England and Wales High Court (Technology and Construction Court) Decisions
You are here:
BAILII >>
Databases >>
England and Wales High Court (Technology and Construction Court) Decisions >>
Alstom Combined Cycles Ltd v. Henry Boot Plc [2001] EWHC Technology 428 (1st May, 2001)
URL: http://www.bailii.org/ew/cases/EWHC/TCC/2001/428.html
Cite as:
[2001] EWHC Technology 428
[
New search]
[
Help]
Alstom Combined Cycles Ltd v. Henry Boot Plc [2001] EWHC Technology 428 (1st May, 2001)
IN THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION
COURT
BEFORE: HIS HONOUR JUDGE
RICHARD SEYMOUR Q.C.
BETWEEN:
|
ALSTOM
COMBINED CYCLES LIMITED
|
Claimant
|
|
and
|
|
|
HENRY
BOOT PLC
|
Defendant
|
AND BETWEEN:
|
ALSTOM
COMBINED CYCLES LIMITED
|
Claimant
|
|
and
|
|
|
AEGON
INSURANCE COMPANY (UK) LIMITED
|
Defendant
|
Cases numbers: HT 00/299 and HT 00/300
Dates of Trial: 2 April 2001
Date of Judgment: 1 May 2001
Roger ter Haar Q.C. for
the claimant in both actions (Lovells, Solicitors)
Stephen Furst Q.C. for the defendant in action HT 00/299 (Taylor Joynson Garrett,
Solicitors)
Michael Bowsher for the defendant in action HT 00/300 (Manches, Solicitors)
JUDGMENT
I direct
that no further note or transcript be made of this judgment.
The text of the Judgment
of His Honour Judge Richard Seymour Q.C. is as follows:
JUDGMENT
Introduction
- By an agreement, called
the Main Civil Works Contract ("the Main Contract"), dated 21 March
1994 and made between Alstom Combined Cycles Ltd. ("Alstom"), called
at that time GEC Alsthom Combined Cycles Ltd., and Henry Boot Construction
Ltd. ("Construction") Construction agreed with Alstom to carry out
the principal works of civil construction at Connah's Quay Power Station in
Clwyd, North Wales. The Main Contract incorporated the standard form Institution
of Civil Engineers Conditions of Contract, 6th edition, with amendments.
In this judgment I shall call that standard form as amended "the Conditions".
Latterly the person named as "the Engineer" for the purposes of the
Main Contract has been Mr. A.J. Cort.
- Construction is a subsidiary
of Henry Boot Plc ("Boot"). Boot entered into a deed ("the Guarantee")
dated 24 June 1994 with Alstom by which it provided a guarantee in support
of the Main Contract.
- Construction and Aegon
Insurance Company (UK) Ltd. ("Aegon") entered into a bond ("the
Bond") dated 23 May 1994 with Alstom in connection with the execution
of the works the subject of the Main Contract. In this judgment I shall call
those works "the Works".
- A number of disputes
have arisen between Alstom and Construction which have been referred to arbitration.
Some awards have already been made and other arbitration proceedings are pending.
It appears that Mr. Cort, as the Engineer for the purposes of the Main Contract,
is continuing to consider the question whether extensions of time for completion
should be granted in relation to certain sections of the Works.
- The present actions were
each commenced by a claim form issued on 2 August 2000. In each action Particulars
of Claim were served on 11 August 2000. In action number HT 00/299 ("the
First Action") Alstom claims payment by Boot under the Guarantee of a
sum of £2,016,000. That sum is alleged to be due in respect of liquidated
damages which Construction should have paid under the Main Contract for failure
to complete particular sections of the Works by the dates specified for completion
of those sections in the Main Contract. In the light of extensions of time
granted by Mr. Cort since the commencement of the First Action, so I was told
by Mr. Roger ter Haar Q.C., who appeared on behalf of Alstom, Alstom does
not seek to recover more in the First Action than £1,620,000. Boot seeks a
stay of proceedings in the First Action under the inherent jurisdiction of
the Court essentially on the ground that the issues which it would be necessary
to investigate in the First Action duplicate to a substantial extent issues
already live in pending arbitration proceedings between Construction and Alstom.
In action number HT 00/300 ("the Second Action") Alstom claims against
Aegon payment of the sum of £2,016,000 under the Bond. Again the alleged foundation
for the claim is that Construction should have paid liquidated damages under
the Main Contract in respect of its failure to complete sections of the Works
by the dates specified in relation to those sections in the Main Contract.
