Before: His Honour Judge Humphrey LLoyd QC
In the Matter of an Arbitration between:
RON JONES (BURTON-ON-TRENT) LIMITED
Claimant
and
JOHN STEWART HALL AND JACQUELINE DOROTHY HALL Respondents
Between:
RON JONES (BURTON-ON-TRENT) LIMITED Appellant
and
MR J.S. & MRS. J.D. HALL Respondents
Case number: 1997-ORB-647
Date of Judgment: 7 April 1998
This was an appeal pursuant to section 1 of the Arbitration
Act 1979 from the interim award of an arbitrator in which he had held that
he had jurisdiction to deal with certain claims which had been the subject
of an earlier arbitration but which had not been adjudicated on by the
first arbitrator. The appeal was allowed and the interim award as varied
was remitted to the arbitrator. The facts and reasons appear from the judgment.
Mr Ian Pennicott for the Appellant (Solicitor: J.E. Taylor)
Mr Geoffrey Conlin for the Respondents (Solicitor:
D. Faulkner)
JUDGMENT
1. The text of the judgment approved by His Honour Judge
Humphrey LLoyd QC is as follows:
1) This is an appeal pursuant to section 1 of the Arbitration Act 1979 from an Interim Award of Mr D.T. Simmonds. The contract between the parties incorporated the standard JCT conditions with Contractor's Design, 1981 edition, clause 39.5.1 of which provides for an appeal to the High Court by consent on any question of law arising out of an award. The contract was for the alteration, refurbishment and extension to the property of the respondents who own and operate a residential home known as "The Alternative Care Centre", The Lauders, 19 Ashby Road, Burton on Trent. The value of the contract was £544,000. The works had begun on 16 December 1991 (although the contract was not entered into until 8 June 1992). Practical completion of the works took place, it is said, on 7 May 1993. Disputes arose between the parties as to the amount payable under the contract, ie as to the adjusted contract sum or final account, and as to whether the work had been performed properly and on time. As a result on 31 May 1994 the appellant contractor wrote to the respondents as follows:
"Alternative Care Centre, 19, Ashby Road, Burton on Trent.2) Thereafter agreement was reached on the appointment of Mr Arthur Goldstraw as the arbitrator. He held a preliminary meeting on 27 September 1994. A defence and counterclaim was served by the respondents on 5 February 1995. The appellant did not regard the defence and counterclaim as adequately setting out the respondents' case, nor was it satisfied with further and better particulars provided pursuant to a request. It therefore sought further directions from the arbitrator who on 5 May 1995 ordered the respondents to provide further and better particulars including specific references to invoices where applicable, and also required the parties to name its experts. The appellant was still unhappy with the particulars received, and went back to the arbitrator who on 5 June 1995 directed the respondents to serve a definitive Scott Schedule in respect of the defects and incomplete work by the end of that month. However, the Scott Schedule was still regarded by the appellant as insufficient and complaints were made about its lack of particularity and the inclusion in the Scott Schedule of new allegations for it had been expanded from 28 items of complaint to some 57 items and the sum claimed by the respondents had increased from £32,000 to £122,000.
2. I am in receipt of your letter dated 25th May 1994 and regret you are not wishing to settle this matter in a business like manner.
3. Your attempts at limiting your liability by initiating counter claims are not accepted.
4. Accordingly, under the terms of Article 5 of the contract, I request you to concur to the appointment of an arbitrator."
3) The appellant wrote to the arbitrator on 14 July 1995 seeking an order that certain items in the Scott Schedule should be struck out including items A1, A5, A7, A14, A15 and B25. The upshot of the application was that the arbitrator permitted the respondents to serve an amended defence and an amended Scott Schedule. On 25 September 1995 the appellant asked the respondents for the original invoices relied on in support of the counterclaim.
