England and Wales High Court (Technology and Construction Court) Decisions
You are here:
BAILII >>
Databases >>
England and Wales High Court (Technology and Construction Court) Decisions >>
Baxall Securities Ltd and Norbain SDC Ltd v. Sheard Walshaw Partnership [2000] EWHC Technology 53 (30th October, 2000)
URL: http://www.bailii.org/ew/cases/EWHC/TCC/2000/53.html
Cite as:
[2000] EWHC Technology 53
[
New search]
[
Help]
Baxall Securities Ltd and Norbain SDC Ltd v. Sheard Walshaw Partnership [2000] EWHC Technology 53 (30th October, 2000)
IN THE HIGH COURT OF
JUSTICE
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION
COURT
BEFORE: HIS HONOUR JUDGE
BOWSHER Q.C.
BETWEEN:
|
(1)BAXALL
SECURITIES LIMITED
(2) NORBAIN SDC LIMITED
|
Claimants
|
|
And
|
|
|
SHEARD
WALSHAW PARTNERSHIP (A FIRM)
|
Defendants
|
Case number:
1999 TCC 162
Dates of Trial: 2,3,4,9 October, 2000
Date of Judgment: 30 October, 2000
Alexander Nissen for the
claimants (Kennedys, Solicitors )
Louise Randall for the defendants (Fishburn Morgan Cole, Solicitors )
JUDGMENT
I direct
that no further note or transcript be made of this judgment.
The text of the Judgment
of His Honour Judge Bowsher Q.C. is as follows:
JUDGMENT
Introduction
- From 1995 onwards, the
claimants jointly occupied an industrial unit in an industrial park at Bredbury,
Stockport, Greater Manchester. One company was tenant and the other, an associated
company, was a licensee of the other. The first claimants manufacture security
systems and the second claimants distribute those systems. For the purpose
of this action they are treated as one entity.
- The building had been
developed by Berisford Property Investments Limited. That company employed
the defendants, Sheard Walshaw Partnership, as architects. Though there have
been other defendants to this action, they are now the sole remaining defendants,
and I shall refer to them simply as "the defendants". The defendants acted
as architects from 1989 to December, 1992 pursuant to a written agreement
made on 16 February, 1990. On 25 March, 1991 the defendants certified practical
completion; on 28 June, 1991 they issued a certificate of making good defects;
and on 3 December, 1992 they gave the final certificate.
- On 29 May, 1995 and 4
September, 1995, there were floods through the roof of the building causing
damage to the property of the claimants. The floods occurred due to the inability
of the drainage system to cope with heavy falls of rain on those days.
- Initially, the claimants
joined as defendants to this action in addition to the architects, the engineers
employed on the project, the building contractor, and two specialist sub-contractors.
By the beginning of the trial, all defendants other than the architects had
dropped out of the action.
- There being no contract
between the claimants and the defendants, this action is brought in tort.
- Damages are agreed, subject
to liability, in the sum of £128,170.43 for the first flood and £612,153.02
for the second flood, totalling £740,323.45. The damages claimed do not include
the cost of remedial works to the building. All the damages claimed are in
respect of property other than the building itself. There is no claim for
economic loss.
The
Building and Drainage
- Unit 1, with which this
action is concerned, is one of several buildings in the development built
on a speculative basis for light industrial usage. It was not intended that
the building should be occupied by the employers of the defendants. The building
has a concrete floor and the walls and roof are supported by a steel frame.
The walls have brick facing to about mid-height and have metal cladding above.
The roof also has metal cladding. The roof is designed with twin pitches running
lengthwise, the two pitches being separated at the inner eaves by a valley
gutter. The building as a whole was described by one witness as being in effect
a large shed, with a small space for an office for the occupants along one
side, away from the valley gutter.
- The intention was that
storm water should drain from the roof partly into perimeter gutters and partly
into the valley gutter. The floods in question went into the building from
the valley gutter. This action has been concerned with the capacity of the
valley gutter and possible obstructions to it. As with most houses in this
country, any overflow from the perimeter gutters was directed outside the
building, and provided overflows did not occur too often those overflows would
be of little importance.
- The valley gutter is
made of metal with a flat base (laid to falls) and vertical sides. It was
not practical to make a seal between the lip of the gutter and the underside
of the metal roof cladding so that if the gutter over-filled, water would
pour over the lip of the gutter into the building below. The valley gutter
was made in sections, secured at the joins by metal bolts. In the base of
the gutter were outlets leading to drain pipes to take the water away.
- The expert witnesses
are agreed that the valley gutter had a fundamental defect. It ought to have
had, but did not have, overflows. If the drain outlets became blocked, or
if a storm occurred that was heavier than any storm for which the drainage
was designed, the overflows, if adequately designed, should take excess water
away without damage to the building. One form of overflow would have been
by wedge shaped cuts at the top of the ends of the gutter, known as weir overflows.
In this building, weir overflows were impractical because the ends of the
gutter were set against girders forming part of the steel frame. Another form
of overflow would have been to have upstanding pipes at intervals along the
gutter leading through the base of the gutter to overflow drains leading to
the outside of the building. Overflows of this latter type would be on the
same principle as the overflow commonly in place in domestic lavatory cisterns.
- It being accepted that
the valley gutter had that fundamental defect, it has been debated whether
the architect was responsible for that defect, whether the architect owed
a duty in that regard to later occupiers other than the client of the architect,
and what causative effect the absence of overflows had on the floods. For
the defendants, it is suggested that the floods were caused by blockage of
the system due to poor maintenance by the claimants. It is also alleged that
the defect ought reasonably to have been discovered by the claimants and that
on that account the duty of the defendants to the claimants was negatived.
- A further criticism is
that the drainage was not designed with sufficient capacity for the rainfall
to be expected in the area.
- The defendants were criticised
for having failed to perform their contractual duty to their clients to collect
manufacturers' and suppliers' maintenance manuals and supply them to their
clients. However, it was not shown that even if such manuals had been supplied
they would have been passed to the claimants, nor was it demonstrated how
possession of such manuals would have resulted in the claimants doing any
maintenance other than the maintenance in fact undertaken. One of the features
of the siphonic system is that so far as the pipes themselves are concerned,
it should be self-cleaning and hence no rodding points were provided. I shall
say no more about that criticism.
- Other criticisms were
advanced but were no longer live by the end of the trial and I shall say no
more about them.
The
responsibility of the defendants
- The defendants were employed
by Berisford on the RIBA conditions. They prepared drawings, a specification
and employer's requirements, each of which referred to the question of roof
drainage. However, the detailed design of the roof drainage was to be carried
out by a specialist sub-contractor to be employed by the successful tenderer
as main contractor.
- In the event, Birse became
the main contractor and they employed FK Roofing Limited to provide the detailed
design of the roof drainage and to construct it. FK Roofing were joined as
defendants to this action but they have never taken any part in the proceedings
and they are in liquidation. Judgment was obtained against them in default.
The defendant architects are criticised for failing to specify drainage of
sufficient capacity or failing to notice that FK Roofing had failed to specify
drainage of sufficient capacity and failing to notice the absence of an overflow
on any inspection whether for the giving of certificates or otherwise. Roof
drainage was within their general responsibility, though detailed design of
the roof drainage was to be done by others.
- It is common ground between
the parties that the contract between the defendants and their employers is
relevant only to determine the scope of the defendants' duties, not to determine
the standard of care owed to the claimants.
The
system of roof drainage
- Originally, the drainage
was to be by conventional gravity drainage with water falling from the pitched
roofs into the valley and perimeter gutters and then falling by gravity down
vertical pipes into underground drainage. In January, 1990, concern was expressed
to the main contractor about methane underground, and as a result FK Roofing
provided a design for siphonic drainage.
- In 1990, siphonic drainage
was little known in England, though more common on the continent of Europe.
The experts who gave evidence before me did not claim any great knowledge
of the detailed design of such systems. Such systems are so designed that
the run off of water produces a siphonic effect sucking water from the gutters
and drains. For that purpose, it is necessary to ensure that the pipes fill
with water excluding the ingress of air.