Again Mr. ter Haar told me that, in the light of extensions of time granted
by Mr. Cort since the commencement of the Second Action, the sum claimed against
Aegon is limited to £1,620,000. Aegon seeks a determination under Part 24
of Civil Procedure Rules that, in the circumstances Alstom has no cause
of action against Aegon. In the alternative, Aegon seeks a stay of proceedings
in the Second Action on essentially the same grounds as those relied upon
by Boot in support of its application in the First Action.
The relevant terms of
the Main Contract
- By clause 43 of the Conditions
it was provided that:-
"The whole of the Works
and any Section required to be completed within a particular time as stated
in the Appendix to the Form of Tender shall be substantially completed as
defined in Attachment E to these Conditions within the time so stated (or
such extended time as may be allowed under Clause 44 or revised time agreed
under Clause 46(3)) calculated from the Works Commencement Date."
Clause 44 of the Conditions
made provision for the grant of extensions of time by the Engineer. By clause
44(1) Construction could apply to the Engineer if it considered that it was
entitled to an extension of time. The other provisions of the clause which
are material for present purposes were:-
"(3) Should the Engineer
consider that the delay suffered fairly entitles the Contractor to an extension
of the time for the substantial completion of the Works or any Section thereof
such interim extension shall be granted forthwith and be notified to the Contractor
in writing. In the event that the Contractor has made a claim for an extension
of time but the Engineer does not consider the Contractor entitled to an extension
of time he shall so inform the Contractor without delay.
"(4) The Engineer shall
not later than 28 days after the due date or extended date for substantial
completion of the Works or any Section thereof (and whether or not the Contractor
shall have made any claim for an extension of time) consider all the circumstances
known to him at that time and take action similar to that provided for in
sub-clause (3) of this Clause. Should the Engineer consider that the Contractor
is not entitled to an extension of time he shall so notify the Employer and
the Contractor.
"(5) The Engineer shall
within 28 days of the issue of the Certificate of Substantial Completion for
the Works or for any Section thereof review all the circumstances of the kind
referred to in sub-clause (1) of this Clause and shall finally determine and
certify to the Contractor with a copy to the Employer the overall extension
of time (if any) to which he considers the Contractor entitled in respect
of the Works or the relevant Section. No such final review of the circumstances
shall result in a decrease in any extension of time already granted by the
Engineer pursuant to sub-clauses (3) or (4) of this Clause."
- Clause 47 of the Conditions
was concerned with liquidated damages. Clause 47(2) made provision for liquidated
damages where, as in the present case, the whole of the Works was divided
into sections. Clause 47(5) was in the following terms:-
"The Employer may
- deduct and retain the
amount of any liquidated damages becoming due under the provision of this
Clause from any sums due or to become due to the Contractor or
- require the Contractor
to pay such amount to the Employer forthwith.
If upon a subsequent or
final review of the circumstances causing delay the Engineer grants a relevant
extension or further extension of time the Employer shall no longer be entitled
to liquidated damages in respect of the period of such extension.
Any sum in respect of
such period which may already have been recovered under this Clause shall
be reimbursed forthwith to the Contractor together with interest compounded
monthly at the rate provided for in Clause 60(7) from the date on which such
sums were recovered from the Contractor."
- Clause 61(1) of the Conditions
was in the following terms:-
"Upon the expiry of the
Defects Correction Period or where there is more than one such period upon
the expiration of the last of such periods and when all outstanding work referred
to under Clause 48 and all work of repair amendment reconstruction rectification
and making good of defects imperfections shrinkages and other faults referred
to under Clauses 49 and 50 shall have been completed the Engineer shall issue
to the Employer (with a copy to the Contractor) a Defects Correction Certificate
stating the date on which the Contractor shall have completed his obligations
to construct and complete the Works to the Engineer's satisfaction."
- Clause 66 of the Conditions
made provision for the settlement of disputes. By clause 66(2) in the first
instance any dispute was to be notified in writing to the Engineer. The clause
went on:-
"(3) Every dispute
notified under sub-clause (2) of this Clause shall be settled by the Engineer
who shall state his decision in writing and give notice of the same to the
Employer and the Contractor within the time limits set out in sub-clause
(6) of this Clause.