4) On 9 October 1995 the hearing of the appellant's claim commenced before Mr Goldstraw. (It had been decided to deal with the claim before the items in the counterclaim.) At that hearing counsel instructed on behalf of the respondents confirmed that the invoices would be delivered by 13 October 1995. However, the hearing had to be adjourned (twice) and its resumption was fixed for June 1996. At that stage the invoices had still not been supplied by the respondents. Accordingly the appellant obtained an order from His Honour Judge Havery QC authorising the arbitrator to act under section 5(2) of the Arbitration Act 1979.
5) At a further meeting before the arbitrator on 2 April 1996 the respondents were ordered to make available at their solicitors' offices in the week commencing 15 April 1996 originals of the invoices for inspection and copying. However in that week their solicitors ceased to act for them. It then transpired that the respondents were in difficulty with obtaining papers from these solicitors. The respondents also indicated that a defect in the lift shaft had been discovered for which an application to amend would be made. On 30 May 1996 the parties came back before the arbitrator. It seems that the respondents did not obtain leave to amend in respect of the lift shaft (or other complaints in respect of floors, fire doors and roof) as the application had not been made in writing. Pursuant to section 5 of the Arbitration Act 1979 the arbitrator made an order that the respondents should make available the original invoices by 7 June 1996 in default of which they would be debarred from adducing any evidence on the issues arising from the items in the Scott Schedule relating to the invoices.
6) The hearing of the appellant's claim resumed on 4 June 1996 and continued for most of that month. The respondents applied to bring in their complaints in respect of the lift shaft, fire doors on the second floor, and ceilings. The respondents also asked for more time to produce the invoices. The arbitrator granted them more time until 14 June 1996 to do so. On 13 June 1996 an application for yet further time was refused by the arbitrator.
7) The application to amend was heard initially on Friday 7 June 1996. In the course of his submissions on that day counsel for the appellant said to the arbitrator:
5. Sir, in my submission you should disallow all of these
amendments. No prejudice will be occasioned to the respondents by you doing
that and certainly not on 21, 22, 38, 38, 39 and 40 and, as far as the
lift shaft is concerned, no prejudice will eventuate to the respondents,
because they will just have to bide their time and take proceedings in
the future, knowing that they don't have a limitation problem.
6. Sir, if you let them in, then obviously the consequences
that I have outlined, or some of them, will follow in terms of the inconvenience
and disruption that is going to be caused to the further progress of this
hearing, and the potential for simply leaving a number of matters hanging
in the air. A final award is what we are striving to achieve in the next
few weeks and that is what we would wish to have. Sir, for those reasons
we oppose this application to amend the defence and the Scott Schedule."
7. Sir, the paramount consideration, in our submission, is
you reaching a final award on the matters that are before you at the moment.
That finality will be taken away, undoubtedly, if all or any of these amendments
are let in, particularly, of course, the lift shaft in that regard. I would
ask you, sir, therefore to disallow these amendments on both levels."
11) The respondents then indicated that they intended to apply for the removal of the arbitrator. Accordingly on 9 July 1996 the arbitrator made orders: unless the respondents took steps by 19 July 1996 to commence proceedings for his removal, the stay of the proceedings would be lifted so as to allow the appellant to obtain an award on its claim, and, secondly, the respondents would be debarred from adducing evidence on the counterclaim which would be struck out. If on the other hand the respondents went ahead with their application, the arbitration would remain stayed until the conclusion of the Court proceedings. In this way the respondents would have had their counterclaim heard and any consequential effect would be reflected in the arbitrator's decision on the claim. The respondents issued proceedings in the High Court, but not within the time required by the arbitrator's order, so that on 30 July 1996 he indicated that since they had not complied with the terms of the order he would be making an interim award on the appellant's claim. This the arbitrator did on 6 September 1996.