Performance
of the architects' duties
- Mr. Walshaw gave evidence.
At the time he was a partner and is now a consultant of the defendants. He
said that although he was responsible for the concept, he left the execution
of the architects' function to a Mr. Kevin Slater under his supervision. Mr.
Slater was not a qualified architect. He worked as an architectural technical
assistant. In the building recession he went out to Hong Kong and then returned
to England. He was last heard of running a public house in Cumbria.
- Mr. Walshaw was able
to give very little evidence of what was actually done on behalf of his practice.
Much of the work was done by Mr. Slater. The documents show that the defendants'
specification made express provision for weir overflows in the valley gutter,
and there is a drawing made by the defendants showing a weir overflow in the
valley gutter. Those requirements for overflows were made before the change
to siphonic drainage, but the manufacturer's literature for siphonic drainage
make it plain that "large capacity overflows are essential". The defendants
failed to ensure that the finished building included the overflows that they
had specified.
- There is no evidence,
written or oral, that the defendants ever considered what was the rainfall
intensity for which the drainage system should be designed. It appears that
the decision as to the design rainfall intensity was made by FK Roofing and
not dissented from by the defendants. FK Roofing selected a rainfall intensity
of 75 mm per hour.
Rainfall
intensity
- Rainfall intensity is
expressed in terms of millimetres per hour. There is a British Standard for
Drainage of Roofs and Paved Areas, BS6367:1983. It is common ground that architects
ought to be familiar with that BS.
- The BS in paragraph 5.2
advises:
"It is
not possible to ensure complete safety from flooding or overflow.
For the
design of paved areas
a design rate of rainfall of 50 mm/h is recommended.
A design rate of rainfall of 75 mm/h (category 2 in Appendix A) is generally
satisfactory for roof gutters where overflow is not likely to occur inside
a building and for other gutters where some risk to the contents of the building
might be acceptable.
For other
cases, design rates of rainfall corresponding approximately to a chosen return
period should be used. The method to be used in the selection of these rates
is described in Appendix A."
- Appendix A includes maps
of the United Kingdom marked to show differing return periods in years for
rainfalls of differing intensity in various parts of the country. The return
period of an event is the approximate chance that the event will recur or
be exceeded in any given year. Appendix A includes the following:
"Five categories of
design rate are proposed as follows:
a. Category 1: A design
rate of rainfall of 50 mm/h should be used for paved areas on which ponding
can be tolerated during a heavy storm and for a few minutes after the storm
has ceased.
b. Category 2: A design
rate of rainfall of 75 mm/h should be used for sloping surfaces where ponding
cannot occur and for flat surfaces where ponding cannot normally be tolerated.
Return periods of this rate are given in Figure 17.
Note:
In some cases (i.e. some valley gutters) the risks associated with categories
1 and 2 will be considered too great and higher design rates of rainfall
should be used (categories 3 to 5)."
Category
3 gives a method of computation "in cases where the building or its contents
require an additional measure of protection".
Category
4 provides a method "that should be used if a higher degree of security
than that provided by category 3 is desirable".
Category
5 is for cases where "the highest possible degree of security
is required".
Floods
and leaks
- There were some comparatively
small leaks from the roof of the building both before and after the claimants
went into occupation. Those leaks were in the main from the joins in the base
of the valley gutter or from defective seals around the bolts securing those
joins. The leaks may have been caused by bad workmanship or by movement caused
by workmen on the roof doing maintenance. Those leaks were wholly different
in type and causation from the floods the subject of this action and no damages
are claimed in respect of them. The floods the subject of this action have
been referred to as "the first flood" and "the second flood", but there is
evidence that there was also some flooding before the claimants went into
occupation.
History
- In 1989, the defendants
were appointed architects for the development by Berisford on RIBA terms.
The appointment required that the defendants should appoint the following
individuals to carry out the architects services, Mr. Walshaw, partner, Mr.
Slater, Project architect, Mr. Merridith, Site supervisor. I have heard no
evidence of the activities of Mr. Merridith.
- In October, 1989, Berisford's
quantity surveyors asked FK Roofing (amongst others) to tender for the design
and supply of the roof and rainwater goods. A copy of that request was sent
to the defendants. The request included a specification that referred to gutters.
The specification included the following:
"Gutters
are to be laid so as to avoid standing water. The gutters are to be tested
by flooding as soon as they have been levelled so as to demonstrate to the
architect that no standing water will occur and further test may be called
for at Practical Completion if it is thought necessary.
Allow
for weir overflows as indicated on drawings at a level slightly lower than
the gutter sides.
".
No design
requirement for the rate of rainfall intensity was included in that specification.
- On 7 December, 1989,
FK Roofing wrote to Birse stating that they wanted to change the overflow
from a side exit to an overflow upstand pipe in the sole of the gutter in
accordance with an enclosed drawing indicating the restriction at the end
of the valley gutter caused by a steel joist. It is clear that this proposal
came to the attention of the defendants.
- On 13 December, 1989,
the defendants issued an Architects Instruction confirming that FK Roofing
were to be domestic sub-contractors.
- In December, 1989 and
January, 1990, FK Roofing issued drawings and explanatory notes indicating
that a design rainfall rate of 75 mm per hour had been used. The notes stated
that the calculations were in accordance with BS 6367:1983. In evidence, Mr.
Walshaw said that the defendants had not approved that design rate but they
had not disapproved it. The sub-contractor's design rate certainly came to
their attention. The evidence of the claimant's expert, which I accept, is
that the defendants ought to have set the design rainfall rate in the tender
specification and not left it to the sub-contractor. The tendency of a sub-contractor
when tendering, if not limited by the specification, would be to choose a
low and inadequate design rate so as to be able to put in a low tender and
get the job. The defendants in the ordinary course received copies of FK Roofings
drawings and design and during 1990 were involved in details of the change
from gravity to siphonic drainage. That change did not affect the design rate.
- A letter of 5 January,
1990 indicates that on 20 December, 1989, there were discussions between Birse
and Mr. Slater about FK Roofing's gutter drawings, and that Birse were happy
with them provided the overflow pipes had open mesh caps on the ends. It is
that letter which makes it clear that the defendants knew that the overflows
were to take the form of upstands. Mr. Walshaw said that he did not discuss
overflows with Mr. Slater, so it is quite possible that he personally did
not know of the change. That is not a relevant factor in this litigation.
- In January and February,
1990 there were conversations and correspondence between Mr. Slater and Birse
and Berisford about the valley gutter. On 20 February, 1990 Birse wrote to
Mr. Slater asking for a detail showing his requirements for an overflow for
the valley gutter.
- On 23 April, 1990 Mr.
Slater on behalf of the defendants wrote to Birse enclosing a copy of Fullflow's
drawing of the siphonic drainage with comments which did not include any adverse
comment about design rate or overflow.
- Before the claimants
went into occupation or signed any tenancy agreement, they instructed Lambert
Smith Hampton, surveyors, to inspect the building. They also instructed Mr.
Meiklejohn of Castle Computer Suites Limited, environmental engineers, to
advise on fitting out. Mr. Meiklejohn has a degree in building management
and technology.
- On 30 July, 1993, Mr.
Meiklejohn wrote to the claimant's finance director in the following terms:
"I spoke with your Surveyor
employed to inspect the above on your behalf earlier this week.
I voiced
my concern regarding the state of the roof to the premises, in that the previous
week whilst I was escorting prospective contractors around the site, I noted
that the Warehouse
floor was flooded in many places with rainwater
Your surveyor explained
that he had been upon the roof and noted that the valley guttering was blocked
with debris which could be the source of the problem.
I pointed out that the
flooding noted was in areas other than those beneath the valleys of the roof.
From the ground I had been unable to see any defect in the roof sheeting other
than some stains on the roof light translucent sheeting - suggesting water
ingress between.