"(4) Unless the Contract
has already been determined or abandoned the Contractor shall in every case
continue to proceed with the Works with all due diligence and the Contractor
and the Employer shall both give effect forthwith to every such decision of
the Engineer. Such decisions shall be final and binding upon the Contractor
and the Employer unless and until as hereinafter provided either
- the recommendation
of a conciliator has been accepted by both parties or
- the decision of the
Engineer is revised by an arbitrator and an award made and published."
The clause went on to
make provision for reference to arbitration in the event that either party
was dissatisfied with a decision of the Engineer.
The Guarantee
- The Guarantee was, so
far as is presently material, in the following terms:-
"1. The Guarantor HEREBY
GUARANTEES that the Contractor will well and truly perform and observe
all the obligations, terms, provisions, conditions and stipulations in the
Contract mentioned or described or implied thereby on their part to be performed
and observed according to the true purport intent and meaning thereof and
if for any reason whatsoever and in any way the Contractor shall fail to perform
the same then the Guarantor shall take over from the Contractor and shall
forthwith perform and observe or cause to be performed and observed such obligations,
terms, provisions, conditions and stipulations as aforesaid and shall be responsible
to the Employer as surety for the Contractor for the payment by them of all
sums of money, losses, damages, costs, charges and expenses that may become
due and payable to the Employer either by reason or in consequence of any
act, omission or default of the Contractor in the performance or observance
of the Contract.
"3. The Guarantor's liability
hereunder shall in no circumstances exceed the liability of the Contractor
under the Contract.
"4. The Guarantor shall
only be released and discharged from any or all of its obligations hereunder
by a formal release and discharge in writing by the Employer. The latest time
for the issue of such release and discharge shall be upon the issue of a Defects
Correction Certificate in accordance with sub-clause 61.1 of the Conditions
of Contract."
For the purposes of the
Guarantee the expression "the Guarantor" meant Boot, the expression
"the Contractor" meant Construction, the expression "the Employer"
meant Alstom and the expression "the Contract" meant the Main Contract.
The Bond
- The Bond was in a traditional
form. In the Bond the three parties thereto, Construction, Aegon and Alstom
were called, respectively, "the Contractor", "the Surety" and
"the Employer". The Main Contract was referred to in the Bond as "the
Contract". The amount of the Bond was £2,433,508. The relevant part of
the operative section of the Bond was in these terms:-
"NOW THE CONDITIONS of
the above-written Bond are such that if:
- the Contractor shall
subject to Condition (c) hereof duly perform and observe all the terms provisions
conditions and stipulations of the said Contract on the Contractor's part
to be performed and observed according to the true purport intent and meaning
thereof or if
- on default by the Contractor
the Surety shall satisfy and discharge the damages sustained by the Employer
thereby up to the amount of the above-written Bond or if
- the Engineer defined
in Clause 1(1)(c) of the said Contract shall pursuant to the provisions
of Clause 61 thereof issue a Defects Correction Certificate then upon the
date stated therein (hereinafter called "the Relevant Date")
this obligation shall
be null and void but otherwise shall remain in full force and effect but
no alteration in the terms of the said Contract made by agreement between
the Employer and the Contractor or in the extent or nature of the Works
to be constructed completed and maintained thereunder and no allowance of
time by the Employer or the Engineer under the said Contract nor forbearance
or forgiveness in or in respect of any matter or thing concerning the said
Contract on the part of the Employer or the said Engineer shall in any way
release the Surety from any liability under the above-written Bond
PROVIDED ALWAYS that
if any dispute or difference shall arise between the Employer and the Contractor
concerning the Relevant Date or otherwise as to the withholding of the Defects
Correction Certificate then for the purposes of this Bond only and without
prejudice to the resolution or determination pursuant to the provisions
of the said Contract of any dispute or difference whatsoever between the
Employer and Contractor the Relevant Date shall be such as may be:
- agreed in writing between
the Employer and the Contractor or
- if either the Employer
or the Contractor shall be aggrieved at the date stated in the said Defects
Correction Certificate or otherwise as to the issue or withholding of the
said Defects Correction Certificate the party so aggrieved shall forthwith
by notice in writing to the other refer any such dispute or difference to
the arbitration of a person to be agreed upon between the parties or (if
the parties fail to appoint an arbitrator within one calendar month of the
service of the notice as aforesaid) a person to be appointed on the application
of either party by the President for the time being of the Institution of
Civil Engineers and such arbitrator shall forthwith and with all due expedition
enter upon the reference and make an award thereon which award shall be
final and conclusive to determine the Relevant Date for the purposes of
this Bond"
The Demands
- Certificates of Substantial
Completion in relation to various sections of the Works were issued on dates
between 28 June 1995 and May 1996. In a letter dated 23 June 2000 to the Managing
Director of Construction Alstom demanded payment of a sum of £2,406,000 "being
the amount of liquidated damages that is now due to ALSTOM Combined Cycles
Limited from you due to delays to Substantial Completion of your Works." A
copy of that letter was sent to Boot under cover of a letter also dated 23
June 2000 which referred to the Guarantee and went on:-
"Therefore, if we do not
receive such payment within the next 10 (ten) working days we will be looking
to you for payment of the liquidated damages in accordance with Clause 1 of
the Parent Company Guarantee."