12) The respondents appealed against that interim award. That application and the respondents' earlier application was listed before me on 4 October 1996, but it was not heard since agreement was reached between counsel for the parties. Its terms were set out in a Consent Order agreed between counsel for the parties on 7 November 1996 and sealed by the Court on 16 January 1997. It included the following [the respondent is the present appellant]:-
(ii) The Unless Order in relation to Security for Costs dated 24 June 1996 be set aside. The costs of the Security for Costs application in the arbitration to be borne by the respondent (the Claimant in the arbitration) in any event.
(iii) The Unless Order dated 9 July 1996 as amended by the arbitrator's letter dated 12 July 1996 be set aside.
(iv) Save for paragraph 4 therein the Order dated 30 July 1996 be set aside.
(v) In the premises of paragraphs (i) to (iv) above, the subject matter of the applicant's counterclaim and/or set-off as pleaded in the pleadings in the Reference, subject to the effect of paragraph (i) herein be remitted to the arbitrator for hearing following which the arbitrator is directed:
(b) to make and publish a Final Award dealing with all issues of costs including those arising out of the Orders referred to above.
8. We would respectfully submit that the proper course should
be for our Set Off to be consolidated with those fresh proceedings to be
heard before a new arbitrator. If you are minded to call a directions hearing
the week commencing the 4th November is not convenient but the 25th would
be."
9. Your solicitor, Mr Falconer, from Haddon Owen & Son,
said he understood what was being said but he made no admissions as to
the correctness or otherwise of [the] legal position and that you wished
to proceed with the course of action."
17) On 19 April 1997 Mr Goldstraw made a further Order in the first arbitration to give effect to the Orders previously made including the parties' Consent Order which resolved the respondents' applications to the Court. He listed the items in the Scott Schedule which were now to be regarded as excluded from the first arbitration, and which totalled nearly £19,000.
18) There was a further excursion to this Court which resulted in an order of His Honour Judge Newman QC directing Mr Goldstraw to make an amended first interim award and to make a final award dealing with costs. Mr Goldstraw on 2 September 1997 published both an amended interim award awarding the appellant £229,566.42 and a final award giving the appellant the costs of the first arbitration and ordering the respondents to pay the arbitrator's costs of approximately £35,000. The respondents have not yet paid either sum.
19) As a preliminary point in the second arbitration the appellant challenged the jurisdiction of the arbitrator to make an award in relation to the 12 heads of claim which were the subject matter of Section C of the respondents' Statement of Case of 25 April 1997. These heads were described as:-
(1) Unfit for purpose;20) The respondents' contentions were developed in some detail in both Section C and Section D of their statement of claim.(2) Plan;
(3) VAT;
(4) Roof space above second floor office kitchen area;
(5) Basic structure;
(6) Lift shaft;
(7) Basement structure;
(8) Training room second floor level (store) 4;
(9) Coffee shop - supporting beams above ground floor level;
(10) Ceilings to cellar, ground floor and first floor;
(11) Change of use of second floor from storage to offices;
(12) Scott Schedule in earlier arbitration.
21) Mr Pennicott (who appeared for the appellant) explained that these heads of claim fall broadly into three categories:-
(ii) Items 1, 2, 3, 4, 5 and 7 did not feature in the counterclaim in the first arbitration nor did they form any part of the amendment application in that arbitration;
(iii) Item 12 now comprises 38 items contained in the Scott Schedule forming the discontinued counterclaim in the first arbitration.
23) The issues relating to the arbitrator's jurisdiction were dealt with on the basis of written and oral statements on behalf of the parties. No witnesses were called, as recorded by the arbitrator. By his interim award of 2 October 1997 the arbitrator reached the following decisions:-
(ii) The Claimants are estopped from including in item (12) of their Statement of Case any items not contained within the Scott Schedule as amended at June 1996. Any such items are res judicata and I have no jurisdiction to deal with them.
10. For the avoidance of doubt items (1) - (11) are deemed
for this purpose as not having been nor being included in the Scott Schedule.
(iii) Save as aforesaid at (i) and (ii) I have jurisdiction to deal with all matters subject of the Claimants' Statement of Case."
