- This action arises out of a fire which started at 6.00 am on 11th December
1995 and which within a short time destroyed Pride Valley's Factory at Seaham
Grange in County Durham where the company makes speciality breads. The fire
spread through the EPS insulating panels in the building with such force that
it was too dangerous for the fire-fighters even to enter the building in order
to try to put out the fire. The claim is that the fire was caused by the Defendants'
negligence in failing to discharge their contractual duty of care as project
managers of the project. There is a subsidiary issue as to whether Pride Valley
contracted with Hall and Partners (a firm) or Hall and Partners (Contract
Management) Limited, in relation to the first of the two stages of the project.
I shall deal with this question after considering the main liability issue.
Until then I shall refer to the Defendants as Halls.
- In the course of the hearing I have received evidence from fire experts,
Mr Calleja and Dr. Bland. I have been impressed by the extent to which they
have been able to agree on important matters. This has meant that they needed
to be called only to give brief oral evidence. I also heard expert evidence
on project management from Mr Forbes Bramble for Pride Valley and Mr Warner
from Halls. There is a serious issue and an important issue of lawas to whether
any, and if so how much, of their evidence is admissible. I shall return to
this question later at paragraph 124 and following.
- It is convenient to identify the key issues between the parties. They can
be summarised as follows:
(a) What was the scope and extent of the services undertaken by Halls?
(b) Should Halls have given Pride Valley advice, particularly in relation
to EPS panels and compartmentation which, if given, would have prevented
or limited the spread of the fire?
(c) Did Halls give such advice?
(d) Were there any other steps which Halls should have taken which would
have prevented or limited the spread of the fire?
- There follow further questions raised by Halls:
(e) In the event of a finding that Halls failed to discharge its duty
of care to give appropriate advice which would have prevented or limited
the spread of fire, did Pride Valley suffer any loss as a result of this
failure or would its Managing Director, Mr Rezaei, have disregarded such
advice?
(f) Were the circumstances of the fire of December 1995 such as to break
the chain of causation?
(g) If not, was there contributory negligence by Pride Valley, and if
so, to what extent?
- It is agreed that issues of quantum of damage will be left for a later hearing.
THE FACTS
- Mr Rezaei came to England in 1978 when he was aged just over twenty. In
1981 he graduated from what was then Newcastle Polytechnic with a degree in
electronic and electrical engineering. He continued to do research at Durham
University in microwave communication. Halls have said that because he was
sometimes called Dr. Rezaei, reflecting a qualification which he did not possess,
I should regard his evidence as unreliable. I do not agree. Having heard his
evidence on this subject I conclude that this issue does not help me one way
or the other to evaluate the reliability of his evidence.
- In 1990 Mr Rezaei realised that there was a large potential market in producing
speciality breads such as nans and pitta breads. He designed and patented
an automated baking process for such breads and started to market them under
the name of Pride Valley Bakery. Production started in a small way from premises
at Fairfield Industrial Park, Bell Quay, Gateshead.
- The business was very successful. On the 1st August 1992 Pride Valley Foods
Limited was incorporated with Mr Rezaei as Managing Director. The Chairman
was Mr McKechnie, a prominent local businessman, who owned Derwent Valley
Foods, a successful company in the food business.
- Mr Rezaei decided that his business needed a purpose built factory. He approached
three potential building contractors including Inline Construction NE Limited
(Inline) He chose Inline.
- Mr Rezaei intended to employ Inline as contractors to design and build the
factory without any outside supervision but after discussing with Mr McKechnie
how to proceed, he agreed to approach Mr Hall of Hall and Partners, a well
known local firm of Chartered Quantity Surveyors and Estate Managers who had
assisted Derwent Valley Foods as Project Managers when it had built its factory.
Mr Hall was and is a Fellow of the Royal Institute of Chartered Surveyors
and carries on a substantial practice in Newcastle.
- Mr Rezaei said that he had little experience in construction and wanted
to provide comfort for his financial backers. I accept this. I find also that
Mr Rezaei was very much in control of the policy of his company and involved
himself in day to day matters. He was dependent on his backers to provide
the money for the building of the factory and had to take note of their opinions.
Mr McKechnie took an active role as non-executive Chairman of the company.
- Mr Hall met Mr Rezaei in early October 1992. There is a dispute as to whether
or not Mr Thompson of Halls was at the meeting. Mr Rezaei said that the meeting
lasted around one hour. Mr Hall told him that he had substantial experience
in constructing large factories including food factories. Mr Hall told Mr
Rezaei what services Halls could perform. Mr Rezaei told Mr Hall about the
development of Pride Valley and how the construction of the factory represented
a large step for the company. He said that it was important to keep costs
as low as possible. Mr Hall looked at the quotations and said that he had
no problem with working with Inline but that Halls should be closely involved
to safeguard Pride Valley's interests.
- The letter from Halls dated 16th October 1992 reflected the discussions
which Mr Rezaei described in his statement. Halls provided two options:
Option 1 is described as a "Schedule of Project Design and Management
Services" "Objective - to achieve through successful management from inception
through design, construction, commissioning and hand-over a building which
is delivered within agreed time, cost and quality parameters.".
Option 2 is described as a "Schedule of post bid submission Project Management
Services." "Objective - to provide necessary service from tender stage
only.".
- Mr Hall's recollection of this first meeting is broadly consistent with
that of Mr Rezaei. Mr Hall said that he explained what services Halls could
provide. Mr Hall placed greater emphasis than Mr Rezaei on the fact that Mr
Rezaei's financial resources were very limited. Mr Hall said that Mr Rezaei
insisted that he required the cheapest possible building that would meet current
food and hygiene requirements. Mr Hall made a note at the meeting that Mr
Rezaei wanted to keep the cost of the building down to £380,000. There is
no note of any warning given to Mr Rezaei by Mr Hall about fire risks.
- Mr Hall says that he had the initial impression that Mr Rezaei was reluctant
to use "Halls" services but that after hearing the details of the services
which Halls could provide, Mr Rezaei recognised the advantages of retaining
their services. Mr Hall designated Mr Thompson to look after the day to day
management of what subsequently became the contract between Pride Valley and
Halls. Mr Thompson had started working for Halls in June 1992 and this was
the first time that he had managed a project of this type. Before his first
meeting with Mr Rezaei he had done some general reading and had found out
about the specifications used in the building of the Derwent Valley factory.
- Mr Rezaei, Mr Hall and Mr Thompson met on the 29th October 1992. Mr Thompson
had prepared a feasibility estimate and outline specification which showed
a total construction cost of £617,372 exclusive of VAT and fees.
- The outline specification used 100 and 140 thick blockwood partitions for
the internal walls and insulated doors to the Cold Store and Blast Freeze
rooms and PVC hygienic wall lining to the preparation area.
- Mr Hall said in his first statement dated 2nd July 1999 that they went through
the specification in detail at the meeting. He said that Mr Rezaei referred
to the EPS (expanded polystyrene) panels which were used in his existing factory
as his preferred alternative. Mr Hall said that during the tour of Pride Valley's
existing facility he, Mr Hall, referred specifically to the EPS panel system
and its inherent combustibility factors and to the fact that insurance companies
were increasingly insistent upon high levels of fire safety. Mr Hall said
that Mr Rezaei was adamant that the budget had to be reduced to £400,000.
- In his second statement dated 14th January 2000 Mr Hall said that at the
meeting on the 29th October 1992 he asked Mr Rezaei if he realised that the
panels were readily combustible.
"I told him that polystyrene burns easily and can spread fire quickly."
- Mr Hall said that Mr Rezaei told him that he had an excellent fire safety
record. Mr Hall said in his statement that after they discussed locating heat
producing plant and equipment near to this panelling system, "he responded
by saying that the ovens would be located far enough from the walls to allow
cleaning on all sides."
- Mr Hall said that after the tour of the building he warned Mr Rezaei again
against building the factory at the lowest possible cost. He said that Mr
Rezaei replied that if Halls could not work to minimum standards he would
find someone who could.
- In oral evidence Mr Hall maintained that he advised Mr Rezaei that EPS panels
could spread the fire rapidly and he advised Mr Rezaei against the use of
the panels.
- Mr Thompson's first account of the meeting is a little different from Mr
Hall's first account. He said that Mr Hall advised Mr Rezaei that if he wished
to use EPS panels he must understand that the material was combustible in
the event of fire and could result in a rapid spread of fire at the premises.
He went on:
"He (Mr Hall) said that the use of such panels could accelerate the spread
of fire. Ray Hall advised that the new facility and the quality of the building
would be seriously compromised by his insistence on specification reductions."
- Mr Rezaei agrees that he told Mr Hall that his budget estimate was too high.
He says that he did not instruct Mr Hall to specify EPS panels and "I was
certainly not advised by Ray Hall or anybody else at this meeting (or at any
other time until after the fire) that EPS panels were highly combustible and
their use could result in the rapid growth of fire.".
- On the 30th October 1992, Mr Hall wrote to Mr Rezaei to summarise Halls
current position in relation to the project.
"Following the informative discussions with yourself which clarified a number
of points both in relation to design and specification, we will now endeavour
to evaluate the viability of the project at an overall contract sum of £450,000
(excluding land purchase, VAT and fees)."
"Having said this, we do realise that your optimum figure would be in the
region of £400,000 and so we will also investigate any possible options which
may bring the total cost closer to this figure."
- There is no reference in this letter, directly or by implication, to the
warnings which Halls say they gave at the meeting in relation to EPS panels.
Nor did the letter suggest that the project could not be completed safely
for such a low figure.