Construction replied to
the letter dated 23 June 2000 to it in a letter dated 28 June 2000 of which
the material part read:-
"…It is a matter of record,
of which you are well aware, that the various Engineers whom you have appointed
to administer the Contract have all conspicuously failed to carry out their
duties under clauses 44(3), 44(4) and 44(5) of the Conditions of Contract.
"Under such circumstances
the right of the Employer to payment of liquidated damages is forfeit and
our obligation reverts to one of completing the Works and the various Sections
thereof within a reasonable time.
"As you will appreciate
from the foregoing the right, under clause 47(5)(b), to which you refer can
no longer be relied upon and we shall therefore not be making the payment
you have requested."
Upon receipt of that letter
Alstom wrote a letter dated 29 June 2000 to Boot calling upon Boot under the
Guarantee to pay the sum of £2,406,000. That demand was repeated in a letter
dated 7 July 2000.
- In a letter to Aegon
dated 3 July 2000 Alstom required it to pay the sum of £2,406,000.
The Defects Correction
Certificate
- On 15 August 2000 Mr.
Cort issued a Defects Correction Certificate that:-
"In accordance with the
Conditions of Contract, it is hereby certified that the Contractor has completed
his obligations to construct and complete the Works to the satisfaction of
the Engineer on the 15 August 2000."
The disputes referred
to the Engineer
- By a letter dated 11
August 2000 Construction referred to Mr. Cort a dispute as to whether Alstom
had lost the right to claim liquidated damages. The grounds relied upon as
leading to the conclusion that the right had been lost were:-
"All the Sections of the
Works have now been substantially complete since 28 May 1996 and yet the situation
is as follows:
- Only 2 milestones
have been addressed by the Engineers pursuant to Clause 44(3).
- No milestones have
been addressed pursuant to Clause 44(4).
- Only 9 milestones
have been addressed pursuant to Clause 44(5).
- 26 out of 37 milestones
have not been addressed by Engineers to the Contract at all.
- Numerous requests
for consideration of these issues throughout the period since they were
first raised.
"We maintain that the
above constitutes a serious breach of Contract by the Engineers to the Contract
and, hence, by ALSTOM. We further maintain that either:
- The breach is so
widespread as to call into question the entirety of the extension of time
provisions causing time to become "at large" in relation to the Project
as a whole and each of the milestones. Hence, the obligation upon HBCL was
to complete the Project (and each of the milestones) within a reasonable
period of time. Furthermore, that time being at large, the Employer's right
to deduct liquidated damages pursuant to Clause 47 is forfeit. Lastly, given
the right to liquidated damages was forfeit pursuant to a substantial and
serious breach of Contract by the Employer, it should not be able to recover
general damages in lieu of liquidated damages for any delay in the completion
of the Works or any milestone.
or
- That the right to deduct
liquidated damages in relation to any milestone must be dependant upon the
Engineer having fully complied with the contractual requirements in relation
to that milestone, pursuant to Clause 44 of the Contract. That no liquidated
damages can be deducted in relation to any milestone until all contractually
required reviews of time have been completed by the Engineer. Thereafter,
liquidated damages could still be payable assuming there is any period of
default in relation to any milestone."
In a letter dated 13 November
2000 to Construction Mr. Cort gave his decision that Astom had not lost its
right to liquidated damages. Construction was aggrieved at that decision and
the dispute has now been referred to the arbitration of Mr. Anthony Butcher
Q.C.
