IN THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
BEFORE: HIS HONOUR JUDGE BOWSHER Q.C.
BETWEEN:
WHITEWAYS CONTRACTORS (SUSSEX) LIMITED
|
Claimants
|
|
and
|
||
IMPRESA CASTELLI CONSTRUCTION UK LIMITED |
Defendants
|
Case number: HT 00 199
Dates of Trial: 19 July, 2000
Date of Judgment: 9 August, 2000
Kim Franklin for the claimants (Solicitors: Bond Pearce)
Delia Dumaresq for the defendant (Solicitors Bevan Ashford)
JUDGMENT
I direct that no further note or transcript be made of this judgment.
The text of the Judgment of His Honour Judge Bowsher Q.C. is as follows:
JUDGMENT
Introduction
History
Issues
Jurisdiction
"In pursuit of the above, and under clause 38A of the Domestic Sub-Contract DOM/1 we hereby give you formal notice of our intention to refer the dispute to adjudication as set out below.
"We invite you to decide on this issue as a matter of urgency as our response to Whiteways Notice of Referral will depend on your decision. Our client does not wish to incur costs on matters which, in our view, fall outside the jurisdiction of the Adjudication."
"I consider that there does appear to be an issue here which is better determined at the outset."
The Adjudicator directed that the claimant should respond to the defendants' submissions in writing, which they did.
"Further to the submissions received from the parties I now attach my determination on the matter of my jurisdiction in this adjudication."
With that letter, the Adjudicator sent a detailed reasoned decision. In respect of each of the disputed items he decided, "I do have jurisdiction to consider this matter".
"When pursuant to Article 3 a Party requires a dispute or difference to be referred to adjudication then that Party shall give notice to the other Party of his intention to refer the dispute or difference, briefly identified in the notice, to adjudication. Within 7 days from the date of such notice or the execution of the JCT Adjudication Agreement by the Adjudicator if later the Party giving the notice of intention shall refer the dispute or difference to the Adjudicator for his decision ('the referral'); and shall include with that referral particulars of the dispute or difference together with a summary of the contentions on which he relies, a statement of the relief or remedy which is sought and any material he wishes the Adjudicator to consider. The referral and its accompanying documentation shall be copied simultaneously to the other Party."
"I find that Clause 38A.4.1 requires that the notice of intention to refer contains a brief description of the dispute or difference to be referred sufficient to facilitate unambiguous identification of the same by the non-referring party and, if subsequently applicable, by the nominated Adjudicator.
Such description would I suggest typically comprise the nature of each separate claim and the relief sought.
I find that in the absence of any ad hoc agreement between the parties to subsequently extend the same, the adjudicator's jurisdiction is limited to the dispute or difference described in the notice of intention to refer.
The inclusion of the words "the dispute or difference " in the second sentence of Clause 38A.4.1 in connection with the Referral is in my view clearly intended to mean the same dispute or difference referred to in the first sentence of that clause in connection with the notice of intention to refer.
Accordingly, if it is Whiteways' contention that the Referral may include matters not briefly described in some sufficient manner in the notice of intention to refer, then I reject that contention.
I find that Whiteways' notice of intention to refer dated 13 January 2000 includes the matters set out in paragraph 8 hereof.
However, I find that such notice also contains reference to other matters."
"19. Although I consider that an adjudicator has no power under Clause 38A of DOM/1 to determine his or her jurisdiction I conclude from the parties' submissions, both from leading firms of Solicitors, that the parties had extended my jurisdiction to determine the matter.
20. I gave my determination on jurisdiction to the parties on 7 March 2000. A copy of that determination is attached to this Decision at Annexure A.
I found that I did have jurisdiction to consider the matters included in Whiteways' Referral. I found that all such matters were included in Whiteways' notice of intention to refer with the sole exception of Whiteways' application for the extension of the Subcontract period in which it was to carry out and complete the Subcontract Works which was not expressly included. Notwithstanding that the notice of intention to refer restricted matters to disputes as to payments I nevertheless concluded that if I was to decide on the merits of Whiteways' claims for payment, which included loss and expense arising from prolongation of the Subcontract period, and also Castelli's claims for loss and expense arising in part from Whiteways' failure to complete the Subcontract Works by the due date, some consideration was necessary of Whiteways' entitlement to the extension of its Subcontract Period vis-a-vis the period actually taken to complete its work."
"If a party challenges the entire jurisdiction of the adjudicator, as Morrison does, it has four options. Firstly, it can agree to widen the jurisdiction of the adjudicator so as to refer the dispute as to the adjudicator's jurisdiction to the same adjudicator. If the referring party agrees to that course, and the appointed adjudicator accepts the reference to him of this second dispute, the jurisdiction of the adjudicator could then be resolved as part of the reference. The challenging party could, secondly, refer the dispute as to jurisdiction to a second adjudicator. This would not put a halt to the first adjudication, if that had already led to an appointment, since the adjudicator has a statutory duty, unless both parties agree otherwise, to decide the reference in a very short timescale. The challenging party could, thirdly, seek a declaration from the court that the proposed adjudication lacked jurisdiction. This option is of little utility unless the adjudicator has yet to be appointed or the parties agree to put the adjudication into abeyance pending the relatively speedy determination of the jurisdiction question by the court. The Technology and Construction Court can, for example, resolve questions of that kind within days of them being referred to it. Fourthly, the challenging party could reserve its position, participate in the adjudication and then challenge any attempt to enforce the adjudicator's decision on jurisdictional grounds. That is the course adopted by Morrison."
In the present case, the parties adopted the first of the courses mentioned by Judge Thornton.
Abatement
"The Respondent's contentions on abatement are as follows:
s 109 and s 111 (of the HGCRA) - deal respectively with "due date" and "withholding".
s110(2)(a) and (b) - give the widest possible description of cross-claims.
One reading of s110 and s111 together is that s111 may not deal with anything not already covered in a s110 notice.
The matters raised in s110(2)(a) are concerned with set-offs for failure to perform - and not sums not being 'due' (work not done/abatement etc).
Under the law concerning abatement the sums never became due and therefore do not fall within the section.
s110(2)(b) could mean all claims arising out of different contracts can be set-off irrespective of non-conformity - although there is a reference to abatement it is rarely if ever that abatement can be applied from one contract against another.
Because s110 has the power to extend the payor's rights in this way it must be complied with and if the payor intends to rely on such extended rights in s111 notice, then he must raise them in s110 notice. s110(2)(a) could mean that all cross claims can be set off irrespective of the existing test as to close/inseparable connection with the claim (as long as it is a matter arising out of some failure to perform)."
"110. Dates for payment
(1) Every construction contract shall-
(2) Every construction contract shall provide for the giving of notice by a party not later than five days after the date on which a payment becomes due from him under the contract, or would have become due if -
specifying the amount (if any) of the payment made or proposed to be made, and the basis on which that amount was calculated.
(3) If or to the extent that a contract does not contain such a provision as is mentioned in subsection (1) or (2), the relevant provisions of the Scheme for Construction Contracts apply.
111. Notice of intention to withhold payment
(1) A party to a construction contract may not withhold payment after the final date for payment of a sum due under the contract unless he has given an effective notice of intention to withhold payment.
The notice mentioned in section 110(2) may suffice as a notice of intention to withhold payment if it complies with the requirements of this section.
(2) To be effective such a notice must specify -
and must be given not later than the prescribed period before the final date for payment.
(3) .
(4) .."
Conclusion