29) The arbitrator set out his reasons in his award. He dealt with each of the grounds relied on by the appellant. In relation to the first head he recorded that:
(b) was it final and on the merits
(c) did it determine the same question(s) as raised in the second arbitration."
31) The second ground argued by the appellant before the arbitrator was that even if the items had not been the subject of a decision attracting the defence of res judicata they were nevertheless caught by the issue estoppel (which appears to merge with the "extended doctrine of res judicata"). "Issue estoppel" is the application of the second limb of the principle in Henderson v Henderson (1843) 3 Hare 100 at pages 114-115:-
33) The principle of issue estoppel applies to arbitration: Fidelitas Shipping Co Ltd v V/O Exportchleb [1965] 1 QB 630 at page 643C per Diplock LJ:
11. In choosing arbitration as the method of determining disputes
as to their respective legal rights and duties, the parties constitute
the arbitrator the exclusive tribunal to determine all disputed questions
of fact, but they do not thereby constitute it the exclusive tribunal to
determine all the legal consequences of those facts...."
12. It will be seen that this passage appears to have opened
the door towards the possibility that cause of action estoppel may not
apply in its full rigour where the earlier decision did not in terms decide,
because they were not raised, points which might have been vital to the
existence or non-existence of a cause of action. The passage has since
frequently been treated as settled law, in particular by Lord Shaw, giving
the advice at the Judicial Committee of the Privy Council, in Hoystead
v Taxation Comr [1926] AC 155 at 170, [1925] All ER Rep 56 at 64. That
particular part of it which admits the possible existence of exceptional
cases was approved by Lord Kilbrandon in Yat Tung Investment Co Ltd
v Dao Heng Bank Ltd [1975] AC 581 at 590, saying:
13. It is to be noted that there appears to be no decided
case where issue estoppel has been held not to apply by reason that in
the later proceedings a party has brought forward further relevant material
which he could not by reasonable diligence have adduced in the earlier.
There is, however, an impressive array of dicta of high authority in favour
of the possibility of this. It was argued for the appellants that exceptions
to the rule of issue estoppel should be admitted only in the case of the
earlier judgment being a default or a foreign judgment and further that
an exception should not be recognised where the point at issue had actually,
as here, been raised and decided in the earlier proceedings, but only where
the point might have been but was not so raised and decided. The later
dicta are, however, adverse to these arguments. It was argued that there
was no logical distinction between cause of action estoppel and issue estoppel
and that, if the rule was absolute in the one case as regards points actually
decided, so it should be in the other case. But there is room for the view
that the underlying principles upon which estoppel is based, public policy
and justice, have greater force in cause of action estoppel, the subject
matter of the two proceedings being identical, than they do in issue estoppel,
where the subject matter is different. Once it is accepted that different
considerations apply to issue estoppel, it is hard to perceive any logical
distinction between a point which was previously raised and decided and
one which might have been but was not. Given that the further material
which would have put an entirely different complexion on the point was
at the earlier stage unknown to the party and could not by reasonable diligence
have been discovered by him, it is hard to see why there should be a different
result according to whether he decided not to take the point, thinking
it hopeless, or argue it faintly without any real hope of success. In my
opinion your Lordships should affirm it to be the law that there may be
an exception to issue estoppel in the special circumstance that there has
become available to a party further material relevant to the correct determination
of a point involved in the earlier proceedings, whether or not that point
was specifically raised and decided, being material which could not by
reasonable diligence have been adduced in those proceedings. One of the
purposes of estoppel being to work justice between the parties, it is open
to courts to recognise that in special circumstances inflexible application
of it may have the opposite result, as was observed by Lord Upjohn in the
passage which I have quoted above from his speech in the Carl-Zeiss
case [1967] 1 AC 853 at 947.
