IN THE HIGH COURT OF
JUSTICE
QUEEN'S BENCH
DIVISION
TECHNOLOGY AND CONSTRUCTION
COURT
BEFORE: HIS
HONOUR JUDGE RICHARD SEYMOUR Q.C.
BETWEEN:
MILLER
CONSTRUCTION LIMITED
|
Claimant
|
|
and
|
||
JAMES
MOORE EARTHMOVING
|
Defendant
|
Case number: 2000 Folio 462
Dates of Trial: 16 and 17 October 2000
Date of Judgment: 1 November 2000
John Marrin Q.C. and Kate
Gordon for the claimants (Dundas and Wilson, Solicitors )
Michael Bowsher and Martino
Giaquinto for the defendant (Wragge & Co., Solicitors )
JUDGMENT
I direct that no further note or transcript be made of this judgment.
The text of the Judgment of His Honour Judge Richard Seymour Q.C. is as follows:
JUDGMENT
Introduction
Mr. Moore's Sub-Contract
"The contract between James Moore Earthmoving, the Claimant and Miller Construction Limited, the Respondent included the Federation of Civil Engineering Contractor's form of sub contract revised in September 1984, intended for use in conjunction with the I.C.E. Conditions of Contract with minor amendments, together with a letter of 25th October 1991 stating "Our price for the total earthworks package is based upon a "Back to Back" arrangement with the Main Contractor on a subcontract FCEC blue form" and a minute of a meeting dated 23rd January 1992. Clause 18 of the FCEC form of sub contract provides for any dispute to be referred to the Arbitration and final decision of a person to be agreed by the Parties, or failing such agreement appointed upon the application of either of the Parties by the President for the time being of the Institution of Civil Engineers."
"Subject to the Sub-Contractor's complying with this sub-clause, the Contractor shall take all reasonable steps to secure from the Employer such contractual benefits, if any, as may be claimable in accordance with the Main Contract on account of any adverse physical conditions or artificial obstructions or any other circumstances that may affect the execution of the Sub-Contract Works and the Sub-Contractor shall in sufficient time afford the Contractor all information and assistance that may be requisite to enable the Contractor to claim such benefits. On receiving any such contractual benefits from the Employer (including any extension of time) the Contractor shall in turn pass on to the Sub-Contractor such proportion thereof as may in all the circumstances be fair and reasonable. Save as aforesaid the Contractor shall have no liability to the Sub-Contractor in respect of any condition, obstruction or circumstance that may affect the execution of the Sub-Contract Works and the Sub-Contractor shall be deemed to have satisfied himself as to the correctness and sufficiency of the Price to cover the provision and doing by him of all things necessary for the performance of his obligations under the Sub-Contract. Provided always that nothing in this Clause shall prevent the Sub-Contractor claiming for delays in the execution of the Sub-Contract Works solely by the act or default of the Main Contractor on the ground only that the Main Contractor has no remedy against the Employer for such delay."
Mr. Moore's Claims
The procedure at the hearing
The Award
"1 Did the Claimant encounter adverse physical conditions and/or obstructions which could not have been foreseen as pleaded in Annex 2 of the Re re amended Points of Claim?
"2 In respect of which if any of these conditions or obstructions is the Claimant entitled to recover sums pursuant to clause 10(2) of the Sub-Contract except insofar as identified by Engineer and paid for by him?
"3 Was the Claimant's performance of its Sub-Contract affected by
"4 Is the Claimant entitled to recover sums calculated on the "entitlement" basis set out in Appendix 3.8 of the Re re amended Points of Claim pursuant to the Sub-Contract or otherwise?
"5 If so, what sum is the Claimant entitled to recover on this basis?
"6 What sum, if any, is the Claimant entitled to recover on the alternative basis of calculation in respect of delay and disruption (Winter working + Prolongation (Annex 4)?
"7 Is the Claimant entitled to recover from the Respondent the sums paid by it as rates in respect of site establishment and tipping areas required for performance of the Sub-Contract?"
That the Arbitrator understood what the Award was intended to address appears from paragraph 7.1 of the Award, where he wrote:
"The Parties have expressed their wish that I make an Interim Award in the following terms given to me on the first day of the Hearing in Birmingham 1st September 1999".
In the event, the fifth of these grounds was, rightly, in my judgment, but faintly pursued, while the sixth rather became subsumed, again, in my judgment, rightly, in the issues raised by the application for permission to appeal on questions of law.
"This does seem to me a most serious matter. The Judge put this test to himself in his judgment: Are the circumstances such as to demonstrate that the arbitrator is not a fit and proper person to conduct the arbitration proceedings? I do not think that was the right test. I would ask whether his conduct was such as to destroy the confidence of the parties, or either of them, in his ability to come to a fair and just conclusion.