- In a letter dated 28
September 2000 Construction referred to Mr. Cort a dispute as to whether the
Defects Correction Certificate was correct as to the date at which the Works
were complete. The grounds for disputing the date were set out in the letter
as follows:-
"Pursuant to Clause 66(2)
of the Conditions of Contract, HBCL dispute the date of your certificate as
we believe that the Engineer either unreasonably delayed in carrying out the
inspection referred to in Clause 49(2)(a) of the Contract and/or unreasonably
delayed notifying HBCL of certain defects and/or delayed the Contractor in
allowing access to carrying out Defects Correction Works identified by the
Engineer. Additionally, certain of the defects which the Engineer has required
to be corrected have not been due to any defective workmanship or materials.
Further, the Engineer unreasonably persisted in requiring guarantees under
Clause 39(1)(d) which guarantees he subsequently waived upon issue of the
Defects Correction Certificate. If these acts of prevention had not occurred,
HBCL contend that the Engineer should have been able to issue the Defects
Correction Certificate on or around 7th December 1999, or at the
latest 28th December 1999."
In a letter dated 21 December
2000 to Construction Mr. Cort communicated his decision in respect of that
dispute, namely that the Defects Correction Certificate was correctly dated.
Construction was aggrieved at that decision and that dispute also has now
been referred to arbitration.
- Construction has also,
by a letter dated 28 September 2000 to Mr. J.C. Quinton, Commercial Director
of Alstom, invoked in relation to the dispute which I have mentioned in the
previous paragraph the procedure for arbitration in the Bond.
Aegon's application for
summary judgment
- Before considering the
applications for a stay of proceedings in each of the First Action and the
Second Action it is necessary, logically, to consider the application of Aegon
for summary judgment against Alstom. If that application succeeds the Second
Action should be dismissed, rather than the subject of a stay or being left
to continue in the usual way.
- The basis upon which
Mr. Michael Bowsher, who appeared on behalf of Aegon, put his submission that
the claim of Alstom on the Bond could not succeed was that, on proper construction
of the Bond, Aegon was discharged from all liability on the issue of the Defects
Correction Certificate, and such certificate had been issued on 15 August
2000. He submitted that the language of the Bond was clear, and it mattered
not that the Second Action had been commenced prior to the issue of the Defects
Correction Certificate. Once the Defects Correction Certificate had been issued,
according to Mr. Bowsher, it was as if the Bond had never existed. Mr. ter
Haar on behalf of Alstom accepted that if it is subsequently found in the
arbitration proceedings now pending that the Defects Correction Certificate
should have certified that the Works had been completed at some date before
the date of commencement of the Second Action any amount recovered in the
Second Action will have to be repaid to Aegon, but he submitted that there
is an obligation on Aegon as bondsman on an interim basis to pay a sum which
was due as at the date of commencement of the Second Action, whatever may
have happened since, and notwithstanding the commencement of arbitration proceedings
to challenge the correctness of the date specified as the date of completion
of the Works in the Defects Correction Certificate. Indeed, Mr. ter Haar's
position in both actions really was that as at the date of the commencement
of each the relevant defendant had no defence because Construction had no
defence to a claim by Alstom for payment of liquidated damages. In fact, for
reasons which are obscure, no proceedings have been commenced against Construction
in which Alstom claims payment of liquidated damages. Mr. ter Haar did not
seek summary judgment in either action, but he made it clear that, dependant
upon the outcome of the applications before me, his client was likely to do
so. His principal ground of opposition to the applications for a stay of proceedings
in each action was that there was no overlap between the issues which might
arise in these actions and any issues in the arbitrations to which I have
referred because, in effect, there was no defence to the claim made in the
First Action or to that made in the Second Action.
- It is, I think, implicit
in Mr. Bowsher's submission as to the proper construction of the Bond that
his contention was that upon, and by virtue of the fact of, the issue of the
Defects Correction Certificate, unless the Bond had ceased to be enforceable
earlier for some other reason, it became null and void both prospectively
and retrospectively. That, however, is not what the Bond said. The obligation
did not become null and void upon the date of issue of the Defects Correction
Certificate, but "upon the date specified therein". Given that the
third condition of the Bond referred in terms to clause 61 of the Conditions
it must be legitimate, it seems to me, to have regard to the terms of that
clause in construing that condition. From clause 61(1) of the Conditions it
is apparent that the date which the Defects Correction Certificate is required
to specify is
"the date on which
the Contractor shall have completed his obligations to construct and complete
the Works to the Engineer's satisfaction."