43) Reference was also made to New Brunswick Railway Company v British and French Trust Corpn. Ltd [1939] AC 1 in which Lord Maugham LC said (at page 21):
45) It is evident from the award that the arbitrator understood one of the key questions which he had to decide for in a section of his reasons headed "Doctrine of extended res judicata" he posed the question "Could the new items of claim with reasonable diligence have been brought into the first arbitration?". He said, amongst other things:-
14. However I do accept the principal thrust of the Claimants'
submission in that it was only as simpler, smaller defects, etc were investigated
in more detail that the more general and more serious problems came to
light and eventually (at least in the Halls' eyes) these latter problems
overtook the earlier ones. Their case needed a complete re-appraisal but
when they endeavoured to make adjustments their application to amend was
rejected.
15. Mr Pennicott made the point that the Halls were subsequently
given the opportunity (through the compromise) to have their Counterclaim
heard by Mr Goldstraw but they rejected this opportunity by withdrawing
it. However their concern that movement was still taking place and advice
received in November/December 1996 .... that the building was allegedly
incorrectly designed created a situation whereby it was sensible to "start
again" as it were giving time to set out their case properly.
16. Thus I accept that the Respondent generally had good reason
for not bringing in or attempting to bring in to the first arbitration
the "new" items in this arbitration, namely those at Section B of its submission.
(2) The assertions in the Claimants' Statement of Claim
go beyond the mere absence or inadequacy of plans. I accept that the alleged
situation may have had some bearing on the time it took for the existence
of other alleged design and structural defects to be appreciated.
...
(4) Roof Space above Second Floor Kitchen Area
17. The alleged inadequacy of the roof design is stated to
have led to movement of the structure below causing fracturing. The visible
evidence is stated to have appeared in December 1996 ..... . In that case
clearly the issue could have been raised earlier."
......
"The various judgments brought to my attention emphasise
that if with due diligence matters could have been raised in an earlier
action and were not then they now may be estopped, subject to the consideration
of special circumstances, e.g. Henderson, page 224, Fidelitas,
page 640. I have particularly studied the Chandler case which in
a number of respects had circumstances similar to those subject of the
present situation. Unfortunately little guidance is given in this and other
cases as to what "special circumstances" encompass although various indications
are given as to what they are not - in particular 'negligence, inadvertence
or accident'. However in Arnold, Lord Keith expressed the opinion
(page 109):
18. Taking account of the overall situation at the time I
am satisfied that circumstances existed which may reasonably be construed
as special circumstances and I conclude that the Claimants are entitled
to pursue some but not all of their claims under Sections B and C of their
Statement of Claim."
49) Mr Pennicott submitted that the first arbitrator's awards had expressly recorded the withdrawal of these items which lay within his jurisdiction and although they were thus awards by default nonetheless the doctrine of res judicata applied, as they were awards as to the amount of the adjusted contract sum which took into account all available defences such as abatement or set-off which might have resulted in a different sum. Secondly, in the alternative, Mr Pennicott submitted that the extended res judicata principle applied: the items were raised in the first arbitration; they could and should have been pursued and there was no legitimate reason or special circumstance available in law to the arbitrator to permit them to be pursued in the second arbitration. Thirdly, the attempt to pursue the items before the second arbitrator was an abuse of the arbitral process. If it were permitted it would enable a party to stop a claim or defence in an arbitration if, for example, that party thought it was not going to be successful, and then to commence a further arbitration to see if it would do any better before another arbitrator. Forum shopping of this kind should not be allowed.
50) As regards items 2, 4, 8, 9 and 11 Mr Pennicott argued that issue estoppel and the extended principle applied and that, since it had been expressly conceded on the respondents' behalf by their solicitor that there were no special circumstances, it was not open to the arbitrator to hold that there were special circumstances displacing issue estoppel or justifying what would otherwise be an abuse. The fact that the items might conceivably constitute separate causes of action (which he did not concede) was irrelevant and did not provide an answer to the appellant's submission. The pursuit of these items would be an abuse of the arbitral process since it had been conceded that they all could and should have been raised in the first arbitration.