- Halls then produced Feasibility Estimate No.2 and Outline Specification
dated November 1992. The total construction costs had been reduced to £472,214
excluding VAT and fees. The wall and ceiling finishes now stipulated insulated
PVC lining to food safe areas. The estimate excluded the cost of the ovens
and the specialist equipment. It was, of course, understood that the factory
was being built as a bakery making specialist breads and that these breads
would be baked in ovens. The estimate made no reference to any reservations
by Halls as to the use of EPS panels.
- There was a further meeting between Mr Rezaei, Mr Thompson and Mr Hall to
go through the revised feasibility estimate and outline specification. Mr
Hall said that he recalled explaining to Mr Rezaei that Mr Rezaei was effectively
rejecting Halls recommendation of masonry walls which would have formed an
effective fire compartmentation. Mr Hall said that Mr Rezaei referred to his
excellent safety record and said that EPS panels were standard throughout
the food industry. Mr Hall says that he went on to recommend an M & E
Consultant. He said that Mr Rezaei told him that he was capable of providing
these consultancy services himself and did not need to employ an M & E
Consultant.
- In his witness statement, Mr Thompson said that they went through specification
number 2 in detail, confirming the changes from specification number 1. "Again
we pointed out to Mr Rezaei the benefits of blockwork partitions against replacing
the same with EPS panels."
- Mr Rezaei says in his statement that the meeting discussed the changes that
had been made to achieve the reduction in price but he cannot remember any
details.
- It is not disputed that in early December 1992, approaches were made to
contractors.
- Halls, not surprisingly in view of the amount of work that they had done
already, were anxious to finalise their fee arrangement. They wrote two letters
to Mr Rezaei on 11th December 1992. The covering letter, written on Hall and
Partners notepaper, enclosed a draft letter of appointment written on the
notepaper of Hall and Partners Contracts Management Limited and a fee proposal.
- The covering letter emphasised:
"I would reiterate my own preference in respect of the design of the project
i.e. that it would be better for us to prepare the design and detailed specification
in order to obtain the most competitive price in open tender from builders
who would all be tendering on the same basis."
Mr Hall's preference was not accepted. Mr Rezaei went ahead with the cheaper
design and build option.
- The letter of appointment and the fee agreement dated 11th December 1992
were signed by Mr Hall, and by Mr Rezaei on 15 December 1992 and provided
that in consideration for the services detailed in Appendix 1, Pride Valley
would pay Halls a fixed fee of £20,000. It is accepted by Halls that in relation
to this agreement ( and the later agreement ), Halls were under an obligation
to exercise reasonable care and skill in relation to the duties which they
agreed to undertake. It is also accepted that this included the giving of
appropriate safety advice to Pride Valley.
- Appendix 1 was headed "Schedule of Project Design and Management Services".
Its stated objective was "to achieve through successful management from inception
through design, construction, commissioning and hand-over, a building which
is delivered within the agreed time, cost and quality parameters.
- The schedule set out 23 items which included:
"1. Prepare and agree with the employer a schedule of requirements which
the project is to meet and the specification appropriate for such requirements...
.
3. Develop schedule of requirements into a design brief which incorporates
and co-ordinates user needs and objectives.
4. Prepare outline sketch plan to include consideration of material selection
having regard to suitability and longevity of life... .
9. Prepare appropriate Employers Requirements, specification and drawings
including any necessary site investigations drawings from which the contractors
will design the structure and submit competitive bids for the overall
project in open tender... .
12. Confirm that all building regulation approvals and consents are obtained
by the contractor, and check upon any further design work the Contractor considers
necessary after the detailed design stage."
- I am satisfied that Appendix 1 sets out the responsibilities which Halls
undertook in relation to phase 1 of the project. Of the two options, the agreement
was closer to the original option 1 under which Halls undertook successful
management from inception through design, construction and commissioning and
hand-over of the building in that it required Halls to undertake some responsibilities
for outline design and materials. The alternative option 2 proposal had required
project management in the sense of co-ordination after the tender stage i.e.
without any responsibility for outline design and materials.
- Halls produced Feasibility Estimate No.3 with a cost of £517,523. The outline
specification continued to specify insulated PVC linings for wall and ceiling
finishes without any qualification by Halls, although Mr Hall says that he
had advised Mr Rezaei that these finishes were unsuitable.
- On 30th December 1992 Mr Thompson of Halls wrote to Mr Rezaei about the
mechanical and electrical installations and suggested to him that he might
wish to appoint a consultant engineer to vet all the existing proposals, "Failing
this we will of course ensure that contractually the contractor bears full
design responsibility for all the mechanical and electrical installations.".
- There followed in January 1993 a schedule of employers requirements and
specifications prepared by Halls (Mr Thompson) and discussed with Mr Rezaei.
These specified originally a fire compartment wall between the offices and
production area and steel faced insulated panels for the ceiling finishes.
- In February 1993 there was a further meeting between Mr Rezaei, Mr Hall
and Mr Thompson to discuss the employers requirements. Amendments included
the omission of a fire wall between the production area and the offices unless
it was required by the Building and Fire Regulations. It was also agreed that
Pride Valley would approve the mechanical installation.
- The job was then put out to tender by Halls. Initially Hilbar Construction
Limited (Hilbar) had the lowest tender and was favoured by Halls. A fax to
Hilbar dated the 3rd March 1993 from Halls asked them to confirm that fireproof
FRA polystyrene had been quoted for in the food safe panelling. Mr Thompson
said that he discussed the issue of FRA with Mr Rezaei and explained to him
that FRA helped to improve the low fire performance of EPS panelling. The
Hilbar tender was £546,423 including an additional cost of £1,861 for fireproofing
to the food safe panels. A note from Mr Hall in the course of the tendering
process indicated that he was concerned about Hilbar's quality of workmanship.
Despite this Halls recommended that the Hilbar tender should be accepted.
- Mr Rezaei conducted separate negotiations with Inline whose original tender
figure was £801,822. After his discussions, the tender figure was reduced
to £626,000. On the 4th March 1993 Halls conducted further discussions with
Inline and produced a revised tender figure of £579,500. Its note of client
discussions said:
"the following points were clarified with Inline:
Fireproofing to the food safe panels was included in their original tender.
In addition we have been informed that their panels are faced with glass reinforced
plastic which is a higher specification than coated metal."
- This revised tender included, among its suggested savings by Halls, the
sum of £10,000 for reducing the thickness of the food safe panelling. This
advice of Halls is inconsistent with the advice which they say they gave earlier
in relation to EPS panels. Here Halls were suggesting that Pride Valley reduce
its level of safety.
- On 18th March 1993 a strategy meeting was held at Pride Valley's offices
at which both Mr Rezaei and Mr McKechnie were present. The note of the meeting
recorded that Pride Valley expected to exchange contracts with Inline on 23rd
March 1993.
- The phase 1 works started in April 1993.
- The contract between Pride Valley and Inline in JCT Form with Contractor's
Design was signed on 6th May 1993. Hall and Partners Contracts Management
Limited was designated as the Employer's Agent. Under the contract Inline
agreed to build the factory for the contract sum of £520,000.
- The final account of 20th December 1994 showed a final figure of £606,183.14.
- The plans for the proposed bakery were considered by the Fire Authority
on 3rd June 1993. The fire report made a number of other comments but none
relating to the use of EPS panels.
- The first of a number of site meetings took place on 15th June 1993. Normally
there were present at these meetings Mr Rezaei, Mr Thompson representing Halls,
and Mr Gatenby representing Inline. At the first meeting Mr Gatenby handed
over the latest construction drawings which were the subject of a discussion.
There was also a discussion about problems which needed to be resolved relating
to the mechanical installations.
- Also on 15 June 1993 Scot-Tech produced its quotations for works including
" enlargement of ductwork system to oven extract hoods." Halls instructed
Inline to accept this quotation on 7 July 1993. Scot-Tech produced a schedule
of works on 2 August 1993.
- At the site meeting on 15th July 1993, Mr Gatenby requested details of the
exact position of the ovens in the production hall and details of all holes
to be cut in the food safe panelling. It was agreed that Mr Rezaei should
supply the information as soon as possible. This followed up a similar request
from Mr Gatenby on 9th July 1993.
- At the site meeting on 9th August 1993, which was attended only by Mr Thompson
and Mr Gatenby, Mr Gatenby confirmed to Mr Thompson that he was still awaiting
these details which were actioned for Pride Valley to undertake.
- Mr Thompson was responsible for agreeing cost estimates for works to be
carried out by Scot-Tech as subcontractors for Inline subject to Mr Rezaei's
approval - see Hall and Partners fax dated 10th August 1993.
- Cost Report No.1 dated 20th August 1993 made it clear that the anticipated
final account did not include Scot-Tech's direct works order with Pride Valley
nor any allowance for the provision of oven hoods.
- Following a site visit by Mr Thompson he was able to issue a certificate
of practical completion for the works on the 18th October 1993. He noted that
the ovens and flues were not yet in place. It is clear that the installation
of the production lines and the ovens and flues took place after the factory
had been built. It was always understood by Halls that such equipment would
be installed in a factory which had as its designated purpose that of a bakery.
- On 4th November 1993, a short time after the certificate of practical completion,
Halls wrote to a number of clients to inform them that Hall and Partners (a
firm) was to cease trading and was to be merged with Hall and Partners Contracts
Management Limited. Pride Valley was not given any notice. Mr Hall said that
he understood that there was no need to do so because Pride Valley had contracted
with the limited company. This remains in dispute.