"The question is whether the way he conducted himself in the case was such that the parties can no longer have confidence in him. It seems to me that if this arbitrator is allowed to continue with this arbitration one at least of the parties will have no confidence in him. He will feel that the issue has been pre-judged against him. It is most undesirable that either party should go away from a Judge or an arbitrator saying, "I have not had a fair hearing".
"I know the inconveniences to which the removal of the arbitrator may give rise – the delay, the extra expense, and the like. But it seems to me that it is far more important that this Court should see that arbitrations are properly conducted so that the arbitrator can have the confidence of those who appear before him. Arbitration is now one of the most important spheres of activity in the system of administering justice in this land. The Courts, I feel, must show an example and see that arbitrations are properly conducted so as to earn and deserve the confidence of those who appear before them. I am afraid that the conduct of this arbitrator was such as to lose that confidence – at least of one of the parties."
Thus, if I were persuaded that the Arbitrator in this case had failed to give one of the parties the opportunity to be heard on some matter before him for determination in the Award, or if I were persuaded that he had decided, in the Award, some matter which was not before him for determination at that stage, I should have to consider most carefully, in the light of other authorities more recent than Modern Engineering (Bristol) Ltd. v C. Miskin & Son Ltd., as well as in the light of that decision itself, what was the appropriate course to take.
"6.1
FIRSTLY
The Respondent pleaded that payment on an entitlement basis is not a contractural [sic] benefit File A2. p.5, claimable in accordance with the main contract within the meaning of Clause 10(2) (of the FCEC sub contract)
"I find from the evidence the entitlement payment is based upon the resources used in carrying out the works which comprised the contract albeit during notional time. I find that these payments are a benefit derived from the execution of the main contract and that in accordance with FCEC Subcontract Clause 10(2) the Contractor shall take all resonable [sic] steps to secure from the Employer such contractural [sic] benefits, if any, as may be claimable in accordance with the main contract on account of adverse physical conditions or artifical [sic] obstructions or any other circumstances which may affect the execution of the subcontract works and the Subcontractor shall in sufficient time afford the Contractor all information and assistance that may be requisite to enable the Contractor to claim such benefits. On receiving such contractural [sic] benefits from the Employer (including any extension of time) the Contractor shall in turn pass on to the Subcontractor such proportion thereof as may, in all the circumstances, be fair and reasonable. etc.
"B.S.C. v Cleveland Bridge and Engineering. Constantine Line v Imperial Smelting and BP Explorations (Libya) v Hunt considered.
"SECONDLY
6.2
The question of notice of claims and the clause of the subcontract under which they are made has been raised in response to J Moore's claims. In particular Mooney v Henry Boot Construction Ltd 80 BLR p 66.has been quoted in support of the Respondents reply to these claims.
"I consider the question of notice within the time and in the form necessary to comply with the requirements of Clauses 6,7 and 10 of the sub contract has been waived by the application of the entitlement method of paying for variation of the works, clause 12 claims and disruption and delay on the main contract, on a notional rather than a factual basis, this view takes into account the sub contract special provision that J Moore and Miller would act "Back to Back" in recovering sums due under the contract, confirmed by the outcome of the meeting between Messrs. J Moore and R Wilson which I find took place in May 1992 at which it was agreed the Parties would proceed together on claims and that J Moore would receive fair treatment, I do not however accept it was agreed at this meeting J Moore was promised payment on the entitlement method. It is acknowledge [sic] the site was unusually open with free exchange of information and co-operation to complete the works on the due date.
"6.3
As a result of this Miller prepared claims based on J Moore's resources to obtain entitlement payments for the Main Contract variations, clause 12 claims and disruption and delay, due to both parties. These claims were largely prepared by Mr.I Hearne Miller's assistant project manager, acknowledged as particularly interested in earthworks, to obtain payments from the Employer under the entitlement method, or should it be withdrawn by the Engineer a private shadow collection of data for the basis of traditional claims.
"6.4
I find J Moore could reasonably rely on these arrangements to relieve him of the need to give notices and details formally to Miller in accordance with the strict terms of the sub contract set out above, to obtain his fair and reasonable proportion of the entitlement payments.
"THIRDLY
6.5
On the question of the Best Endeavours Programme and it's effect upon the timing and efficiency of J Moore's work. I find the Best Endeavours Programme was an internal concept of Miller to achieve the Employers desired completion date and that this target was achieved by Miller's site short term programmes which caused disruption to J Moore, I find, Mr O' Neil's evidence that these short term programmes were not instructions, unconvincing particularly as Clause7 (2) of the sub contract binds the sub contractor to comply with the main contractors instructions."