My concern is that the
matter is entirely settled before we commence any works on site, particularly
those which entail the
suspension of services from the roof structures.
Otherwise it will appear
reasonable to suggest later that any roof leakage problems are related to
the services installation works, rather than a latent defect.
My advice would be that
you do not take on any commitments regarding the premises until this matter
is resolved. To do otherwise could leave us in dispute as to who is going
to pay for a new roof."
- In oral evidence, Mr.
Meiklejohn explained that although he referred in his letter to staining by
floods in areas other than under the valley guttering he also saw stains under
the valley guttering. It is clear that before the claimants went into occupation,
there had been floods into the building, as opposed to small leaks, and the
claimants were aware of that.
- In August, 1993, Lambert
Smith Hampton, the surveyors referred to by Mr. Meiklejohn, reported in writing
to the claimants. Their report included the following:
"Rainwater
disposal from the main roof comprises a galvanised steel box gutter with bolted
sections around the perimeter of the building and a similar central valley
gutter. There is a large amount of debris and silt in the central valley gutter
and this requires cleaning as soon as possible since as we discuss later,
there appears to have been problems of rainwater penetration through the gutter
system.
Weir outlets
are provided in the event of blockage to the system."
- So not only did Lambert
Smith Hampton fail to notice the absence of overflows, they positively misled
their clients by saying that weir outlets existed when, as we know, they did
not. However, even on the false assumption that there were overflows, even
a layman could have asked the question, "Why did not the overflows prevent
a flood when the primary drains were blocked?" Mr. Lynch, called as an expert
witness on behalf of the defendants said that although the architects should
have seen that there were no overflows, it was reasonable for Lambert Smith
Hampton to have missed their absence, though I cannot see how that can be.
Still less can I see why the surveyors should have said that there were overflows
when there were not. Mr. Lynch said that when he himself inspected, he found
difficulty in seeing the ends of the valley gutters, so he went back with
a torch and could then see. Why could not anyone else who was looking have
done the same?
- The Lambert Smith Hampton
report continued,
"As previously
mentioned, the gutter is particularly silted with debris and the rainwater
outlets are partly blocked. We suspect that there has been a serious failure
of the drainage system in the past causing extensive flooding internally as
evidenced by the water staining to the floor. Such a system with small bore
outlets is particularly vulnerable in the event of blockage and it is extremely
important that the gutter is kept clear. We suggest, however, that the Landlords
investigate the source of the problems and undertake any remedial action that
is required.
The small
bore outlets and single large diameter rainwater pipe system is a relatively
new concept in rainwater disposal and involves careful calculation of the
anticipated rain fall and flow levels. The system also relies on deep section
gutters discharging to the small bore outlets and it is therefore particularly
important that the outlets do not become blocked."
- The conclusions of the
Lambert Smith Hampton report included the following:
"Firstly,
it is evident that there have been problems of rainwater penetration through
the roof construction. Our initial views are that this is a result of blocked
and leaking gutters particularly to the central valley gutters and these areas
require further investigation and remedial works. The damp staining affecting
the floor suggests that there has been a major flood of water into the building
at some time in the past and we are proposing to investigate the circumstances
surrounding this with the Developers. There is also a separate roof leak isolated
away from the gutter areas which requires further investigation since there
are no obvious signs of failure of the roof covering in this area. The siphonic
rainwater disposal system and the central valley gutter are always likely
to be a cause of water penetration without regular and routine maintenance."
- No witness was called
from Lambert Smith Hampton to give evidence and there is no evidence of what
further investigations, if any, were made by Lambert Smith Hampton or by anyone
else. In fairness to Lambert Smith Hampton I should make it plain that because
no one from that firm has been called as a witness, they have not had any
opportunity to deal with any of the criticisms made by me or others about
their conduct. On the evidence I have heard, without any evidence from Lambert
Smith Hampton, the absence of overflows ought reasonably to have been discovered
by Lambert Smith Hampton. It was not alleged on behalf of the defendants that
the under design of the drainage system ought reasonably to have been discovered
by Lambert Smith Hampton or by the claimants.
- On 5 August, 1993, Lambert
Smith Hampton wrote to the claimants enclosing a Schedule of Defects which
the writer said, "I feel should be resolved by Landlords. I gather that you
have agreed to an Agreement to Lease subject to these items being dealt with....
In addition to dealing with the items contained in the Schedule, I suggest
that agreement is reached that the Landlord will remain responsible for repairs
for the first 12 months..." A handwritten note on the document suggests
that Landlord will not agree to remain responsible for repairs for the first
12 months. The defects list sent with that letter was the same as the list
appended to the Lambert Smith Hampton report and included:
1.1 Clean out gutters
of debris.
3.1 Investigate and
repair water penetration along line of valley gutters.
3.2 Investigate
and repair penetration between grid lines 6-7/P-Q.
- On 6 August, 1993, Mr.
Meiklejohn wrote to the claimants:
"With
regard to your Surveyor's report. My only comment is that I know that the
roof has been leaking extensively. I had discussed this matter with the Surveyor
after his first visit and then we were unable to decide what the precise fault
might be.
I am not
sure how we might resolve this matter, but am concerned that it is highlighted
as a latent defect that remains the Landlord's responsibility until remedied."
- On 17 August, 1993, Chestertons
wrote to Lambert Smith Hampton saying that items 3.1 and 3.2 of the schedule
of defects "will be remedied as a result of the works undertaken to the main
roof gutters". In reply on 18 August, 1993, Lambert Smith Hampton simply said
in relation to that statement, "Noted". There is no evidence what works were
undertaken or to be undertaken to the roof gutters.
- On 13 September, 1993,
the claimants wrote to Mr. Meiklejohn enclosing "a list of works to be performed
by ourselves as ingoing tenants and the landlord". A list was enclosed similar
to the previous list made by Lambert Smith Hampton but without any reference
to items 3.1 or 3.2. Mr. Meiklejohn wrote on that list,
"What about
(ii) roof guttering
(v) roof leaks".
- In his oral evidence,
Mr. Meiklejohn said that on 29 September, 1993, the claimants knew about the
problems to the roof and there was no reason why they should not have put
it right. The problem was flooding inside the building. It is clear from his
evidence that he responded to that letter either orally on the telephone or
in writing. He wrote on 29 September, 1993 and he thinks that he would have
responded earlier than that orally. In his letter of 29 September, he did
not mention the valley gutter expressly.
- Meanwhile, on 16 September,
1993, the claimants had entered into an agreement for a lease with Berisford.
That agreement identified works to be carried out by Berisford. Those works
did not include any works to the valley gutter other than "Clean out gutters
of debris" and "Repaint gutters with bitumen paint".
- There is no evidence
that anything more was done by the claimants to solve the known problem of
flooding (as opposed to leaks) from the roof before the first flood the subject
of this action except that there was intermittent cleaning of the valley gutter.
- On 11 November, 1993,
Lambert Smith Hampton wrote to the claimants saying that there were still
two leaks to the valley gutter which required attention.
- On 12 November, 1993,
Powell Williams Partnership, Surveyors, wrote to Lambert Smith Hampton saying
that they were dealing with two leaks in the valley gutter, but on 1 December
Lambert Smith Hampton complained that there was still one leak which on 2
December, Powell Williams Partnership claimed to have rectified. On 14 January,
1994, Lambert Smith Hampton wrote to the claimants:
"As far
as I am aware [the outstanding works] have now been carried out. There were
only three items outstanding from my last inspection, namely a leak to the
valley gutter
.Although I have had written confirmation that these have been
done, I have not had the opportunity of checking them on site, mainly because
I wanted to see how the gutter performed over a period of time, since this
should establish whether there are any leaks. I understand you have an understanding
with Landlords to rectify any defects in works that they have completed and
therefore if there are any leaks then I am sure you can get Landlord's Contractor
back to deal with them."
It is
clear from that letter that Lambert Smith Hampton had not recently done anything
even to check the leaks from the valley gutter and had certainly not made
any close enquiries to find out the cause of the floods and the attitude was
that if anything went wrong the landlords would deal with it.