- On 8th December 1993 Easington District Council issued a fire safety completion
certificate in relation to the work on phase 1.
- A dispute arose between Pride Valley and Scot-Tech in relation to the ventilation
system. Halls told Mr Rezaei in a letter dated 7th December 1993 that they
would assist in resolving the dispute but only on a time-charge basis "Given
the fact that our original fee was extremely competitive and the fact that
the works in dispute are outwith our original contract.".
- In the course of discussions which then took place Mr Thompson requested
Scot-Tech to provide a comprehensive list of design information which Scot-Tech
would require to enable the project to proceed. Scot-Tech was also asked to
confirm that the second oven which was being assembled was identical in every
way to the first oven.
- By a letter dated 26th January 1994 Mr Thompson advised that the ventilation
system was not adequate for Pride Valley's needs and that remedial works were
necessary. He again suggested that Halls' should be instructed to resolve
the issue and that Mr Rezaei should agree to pay Halls costs. This is an example
of the firm written advice which Halls gave when they thought it was appropriate
to do so.
- At the site meeting on 27th January 1994 the scheme for the ventilation
of the ovens was discussed by Mr Rezaei, Mr Thompson, Mr Gatenby, and Mr Anson
and Mr Foster from Inline.
- The note indicates that the proposed scheme for ventilating the ovens was
discussed in detail:
"The basic proposal now is to ventilate oven No.1 (pitta) and oven No.2
(nan) by means of a bifurcated fan and fresh air fan and to ventilate
oven No.3 (lavash) directly to the outside building by non-mechanical
means.
- The note of the meeting records that "2.4 PVB (Pride Valley Bakery) raised
the question of the heat which would emanate from the actual oven hoods themselves.
ST (Scot-Tech) said that the hoods would be cooled to a certain extent from
the fresh air being supplied to the area and did not see this as being a problem."
- On 28th January 1994 Mr Thompson gave his considered opinion in relation
to the ventilation system. He identified the problem that the oven hoods were
considerably larger than had been allowed for by Scot-Tech in their drawings.
He pointed out that this had been agreed between Mr Rezaei and Scot-Tech and
that Halls had not been involved at least until after their contract was complete.
- After a considerable amount of negotiation, in which Mr Thompson was involved,
(he says as an intermediary) Halls issued an instruction to Inline on 4th
February 1994 on behalf of Pride Valley for:
A supply and extract ventilation system to the two ovens and a modification
and extension to the lavash oven flue system to vent externally by non-mechanical
means in the sum of £11,471, and
Modifications to the existing ventilation system in the sum of £400
- On 8th February 1994 Scot-Tech quoted a price to Inline to fit a washable
grease filter onto the nan line. In a separate quotation on 8th February 1994
Scot-Tech quoted a price for providing and installing a steel duct to each
oven. The order specified that "the duct shall terminate just above the food
safe ceiling and be fitted with a marking flange.".
- It is clear that Halls supervised the work on Pride Valley's behalf. On
the 7th March 1994, Mr Thompson wrote to Mr Rezaei, "Please find enclosed
the valuations relating to the works to your oven hood. Would you please note
that there is still an outstanding amount of £400 for which I am awaiting
substantiation. The figure has not been included in the valuation.".
- A Fire Report from Mr Pickersgill of 11th April 1994 by Lombard General
Insurance Company was sent to Mr Quinn and Mr Ryder of Pride Valley. Its opinion
of the risk was as follows:-
"This may be regarded as a good class food manufacturing risk of moderate
fire inception hazard as the main process is baking.
No frying undertaken.
A high standard of cleanliness is maintained.
The only adverse feature is the extensive use of combustible wall linings,
ceilings and partitions. Stock is particularly susceptible to damage by
heat, smoke, fire and water and spoilage."
- The reference to no frying undertaken may have been to a fire at the premises
of Sun Valley Poultry in Hereford on 6th September 1994 which began in a frying
machine and rapidly destroyed the building. Two members of the fire service
lost their lives. A significant factor in the rate of spread of that fire
was the presence, in the majority of areas, of linings of polystyrene encased
in PVC coated steel sheeting. An article in the magazine "Building Control"
in July 1994 referred to the fire and noted that the Building Regulations
did not require cavity barriers or compartmentation.
- In January 1994 Pride Valley was considering an extension to the factory
at Seaham. Mr Rezaei sent a letter of intent to Inline dated 5th January,
drafted by Halls, requesting them to carry out the work on an extension to
the building at a price in the region of 1.2 million pounds.
- On 19th July 1994, Mr Rezaei contacted Mr Hall to start discussions on the
phase 2 extension.
- In September/October 1994 there was a general discussion between Mr Rezaei,
Mr Hall and Mr Thompson about phase 2. There is a dispute as to what was said.
The meeting also included Mr Ryder, who was to be responsible for the project
for Pride Valley although it was understood by all parties that Mr Rezaei
would take the final decisions. Mr Thompson said that they discussed the quality
and performance of the internal partitions and the various panels and their
fire ratings. He said that he outlined how the panels would perform in the
event of a fire. Mr Thompson also said that Halls advised that a stainless
steel faced panel gave the best rating for reducing the spread of the flames.
He also said that Mr Rezaei was not prepared to increase the phase 1 specification.
- Mr Thompson said that Halls also advised that the Fire Officer might well
require a fire wall to be constructed between the phase 1 factory and the
extension in order to contain the spread of any fire.
- In his written statement, Mr Hall said that they discussed in detail the
alternatives available with reference to the types of panel that could be
utilised including the fire ratings and performance in the event of fire.
He also said that he raised the suggestion that the Fire Officer might well
require a fire wall to be constructed between the new factory and the extension
to contain the spread of fire. He said that Mr Rezaei rejected his advice.
- Mr Ryder said in his statement that he was familiar with the requirements
of fireproofing and the methods of fire protection within a production facility.
He said "we discussed the EPS panelling used in phase 1 and the alternatives
available including fire ratings and their respective cost. Mr Rezaei made
it clear that he was not prepared to incur any extra expenditure that was
not absolutely necessary."
- Mr Rezaei said in his statement that EPS panels were discussed at the meeting.
He had found the panels excellent in terms of hygiene and insulation. He said
that alternatives were discussed. He said that Mr Thompson told him that the
alternatives would cost over three times the cost of the EPS panels i.e. a
cost of over £600,000. He said that he did not receive any warning at the
meeting or otherwise as to the severe fire risk posed by the panels. He said
that if he had been advised at the meeting that the panels should not be used
in phase 2 that would have stuck in his mind. He said that he did not receive
any such advice at any later meeting concerning the fire risk which EPS panels
posed. He also said that he was not advised as to the necessity of having
a fire break wall between phase 1 and phase 2. He said that if he had been
so advised he would have accepted the advice.
- The matter was taken further on the 6th October 1994 in the fee proposal
for Project Design and Management Services in connection with the extension
to the factory. Mr Thompson recommended the appointment of a services engineer
to cover all the mechanical and engineering services, thus avoiding the problems
which had occurred in the first phase of the bakery.
- The fee which Halls charged for their services in relation to phase 2 is
set out in the Memorandum of Agreement of 3rd November 1994 in the sum of
£51,000. Appendix 1, setting out the schedule of Project Design and Management
Services is in identical terms as for phase 1 except that it omitted item
eight relating to the selection of suitable contractors. This provision was
not necessary since it was always understood that Inline would undertake the
project.
- On 17th November 1994 Halls entered into an agreement with TG Armstrong
and Partners who were appointed as service engineers for a fee of £4,000.
- Also in November 1994 Halls produced its cost plan and outline specification
for the factory and office extension. The total construction cost was to be
the sum of £1,396,884 exclusive of VAT and fees.
- The outline specification for the internal doors, wall and floor finishes
was specified as insulated PVC linings. The note at the end of the specification
stipulates that ovens, flour, silos and specialist equipment were to be excluded.
It was understood by the parties that the panels were being installed in a
bakery and in specifying the materials Halls would need to have had well in
mind the purpose for which the extension was being built.
- On 19th December 1994 Mr Ryder sent Pride Valley's service requirements
for the factory extension.
- There was a meeting to discuss the extension on the 25th January 1995 at
which Mr Rezaei and Mr Thompson were present. Mr Thompson emphasised that
he was not a mechanical and electrical specialist and that he was relying
on his service consultant T G Armstrong and Partners. Mr Thompson's letter
made various firm observations on the project and ended:
"I do not wish to appear negative but it is my duty as your Consultant to
make you aware of the situation as I perceive it."
This is another example of Halls setting out their views in writing to Mr
Rezaei when they felt that it was appropriate to do so.
- After further negotiations the revised contract price agreed in February
1995 was £1,200,00. The contract was in the standard JCT Form with contractor's
design.
- On 5th May 1995 Mr Pickersgill surveyed the factory and considered the alterations
which had been made to see whether or not they altered the fire risk. He noted
in his report dated 22nd May 1995 that the main adverse feature regarding
the existing risk was the extensive use of combustible wall linings, ceilings
and partitions and that these features were to be repeated in the new extension.
The report referred to a number of risk improvements which could be made.
The letter code alongside each risk improvement denoted the action which Mr
Pickersgill required to be taken. Categories A - D referred to measures that
were required to be undertaken.
- Category E referred to risk recommendations which while not mandatory were
areas for risk improvement which if carried out might avoid the need for increased
terms/excess levels at some future date. They included a number of items in
Categories A-C and the following:
"95/05 (E) Food Industry Insulation Panels
Panels incorporating either polyurethane or polystyrene insulation reflect
an increased fire hazard. To improve the fire risk the following should be
considered:-
Non-combustible core panels using mineral wall instead of foam should be
utilised.
