of action: (a)(i) and (ii) in July 1988, (iii) in September or October 1988; (iv) October 1988.
(e) No.
(f) The defendant owed a duty of care to the claimants (and any person likely to lend money secured on the house) as described under (g) below. The defendant also owed a duty of care under the Defective Premises Act 1972 in respect of the duties undertaken by him as set out in answer to (a) above.
(g) A duty to take care that the statements made in the letter certificate were reliable; that the design had been prepared with reasonable care and, in so far as the designer had investigated the ground conditions, that reasonable care had been taken in the investigation and that the design was reasonably based on it.
(h) Yes, but only as regards (i) and then in respect only of the loss in value of the property measured by reference to the costs of the remedial work to the property or otherwise and assessed at the date when the property was bought, (iii) and (iv).
(i) Yes, but subject to (j):
(j) Each claimant falls within section 14(A) of the Act.
2. Yes.