- On 18 January, 1994,
the claimants and Berisford entered into a Lease and a Latent Defects deed.
By the latter instrument, Berisford undertook to be responsible over a period
from 14 September, 1995 up to and excluding 14 September, 2002 for latent
defects subject to certain qualifications.
- In January, 1994 Mr.
Meiklejohn was not satisfied that anything had been done about roof leaks,
and in a letter to the claimants dated 20 January, 1994 he reminded them of
the need to attend to roof leaks.
- Through 1994 and into
1995, Mr. Meiklejohn remained dissatisfied about roof leaks. He had recommended
monthly cleaning of the roof and there is some evidence that some cleaning
was done but there was no contract for regular maintenance until 21 December,
1994. On 23 August, 1994, Hayes Building Services did some cleaning and also
laid some roofing mastic. Hayes told Mr. Meiklejohn that the problem was from
seagulls roosting on the roof. Mr. Meiklejohn wrote accordingly on 14 September,
1994 to the newly appointed Finance Director of Baxalls to try to get him
to provide the funds to pay for regular maintenance. The letter, referred
to as the "Seagulls letter" was in the following terms:
"Re: Seagulls
Yes Seagulls.
They have adopted the
roof of your premises and roost in the gutter which runs the whole length
of the building.
Their feathers, food and
droppings accumulate quickly and block the drain outlets.
This only becomes evident,
of course, when it rains.
The gutter then fills
up and overflows.
As it is in the centre
of the roof it overflows into the building, mainly in the Norbain half.
A local builder has been
employed by Norbain to clear the blockage on a couple of occasions
and has reported the build up occurring over a period of just two weeks.
I have
discussed the problem with Dermot, who quite rightly suggested that it was
a Landlord's problem, ie. Baxall's.
If the problem was one
of Herons or Pigeons I could suggest mounting a replica of another bird on
the roof.
Seagulls, however. seem
to fear nothing - other than Killer Whales - which might prove difficult to
fit and would require Planning Permission, (Someone suggested Ron Philips).
I suggest that the solution
might be to take out a maintenance contract with the local builder to regularly
inspect and clean the gutters as and when necessary.
His details are: Hayes
Building Services
"
- There followed many more
visits from a builder on a reactive basis to clear gutters after a leak, but
there was no maintenance contract entered into before the first flood. Mr.
Meiklejohn said that 90% of those leaks were minor. He qualified his previous
statement that there was no reason why the claimants should not have put the
roof right by saying that the claimants had no reason to believe that they
were at risk of a flood. I do not accept Mr. Meiklejohn's evidence that the
claimants had no reason to believe that they were at risk of a flood. They
had been told of previous flooding and they had not ascertained that the cause
of the previous flooding had been removed. He said that he himself never saw
any evidence of seagulls when he went onto the roof. When he wrote the seagulls
letter he had not been on the roof.
- The gutters were cleaned
by Hayes on 31 January and 28 February, 1995.
The
first flood
- The first flood the subject
of this action was on 29 May, 1995.
- There is little first
hand evidence of the first flood. Mr. Alan Heath, Operations manager for Norbain
was there but can remember little about the first flood, though he could recall
the second flood. Mr. David Beech, Technical Director of Norbain gave a statement
which was submitted as agreed evidence, but he did not see the warehouse until
a few days after each flood.
- On the basis of expert
metereological evidence, it is agreed that the first flood was due to rainfall
of an intensity even for periods of less than 2 minutes of less than the design
rate adopted by the sub-contractors, that is, less than 75 mm per hour. Evidence
was given by Mr. David Crabbe, Senior Forensic Meteorologist of the Meteorological
Office that it was very unlikely but not impossible that the rain exceeded
75 mm. per hour over 2 minutes. It is agreed that for a flood to be caused
it would be necessary for the rainfall to exceed the design rate for over
2 minutes. Mr. Crabbe also said that the return rate for a 75 mm per hour
rainstorm for two minutes in the Manchester area was about once per year.
- The day after the flood,
on 30 May, 1995, two men spent a total of 5 hours cleaning the gutter outlets
and removed a considerable quantity of material.
- There was clearly a flood
rather than merely leaks. On the fairly sparse evidence, it seems clear enough
that the first flood was not due to the low design rate for the valley gutter.
The first flood was caused by a combination of obstructions in the gutter
and the absence of any overflow to deal with excess water not taken away by
obstructed drains.
- Thereafter, the gutters
were cleaned on 26 June, 31 July, and 1 September, 1995.
- Mr. Heath said that he
consulted Mr. Meiklejohn after the first flood, though there is no written
evidence that he did so. I prefer Mr. Meiklejohn's evidence that he was not
consulted after the first flood. The furthest Mr. Meiklejohn would go was
that he might have been asked about it in the canteen and would, if asked,
have advised systematic maintenance of the roof.
The
Second Flood
- On 4 September, 1995
there was another flood from the valley gutter. Mr. Heath has a clear recollection
of some facts about that flood. He was driving home from the warehouse at
about 6 p.m. when someone from the warehouse telephoned him on his mobile
telephone to tell him that water was pouring through the roof and the warehouse
was flooding. He turned his car round and drove back to the warehouse arriving
there at about 6.45 p.m. On the return journey, his windscreen wipers could
hardly cope with the volume of rainfall. However, the rainfall was not so
heavy as to cause him to pull over and stop the car. Mr. Crabbe said that
that would describe rainfall of an intensity of between about 75 and 150 mm.
per hour. Mr. Crabbe said that it was possible though unlikely that the rainfall
in the area of the premises would have exceeded 150 mm. per hour even for
a very short period. Probably the rainfall there was in excess of 75 mm per
hour but less than 150 mm. per hour. Mr. Crabbe had limited relevant data
but I accept his evidence. When Mr. Heath arrived back at the warehouse he
saw "a scene of total devastation". The whole warehouse was flooded and water
was still pouring through the roof. 4.00 p.m. to 8 p.m. is the busiest time
in the warehouse as that is when the bulk of orders are processed and as a
result a large amount of stock was exposed awaiting packaging or processing.
As a result much damage was caused to stock, most of it electrical goods.
- The day after the flood,
Mr. Meiklejohn gave an order to Hayes Building (with a copy to the claimants):
"Please
cut out and form an outflow from either end of the valley gutter to the above.
The purpose
of this is to ensure that the rainwater level within the gutter is limited
to two thirds of its depth and so unable to overflow into the premises along
its length.
Please
carry out a full endoscopic survey of all the pipes involved in the high level
siphonic drainage system
"
- I find that the cause
of the second flood was the underdesign of the gutter and the absence of overflows.
Since the gutter was cleaned only four days before the flood, lack of maintenance
was not a cause of the second flood. There has been some suggestion that there
may have been a blockage in the pipework of the drain as opposed to the gutter
itself. I will consider that suggestion in more detail when I turn to the
expert evidence, but I say at once that I have no hesitation in rejecting
that suggestion.
The
expert evidence
- Expert evidence was given
by Mr. Andrew Lynch on behalf of the defendants and by Mr. Barry Woodward
on behalf of the claimants.
- Mr. Woodward is a partner
of the Mason Richards Partnership, a multi-disciplinary practice of architects.
He has a BSc (Building) from Aston University and is a member of the British
Institute of Architectural Technologists. Although not a member of the RIBA,
no objection was made to his qualifications, which are considerable. He has
frequently investigated and reported on matters involving allegations of professional
negligence and is experienced in giving expert evidence.
- Mr. Lynch is an Associate
Member of the Royal Institute of British Architects. He qualified in 1958
and is now in practice on his own account. He has been a Senior Associate
at the Mason Richards Partnership and has investigated and reported on many
cases involving arbitration and legal proceedings.
- Those experts provided
a most helpful written statement of matters agreed and not agreed.
- The statement of matters
agreed included the following:
"The valley
gutter ought to have incorporated weir overflows in accordance with BS6367:1983.