While the Bond provided
that upon the satisfaction of any of the conditions to which it was subject
"this obligation shall be null and void", and thus appeared to be considering
prospectively a time when the obligation would become null and void, at least
in a case in which the Bond ceased to be valid as a result of the satisfaction
of the third condition the relevant date would actually be a date in the past.
In my judgment it is clear from the wording of the third condition in the
Bond that the obligation created by the Bond only becomes null and void with
effect from the date which should be specified in the Defects Correction Certificate
as the date of completion of the Works prospectively. It would be a very strange
result if a liability to pay under the Bond which had crystallised prior to
the issue of the Defects Correction Certificate simply vanished because the
Defects Correction Certificate had been issued, especially as under the Main
Contract the Engineer had no power to decline to issue the Defects Correction
Certificate, if otherwise it should be issued, on the ground that he wished
to avoid the Bond becoming null and void. I do not think that the wording
of the Bond compels that conclusion. Thus it seems to me that the point taken
by Mr. Bowsher is not well-founded.
- The provisions for arbitration
in the Bond would only have a limited purpose if Mr. Bowsher's submission
were sound, for Aegon would have been discharged upon any issue of a Defects
Correction Certificate, whether the date specified in it were right or wrong,
and if Construction wished to challenge the correctness of the date specified
as the date of completion of the Works it could do so by following the procedure
in clause 66 of the Conditions. This consideration seems to me to be a further
significant indication that the construction of the Bond for which Mr. Bowsher
contended is not correct. While the language of the Bond seems even more obscure
than that of most documents of this kind, I consider that it is tolerably
clear that, to make commercial sense of the third condition it is necessary
to construe it as meaning that the obligation is to be taken as having become
null and void on the date upon which, for the purposes of clause 61(1) of
the Conditions, the Works were in fact complete, whether such date is arrived
at by the Engineer by a correct application of clause 61(1) or as a result
of arbitration proceedings. In the present case, therefore, the arbitration
provisions in the Bond having been invoked, it is not at the moment possible
to say what "the Relevant Date" is for the purposes of the Bond. However,
if the Bond only became null and void on the date specified in the Defects
Correction Certificate as issued by Mr. Cort on 15 August 2000, namely that
date, it was not null and void as at the date upon which Alstom made its demand
upon Aegon. It follows that the application of Aegon for summary judgment
fails.
The applications for a stay
of proceedings
- As I have indicated,
Mr. ter Haar submitted, in reality, that neither Boot nor Aegon had any defence
to Alstom's claim against it. If that is correct, it must mean, in my judgment,
that it would not be right to stay proceedings. To do so in circumstances
in which there was no defence would be to deny justice to Alstom. For it to
be appropriate for me to grant a stay of proceedings in either the First Action
or the Second Action there must, I think, be an arguable defence to the claim
in the relevant action, and that defence, or at least one of the defences,
if more than one is contended for, must raise issues which are already the
subject of existing proceedings.
- The applications before
me were not countered by applications for summary judgment on behalf of Alstom,
and it may be that Mr. ter Haar, had he been appearing on such applications
would have wished to put forward arguments which he did not advance before
me. I would not wish to express any concluded view as to the merits of Alstom's
case in either the First Action or the Second Action without the benefit of
full argument. However, it does appear to me that the submission made to me
by Mr. Stephen Furst Q.C. on behalf of Boot that Boot is not bound to pay
to Alstom under the Guarantee a sum representing liquidated damages unless
Construction itself is obliged as against Alstom to pay such damages must
be correct. It is right, as Mr. ter Haar submitted, that, although Construction
has commenced arbitration proceedings in which it seeks to challenge Mr. Cort's
decision that Alstom is not precluded from recovering liquidated damages,
for the present the effect of clause 66(4) of the Conditions is that Construction
bound by the decision of Mr. Cort. Mr. ter Haar submitted that both Boot and
Aegon were similarly bound, because each was to be treated as being in an
identical position to that of Construction. I do not think that that is right.