If alternative panels cannot be used then the ends of the sandwich panels
must be sealed and locked together in a non-combustible wall intumescent seal."
- A requirement in Category (C) ( "must receive early attention" ) was a roller
shutter between phase 1 and phase 2. The risk improvement requirements were
passed on to Pride Valley on the 12th July 1995.
- These matters were known to at least Mr Wharton who was Pride Valley's Operations
Manager and Mr Quinn, the company's Accountant. They had actual or ostensible
authority to receive communications on Pride Valley's behalf - (see El
Ajou v Dollar Land Holdings [1994] 1 BCLC 464 at 472) and notification
to them constituted notification to Pride Valley.
The note of the site meeting on 22nd May 1995, at which Mr Ryder for Pride
Valley, Mr Thompson and Mr Gatenby were present, said in relation to the extension
that all outstanding matters with building control and the Fire Officer would
be resolved that week.
- It does not appear that either Mr Thompson or Mr Gatenby raised the question
at the meeting of whether the food safe panels were appropriate or whether
they constituted too great a fire risk.
- On 25th May 1995 Mr Anson of Scot-Tech wrote to Mr Gatenby with copies to
Mr Rezaei and Mr Thompson in relation to proposed modifications to the ventilation
system in the production area. The letter noted that the "extract system from
the Nan oven is contaminated with grease and products of the process which
are building upon ductwork internally and particularly on fan impeller"
" This is resulting in considerably reduced airflows causing smoke spillage
into the room and eye irritation to operators."
- At about this time there was a complaint about smoke and heat in the production
room which was investigated by the Health and Safety Executive. It appears
from Mr Rezaei's fax to Mr Anson of the 12th June 1995 that Mr Rezaei thought
that these problems could be dealt with by adequate ventilation which would
ensure that the production room remained at a constant temperature.
- On the 5th July 1995 Mr Anson wrote to Mr Rezaei with a copy to Mr Gatenby
in relation to the pitta oven:
"We understand that there is a possibility of temporarily redesignating
this oven to produce nan breads. As there is no means of filtration we
have recommended that the existing mechanical ventilation system remain
until such time as the oven is used again only for Pitta production."
- Mr Anson also warned Mr Rezaei generally:
"We would also point out with any grease build up there must be a risk
of fire hazard and would recommend that you monitor this situation."
This warning is of some significance in that it put Mr Rezaei on enquiry
in relation to the risk of fire caused by the build up of grease, particularly
relevant in the use of the pitta oven to produce mini nans. This warning was
not acted on. Grease was allowed to build up in the pitta oven.
THE FIRST FIRE ON THE PRODUCTION LINE
- There was a fire on the main production line at 2.00 am on 28th June 1995.
The Fire Report from Miller Knight, the loss adjusters to Lombard Continental
Insurance, said that at 2.10 am one of the employees heard noises coming from
the extraction unit directly above the oven to the nan bread production line.
The base of the stainless steel extraction unit was showing red. The production
line was switched off immediately. Nevertheless within a short time, smoke
was coming from the oven and spread throughout the building which was evacuated.
- Apart from damage in the roof space to the electric motor and extraction
unit, damage to the building was confined to the roof panels directly above
the area of the extraction unit and to internal cladding in the production
room. There was extensive damage to the oven. The control panels and switches
had melted and the extraction unit needed to be replaced. Matters were discussed
with Mr Rezaei. The machinery was cleaned and repairs to the machinery were
put in hand.
- The report emphasised that had it not been for the quick actions of the
Pride Valley employees the loss would have been much greater.
- In the event both the extraction unit and the oven needed to be replaced.
This caused a lengthy interruption of the business. The claim was finally
settled at £460,514.23 including loss adjusters fees. Although extensive damage
occurred, the EPS panels did not ignite.
- Mr Rezaei gave prompt instructions for Scot-Tech to provide a fire damper
for the nan line above the grease filter.
- By a letter dated 12 July 1995 written to Mr Quinn of Pride Valley, the
agent of the Insurers ( Mr Brewis of Bishop Skinner Northern Limited) referred
to the recommendation of Mr Pickersgill in May 1995 relating to Food Industry
Insulation Panels. He said that " 95/05 has been included as extensive use
of combustible wall linings was a major feature in a recent substantial fire
(in excess of £5 million) in the food production industry. In all probability
you will not be able to abide by this suggestion mainly on the basis of cost
but I would appreciate your comments." I note that this was put to Pride Valley
in the form of a suggestion and not a requirement.
- By their letter of 13th July 1995 Scot-Tech indicated that there were problems
with the availability of a fire damper and proposed an alternative option.
There was no proposal to provide a fire damper ( or alternative option for
the pitta line ) even though it was then being used for the production of
mini-nans.
- On 4th August 1995, Scot-Tech agreed to supply a grease filter for the nan
line at a cost of £2,750. The reason why it was felt unnecessary to provide
additional safety precautions for the pitta line was that pittas used very
little oil. Nans on the other hand used a considerable amount of oil. Unfortunately
the pitta line was already being used for the production of mini nans so this
consideration should not have applied.
- There is a dispute over what period mini-nans were produced on the pitta
line. Mr Henry, then a Shift Manager at Pride Valley, said that it went on
for six to eight weeks. Mr Ryder said it was for 30 - 40% of the time up to
October/November i.e. it went on until within six weeks of the fire. Mr Robinson,
then employed as Production Manager at Pride Valley, said in evidence that
it went on for 30% -40% of the available time. In his oral evidence Mr Robinson
described graphically the poor level of safety and cleanliness of the mini-nan
line.
- Site Minute No.6 of 15th August 1995 contained a postscript which said that
"the damaged food safe panelling over the existing high care area was inspected
and found to be in extremely poor condition. Neither PVF or IC (Inline) were
prepared to accept liability for the damage. It was agreed that IC would obtain
a price for renewing the damaged areas and then the whole issue of liability
etc: would be discussed. This needs resolving as a matter of urgency ".
- On 1st September 1995 Mr Anson of Scot-Tech wrote to Inline with an urgent
copy to Mr Thompson regarding the effect of the increase in the oven sizes
with the higher increase in heat and exhaust fumes. No changes were proposed
to the pitta oven, "As requested by the Client.". Changes were proposed to
the ventilation of the nan line costing £30,000. The letter also advised that
modifications would be required to the pitta line oven and that this would
require further discussions with Pride Valley " as we feel exhaust by natural
means would not exhaust sufficient air ". The letter concluded:
"As the project is nearing completion it is imperative that the contents
of this letter are discussed with yourselves, the client and project Quantity
Surveyors as a matter of urgency.".
- On 11th September 1995 there was a further Site Meeting, No 7, at which
Mr Thompson and Mr Gatenby were present with Mr Ryder from Pride Valley. Mr
Ryder expressed Pride Valley's strong concern over the food safe panelling
to the existing factory which seemed to be delaminating in a number of areas.
Halls said that it would help if an independent expert could agree that the
problem was occurring because of a latent defect in the panels such as defective
bonding.
- The areas of delamination of the panels of food safe cladding in the existing
factory continued to be a source of concern to Mr Rezaei and Mr Ryder.
- Mr Ryder wrote a detailed fax to Mr Thompson on 17th October 1995, copied
to Mr Rezaei. He said in evidence that in the list he did not include areas
where he considered the damage to panels was due to work being carried out
internally, i.e. round the nan oven flue.
- A further Fire Report was sent by Mr Pickersgill to Mr Quinn of Pride Valley
as a result of a further survey on 2nd October 1995. Mr Pickersgill noted
that there was a structural maintenance programme with ovens receiving attention
on a daily, weekly or monthly basis. "In the past the nan oven would produce
carbon deposits but this problem has been substantially reduced following
the installation of a new oil applicator."
- His opinion of the fire risk was that "Fire inception hazard is moderate
as the main process is baking. No frying undertaken.". He reiterated that
the main adverse feature was the extensive use of combustible wall linings,
ceilings and partitions but that this was not uncommon in the trade. This
item is not, however, included in the list of risk recommendations i.e. recommendations
for improvement that were required to take place or where it was advised that
they should take place.
It is significant that Mr Pickersgill had to note that the majority of the
improvements required in his earlier report and referred to in Lombard's letter
to Mr Brewis dated 27 June 1995, with completion dates of 1st August 1995
and 1st September 1995 had not been attended to.
- An internal fire survey report of the Commercial Union in November 1995
noted that Pride Valley's major competitor in Scotland with similar insulated
panels had suffered a serious fire earlier in the year which had put them
out of business. The report advised "In view of the large presence of highly
combustible insulation materials and the inability to divide the risk I consider
this risk should be declined.". This report was not sent to either of the
parties
THE FIRE
- On 11th December 1995, just before 6.00 am, the Durham Fire Service was
called to a fire at the factory. The fire was not brought under control until
9.56 am, by which time the factory had been destroyed. In fact the factory
comprising some 72,000 square feet, had been completely destroyed in about
1 hour. The Fire Report said that cooking fats and oils ignited first and
were mainly responsible for the development of the fire.
- The speed with which Mr Rezaei dealt with the disaster was most impressive.
Between January 1996 and May 1996, new premises were fitted out. Today the
business is even more successful than it had been before.