Based
upon calculations provided by F.K. Roofing Ltd. the adopted design criteria
for the gravity rainwater system incorporated a rainfall intensity of 75mm
per hour.
The building, as now occupied,
ought to incorporate a rainwater disposal system designed for a rainfall intensity
of 15Omm per hour.
The valley gutter incorporated
seven outlets but would have required ten outlets to discharge a rainfall
intensity of 150 mm. per hour."
- The words, "as now occupied"
in the sentence, "The building, as now occupied, ought to incorporate a rainwater
disposal system designed for a rainfall intensity of 15Omm per hour" are important
because of a difference between the experts about what ought to have been
foreseen as the likely occupation of the premises.
- The statement of differences
of opinion as to causation of the floods reveals a considerable measure of
agreement.
- Mr. Woodward said:
"In my opinion the most
likely causes of the floods were:-
The rainfall exceeded
the design capacity of the system and/or
Gutter
outlet or outlets became partially blocked and no weir overflows were available
thus preventing the rainwater from being discharged clear of the building
and/or
The different
levels of outlet connections into the system allowed induced syphonage
to break the siphon in the sole discharge pipe diminishing the rate of
discharge."
- Mr. Lynch said:
"In my opinion the most
likely causes of the floods were:-
the outlets and/or pipework
of the syphonic system were unable to act at full capacity or at all as a
consequence of blockages
the rainfall exceeded
the capacity of the syphonic system and/or the capacity of the below-ground
drainage system
lack of adequate maintenance,
which is the responsibility of the building owner or tenant, as the case may
be."
- The reference by Mr.
Woodward to the different levels of outlet into the system is a matter no
longer pursued.
- Those views were given
when the experts were unaware of what would be said about the rate of rainfall
on the days in question. They also did not know what would be said about the
regularity of maintenance.
- Mr. Lynch agreed with
Mr. Woodward that the rainfall exceeded the capacity of the drainage system.
In his oral evidence, though not in his written report, Mr. Lynch said that
overflows were an obvious requirement.
- Mr. Lynch and Mr. Woodward
disagreed about the required design capacity of the system. Their disagreement
comes down to a matter to be decided by the court, namely, what was the use
of the premises that ought to have been reasonably anticipated by the architects.
- Mr. Woodward gave unchallenged
evidence that the defendants took on the normal responsibility for providing
detail design, specification information, inspection of the works and advice
on maintenance.
- Mr. Woodward also said,
and I accept, that there was a fundamental deficiency in the design information
given by the defendants. To enable the potential tenderers for the roof drainage
to carry out their technical design, they ought to have been given information
of the design requirement for the rate of rainfall. That requirement was not
given. The tenderers provided their own design requirement and left to their
own devices, would have been tempted to put in the lowest and cheapest requirement.
Mr. Woodward gave it as his opinion, with which I agree, that any shortfall
in the capacity of the gutters to dispose of short duration rainfall appropriate
to the location of the building would be as a direct result of the failure
of the architect to incorporate the necessary information within the specification
requirement.
- Mr. Woodward said that
the design rate of intensity of 75 mm per hour that was in fact adopted by
the roofing specialists was inadequate. In accordance with the BS, it ought
to have been 150 mm per hour. An ordinarily experienced architect ought to
have consulted the BS 6367: 1983. Mr. Lynch on the other hand said that the
rainfall intensity criterion of 75 mm per hour was an acceptable basis for
the design since the building was of a speculative nature at an economical
cost and since no more precise knowledge of the degree of protection which
might be required by a future occupant was ascertainable. But Mr. Lynch accepted
that the building was built with planning permission for light industrial/warehouse
use. He further accepted that the customer of almost any light industrial
supplier would be supplied with goods wrapped in cardboard or plastic and
would expect the goods to be dry. Mr. Lynch accepted that the design criteria
in fact adopted would be likely to result in the area in question of flooding
on a return period of once per year, but maintained nonetheless that that
would be satisfactory. The only usage he could think of for which such a return
period of flooding would be acceptable was the storage of bricks. I regard
that part of Mr. Lynch's evidence as a mistaken attempt at advocacy on behalf
of his client and I reject it without hesitation. I find that the architects
ought not to have allowed the specialists to choose their own rate and having
done so, the architects should have disapproved that rate and required a rate
of 150 mm per hour. In those respects, they were in my view negligent.
- The BS also required
overflows. The architect did specify weir overflows, later changed to upstand
overflows for reasons of practicality that I have mentioned. Having specified
overflows, an ordinarily experienced architect ought to have ensured by inspection
that such overflows were installed. They were extremely important. Mr. Lynch
agreed that there was no argument about the need for overflows. The architect
should certainly not have given any of the certificates to which I have referred
until he had satisfied himself that the overflows were there. If for any reason
he could not see overflows, he should withhold a certificate until it had
been demonstrated that there were overflows as specified.
- Mr. Woodward said that
roof outlets, valleys, gutters and overflows need to be inspected and cleaned
twice each year, once in the autumn and once in the spring. Siphonic systems
are claimed to be self cleansing, but the efficiency of the self cleansing
mechanism depends on the frequency and velocity of rainfall.
- Mr. Woodward stated the
causes of the floods to be that the rainfall exceeded the design capacity
of the system and that in the case of the first flood the valley gutter outlets
or some of them became blocked and no overflow mechanisms were available.
- In keeping with Mr. Woodward's
evidence, I find that the architects were negligent in failing to specify
a design requirement for the drains for rainfall intensity of 150 mm per hour
and in failing to ensure that the overflows that they did specify were installed.
- As regards the first
flood, I do not accept Mr. Woodward's conclusion that the flood was partly
caused by the under design of the system. That view was expressed by him before
he had heard the meteorological evidence. The system was certainly under designed,
but the rainfall preceding the first flood was probably of an intensity that
fell within the design limits that were actually selected by the sub-contractors.
The first flood, in my view was caused partly by blockage of the outlets to
the valley gutter and the absence of overflows. If there had been overflows,
it is unlikely that they themselves would have been blocked. If it had been
possible to have weir overflows, they would have been at the top lip of the
gutter. In the alternative to weir overflows, the upstand pipes would be about
75 mm high and it is most unlikely that any blockage would have extended to
that height. Whether the overflow would deal with the excess water would depend
on the capacity of the overflow.
- As to the second flood,
I agree with Mr. Woodward's view that it is extremely unlikely that the outlets
or siphonic pipework were blocked at that time. The gutters had been cleaned
only four days beforehand and there is no evidence that the pipework of the
siphonic system was ever blocked. Mr. Lynch tried to suggest that they might
have been blocked and then cleared by the storm, and I suppose that that might
have happened, but there is absolutely no evidence that any such thing did
happen. Almost immediately after the second flood, an endoscopic survey was
conducted of the pipework and there were no signs of any blockage nor even
of any residual material that might have formed part of a blockage. I accept
the meteorological evidence that the rainfall leading to the second flood
was in excess of the design criteria adopted but was probably not in excess
of the design criteria that ought to have been adopted. I find that the second
flood was caused by a combination of under design of the drainage system and
the absence of overflows.
The
defendants' duty of care
- For the claimants it
is submitted that in certain circumstances, an architect owes a duty in tort
to an occupier of premises that the architect has designed and whose construction
he has supervised even though the architect had no contract with that subsequent
occupier. In argument, I asked whether an architect might be liable to such
subsequent occupier even though he had by contract settled all continuing
liability with his client, and it was submitted that he might be so liable.
- The liability alleged
is said to spring from the decision in Donoghue v. Stevenson [1932] AC 562. That decision is so well known that it is usually cited without any
quotation from the speeches. But in the present case it may be helpful to
remind oneself of the speeches of their Lordships. Donoghue v. Stevenson
was a case of the supply of consumer goods, in that case, a drink. In a dissenting
speech, one of the members of the appellate court protested that if such a
duty were held to exist, he could not see any reason why it should not apply
to the building of a house, which he plainly regarded as an impossible proposition.