Neither the Guarantee nor the Bond provided in terms that Boot, in the case
of the Guarantee, or Aegon, in the case of the Bond, was to be treated at
all times and for all purposes as in the same position, as against Alstom,
as Construction. Under the Guarantee Boot agreed to answer for Construction's
performance and observance of the Main Contract "according to the true
purport intent and meaning thereof". That must, I consider, mean that
it is open to Boot, if called upon under the Guarantee, to argue that some
alleged breach of the Main Contract on the part of Construction is not a breach
on true construction of the Main Contract. The first condition to which the
Bond was subject also provided for discharge of the obligation created by
the Bond if Construction performed the Main Contract "according to the
true purport intent and meaning thereof". A similar point is therefore
potentially open to Aegon. I accept the submission of Mr. Furst that clause
66(4) has no application so far as Boot is concerned, so that I consider that
it would be open to Boot in the First Action to contend that Construction
is not bound to pay liquidated damages to Alstom by reason of the failure
of the mechanism in the Main Contract for dealing with extensions of time.
I express no view as to the merits of that case. It is enough for present
purposes that that case, whatever its merits, is the same as that which is
going to be considered in the arbitration proceedings to which I have referred.
The same point is, it seems to me, also available to Aegon, because, as Mr.
ter Haar accepted, Alstom must prove, in order to succeed as against Aegon,
that it has suffered loss, and it can only do that if it can show that it
is entitled to liquidated damages from Construction which Construction has
not paid.
- Mr. Furst also relied
upon the fact that it would, he submitted, be open to Boot to contend in its
defence that the date specified in the Defects Correction Certificate as the
date of completion of the Works should have been a date earlier than the date
of the demand upon Boot upon which the First Action is founded, because, if
that were right, Boot could say that it should have been released under clause
4 of the Guarantee before the alleged liability arose. Although his concession
was made in the context of the position of Aegon, the logic of Mr. ter Haar's
acceptance that, if the completion date specified in the Defects Correction
Certificate is hereafter found to be incorrect, and a date prior to the date
of the demand upon which the Second Action is based is found to be correct,
Aegon would cease to be liable to Alstom, must also apply to Boot. It seems
to me, therefore, that it is open to Boot to take such a point in its defence
in the First Action. As I have already recorded, the question of the correct
date to be specified in the Defects Correction Certificate is the subject
of existing arbitration proceedings.
- A further line of defence
which Mr. Furst submitted was available to Boot was set-off. He submitted
that sums which have yet to be quantified are due to Construction from Alstom
as a result of previous arbitration proceedings. Mr. ter Haar contested that
submission on the facts, because there was, apparently, a payment by Alstom
to Construction in excess of sums certified as due under the Main Contract,
and as a matter of construction of the Conditions. He submitted that on proper
construction of clause 47(5) of the Conditions the mechanism provided for
recovery of liquidated damages did not contemplate any set-off. Mr. Furst
submitted that the question of whether, on the facts, any set-off was available
to Construction was to be resolved in the arbitration proceedings to which
I have referred.
- For the reasons which
I have given in the preceding paragraphs it seems to me that there are arguable
defences available both to Boot in the First Action and to Aegon in the Second
Action. The defences which I have considered are not necessarily the only
defences available, but they have been put before me as raising issues which
are already the subject of arbitration proceedings, and that on that account,
so it was submitted, in order to avoid duplication and the risk of inconsistent
findings, I should grant a stay of proceedings in each of the First Action
and the Second Action. Each of Boot and Aegon has given an undertaking to
be bound by the outcome of whichever arbitration or arbitrations potentially
affect its position as against Alstom. In my judgment it would be right, proportionate
and in the interests of justice to grant a stay of proceedings in each of
the First Action and the Second Action until the later of the final resolution
of whichever of the currently outstanding arbitration proceedings last reaches
a conclusion. In practical terms all that turns potentially upon whether I
accede to the applications to grant a stay of proceedings in the First Action
and the Second Action is whether Boot and Aegon hold onto the sum pursued
against them, £1,620,000, pending the resolution of the arbitration proceedings
between Construction and Alstom, or whether Alstom holds it subject to a contingent
requirement to repay the whole or some part of it. It is difficult to resist
the conclusion that the commencement of the First Action and the Second Action,
and the applications now before me, are but manoeuvres for advantage in a
much larger war. I will hear Counsel as to the precise form of order which
I should make in the light of my conclusion on the points of principle, as
matters have moved on somewhat since the preparation of the draft orders put
before me.
© 2001 Crown Copyright