The "entitlement method" referred to in the passage quoted was, in essence, a method of compensation agreed between Miller and the Engineer appointed under the terms of the contract between Miller and its client which was intended as a means of recompensing Miller for the delays and disruptive effect of various events which occurred during the course of the Main Contract Works.
Issue 2 and Issue 4
"2.1
In respect of which if any of these conditions or obstructions is the Claimant entitled to recover sums pursuant to clause 10 (2) of the Sub-Contract except in so far as identified by the Engineer and paid for by him?
"2.2
The Engineer certified the direct costs of meeting the unforseen [sic] conditions or obstructions under Clause 12 of the main contract as follows:
£ | |||
Additional Rock Quantities | 20,066.95 | ||
Unforseen [sic] conditions in rock cuttings | 25,000.00 | ||
Rock encountered in spoil heap cut | 9,896.02 | ||
Stiffer clay matrix and larger and | |||
more numerous boulders in Broughton Road cut | 90,198.00 | ||
£ 145,160.97 |
"2.3 This sum includes ££9896.02, spoil heap cut, which the Respondent admits should have been paid to J Moore. In addition a proportion of the entitlement payment is due for disruption and delay associated with this work. Noted from Mr Rodger's evidence and Mr Forrest calculation of a period of 5 weeks entitlement.
"2.4 J Moore alleges Miller did not pursue his claims for unforseen [sic] adverse physical contions [sic] with due dilligence [sic], particularly for those encountered in June and October 1992 which Miller claimed late, resulting in rejection on this ground by the Engineer. J Moore states Miller had little incentive to make Clause 12 claims as it was concentrating on entitlement, confirmed by Mr Notman's evidence. On the subject of disruption and delay both, Mr Sleightholm and Mr Mycock acknowledged the sub contractor is entitled to payment for his substantiated claims.
"2.5
Taking account of the precedents Mooney v Henry Boot Construction Ltd., Wharfe Properties and another v Eric Cumine Associates, British Steel Co v Cleveland Bridge and William Lacey v Davis and the evidence adduced before me:
"2.6
I find the alleged breach of contract arising from Millers failure to present claims in which a portion was due to J Moore cannot be sustained. Claims were submitted to the Engineer for consideration, albeit the claim for work in 1992 was submitted late and rejected by the Engineer on that ground rather than consideration of it's [sic] merits, leaving the potential result unknown. Under the terms of the sub contract Clause 10 (2) the sub contractor's payment for unforseen [sic] adverse physical conditions or artificial obstructions (including any extension of time) is only due to be paid by the main contractor if it is a contractural [sic] benefit payable by the employer. The Employer is bound to comply with the terms of Clause 12 of the main contract and the Engineer's decisions thereon which limits the sums to be paid to the sub contractor under the sub contract Clause 10 (2), to those certified by the Engineer on this Issue No.2.
"2.7
I find the sums awarded by the Engineer's certification of the Clause 12 claims to Miller and to be paid by Miller to J Moore are limited to the direct costs plus a portion of the entitlement identified by the Engineer and assessed by Mr Forrest at 5 weeks, which I consider fair and reasonably due to J Moore
£ | |||
Direct costs less already paid | 9,896.02 | ||
5 x one 45th of the notional entitlement (appendix 3.8) | |||
of £778.271.98 | 86,092.03 | ||
Total | £ 97,988.05 " |
"The engineer accepted that rock was not foreseeable at all in Spoil Heap Cut and therefore certified a net sum of £9,896.02. By oversight, this sum has not been paid to the Claimant and it is admitted that it should have been paid".
That is all that was said on the subject of the £9,896.02 in the closing submissions. Although Mr. Marrin sought to suggest in his submissions to me that the apparent acceptance of a liability to pay £9,896.02 should be viewed as, in effect, an acceptance that that element, subject to any other adjustments which were appropriate, was due, not an admission that it was immediately due, I see no reason to regard the statement in Mrs. Gordon's closing submissions as so qualified.
"4.1
Is the Claimant entitled to recover sums calculated on the "entitlement" basis set out in Appendix 3.8 of the Re re amended Points of Claim pursuant to the Sub-Contract or otherwise
"4.2
This question arises from arrangements made at a meeting or series of meetings of the 6th May 1992 when an acknowledged shortage of tipping space and variation of the works at Hagg Gill were likely to delay the works, and likely to lead to claims for disruption and delay. Prior to this meeting, in mid April 1992 the Engineer had indicated to Miller that he proposed to deal with matters which normally led to traditional claims in a novel way which he described as the "entitlement method" as defined in Appendix C.