But in Murphy v. Brentwood District Council [1991] AC 398 such a duty
was found by the House of Lords to exist. The claimants in this action say
that if it applies to a builder it also ought to apply to an architect, though
the question whether it does apply should be subjected to the test of "fair
just and reasonable" as advanced by the House of Lords in Marc Rich v.
Bishop Rock Marine [1996] AC 211. At the beginning of this case, it was
thought by counsel that there was no direct authority for imposing such liability
on an architect, but during the trial the researches of counsel unearthed
the report of a decision of His Honour Judge Esyr Lewis in Tesco Stores
v. The Norman Hitchcox Partnership and Clark Care Group v. The Norman Hitchcox
Partnership [1997] CILL 1301 and [1998] 56 ConLR 42. Judge Esyr Lewis
was, of course, the judge who tried Murphy v. Brentwood District Council
at first instance. However, it seems to me that I ought to consider the matter
afresh.
- In Donoghue v. Stevenson,
at page 580 Lord Atkin famously described the "Neighbour principle". It is
worth reading a fuller citation than is usually given. That wider citation
is valuable both for a fuller understanding of the concept of the neighbour
principle and for a statement of its limit to latent defects:
"At
present I content myself' with pointing out that in English law there
must be, and is, some general conception of relations giving rise to
a duty of care, of which the particular cases found in the books are
but instances. The liability for negligence, whether you style it such
or treat it as in other systems as a species of "culpa," is no doubt
based upon a general public sentiment of moral wrongdoing for which
the offender must pay. But acts or omissions which any moral code would
censure cannot in a practical world be treated so as to give a right
to every person injured by them to demand relief. In this way rules
of law arise which limit the range of complainants and the extent of
their remedy. The rule that you are to love your neighbour becomes in
law, you must not injure your neighbour; and the lawyer's question,
Who is my neighbour? receives a restricted reply. You must take reasonable
care to avoid acts or omissions which you can reasonably foresee would
be likely to injure your neighbour. Who, then, in law is my neighbour?
The answer seems to be - persons who are so closely and directly affected
by my act that I ought reasonably to have them in contemplation as being
so affected when I am directing my mind to the acts or omissions which
are called in question. This appears to me to be the doctrine of Heaven
v. Pender 11 QBD 503, as laid down by Lord Esher (then Brett M.R.)
when it is limited by the notion of proximity introduced by Lord Esher
himself and A. L. Smith L.J. in Le Lievre v. Gould [1893] 1 QB 491
at 497 Lord Esher says: "that case established that, under certain
circumstances, one man may owe a duty to another, even though there
is no contract between them. If one man is near to another, or is near
to the property of another, a duty lies upon him not to do that which
may cause a personal injury to that other, or may injure his property."
So A. L. Smith L.J.: "The decision of Heaven v. Pender was founded
upon the principle, that a duty to take due care did arise when the
person or property of one was in such proximity to the person or property
of another that, if due care was not taken, damage might be done by
the one to the other." I think that this sufficiently states the truth
if proximity be not confined to mere physical proximity, but be used,
as I think it was intended, to extend to such close and direct relations
that the act complained of directly affects a person whom the person
alleged to be bound to take care would know would be directly affected
by his careless act. That this is the sense in which nearness of "proximity"
was intended by Lord Esher is obvious from his own illustration in Heaven
v. Pender (3) of the application of his doctrine to the sale of
goods. "This" (i.e., the rule he has just formulated) "includes the
case of goods, etc., supplied to be used immediately by a particular
person or persons, or one of a class of persons, where it would be obvious
to the person supplying, if he thought, that the goods would in all
probability be used at once by such persons before a reasonable opportunity
for discovering any defect which might exist, and where the thing supplied
would be of such a nature that a neglect of ordinary care or skill as
to its condition or the manner of supplying it would probably cause
danger to the person or property of the person for whose use it was
supplied, and who was about to use it. It would exclude a case in which
the goods are supplied under circumstances in which it would be a chance
by whom they would be used or whether they would be used or not, or
whether they would be used before there would probably be means of observing
any defect, or where the goods would be of such a nature that a want
of care or skill as to their condition or the manner of supplying them
would not probably produce danger of injury to person or property."
I draw particular attention to the fact that Lord Esher emphasizes the
necessity of goods having to be "used immediately" and "used at once
before a reasonable opportunity of inspection." This is obviously to
exclude the possibility of goods having their condition altered by lapse
of time, and to call attention to the proximate relationship, which
may be too remote where inspection even of the person using, certainly
of an intermediate person, may reasonably be interposed. With this necessary
qualification of proximate relationship as explained in Le Lievre
v. Gould (1), I think the judgment of Lord Esher expresses the law
of England; without the qualification, I think the majority of the Court
in Heaven v. Pender (2) were justified in thinking the principle
was expressed in too general terms. There will no doubt arise cases
where it will be difficult to determine whether the contemplated relationship
is so close that the duty arises. But in the class of case now before
the Court I cannot conceive any difficulty to arise. A manufacturer
puts up an article of food in a container which he knows will be opened
by the actual consumer. There can be no inspection by any purchaser
and no reasonable preliminary inspection by the consumer."
- It is to be noted that
Lord Atkin, following earlier authority, spoke of "no reasonable preliminary
inspection by the consumer" and did not enter into questions of duty to inspect
or whether there was in fact inspection the question was simply whether
there was a reasonable possibility of inspection.
- Lord Atkin cautioned
against stating propositions of law in terms wider than necessary for the
facts (page 584), but he must have been a party to discussions of the wider
implications of the decision in that case, as shown in the dissenting speech
of Lord Buckmaster (with which Lord Tomlin agreed) at page 577:
"The principle
contended for must be this: that the manufacturer, or indeed the repairer,
of any article, apart entirely from contract, owes a duty to any person by
whom the article is lawfully used to see that it has been carefully constructed.
All rights in contract must be excluded from consideration of this principle;
such contractual rights as may exist in successive steps from the original
manufacturer down to the ultimate purchaser are ex hypothesi immaterial. Nor
can the doctrine be confined to cases where inspection is difficult or impossible
to introduce. This conception is simply to misapply to tort doctrine applicable
to sale and purchase.
The principle
of tort lies completely outside the region where such considerations apply,
and the duty, if it exists, must extend to every person who, in lawful circumstances,
uses the article made. There can be no special duty attaching to the manufacture
of food apart from that implied by contract or imposed by statute. If such
a duty exists, it seems to me it must cover the construction of every article,
and I cannot see any reason why it should not apply to the construction of
a house. If one step, why not fifty? Yet if a house be, as it sometimes is,
negligently built, and in consequence of that negligence the ceiling falls
and injures the occupier or any one else, no action against the builder exists
according to the English law, although I believe such a right did exist according
to the laws of Babylon. Were such a principle known and recognized, it seems
to me impossible, having regard to the numerous cases that must have arisen
to persons injured by its disregard, that, with the exception of George
v. Skivington LR 5 Ex 1, no case directly involving the principle has
ever succeeded in the Courts, and, were it well known and accepted, much of
the discussion of the earlier cases would have been waste of time, and the
distinction as to articles dangerous in themselves or known to be dangerous
to the vendor would be known to be meaningless."
- It is an open question
whether Lord Buckmaster would have been surprised to learn that 50 years later
in Murphy v. Brentwood D.C. the House of Lords would adopt principles
closer to the laws of Babylon though without the pains and penalties imposed
by those laws.
- The extent to which Lord
Buckmaster and Lord Tomlin were engaged in a hopeless argument against the
tide of legal development in favour of a compensation culture was shown by
a passage from Lord Tomlin's speech at page 600:
"The declaration
averred (inter alia) that the defendant 'so improperly and negligently conducted
himself' that the accident complained of happened.
The plaintiff's
counsel said 'Here the declaration alleges the accident to have happened through
the defendant's negligence and want of care.'