The Cause Of The Fire
- On 8th July 1999 the experts, Mr Calleja and Dr. Bland, agreed a statement
of fact relating to the cause and spread of the fire. They concluded that
the fire initially developed at the bottom of the flue serving the No 1 Pitta
line and that it was caused by the ignition of cooking deposits, either by
a burning brand from the flour sack used to light the burners which entered
the flue system heating the cooking deposits, or by flame migration from the
burners resulting in the ignition of cooking deposits on the underside of
the hood. The main source of fuel for the fire was a substantial build-up
of cooking deposits in the horizontal duct where after the fire a large quantity
of burned deposits were apparent.
- The experts concluded:
"3. There were sufficient cooking deposits in the flue system to fuel
a fire of long enough duration to cause the vertical section of flue to
glow red hot. It is likely that the hot flue pipe spread the fire to the
polystyrene of the expanded polystyrene panels (EPS panels) either directly
due to radiant or conducted heat or by causing the polystyrene to melt
and flow onto the hot flue pipe."
- They went on to say that once the fire had spread to the EPS panels, it
would have spread rapidly through the building due to the burning of the polystyrene.
"The panels would have delaminated and the burning polystyrene would have
melted and flowed out spreading the fire to adjacent areas."
- The experts said that from their experience there was a risk of flue fire
in gas fired cooking appliances due to the build up of deposits in the flue
system. This risk which required special precautions does not exist in gas-fired
space heating appliances.
- In the view of these experts, the flue should have penetrated the ceiling
and roof void within a factory-made insulated chimney. Alternatively there
should have been a thick non-combustible sleeve around the flue pipe with
sufficient insulating and screening properties so as to prevent the ignition
of any combustible components of the ceiling or roof.
- They also agreed that there was insufficient clearance and/or insufficient
screening and insulation between the flue pipes and the EPS panels where the
pipes passed through the ceiling and that the flue system should have been
accessible for cleaning throughout its length.
- Finally they also concluded that a properly designed automatic fire extinguishing
system e.g. carbon dioxide incorporating fire dampers fitted to the oven and
flue system, should have controlled the fire and prevented fire spreading
to the building structure.
- In relation to the installation the experts agreed: (i) that the Pitta line
was a single skin flue; (ii) that if there was any oil in the pitta mix they
would have expected some cooking deposits in the flue system but they could
not quantify the amount that would have been deposited; (iii) if there was
no oil in the pitta mix the cooking deposits must have come from the previous
mini-nan production; and (iv) the mini-nan production would have caused significant
quantities of deposits in the flue system.
- The remaining question, upon which they gave brief and helpful oral evidence,
related to the cooking deposits in the pitta mix. Mr Calleja said that any
process involving cooking with oil either as a part of an ingredient mix or
added to it will inevitably produce breakdown products and that will be significant
in terms of fire risk because of the risk of ignition. He said that there
was a more significant risk of a fire occurring sooner with the nan process,
where oil is applied, than with the pitta process. The more deposits you have,
the greater the severity of the fire. Cleaning would therefore, in his opinion,
need to occur more frequently with mini-nans than pitta bread. There would
be deposits even from the pitta bread which, over a period of time, would
lead to a real risk of a fire occurring. This would be so even if the oil
in the pitta mix was only of the order of 1% - 2%. Mr Calleja said that from
his observations of the horizontal duct and the flue there was no provision
by the manufacturers for the horizontal duct to be cleaned.
- Dr. Bland, who had not been to the site and seen the debris, agreed in broad
terms with Mr Calleja but was more doubtful as to the significance of the
oil in the pitta bread. I accept Mr Calleja's evidence on these matters.
EXPERT EVIDENCE
- The starting point in a discussion of the role of expert evidence is the
judgment of Oliver J in Midland Bank Trust Co Ltd v. Hetts, Stubbs and
Kemp [1979] 1 Ch 384 at 402, which has since been cited with approval
many times.
"The extent of the legal duty in any given situation must, I think, be a
question of law for the court. Clearly, if there is some practice in a particular
profession, some accepted standard of conduct which is laid down by a professional
institute or sanctioned by common usage, evidence of that can and ought to
be received. But evidence which really amounts to no more than an expression
of opinion by a particular practitioner of what he thinks and would have done
had he been placed, hypothetically and without the benefit of hindsight in
the position of the Defendants is of little assistance to the court; whilst
evidence of the witnesses' view of what, as a matter of law, the solicitors
duty was in the particular circumstances of the case, is I should have thought
inadmissible for that is the very question which it is the court's function
to decide."
- Oliver J went on to emphasise, also at page 402, that in many cases the
extent of the professional's duty depends on the terms and limits of the retainer
and any duty of care to be implied must be related to what he is instructed
to do.
- In Bown v. Gould & Swayne [1996] PNLR at 135 Simon Brown L J
reinforced Oliver J's dictum that evidence which amounts to no more than an
expression of opinion as to what the expert would have done, does not assist
the court and an expression as to what he thinks should have been done usurps
the function of the Judge.
- In re Barings PLC [1999] 1BCLC433 at 489 Jonathan Parker J treated
these principles as being of general application.
- In Pozzolanic Lytag v. Bryan Hobson Associates [1998] 63 Con LR 81
at 92 Dyson J said:
"In my view the only issue to which expert evidence could properly have been
directed was whether there is a common practice in the engineering profession
as to what engineers who are engaged as project managers do in relation to
the insurance obligations of contractors. That would have been a short point
which should have resulted in short reports. Instead of this the experts prepared
quite elaborate reports, dealing with a number of other issues which were
inappropriate, and which no doubt added very considerably to the costs
of this litigation... . "
" The experts plainly went well beyond what the Official Referee had
authorised. In view of the imminent implementation of the Woolf Reforms,
it is now opportune for everyone who is concerned in civil justice to
take a hard look at the whole question of expert evidence. It seems to
me that all have a role to play in this, case management Judges, legal
representatives and the experts themselves. Prolix experts' reports directed
to issues with which they should not be concerned merely add to the expense
of litigation. Everything possible should be done to discourage this.
In appropriate cases, this includes making special orders for costs.".
- In United Bank of Kuwait v. Prudential Property Services (Court of
Appeal 27th November 1995 at page 28 of the transcript) Evans LJ adopted a
somewhat more relaxed view in saying that in certain circumstances where the
expert is in reality giving evidence of good practice in a particular field,
evidence may be admitted in which he or she says what he would have done or
would have expected to be done if the expert had been placed in a similar
situation.
- Evans LJ went on:
"I would hold that it is a mistake to include all experts in one category.
They range from, for example, the translator of foreign languages to a
person who can explain advanced scientific concepts and from describing
practices in highly technical areas to those in other areas where the
court has sufficient personal experience of its own.
The interpretation of accounts, perhaps, comes midway in this scale.
The courts, meaning individual Judges, may have some understanding of
them but they cannot be confident. Therefore expert evidence is potentially
available under both heads, that is to say as to practice and opinion
because it is helpful in assisting the court to reach a fully informed
opinion which in my judgment is the over-riding principle."
- If one concentrates on the Court's opinion that it is admissible for an
expert to give evidence of good practice in a particular field and that this
may, in certain circumstances, of necessity, require an expert to explain
what he or she would have done in a particular situation, this judgment can
be reconciled with those that I have already cited.
- I also bear in mind that in Sansom v. Metcalfe Hambleton [1998] 26EG154
at 156, the Court of Appeal held that:
"A court should be slow to find a professionally qualified man guilty
of a breach of his duty of skill and care towards a client (or third party)
without evidence from those within the same profession as to the standard
expected on the facts of the case and the failure of the professionally
qualified man to measure up to that standard. It is not an absolute rule
as Sachs LJ (in Worboys v. Acme Investments Ltd [1969] 4BLR133 at
139) indicated in his example but unless it is an obvious case, in the
absence of the relevant expert evidence, the claim will not be proved.".
- In re Barings PLC [1999] 1BCLC 433 at 493 Jonathan Parker J noted
that Bown v. Gould and Swayne had not been cited as in Sansom's
case.
- I must bear in mind that S3 of the Civil Evidence Act 1972 ("The 1972 Act")
provides that:
"1. Subject to any rules of court made in pursuance of Part 1 of the Civil
Evidence Act 1968 or this Act, where a person is called as a witness in
any civil proceedings his opinion on any relevant matter on which he is
qualified to give expert evidence shall be admissible in evidence...
(3) In this section "relevant matter" includes an issue in the proceedings
in question.
- I agree with Jonathan Parker J's judgment in re Barings at page 493
that s.3 of the 1972 Act does not render relevant that which is irrelevant.
The effect of Section 3 is to render expert evidence relevant to an issue
in the proceedings subject to the over-riding requirement that the evidence
is in fact relevant to that issue. Jonathan Parker J went on:
"Expert evidence as to what is the legal test in any particular case must
be irrelevant notwithstanding that there may be an issue as to that very matter.
On the other hand expert evidence on the question of whether that test has
been satisfied may be relevant (e.g. if it relates to matters such
as those to which Oliver J specifically referred in his dictum in Midland
Bank) but it will not be relevant if on analysis it amounts to no more
than an expression of opinion as to what the expert himself would have done
in similar circumstances."
- In this case I made observations, both in the course of the interlocutory
procedure and at trial, as to the value of expert evidence relating to project
management. I expressed the view that what Halls had agreed to do depended
on the terms of the contracts with Pride Valley and in particular on the scope
of their duties as set out in Appendix 1 to their terms of engagement. I was
persuaded by Leading Counsel specialising in construction work that I should
receive the evidence subject to questions of relevance and deal with the issue
in my final judgment.