"4.3
The sub contract included an arrangement requiring the Parties to act "Back to Back" which I take to mean on matters of costs recovery from the Employer via the Engineer the Parties would look after each others interests. This situation was discussed at the 6th May 1992 meeting or meetings. The differences in the site administration resources of Miller compared to J Moore made this approach desirable as Miller would need to incorporate J Moore's costs in representations to the Engineer, although not following the traditional operation of the sub contract in relation to the main contract where notices and detailed claims are passed from the Sub Contractor to the main Contractor for submission to the Engineer. A Mr Hearne, Miller's assistant projects manager was responsible for the assembly of the necessary data for both Parties.
"4.4
Miller was doubtful whether the Engineer and Employer would persist with the novel entitlement method, consequently as a safeguard it prepared shadow private traditional claims using information collected from J Moore acknowledged by Mr Mycock. J Moore received interim payments in response to their submissions, excluding disruption and delay costs which were covered by the Entitlement method.
"4.5
Miller's Counsel Mrs Gordon avered [sic] the lack of pressure from J Moore suggested it did not expect to receive money from the Entitlement route. However J Moore was not party to the entitlement cost recovery meetings. The Entitlement payments to Miller certified by the Engineer are set out in the Claimants pleadings p.250. It is clear from the evidence adduced J Moore incurred additional costs to the measured work recovery, due to disruption and delay and that his resources involved have been used to assess the Entitlement payments to Miller for variation of the works and unforseen [sic] physical conditions.
"4.6
I am satisfied the meeting between Messrs J Moore and R Wilson took placed [sic] during which, although the form of and the details of the Entitlement method were unknown, Miller agreed an arrangement to give notices and prepare details of costsof disruption and delay of voth Parties on the "Back to Back" contractural [sic] basis. I do not accept Mrs Gordon's averment that J Moore's delay in persuing [sic] payments for disruption and delay is justification for saying he did not expect payment, for on civil engineering work this payment is usually delayed by protracted negotiations with the Engineer. Miller admits J Moore is entitled to it's proven disruption and delay costs.
"Taking into account the precedents. Mooney v Henry Boot Construction Ltd. Constantine Steamship Line Ltd v Imperial Smelting Corporation Ltd. BSC v Cleveland Bridge and Engineering Co. Ltd. BP Exploration Co. (Libia) Ltd v Hunt William Lacy v Davis Way v Latilla Mid Glamorgan v J Devonald Williams and Partner Costain v Zanex Text "The Law of Restitution" Wharf Properties Ltd v Eric Cumine Associates London Borough of Merton v Leach and Crosby v Portland U.D.C.
The documents presented, the evidence adduced and the matters set out above.
I find the answer to the question raised as Issue 4 is "Yes"
17. The Arbitrator's findings about Issue 5 were:
"5.2
I find the sums the Claimant Sub Contractor J Moore is entitled to recover on the Entitlement basis are most accurately and reasonably proven by the Engineers dispassionate assessment of the Sub Contractor's costs set out in Appendix 3.8 of the Entitlement recovery schedule Page 272 of the Claimant's Pleadings. Having awarded 5 weeks of this entitlement to the Sub Contractor under Issue 2. I find he is entitled to the 40.2 weeks sums set out in Appendix 3.8 Entitlement Recovery Schedule. Page 272 of the Hearing bundle in the sum of:-
40.2 x £778,271.98 =£692,179.94
45.2
"9.(a)
Issue 5 which requires a Quantum Award is connected with Issue 2. For clarity it is sensible to separate the sums identified by the Engineer to the separate issues rather than deal with moneys related to two issues under Issue 5.
"9.(b)
Issue 2 wording refers to sums identified by the Engineer related to Clause 10.2 events, the sum awarded was that identified by the Engineer to this issue. No prohibition on the Award of Quantum is present in the issue wording."
"Do there exist grounds from which a reasonable person would think that there was a real likelihood that (the arbitrator] could not, or would not, fairly determine the [relevant issue or issues] on the basis of the evidence and arguments to be adduced before him?"
Later he said:-
"The reasonable person does not have to establish that his confidence has been wholly destroyed: it is enough that there is a real likelihood that the issue which is left to be determined would not be fairly determined if remitted to the arbitrator."
Ackner LJ had previously indicated that, in his view, the outcome in Modern Engineering (Bristol) Ltd v C. Miskin & Son Ltd would have been the same whether an objective or a subjective test had been adopted, saying:-
"In my judgment Lord Denning,MR, was not applying his mind as to whether the test was an objective or a subjective one, understandably, in that case, because whether one applies a subjective test or one which is based upon an objective approach, the reaction of a reasonable person, the result in that case would have been the same. Therefore I do not view that case as being a decision which deals the point at issue."