The alarming
consequences of accepting the validity of this proposition were pointed out
by the defendant's counsel, who said: 'For example, every one of the sufferers
by such an accident as that which recently happened on the Versailles Railway
might have his action against the manufacturer of the defective axle.' ''
- In Murphy v. Brentwood
D.C, the House of Lords took the 50th step feared by Lord Buckmaster
and declared that a duty rested on builders towards subsequent occupiers with
whom they had no contract. Should I take the 51st step and find
that architects owe a duty in similar circumstances?
- The decision of the House
of Lords in Murphy v. Brentwood D.C did not directly result in a builder
paying damages to compensate for injuries suffered as a result of the building
of an unsafe building. Rather, the decision of the appeal itself was to deny
liability on the part of a local authority in a case where the application
of a previous decision of the House of Lords in Anns v. Merton L.B.C
[1978] AC 728 had persuaded the judge at first instance to award damages against
the local authority. But the reasoning of the House of Lords in Murphy
v. Brentwood D.C made it clear that in certain circumstances a builder
would be liable to a subsequent owner of a building.
- In Murphy v. Brentwood
D.C, at page 487, Lord Oliver of Aylmerton said:
"There
can, of course, be no doubt that it can reasonably be foreseen that if an
inherently defective house is built or an inherently defective chattel is
manufactured some future owner will be likely to sustain loss when the defect
comes to light, if only because it is less valuable than it was thought to
be when he bought and paid for it. A series of decisions in this House and
in the Privy Council since Anns, however, have now made it clear beyond
argument that in cases other than cases of direct physical injury the reasonable
foreseeability of damage is not of itself sufficient and that there has to
be sought in addition in the relationship between the parties that elusive
element comprehended in the expression "proximity": see Governors of the
Peabody Donation Fund v. Sir Lindsay Parkinson & Co. Ltd. [1985] AC 210; Yuen Kun Yeu v. Attorney-General of Hong Kong [1988] A.C. 175;
Hill v. Chief Constable of West Yorkshire [1989] A.C. 53. It
is an expression which persistently defies definition but my difficulty in
rationalising the basis of Dutton and Anns is and has always been not
so much in defining it as in discerning the circumstances from which it could
have been derived. For reasons which I have endeavoured to explain, the starting
point in seeking to rationalise these decisions must, as it seems to me, be
to establish the basis of the liability of the person who is the direct and
immediate cause of the plaintiff's loss. Anyone, whether he be a professional
builder or a do-it-yourself enthusiast, who builds or alters a semi-permanent
structure must be taken to contemplate that at some time in the future it
will, whether by purchase, gift or inheritance, come to be occupied by another
person and that if it is defectively built or altered it may fall down and
injure that person or his property or may put him in a position in which,
if he wishes to occupy it safely or comfortably, he will have to expend money
on rectifying the defect. The case of physical injury to the owner or his
licensees or his or their property presents no difficulty. He who was responsible
for the defect - and it will be convenient to refer to him compendiously as
"the builder" - is, by the reasonable foreseeability of that injury, in a
proximate "neighbour" relationship with the injured person on ordinary Donoghue
v. Stevenson principles. But when no such injury has occurred and when
the defect has been discovered and is therefore no longer latent, whence arises
that relationship of proximity required to fix him with responsibility for
putting right the defect? Foresight alone is not enough but from what else
can the relationship be derived?"
Lord Oliver
then went on to discuss problems relating to economic loss which do not arise
in the present case.
- Lord Keith in the same
case, at page 460 cited words from the speech of Lord Wilberforce in Anns:
""Through
the trilogy of cases in this House - Donoghue v. Stevenson [1932] AC 562, Hedley Byrne & Co. Ltd. v. Heller & Partners Ltd. [1964] AC 465, and Dorset Yacht Co. Ltd. v. Home Office [1970] AC 1004,
the position has now been reached that in order to establish that a duty of
care arises in a particular situation, it is not necessary to bring the facts
of that situation within those of previous situations in which a duty of care
has been held to exist. Rather the question has to be approached in two stages.
First one has to ask whether, as between the alleged wrongdoer and the person
who has suffered damage there is a sufficient relationship of proximity or
neighbourhood such that, in the reasonable contemplation of the former, carelessness
on his part may be likely to cause damage to the latter - in which case a
prima facie duty of care arises. Secondly, if the first question is answered
affirmatively, it is necessary to consider whether there are any considerations
which ought to negative, or to reduce or limit the scope of the duty or the
class of person to whom it is owed or the damages to which a breach of it
may give rise: see [the] Dorset Yacht case [1970] AC 1004, per
Lord Reid, at p. 1027. Examples of this are Hedley Byrne's case
[1964] AC 465 where the class of potential plaintiffs was reduced to those
shown to have relied upon the correctness of statements made, and Weller
& Co. v. Foot and Mouth Disease Research Institute [1966] 1 Q.B. 569;
and (I cite these merely as illustrations, without discussion) cases about
"economic loss" where, a duty having been held to exist, the nature of the
recoverable damages was limited: see S.C.M. (United Kingdom) Ltd. v. W.
J Whittall & Son Ltd. [1971] 1 Q.B. 337 and Spartan Steel &
Alloys Ltd. v. Martin & Co. (Contractors) Ltd. [1973] QB 27."
After
further consideration of authority, Lord Keith said:
"Lord
Wilberforce went on, at pp. 758-759, to consider the position of the builder,
upon the view that it would be unreasonable to impose liability in respect
of defective foundations upon the council if the builder, whose primary fault
it was, should be immune from liability. This consideration was, I think,
a necessary part of the reasoning which led to his conclusion about the liability
of the local authority. The Dorset Yacht case, upon which Lord Wilberforce
was proceeding, was concerned with the liability of prison officers for failing
to take reasonable care to prevent the Borstal boys in their charge from acting
tortiously towards the owners of yachts moored in the vicinity of their encampment.
If the conduct of the boys had not been tortious there would have been no
liability on the prison officers. So, likewise, if the builder of defective
foundations had been under no liability in tort, the local authority could
have been under no liability for not taking reasonable care to see that he
did not construct defective foundations. Lord Wilberforce took the view that
the principle of Donoghue v. Stevenson [1932] AC 562 applied to the
builder of defective premises, there being no sound reason why that principle
should be limited to defective chattels.
I see
no reason to doubt that the principle of Donoghue v. Stevenson does
indeed apply so as to place the builder of premises under a duty to take reasonable
care to avoid injury through defects in the premises to the person or property
of those whom he should have in contemplation as likely to suffer such injury
if care is not taken. But it is against injury through latent defects that
the duty exists to guard. I shall consider this aspect more fully later."
At page
465, Lord Keith returned to the subject:
"However
an essential feature of the species of liability in negligence established
by Donoghue v. Stevenson was that the carelessly manufactured product
should be intended to reach the injured consumer in the same state as that
in which it was put up with no reasonable prospect of intermediate examination:
see per Lord Atkin, at p. 599; also Grant v. Australian Knitting
Mills Ltd. [19361 A.C. 85, 103-105, per Lord Wright. It is the
latency of the defect which constitutes the mischief. There may be room for
disputation as to whether the likelihood of intermediate examination and consequent
actual discovery of the defect has the effect of negativing a duty of care
or of breaking the chain of causation (compare Farr v. Butters Brothers
& Co. [1932] 2 K.B. 606 with Denny v. Supplies & Transport
Co. Ltd. [1950] 2 K.B. 374). But there can he no doubt that, whatever
the rationale, a person who is injured through consuming or using a product
of the defective nature of which he is well aware has no remedy against the
manufacturer. In the case of a building, it is right to accept that a careless
builder is liable, on the principle of Donoghue v. Stevenson, where
a latent defect results in physical injury to anyone, whether owner, occupier,
visitor or passer-by, or to the property of any such person. But that principle
is not apt to bring home liability towards an occupier who knows the full
extent of the defect yet continues to occupy the building."