- Mr Forbes Bramble for Pride Valley is a member of the Royal Institute of
British Architects and of the British Academy of Experts. His report runs
to over 100 pages with another 100 pages of Appendices. It deals with a number
of questions which appear to have been posed by his own solicitors. Many of
these are questions for the court and not questions for the experts. The report
contains throughout many expressions of opinion as to what Mr Forbes Bramble
himself would have done in similar circumstances. He proports to make many
findings of fact on questions which are matters for the Judge. He makes judgments
from the standpoint of a professional architect and designer on matters of
professional practice which must be judged from the standpoint of a Chartered
Surveyor who is acting as a Project Manger. His report offends against the
established basis on which experts should give evidence. In particular I reinforce
strongly the points made by Dyson J. in Pozzolanic Lytag v Bryan Hobson
Associates, which I have cited above.
- Mr Warner is head of the Building Consultancy Department of Richard Ellis
St Quentin and is a professional Building Surveyor. He studied Project Management
for his dissertation for a Masters Degree in architecture in 1975. His report
is 17 pages in length. Mr Friedman for Halls puts forward the evidence of
Mr Warner only on those matters of expertise on which I find that Mr Forbes
Bramble's evidence is admissible.
- Mr Warner's report sets out the views of the industry relating to EPS panels
in 1992. It expresses views as to what Mr Warner concludes is acceptable practice
for a Quantity Surveyor acting as a Project Manager. Mr Warner also expresses
the view that once the fire had started in the flues, the poor detailing of
the flues passing through the EPS panels was the root cause of Pride Valley's
losses. This judgment is more within the expertise of the fire experts than
that of the Project Manager. I have already accepted the evidence of the fire
experts as to the cause of the fire.
- There is an initial difficulty in accepting expert opinion evidence in relation
to the duties of Project Managers. There is no chartered or professional institution
of Project Managers nor a recognisable profession of Project Managers. In
so far as it may be appropriate to accept expert evidence, the nature of the
evidence that might be acceptable will depend on what the Project Manager
has agreed to do. In some cases the Project Manager will be the Architect
who will design the project and then, acting as Project Manager, supervise
the contractor and the sub-contractors in carrying out the work. This is the
role with which Mr Forbes Bramble is familiar. At the other end of the scale
the Project Manager will supervise the work of the contractor and sub-contractors
and ensure that the work is carried out in conformity with the design drawings.
In these circumstances the Project Manager will have no design function even
to the extent of providing an outline specification. This bears no relation
to the function of the Architect acting to project manage his project.
- In this case Halls agreed duties are set out in Appendix 1 of the agreements
for phase (I) and phase (ii) of the project. They include:
"3. Development of the schedule of requirements into a design brief.
4. Preparing an outline sketch plan to include consideration of material
selection... .
9. Prepare appropriate employers requirements, specification and drawings
from which the contractor will design the structure and submit competitive
bids for the overall project in open tender... .
12. Confirm that all building regulation approvals and consents are obtained
by the contractor and check on any further design work the contractor considers
necessary at the design stage.
- Halls were selected by Mr Rezaei as Chartered Surveyors not as Architects.
They agreed to provide the design brief and specify the schedule of requirements
and to manage the project through to completion. Apart from the fact that
much of his evidence was in any event inadmissible in that it usurped the
functions of the judge, Mr Bramble's evidence was given from the perspective
of an Architect who was used to taking responsibility for designing a project
and then project managing it.
- While Mr Warner is a Chartered Surveyor with experience of project management
his evidence in relation to the first agreement of experts also goes beyond
what is appropriate. This may well be because out of an abundance of caution
Halls felt it necessary to provide a brief reponse to Mr Forbes Bramble's
Report.
- I agree with Mr Friedman's criticism of the first joint statement of the
experts. The only relevant issue on which these experts were qualified to
give relevant evidence was issue three. "To what extent could that risk (i.e.
the fire risk of the baking operations undertaken in the factory ) have been
reduced and at what cost by alternative means?" Even here the agreement is
to some extent overtaken by the evidence of the cost of the alternative panels
which Mr Thompson estimated would cost three times the price of the EPS panels.
- It is elementary that questions like Issue 10 - was the Claimant, Inline
and/or Scot-Tech negligent in any of the respects alleged at paragraph 30
and 31 of the defence?" Should never have been asked of these experts or answered
by them.
- Having reviewed the evidence of these experts I remain of the view that
they provide little or no assistance. I accept Mr Friedman's submissions on
this aspect of the case.
THE DUTIES OF HALLS
- It is accepted that Halls were under a duty to exercise care and skill in
carrying out their duties as project managers who had agreed to achieve through
successful management from inception, through design, construction, commissioning
and hand-over, a building which was delivered within the agreed time, cost
and quality parameters.
- The duties included specifically a duty to prepare a schedule of requirements
in phase 1 for the construction of a bakery including the selection of appropriate
materials.
- In providing the outline specification and in selecting the materials Halls
would need to have well in mind that the materials were being placed in a
building that was to be used as a bakery. This meant that even though Halls
did not commission the ovens, they must have foreseen that ovens would be
placed within the building. By the time of phase 2, the ovens were in the
building. Halls were required to consider the safety of the existing building
and the appropriate design of the extension.
- In carrying out these duties Halls were entitled to have regard to the requirements
of the Planning and Fire Authorities and to the fact that the building would
be inspected by Fire Assessors for insurance purposes who were specialists
in assessing fire risks. They were under a duty to prepare a schedule of requirements
which to their knowledge did not constitute a serious or unacceptable fire
risk. If the employer wanted to specify materials which Halls did know constituted
an unacceptable fire risk they were under a duty to warn the employer of the
risk which they thought that the employer was undertaking.
- In this case the general practice in the construction industry was that
EPS panels were customarily used in food production factories - see Mr Rowe's
evidence. Mr Rezaei said in evidence that EPS panels were an industry recognised
product. Both at the time of phase 1 and phase 2 specialist insurers were
prepared to accept the fire risk of using EPS panels, albeit with some unease.
- In May 1994 Mr Pickersgill assessed the risk in phase 1 as "a moderate fire
inception hazard".
- In his report of 2nd October 1995, shortly before the fire, Mr Pickersgill's
opinion of the fire risk was that "fire inception hazard is moderate as the
main process is baking".
- Halls' case is that they accept that they were under a duty to warn Mr Rezaei
of any fire risks of which they knew and that they discharged this obligation
by warning Pride Valley fully of the risks that Pride Valley was taking and
that their warnings were rejected. The specific tasks which Halls agreed to
undertake are set out in the twenty-three items of Appendix 1 to the Schedule
of Project Design and Management Services and in particular to items 1, 3,
4, 9 and 12. The contract did not require Halls to undertake detailed design
work itself but required it to undertake to produce a design brief an outline
sketch plan and appropriate employers requirements, specification and drawings
from which the contractor would design the structures.
- These duties included specifying the materials to be used in the construction
and fitting out of the factory. The duty to advise on overall design included
the duty to advise on compartmentation.
- It is clear that in arriving at the appropriate specification Halls had
to have well in mind that this was a bakery which would house ovens and flues
and that the materials which they specified would need to be such as to render
the building reasonably safe from known hazards including fire.
- There is really no dispute about the scope and extent of Halls' duties.
Halls did provide sketch plans e.g. the plans for the proposed ground and
first floor extension, drawing numbers J807.01 and J807.02, dated November
1994. Halls did specify EPS panels on the two contracts. Halls did not specify
compartmentation between phase 1 and the new phase 2 building.
- The issue between the parties is whether Halls did so having advised Mr
Rezaei appropriately and had their advice rejected, or whether on the evidence
Halls never advised Pride Valley appropriately about the dangers of using
EPS panels and the necessity of compartmentation.
- I am satisfied on the evidence that Halls knew that EPS panels were highly
combustible, that they knew that if EPS panels were ignited there would be
a rapid spread of fire. That in a bakery, even though the process was baking
rather than cooking, there was a serious risk of fire. I am also satisfied
that Mr Hall knew that FRA only had a minor effect in reducing such risks.
- In answer to the question "Should Halls have given Pride Valley advice particularly
in relation to the use of EPS panels and compartmentation which if given would
have prevented or limited the spread of the fire? The answer is "yes". The
advice that the Halls should have given in accordance with their knowledge
at the time was
a) EPS panels were combustible and offered no resistance to fire.
b) If ignited there would be a rapid spread of fire.
c) EPS panels could accelerate the spread of fire.
d) There was a serious risk of fire if they were placed next to flues,
hot plant or ovens.
e) The use of EPS panels would seriously compromise safety
f) The use of FRA would not reduce the risk significantly (although Mr
Rezaei thought it would)
g) It was essential on safety grounds that a fire break should be installed
between phase 1) and phase 2)
h) The use of EPS panels represented a much greater risk to safety to
the building than available alternatives.
- This knowledge of the danger of installing EPS panels went beyond that which
was generally accepted by Fire Officers and others in the industry for whom
the use of such panels was acceptable. If Halls had such knowledge at the
time they should have communicated the nature and extent of the risk of the
use of EPS panels to Pride Valley. Equally if they had regarded compartmentation
as essential they should have communicated this to Pride Valley. They should
also have ensured that these panels were not placed next to flues, hot plant
or ovens. If Halls had given Pride Valley this advice and it had been accepted
I find that on the balance of probabilities the fire would not have occurred.
- Did Halls give such advice?
The evidence on this represents the clearest conflict in the case. On Mr
Rezaei's case, when cross-examined about EPS panels Mr Rezaei was asked the
following questions:
"Q When you were concerned with phase (I), you knew did you not that polystyrene
was inflammable?
