IN
THE HIGH COURT OF JUSTICE
QUEENS BENCH
DIVISION
TECHNOLOGY
AND CONSTRUCTION COURT
IN THE MATTER OF THE HOUSING, GRANTS, CONSTRUCTION AND REGENERATION ACT 1996
BEFORE HIS HONOUR JUDGE BOWSHER Q.C.
BETWEEN:
ABB ZANTINGH LIMITED
Claimant
AND
ZEDAL BUILDING SERVICES LIMITED
Defendant
Case
number: 00 400
Dates of
trial: 1 Dec 00
Date of judgment: 12
Dec 00
For the claimant:
Mark Raeside (DLA, solicitors)
For the defendant:
Simon Lofthouse (Eversheds, solicitors)
JUDGMENT
I direct that no further note or transcript be made of this judgment
Judgment:
Introduction
History
"Zedal's work under this contract was the supply, installation and testing of HV and LV electrical works to a colour printing facility. The primary activity of the site is that it is a printing works, which does not fall under any of the exemptions under section 105(2)(c) of the Housing Grants Construction and Regeneration Act, 1996".
That statement of Zedal's case directs attention to the principal point at issue in this case. What is the site? Is the site the whole of the printing works, or is it limited to the enclosure within that larger site in which the generating equipment was erected?
The evidence
"i. "The Mirror Colour Print Sites include the land upon which the standby generators are located (Brown 1 para 2.1 [File 2/p393]/ Hayton 1 para 11 [File 1/p8])
ii. The standby generators are owned by MCP under a lease from SSE (Hayton 1 para 10[File 1/p8])
v. Similarly at the Oldham Site, limited planning permission for temporary siting of standby generators was granted to 30.6.00 [p391].
vi. Mirror Colour Print are not a power generating company [Brown 1 para 2.3 [File 2/p393]). Their principal activity is contract newspaper printing primarily for fellow subsidiary undertakings [File 2 p414 and 427].
(In the light of the above it is, perhaps, unsurprising that there is no evidence of any arrangement for the supply of electricity by MCP back to the National Grid."
The Law
"105(1) In this Part "construction operations" means, subject as follows, operations of any of the following descriptions-
(a) construction, alteration, repair, maintenance, extension, demolition or dismantling of buildings, or structures forming, or to form, part of the land (whether permanent or not);
(b) construction, alteration, repair, maintenance, extension, demolition or dismantling of any works forming, or to form, part of the land, including (without prejudice to the foregoing) walls, roadworks, power-lines, telecommunication apparatus, aircraft runways, docks and harbours, railways, inland waterways, pipelines, reservoirs, water-mains, wells, sewers, industrial plant and installations for purposes of land drainage, coast protection or defence;
(c) installation in any building or structure of fittings forming part of the land, including (without prejudice to the foregoing systems of heating, lighting, air-conditioning, ventilation, power supply, drainage, sanitation, water supply or fire protection, or security or communications systems;
(d) external or internal cleaning of buildings and structures, so far as carried out in the course of their construction, alteration, repair, extension or restoration;
(e) operations which form an integral part of, or are preparatory to, or are for rendering complete, such operations as are previously described in this subsection, including site clearance, earthmoving, excavation, tunnelling and boring, laying of foundations, erection, maintenance or dismantling of scaffolding, site restoration, landscaping and the provision of roadways and other access works;
(f) painting or decorating the internal or external surfaces of any building or structure.
(2) The following operations are not construction operations within the meaning of this Part-
(a) drilling for, or extraction of, oil or natural gas;
(b) extraction (whether by underground or surface working) of minerals, tunnelling or boring, or construction of underground works, for this purpose;
(c) assembly, installation or demolition of plant or machinery, or erection or demolition of steelwork for the purposes of supporting or providing access to plant or machinery, on a site where the primary activity is-
(i) nuclear processing, power generation, or water or effluent treatment, or
(ii) the production transmission, processing or bulk storage (other than warehousing) of chemicals, pharmaceuticals, oil, gas, steel or food and drink,
(d) manufacture or delivery to site of-
(i) building or engineering components or equipment,
(ii) materials, plant or machinery, or
(iii) components for systems of heating, lighting, air-conditioning, ventilation, power supply, drainage, sanitation, water supply or fire protection, or for security or communications systems,
except under a contract which also provides for their installation;
(e) the making, installation and repair of artistic works, being sculptures, murals and other works which are wholly artistic in nature."
"The following operations are not construction operations ... installation ...of plant... on a site where the primary activity is ... power generation."
In the present case (though not necessarily in others) the most important word there is "site". How is "site" to be defined in the circumstances of this case?
"Installation
Plant
Site
Power generation."
Power generation is not in issue. I shall consider the other three topics suggested by counsel.
Zedal accept that they installed (1) neutral earthing contactors and resisters; (2) the switch gear cabling and marshalling boxes; (3) the LV distribution boards. Zedal do not appear to contest their involvement in the control cables for the computer management system and the measuring and management system. There are issues about other work alleged to have been done by Zedal. I cannot resolve those issues on the evidence before me, and I do not think it important that I should try to do so. On the contrary, I think it important that I should not comment on those issues since they may be the subject of later dispute in arbitration or litigation. Zedal's contract was for a relatively small amount of work that was increased by variations. Both the making and the execution of the variations may be matters of dispute later.
Mr. Malcolm Evans in his witness statement on behalf of Zedal said that cables, cable trays and cable ladders are not referred to as plant within the electricity construction industry. Clearly, one does not want to have lawyers' language about these things that differs from the language of the man on the shop floor. But there is a difference between a drum of cable on the floor and the same cable worked into a piece of plant, or even joining one piece of plant with another. The drum of cable on the floor is just a piece of material. When the cable is worked into the plant or even joins two pieces of plant it becomes part of the plant and is properly referred to as plant. Similarly, a screw is just a screw when it is in the engineer's pocket, but it becomes part of the plant when he screws it into the generator. In keeping with the sense of the earlier authorities to which I have referred, it seems to me that one cannot make sense of the Act by a minute analysis of the work to see what was plant and what was not. One must look at the nature of the work broadly. Adjudication cannot be divided in its jurisdiction between minute parts of a sub-contractor's work. Looking at the work overall, and regardless of any disputes about the ambit or nature of that work, I have no doubt that Zedal were employed to install plant. The exception provided by section 105(2)(d) itself suggests that cables, cable trays and cable ladders may become plant when installed. The manufacture and delivery to site of such items for power supply are excepted from the operation of the Act "except under a contract which also provides for their installation". In conformity with the decisions in Homer Burgess v. Chirex and ABB Power v.Norwest Holst (paragraph 15) and for the reasons there stated, I find that the materials used by Zedal became plant.
It seems to me that this is the central issue between the parties. If the site is defined as the small areas on which the generators stood in Oldham and Watford, surrounded by a security fence, then the primary activity of the sites must be power generation, because the only activity of those sites is power generation. That must be so even though the activity (as shown by the planning applications) was intended to be merely temporary. If the site is defined as the whole areas occupied by MCP at Oldham and Watford, then it cannot conceivably be said that the primary activity of those sites is power generation. Taking those sites as a whole, power generation can only be regarded as ancillary to the primary activity of printing colour magazines whether or not excess power might be sold to others.
"'Site' means the actual place or places, provided or made available by the purchaser, to which plant is to be delivered or at which work is to be done by the contractor, together with so much of the area surrounding the same as the contractor shall with the consent of the purchaser actually use in connection with the works otherwise than merely for the purposes of access."
Conclusion