- The last sentence was
qualified by the Court of Appeal in Targett v.Torfaen B.C. [1992] 3
All ER 27 (following Rimmer v. Liverpool City Council [1984] 1 All ER 930) where it was pointed out that in some cases, (for example a person
of limited means in residential property) an occupier of premises may become
aware of a defect and be unable in effect either to move from the property
or remedy the defect and in those circumstances that person is not deprived
of a remedy. That consideration does not apply in the present case.
- Counsel have cited to
me other decisions, including D & F Estates v. Church Commissioners
for England [1989] AC 177 and Department of the Environment v. Bates
[1991] AC 499, both decisions forming part of the line of ground breaking
decisions in cases started before the Official Referees. Those two decisions
are mainly concerned with considerations of "pure economic loss" which do
not concern me.
- By the decision in Marc
Rich v. Bishop Rock Marine [1996] AC 211 the House of Lords made plain
that in addition to foreseeability and proximity, there were other requirements
before a duty of care was imposed on a defendant. At page 235 Lord Steyn said:
"
since
the decision in Dorset Yacht Co. Ltd. v. Home Office [1970] AC 1004 it has been settled law that the elements of foreseeability and
proximity as well as considerations of fairness, justice and reasonableness
are relevant to all cases whatever the nature of the harm sustained by the
plaintiff. Saville L.J. explained, at p. 1077:
'whatever
the nature of the harm sustained by the plaintiff, it is necessary to consider
the matter not only by inquiring about foreseeability but also by considering
the nature of the relationship between the parties; and to be satisfied that
in all the circumstances it is fair, just and reasonable to impose a duty
of care. Of course . . . these three matters overlap with each other and are
really facets of the same thing. For example, the relationship between the
parties may be such that it is obvious that a lack of care will create a risk
of harm and that as a matter of common sense and justice a duty should be
imposed. . . . Again in most cases of the direct infliction of physical loss
or injury through carelessness, it is self-evident that a civilised system
of law should hold that a duty of care has been broken, whereas the infliction
of financial harm may well pose a more difficult problem. Thus the three so-called
requirements for a duty of care are not to be treated as wholly separate and
distinct requirements but rather as convenient and helpful approaches to the
pragmatic question whether a duty should be imposed in any given case. In
the end whether the law does impose a duty in any particular circumstances
depends upon those circumstances.'
That seems
to me a correct summary of the law as it now stands."
- So, in the present case,
have the claimants shown foreseeability of harm and proximity on the part
of the defendants, and that it is fair just and reasonable that the defendants
should be found to owe a duty to the claimants?
- I have no difficulty
in finding that it was reasonably, indeed easily, foreseeable by the defendants
that a future occupier of the premises falling within a class of persons likely
to occupy the premises would suffer damage to his goods as a result of the
defects that the defendants caused or allowed to exist in the premises.
- The requirements of proximity
and "fair just and reasonable" are difficult to define and they overlap. They
are also closely linked in this case with the consideration in Donoghue
v. Stevenson of "reasonable opportunity of inspection". In Donoghue
v. Stevenson, Lord Atkin propounded the relationship between reasonable
opportunity of inspection and proximity:
"I draw
particular attention to the fact that Lord Esher emphasizes the necessity
of goods having to be 'used immediately' and 'used at once before a reasonable
opportunity of inspection.' This is obviously to exclude the possibility of
goods having their condition altered by lapse of time, and to call attention
to the proximate relationship, which may be too remote where inspection even
of the person using, certainly of an intermediate person, may reasonably be
interposed."
- In Murphy v. Brentwood
D.C., in the passage that I have already cited, Lord Oliver said that
he found difficulty in defining "proximity". Later he said,
"The case
of physical injury to the owner or his licensees or his or their property
presents no difficulty. He who was responsible for the defect - and it will
be convenient to refer to him compendiously as "the builder" - is, by the
reasonable foreseeability of that injury, in a proximate "neighbour" relationship
with the injured person on ordinary Donoghue v. Stevenson principles.
But when no such injury has occurred and when the defect has been discovered
and is therefore no longer latent, whence arises that relationship of proximity
required to fix him with responsibility for putting right the defect? Foresight
alone is not enough but from what else can the relationship be derived?"
- One must now accept,
following Murphy, that a builder owes a duty to a subsequent occupier
in appropriate circumstances. I think it must follow that I must take the
51st step and hold that an architect also may owe a duty and be
liable in appropriate circumstances.
- In the present case,
the precise defects had not been discovered before the floods, but there had
been at least one previous flood evidenced by markings on the floor of the
building. In my opinion, the duty of the defendants to the claimants must
depend on the question, "Was there a reasonable opportunity of inspection
of the drainage system and discovering the defects before the floods?" If
the claimants had a reasonable opportunity of inspecting the drainage system
and discovering the defects before they suffered damage, it would not be fair
just or reasonable to hold the defendants liable for that damage nor would
it be right to say that there was a proximate relationship between the claimants
and the defendants.
- There was a reasonable
opportunity of inspecting the building before the claimants took a lease.
It would be normal procedure for any incoming tenant to have the building
inspected by a surveyor, and that is what they did. Although the claimants
received warnings from both the surveyors and from Mr. Meiklejohn of a danger,
they were not told what was the precise problem. The surveyors could, and
in my view should, have told the claimants that there were no overflows and
that overflows should be provided. The cost of overflows was very small and
if the claimants had been advised to install them I cannot think that they
would have failed to do so.
- If Lambert Smith Hampton
had been more assiduous in the performance of their duties, the claimants
would have been expressly warned of the absence of overflows and the floods
would not have occurred. To what extent is the claimants' claim affected by
the acts of their professional advisers? Are they entitled to say, as they
might in response to a defence of contributory negligence, that they took
skilled advice and are entitled to rely on that advice? I do not think that
is the right approach. I do not think that it is fair just or reasonable that
the extent of the liability of the defendants should depend on the assiduity
of the surveyors instructed by the claimants. The claimants had the opportunity
to discover the absence of overflows by reasonable inspection by professional
advisers who might reasonably be expected to be instructed: whether that reasonable
opportunity in fact revealed the defect is irrelevant. Because there was a
reasonable opportunity to inspect, the defendants were not in a proximate
relationship to the claimants so far as concerns defects which could have
been discovered by that inspection, namely, the absence of overflows. But
I repeat my previous finding that neither the claimants nor their surveyors
could reasonably be expected to have discovered the under design of the drainage
system.
Conclusion
- I find that:
- The defendants owed
a duty of care to the claimants in respect of latent defects in the building
occupied by them in respect of which there was no reasonable possibility
of inspection.
- In considering the
question whether there was a reasonable possibility of inspection, it is
not open to the claimants to say that they reasonably relied on competent
advisers and on that account the duty is not negatived.
- There was a reasonable
possibility of inspection by the claimants or their professional advisers
which would have discovered the absence of overflows but not the under design
of the system.
- The first flood was
caused by a combination of blockages of the drains for which the defendants
were not responsible and the absence of overflows. The under design of the
system was not a contributing cause of the first flood. Since the claimants
could reasonably have discovered the absence of overflows, the defendants
no longer owed them a duty in that regard and therefore the claimants can
prove no breach of duty in relation to the first flood.
- The second flood was
caused by a combination of the under design of the system and the absence
of overflows. Blockages of the system were not a contributory cause of the
second flood. While there was a reasonable opportunity to inspect which
should reasonably have revealed the absence of overflows, it cannot be said
that the opportunity to inspect should reasonably have revealed the under
design of the system. The defendants are therefore responsible for one primary
cause of the second flood though not for the other. On ordinary principles
of liability in tort, the defendants are therefore liable for the whole
of the loss arising from the second flood. Blockage of the system not being
a contributory cause of the second flood, the question of contributory negligence
does not arise.
- The claimants are entitled
to no compensation in respect of the first flood but they are entitled to
damages and interest on those damages in respect of the second flood. In
respect of the second flood, the claimants were not guilty of contributory
negligence. The damages are agreed at £612,153.02. The interest will be
calculated up to the date of this judgment.
© 2000 Crown Copyright