A. Polystyrene - yes.
Q. You knew did you not that EPS panels contained inflammable material?
A. Yes.
Q. You knew therefore that using them created a risk in the event that
there was a fire?
A. No.
Q. Can you explain that answer please?
A. The explanation to that, my Lord, is that the risk of having polystyrene
packaging that you have around the television, for example, if it catches
fire, yes, it catches fire. It is combustible like everything else in this
room. (Referring to the court room.) But it is confinable and on the information
that I had is that because of the steel facings and of the ends being capped,
and the fact that we had this FRA which I still do not know what the answer
to it is, and the only thing I have is fireproofing which it is my belief
controlled the thing and I had a hazardous or combustible material made non-combustible
and it was put into my factory (sic) that was my final belief why would I
have that idea that you suggest?"
- Mr Rezaei was asked pointedly:
"Q You asked my Lord to believe that when you wrote down FRA even though
as I understand what you are saying you knew that it stood for fire resistant
additive, you thought it meant fireproofing in the sense that it would not
catch fire?
A. Yes
- When Mr Hall was asked about these matters he answered as follows:
"A. I was aware that they (EPS panels) were combustible and the effect
which they would have.
Q. You were aware that they had no resistance to fire?
A. Yes other than the flame retardant which had been added to them but
I have not reasoned that that was a minor improvement.
Q. You knew that EPS panels could result in rapid spread of fire and indeed
accelerate the spread of fire?
A. I was aware that it could spread fire quickly... .
Q. You were aware of that at the time in 1992?
A. Yes and I advised Mr Rezaei accordingly."
- Mr Hall said in answer to me that he was not aware of the statistics that
were building up around the country in terms of total loss fires and he also
said that the full extent of their potential inflammability was not understood
generally at the time.
- The cross-examination went on:
"Q You knew they were combustible?
A. I knew they were combustible.
Q. You knew they offered no resistance to fire?
A. Yes.
Q. You knew that they could result in the rapid spread of fire?
A. Yes. I appreciated that anything that is combustible would add to the
spread of fire
Q. You knew that EPS panels could result in a rapid spread of fire?
A. I was aware of that, yes, they spread fire quickly.
Q. And you knew that they could accelerate that spread of fire?
A. I have just explained. Anything that is combustible will accelerate
the spread of fire."
- In relation to the design of the flues, Mr Hall was asked:
Q. Is it right that you would have known that it was inappropriate to
place hot flues through EPS panels without adequate protection fire-resistance
wise between the flues and the EPS panels?
A. I would be aware that putting any sort of hot plant and if we could
call flues hot plant or ovens next to such material you would run the
risk of fire - yes."
- Mr Hall said clearly that both in relation to EPS panels in phase 1 and
phase 2 that Mr Rezaei was given clear advice and did not take it. Mr Hall
went on to say in relation to phase one that he suggested to Mr Rezaei that
he should check with his insurers.
- Mr Hall and Mr Thompson conceded that they did not put into writing the
advice which they say they gave although it was their practice to do so.
- In relation to compartmentation Mr Thompson was asked in oral evidence in
relation to
phase 2:
"Q. In the light of what you have told his Lordship about your views about
EPS several years before, (namely that they were very combustible) you had
a fear did you that if a fire started in phase 1 or phase 2, it could go right
through the factory without a fire break?
A. Yes.
Q. That was your view at the time?
A. Yes.
- Judge Toulmin: Was that view expressed at the meeting?
A. It was discussed at the meeting to pick up general design parameters.
I did not discuss at the meeting that in the event of there being a fire
in phase 1 the whole place would catch fire and spread through to phase
2. It was just discussed from the point of view of practical common sense,
regardless of the risk of fire there should be a wall and it would be
likely to be required by building control in any case."
- Later in the cross-examination the following occurred:
"Q. Your client was not prepared, you say, to follow your advice on the
fire wall?
A. Unless it was absolutely required by the regulations.
Q. Your advice had been that the fire wall should be put in irrespective
of what the Fire officer said?
A. Yes.
Q. Did you explain to Mr Rezaei at this meeting or at any time precisely
why in your view a fire wall was required.
A. Yes in short.
Q. Did you explain it?
A. Yes.
Q. And did you tell him because there is a real risk that if a fire starts
in one or other phase it will just spread through the existing wall?
A. Yes.
Q. So your client was failing to follow important safety advice which
you believed yourself qualified to give?
A. Yes."
- By this stage Mr Ryder had taken over much of the day to day supervision
on behalf of Pride Valley from Mr Rezaei. He was also at the meeting in October
1994. He did not recall Mr Hall saying words to the effect "We recommend that
you put in a fire wall whether the Council recommend it or not.". He said
that he would have remembered it if it had been said. He said he did recall
at the meeting that he said that EPS panels were combustible although he agreed
it was not in his written statement. He did not recall anyone saying that
there was a very real risk that if a fire started in phase 1, it would spread
through the existing wall.
- Mr Ryder went on "At no stage did Hall and Partners ever turn round and
say to Pride Valley "You must not use that or we will walk away from this."
They explained various options with risks, with costs and we selected one
of them."
"Q. I will put it again they never advised against using EPS panels for
stage 2?
A. No."
- Mr Ryder said in relation to the implication of there being no fire wall
between phase 1 and phase 2 that there was a discussion about the openings
but not about the wall itself.
- It is relevant to note that in re-examination Mr Ryder said that even if
there had been a strong recommendation for a fire wall, Pride Valley would
not necessarily have put one in. He went on:
"The building was constructed with the purpose of being as low cost as
possible and if it was a statutory requirement of a building control to
have a wall in then we would have put one in but if not we would not."
- Mr Rezaei disputes this .He says that if the matter had been clearly explained
to him and he had received clear advice from Halls that something had to be
done he would have done it.
Conclusion on this issue
- I find on the balance of probabilities that Halls did not give the advice
that they say they gave. They did not give a warning to Mr Rezeai of the risks
of fire which were commensurate with the dangers which they knew to exist.
Had they given the advice in the form in which they say they did both in witness
statements and in evidence and had that advice not been accepted by Mr Rezaei,
I have no doubt that they would, as a competent and prudent firm of Quantity
Surveyors and Project Managers, have given that advice in writing. If the
advice had been was given in the terms in which they say they gave the advice
I have no doubt that there would have been a record by way of a letter to
Pride Valley or at least an internal memorandum which either said in detail
or made direct reference to advice which they had given in relation to the
combustibility of the EPS panels and to the necessity for compartmentation
or the minimal effect of the use of FRA. There is not even any internal memorandum
which refers to the giving of such advice or even any reference in a note
of any meeting from which one could infer that such advice had been given.
I note also that this explanation was not given to PrideValley prior to the
service of Halls' defence.
- I accept Mr Rezaei's evidence that Halls did not say that the EPS panels
were highly combustible or advise in terms that there should be compartmentation
between phase 1 and phase 2 to prevent or limit the spread of fire or explain
the minimal effect of FRA minimising fire risk. I find therefore that Halls
failed to discharge their duty of care to give appropriate advice which would
have prevented or limited the spread of fire.
If Halls had given the advice, would Pride Valley have acted upon it?
- This is put by Halls on the basis that Mr Rezaei required the factory to
be constructed at as cheap a price as possible. It is claimed therefore that
Mr Rezaei would have rejected Halls' advice unless it was supported either
by the Planning and Fire Authorities i.e. Easington District Council or Durham
County Council and/or was required by his insurers. The evidence of Mr Ryder
supported this in relation to compartmentation when he said in evidence that
if it had been a requirement of building control to have a wall then Pride
Valley would have done it but not otherwise. Mr Rezaei says that if the advice
had been given in clear terms he would have accepted it even if it meant that
the cost of the building was substantially increased.
- I find that Mr Rezaei was an honest witness who now genuinely believes that
if Halls had given the advice in the terms in which they say they did he would
have accepted such advice and the fire would never have occurred.
- I do not find that he would have done so. I have come to the conclusion
that Mr Rezeai would have rejected Halls' advice unless it was supported by
a requirement from the Planning or Fire Authorities and /or was required by
his insurers.
- I do not regard this attitude as unreasonable. He regarded the Planning/Fire
Authorities as the experts and the insurers as the people who would carry
the insurance risk. Halls' information did not include the statistics which
were building up round the country in terms of total loss fires. These statistics
were the most compelling evidence of the danger of rejecting Halls' advice.
- Mr Rezaei was rightly concerned that the factory would conform to high standards
of hygiene. He was also concerned that the factory should be built at the
lowest cost. Mr Rezaei had used the EPS panels in his factory at Bill Quay.
He was inclined to use them again- see the quotations that he himself obtained
for the first contract. They were inexpensive and enabled the new factory
to be built at a cost which he thought he could afford. He was even prepared
to use them in the building of his new factory after the devastating fire
on 11 December 1995 and was only prevented from doing so by Mr Rowe who told
him that General Accident would not insure him if he insisted on using the
panels.
- I accept the evidence of Mr Ryder who said that if Halls had recommended
that it was necessary to put in a fire wall between phases 1) and 2) Mr Rezaei
would not have followed the advice unless the fire wall was required by building
control.