In Lovell Partnerships (Northern) Ltd. v A W Construction plc (1996) 81 BLR 83 at p.99 Mance J, as he then was, said, in the context of whether, in a case in which the question arose what remedy was appropriate if an arbitrator had misconducted himself or the proceedings, that the test to be applied was:-
"…whether a reasonable person would no longer have confidence in the present arbitrator's ability to come to a fair and balanced conclusion on the issues if remitted ".
Issue 6 and Issue7
24. In relation to Issue 6 the Arbitrator found in the Award as follows:-
"6.2
Due to the difficulty and potential delay in obtaining the attendance of the Quantum Experts at a meeting with me to explain the convoluted nature on the quantum evidence on this Issue. I find I am unable to answer the question raised in this Issue
"6.3
I find from the precedent Shore and Horwitz Construction Co. Ltd and Franks of Canada and the text Keating on Building Contracts P.230. The following matters need to be considered:-
a. Mr J Moore's evidence that scrapers and their motive power plant would in a normal winter, stand unused and non earning part of the time.
b. I find Mr Notmans view that the plant rates used in calculating plant standing should be the sub contract inter company rates adjusted to allow for unused consumables, to be the most reasonable and convincing of the various plant rates considered.
c. Allowance shall be made for the costs which would have been recoverable for the use of plant taken as standing which would have been used if the original Clause 14 programme timing had been followed."
"7.2
I find from consideration of the precedent South West Aluminium Co. Ltd v Assessment Committee for the North Assessment Area. The tips obtained specifically for disposal of material excavated for the works if subject to business rates are, in my view, the responsibility of the Employer or failing him the Main Contractor. Business rates due on quarries from which J Moore extracted rock for the works and the subsequent void filling, are the responsibility of the Sub Contractor who negotiated the use of the quarries with the owner for his own purposes. On the question of business rates for the Sub Contractors temporary buildings, I consider he is responsible for these rates including those on the buildings which the Main Contractor provided under the terms of the memorandum of 23 January 1992, for a tenant subject to a special agreement otherwise, is normally liable for such rates. Providing the demand for these rates and clear evidence of the areas or structures to which they specifically apply are provided, the sums paid for the tips obtained specifically for disposal of material excavated from the works are due to be paid by Miller to J Moore".
The substance of Mr. Marrin's complaint in relation to Issue 7 is similar to that of his complaint in relation to Issue 6, namely that the parties had been expecting the Arbitrator to decide the issue on the evidence and argument which he had already heard and it was wrong of him not to do so without giving the parties the chance to make submissions.
The applications for permission to appeal
"If and insofar as the basis of the Award on Issue 4 was that the Defendant was entitled to recover on the Entitlement basis under 10 (2) of the sub Contract, the Arbitrator erred in law in finding that entitlement receipts by the Claimant were contractual benefits claimable under the Main Contract on account of any adverse physical conditions or artificial obstructions or any other circumstance that may affect the execution of the sub-contract works"
and
"The arbitrator erred in law in that he found (paragraph 7.2) that sums paid by the Defendant as rates on tips obtained specifically for disposal of material excavated from the works are due to be paid by the Claimant to the Defendant"
The first of these grounds involved the submission that, on a proper understanding of the Award, what the Arbitrator had done was to hold that Mr. Moore was entitled to recover from Miller under clause 10 (2) of its sub-contract, the terms of which I have quoted above, a proportion of the sums paid to Miller on the "Entitlement" basis, notwithstanding that it appeared on the face of the Award that the sums so paid included monies paid in respect of what, under the Main Contract, were variations. It was submitted by Mr. Marrin that, in so finding, the Arbitrator had disregarded, or misunderstood, the effect of the decision of the Court of Appeal in Mooney v Henry Boot Construction Ltd (1996) 80 BLR 66 that clause 10 (2) of the form of sub-contract with which I am here concerned only entitled a sub-contractor to benefits obtained by the main contractor under clause 12 (3) of the ICE Form, and only then if those benefits were not the result of an instruction or variation. The second of the grounds depended upon the submission that the Arbitrator had disregarded, or misunderstood, the effect of the decision in South Wales Aluminium Co. Ltd. v Assessment Committee for the Neath Assessment Area [1943] 2 All ER 587, to which the Arbitrator himself referred in paragraph 7.2 of the Award, which I have quoted above, in reaching his conclusion that tips and quarries were "structures" for the purposes of clause 26 of the ICE Form.
The appeal on Ground 2