51) Mr Conlin for the respondents essentially emphasised the apparent concession made by counsel for the appellant on the first occasion in which the respondent's application to amend had been argued before Mr Goldstraw ie that if, for example, the lift shaft item were not allowed into the first arbitration by an amendment the respondents might nevertheless pursue a second arbitration in respect of it as a new cause of action. That concession had been referred to in the respondents' statement of claim and in their written submissions to Mr Simmonds and was seemingly mentioned by him in his interim award (albeit only in his summary of the respondents' case as presented to him).
52) Mr Conlin submitted that it was doubtful whether Henderson v Henderson applied to arbitration since the jurisdiction of an arbitrator was confined to the reference. He referred to Mustill & Boyd on Commercial Arbitration at page 413:
(b) in the absence of special circumstances, issue estoppels bar all questions whether raised or not;
(c) all remedies for a cause of action must be sought in the one proceeding;
(d) causes of action arising out of the same factual context which have not been adjudicated upon in earlier proceedings will be barred;
(e) causes of action arising out of the same factual context which have not been adjudicated upon in earlier proceedings will be barred by the extended doctrine where the relief sought in the later proceedings, if granted, would be inconsistent with the relief in the former proceedings."
56) As regards items 2, 4, 8, 9 and 11 Mr Conlin submitted that there were new and separate causes of action which the respondents were entitled to pursue and in any event the arbitrator found that there was special circumstances. The arbitrator had benefit of the copy of the relevant extract from the transcript when he arrived at his decision as to whether there were matters which could have been established with reasonable diligence: that was a formal admission which the arbitrator obviously took into account, and was entitled to act on the formal admission.
Decision
57) An appeal from the award of an arbitrator lies only if questions of law arise on the award. In deciding whether an arbitrator has reached the correct conclusion on a question of law, the facts found by the arbitrator and set out in the award are the only facts which a court can take into account. Here however, it is common ground between the parties that in order to understand the facts found by the arbitrator it is necessary to look at what had happened. I have therefore done so but only to see what facts were before the arbitrator when he came to make his award so as to see what he was referring to. It is convenient to consider each of the questions of law in turn as set out in the Notice of Motion. First , as to Item 12 - The Scott Schedule items - the question posed in the appellant's notice of motion is:
(b) that party expressly agreed, by virtue of a Consent Order of the Court to pursue such issues and matters in the earlier arbitration proceedings,
60) It is desirable to deal first with two general points raised by Mr Conlin's arguments. The first is whether in some way the doctrine of res judicata, or cause of action or issue estoppel does not apply to arbitrations.
61) There are some differences between arbitration and litigation. An arbitration is a contractual method of dispute resolution and is initiated so that there may be a decision on the dispute or disputes required by the contract to be referred to arbitration. A contract may require the dispute to be defined so in this instance clause 39.1 of the JCT form calls for written notice to be given "to such effect and such dispute or difference shall be referred to the arbitration and final decision of [the arbitrator]". The reference of a dispute necessarily includes any defence to the claim of the referring party whether or not it created the dispute. Furthermore where the arbitration is conducted under specific rules which permit a party to include other claims or to make counterclaims then the disputes referred also include all the issues arising from such additional claims or counterclaims. In this case clause 39.8 of the JCT form required the arbitration to be conducted in accordance with the JCT Arbitration Rules. These set out a basic procedure and a timetable which are intended to ensure that each party has a fair opportunity of presenting its case in full. A respondent has a right to submit both a defence and a counterclaim. The claimant is to answer the counterclaim. Accordingly where this is done the dispute referred will be enlarged to cover the issues arising from defence, counterclaim and the defence to the counterclaim.