- I should add that it is also significant that Mr Rezaei did not act on the
advice which he was given after the fire on 28 June 1995. It was no doubt
some comfort on that occasion that the EPS panels did not ignite but despite
the warning that the fire presented, no changes were proposed to the pitta
oven at Mr Rezaei's request - see Mr Anson of Scot-Tech's letter to Inline
dated 1st September 1995. This was at a time when the pitta oven was being
used for mini-nans. Despite the increased danger of fire the pitta line was
not modified. It is also an indication of Mr Rezaei's attitude to fire safety
that he did not carry out promptly the modifications required by his insurers
in the Report ofMay 1995.
ISSUES OF LAW
- Since I have found that Pride Valley would not have acted on the warnings
which Halls should have given, the issues of causation, contributory negligence
and whether Halls contracted as a partnership or a limited compnay do not
arise. I deal with them relatively briefly.
CAUSATION/CONTRIBUTORY NEGLIGENCE
- In this case Halls say that if I find against them on the facts they are
not liable because the chain of causation was broken. They argue further that
if I find against them on causation, damages should be significantly reduced
as a result of Pride Valley's contributory negligence.
CAUSATION
- In Caswell v. Powell Duffryn Associated Collieries Ltd [1940] AC152
at 165
Lord Atkin said:
"On the other hand if the Plaintiff were negligent but the negligence
was not a cause operating to produce the damage there would be no defence.
I find it impossible to divorce any theory of contributory negligence
from the concept of causation."
- In order to recover damages, the Claimant must show:
(a) That the kind of loss for which he claims damages (but not necessarily
its extent) was reasonably foreseeable, and
(b) That the loss which he suffered was in fact caused by the Defendants
breach of duty - it is enough if the breach was an effective cause of
the loss - see Banque Bruxelles SA v. Eagle Star [1995] 1QB375
per Sir Thomas Bingham MR at page 406E and
(c) the loss was not too remote - see Clerk & Lindsell on Torts 17th
Ed 2 - 02 -- 2 - 31.
- Although the chain of causation may be broken by the actions of the Claimants,
by the actions of third parties or by intervening events in general, an act
or event which is reasonably foreseeable will not be deemed to break the chain
of causation - see McGregor on Damages 16th Ed paragraphs 151 ff .
- In my view it was reasonably foreseeable that if EPS insulating panels,
which were readily combustible were placed in close proximity with a process
which involved baking a product which included oil, there was a foreseeable
risk of fire. This risk was identified in the Fire Reports and those of the
insurers. The estimate of the risk ranged from moderate from Mr Pickersgill,
to so serious that the insurance should not be undertaken from the Commercial
Union shortly before the fire.
- I conclude on all the evidence that the loss i.e. damage by fire was entirely
foreseeable and that the failure of Halls to warn Mr Rezaei of the nature
and the extent of the risk of which they were aware would have been an effective
cause of the loss if I had concluded that Pride Valley would have accepted
and acted upon the advice.
CONTRIBUTORY NEGLIGENCE
- The Law Reform (Contributory Negligence) Act 1945 provides as follows:-
Section 1 (1) "Where any person suffers damage as the result partly of his
own fault and partly of the fault of any other person or persons a claim in
respect of that damage shall not be defeated by reason of the fault of the
person suffering the damage but the damages recoverable in respect thereof
shall be reduced to such extent as the court thinks just and equitable having
regard to the Claimant's share in the responsibility for the damage."
- "The defence of contributory negligence is available whenever the Plaintiff's
own negligence contributes to the damage of which he complains." See Clerk
& Lindsell (17th Ed (1995) at 3-10."
- It does not matter in this regard whether the operative fault of the Claimant
is prior, or subsequent, to the wrong doing of the Defendant. Broad common
sense should be used to judge cause and effect on the facts of each particular
case - see Clerk & Lindsell at 3-13.
- In this case it is agreed by the fire experts that the fire was caused by
the ignition of cooking deposits that had accumulated in the flue pipe of
the number 1 pitta oven. This accumulation of cooking deposits was caused
by Pride Valley's failure to clean the inside of that oven (and in particular
the canopy and flue) adequately or at all and/or to modify the line to facilitate
cleaning. Part of the problem occurred no doubt because the safety arrangements
were made on the basis that the pitta oven would be used solely for pittas,
which did not use much if any oil, and not for mini-nans which used a considerable
amount of oil.
- It is clear from Mr Henry's evidence that when the pitta line was being
used for the production of mini-nans neither Mr Henry nor any of his staff
cleaned the inside of the oven hood and the ducting above that oven. Further,
as far as Mr Henry knew, and he was in a good position to know, no one else
cleaned the inside of the oven or the flue.
- The statement given by Mr Carne, the baker on the pitta line at the time
of the fire, confirmed that (a) the oven had not been cleaned for three days
before the fire, and (b) even when it was cleaned, the staff only wiped down
the outside of the oven. They did not clean the inside of the oven hood or
flue.
- The expert evidence is clear that this level of cleaning would not prevent
deposits from building up on the pitta line. Combustible deposits would also
have built up within the flue to that oven.
- I am satisfied therefore that deposits of oil built up on the pitta line
either as a result of the small amount of oil in the pittas which were produced
immediately before the fire and/or in the oil which had built up during the
time of the mini-nan production and was not properly cleaned. I do not need
to reach a conclusion as to whether or not the mini nans were produced from
six to eight weeks from June 1995 or for the longer period which was given
in evidence by Mr Ryder and supported by Mr Robinson. I find that oil had
accumulated from the time of the mini-nan production on the inside of the
oven hood or flue in addition to any oil which had accumulated from the resumed
production of pittas.
- On the 28th June 1995 there was a fire in the nan oven. As a result of that
fire grease filters were fitted to the nan oven but not to the pitta oven.
The purpose of those filters was to prevent the oily deposits from accumulating
in the canopy and flue so as to avoid the possibility of a further fire on
the nan line. No modification was made to the pitta oven even though the pitta
oven was used for a substantial period of time for the production of mini-nans.
- On the 5th July 1995 Scot-Tech warned Pride Valley of the fire hazard associated
with any grease build-up if the pitta line was used for the production of
nans. Scot-Tech recommended that Pride Valley should monitor this situation.
Pride Valley was therefore warned in terms by Scot-Tech of the fire risks
associated with the build up of grease on the pitta line.
- Despite Pride Valley's knowledge and Scot-Tech's warning, Pride Valley continued
to use the pitta line for the production of mini-nans, failed to fit a grease
filter to the pitta line during such production, and failed to ensure that
steps were taken to clean the inside of the oven canopy or the flue even though
so much oil was being used in the production of mini-nans that it flooded
onto the floor and burnt on the oven slats.
- In my view this matter falls within the terms of the Law Reform (Contributory
Negligence) Act 1945 in that Pride Valley suffered damage partly as a result
of the fault of Halls and partly as a result of their own fault. The matters
which I have just set out represent a serious fault on the part of Pride Valley.
If I had concluded that Pride Valley was entitled to recover damages I should
have reduced those damages by 50%.
THE PARTNERSHIP ISSUE
- The issue between the parties is whether or not Halls contracted as Hall
and Partners (a firm) or Hall and Partners Contracts Management Limited (a
limited company). This issue must be decided objectively. The problem is encapsulated
by the two letters sent to Mr Rezaei by Halls on 11th December 1992. The covering
letter written on Hall and Partners notepaper, enclosed for consideration
by Mr Rezaei a letter of appointment written on the notepaper of Hall and
Partners Contracts Management Limited. Pride Valley say that both contracts
were made with the partnership. Halls say that both contracts were made with
the limited company. The signed contract dated 11th December 1992 was on the
notepaper of Hall and Partners Contracts Management Limited. The signatures
at the end were given by Mr Rezaei on behalf of Pride Valley Bakery and by
Mr Hall on behalf of Hall and Partners. The designation at the end of the
proposal letter is not intended to give any indication as to whether or not
either side was contracting as a limited company.
- The previous correspondence between the parties is not conclusive but the
letter of 16th October 1992 which set out the original analysis of the two
alternative services to be provided by Hall and Partners refers in the notepaper
to Hall and Partners having partners, Mr Hall, Mr Duncan, Mr Dunn and Mr Cosgrove.
It was explained to me and I accept that there was nothing sinister in the
fact that the only genuine partner in terms of equity was Mr Hall. It was
accepted by Hall and Partners that Mr Hall, Mr Duncan, Mr Dunn and Mr Cosgrove
were able to hold themselves out as being entitled to contract on behalf of
the firm.
- The next letter dated 29th October 1992 is again on Hall and Partners notepaper
with reference to the same four named individuals as partners.
- The feasibility estimate number 1 and outline specification is on the notepaper
of Hall and Partners Chartered Quantity Surveyors Project and Estate Managers
but does not make it clear whether this is Hall and Partners, the designated
firm, or Hall and Partners the limited company.
- The next letter from Mr Hall dated 30th October 1992 is on Hall and Partners
Limited notepaper and it has three names at the bottom which make it appear
that they are the three Directors.
- Mr Rezaei did not sign the contract letter dated 11 December 1992 immediately
after he received it. He also received a further letter from Hall and Partners
signed by Mr Thompson and dated 15 December 1992 before he signed the contract.
This letter was also on the notepaper of Hall and Partners Contracts Management
Limited. This covering letter referred to a telephone conversation that day
with Mr Hall and accepted that Mr Rezaei was not going to accept the full
design service which Halls were offering. It was after receiving this letter
that Mr Rezaei signed the earlier copy of the terms of engagement which had
been enclosed with the earlier letter.
- Having considered the evidence objectively I conclude that the contract
was made with Hall and Partners Limited.
CONCLUSION
- On my findings of fact Pride Valley 's claim fails and I find for the defendants.