62) The respondents elected to advance defences to the appellant contractor’s claims for the appropriate adjusted contract sum and final account since they wished to defend those claims on the grounds that the value of the contract works was not that claimed since the works had not been executed or completed in accordance with the contract and were defective, incomplete or late. These contentions were the subject of what was termed the set-off or counterclaim. Procedurally Mr Goldstraw heard first issues relating to calculation and composition of the final account and adjusted contract sum (on the assumption that the works was properly carried out and completed) and was secondly to hear the issues relating to defects etc before he made his award taking into account his conclusion on each set of hearings. If therefore the respondents' case had been sustained on the facts they would then in law be entitled to an abatement of the adjusted contract sum or a set-off or set-offs on account of their losses. I can see no reason of policy why such a party to such arbitration should not be required to advance the whole of its case in answer to such a claim as made by the appellant. If it were not obliged to do so the claimant might obtain an award for the final contract sum only to be unable to enforce in full or to be deprived of it by having to repay some or all of it in subsequent proceedings. Further to sanction the withdrawal of a defence, set off or counterclaim could lead to a party picking and choosing between arbitrators until the "right" one was found. This would indeed by an abuse of the arbitral process. Although arbitration is an alternative to litigation as a form of dispute resolution it does not provide such a series of alternatives.
63) Mr Conlin's submission is in my judgment contrary to the clear statement of principle by Diplock LJ in Fidelitas Shipping Co Ltd v V/O Exportchleb [1965] 1 QB 630 at page 643C. I do not consider that simply because he was there dealing with cause of action and issue estoppel in the context of one arbitration proceedings his statement is not applicable to successive arbitrations. Similarly Mustill & Boyd on Commercial Arbitration at page 413 serves only to emphasise that cause of action or issue estoppel operate only on claims or issues which fall within the scope of the arbitration agreement, and the particular reference. However as the authors say: "On the other hand, a claim which does fall within the scope of the reference is deemed to be abandoned if it is not repeated in the claimant's pleading, and although the arbitrator has a discretion to allow it to be revived by amendment during the reference, the abandonment becomes irrevocable once the arbitrator has made his award."
64) Secondly, on the facts and circumstances set out in the award the claims made by the respondents in the first arbitration and which reappeared in the second arbitration do not appear to be separate causes of action: they were all complaints about the respects in which the appellant had failed to comply with its obligations under the building contract. The respondents had one cause of action for breach of contract and effectively one defence namely that of abatement or set-off. There are instances where as a matter of fact and degree a distinction is validly to be made between some complaints of defective work such that some may as a matter of impression be treated as giving rise to separate causes of action: Steamship Mutual Underwriting Assn Ltd v Trollope & Colls Ltd (1986) 33 BLR 77. However since the respondents' claims in the second arbitration were either the same as those advanced in the first arbitration or were according to the arbitrator's findings a development or continuation of the original claims they cannot in my judgment be regarded as separate and new causes of action or defence or, in any event, materially different from those advanced in the first arbitration.
65) The first ground relied by the appellant was that item 12 was barred by what was termed by Stuart-Smith LJ in Talbot's case "res judicata in the strict sense. (The circumstances set out in paragraphs (a) and (b) are irrelevant to this ground; those in paragraph (a) were not found by the arbitrator to be relevant for either of the other grounds and I shall therefore ignore them.) That rule only applies where there has been truly a decision either on the merits or which is to be treated as a decision on the merits. Where a party voluntarily withdraws a cause of action or defence from an arbitration whereby an award is made dismissing it and determining an amount that would or might have been different had the cause of action or defence been pursued that award is in my judgment tantamount to a decision on the merits and it cannot be right that there should thereafter be a resurrection of that cause of action (or defence in the form of a cause of action) against the party affected with consequences of the kinds that I have already described. To allow a party to do so would be contrary to the principles underlying the doctrine which were restated by Lord Keith in Arnold v National Westminster Bank [1991] 2 AC 93 at page 104F:
67) However it is in any event clear that issue estoppel also applies. Items in the Scott Schedule were plainly before the arbitrator. Therefore the respondents are plainly issue estopped (unless there is, in effect, a public policy reason why they should be exempted) for the items are all matters which could and therefore should have been litigated in the first arbitration. It is in my view plain from the authorities that there have to be special circumstances to displace the application of the doctrine: a party is estopped from raising those matters and not, as the arbitrator said: "if with due diligence matters could have been raised in an earlier action and were not then they now may be estopped". Unfortunately, as the arbitrator observed, little guidance is given as to what might displace the doctrine, ie what are "special circumstances". In my judgment it is clear from the application of Henderson v Henderson in Arnold and in the other cases referred to above that it is not sufficient that the items were known but through inadvertence or lack of reasonable diligence etc were not pleaded for otherwise there would have been no need for the House of Lords to emphasise that issue estoppel does not apply where the matter could not with reasonable diligence have been discovered. Indeed since neither lack of diligence nor "negligence, inadvertence, or even accident" suffice the special circumstances must be exceptional and additional to the circumstances which do not suffice. Furthermore, unless it had been found by the arbitrator that the reason why the respondents had elected to take the course that they did namely to withdraw certain Scott Schedule items from the jurisdiction of the first arbitrator (disregarding their agreement in the consent order to allow the first arbitrator to deal with them) was prompted by what was said by counsel for the appellant before the first arbitrator (and as I have already recorded there was no such finding), there appears to me to be no special circumstances which would be regarded in law as permitting the arbitrator, properly directing himself as to the principles of law, to have held that the respondents could maintain these items in the second arbitration. The arbitrator's findings are that the respondents had either advanced the items in the first arbitration or could with diligence have done so had they pursued the requisite investigations and sought and obtained proper advice. Accordingly I have come to the conclusion that the arbitrator was wrong in law in allowing item 12 of the Scott Schedule: Mr Goldstraw's award is final and binding on the subject-matter of item 12.
68) I do not consider it necessary to decide whether the learned editor of Spencer Bower Turner & Handley is right in the fascinating argument in chapter 26 of The Doctrine of Res Judicata, relied upon by Mr Pennicott. The authorities to which I was referred in Mr Pennicott's careful submissions go some way to justifying the proposition that there is some third and more general principle of law that it is an abuse of the arbitral process to withdraw claims and defences and then to revive them in a fresh arbitration. My principal difficulty in accepting the argument is that it seems to me that on the authorities binding on me to be merely another way of expressing or justifying issue estoppel: see eg Arnold and Talbot which speak "abuse of process" as the rationale for the "extended Principle". The Australian authorities do however suggest that there might be a broader approach. In my judgment the same result is to be achieved as a matter of analysing the nature of an agreement to arbitrate and its implications, as I have set out above when considering the first ground relied on.
69) The question of law posed by the applicant in reality asks whether the circumstances found by the arbitrator could in law justify an exception to the principle that a party cannot in subsequent proceedings bring forward points which were or which might have been advanced in earlier proceedings, but were not. The answer must be: No.
70) I now turn to items 2, 4, 8, 9 and 11. Items 2 and 4 were not part of the counterclaim in the first arbitration and as such do not obviously fall within the appellant's first ground. However they formed part of those within Section B of the respondents' submissions to Mr Simmonds with regard to which the arbitrator found that the respondents "generally had good reason for not bringing [them].... There are however exceptions....". Amongst the exceptions were items 2 and 4. The first item related to general inadequacy of plans which plainly was known to the respondents prior to the commencement of the first arbitration as was item 4 for the arbitrator found that the movement of the structure was on the respondents' own evidence visible to them in December 1996. Items 8, 9 and 11 were all items which, as the arbitrator found, were ones in respect of which the respondents had unsuccessfully applied to amend their counterclaim in the first arbitration.
71) In my judgment for the same reasons that I have given in relation to item 12 the strict rule applies to all these items, other than, perhaps, item 2 (since on the arbitrator's finding item 2 may not have been a matter of abatement, even though it was conceded before the arbitrator to be one for which no special circumstances existed). They are all matters which if established would or might have affected the determination of the adjusted contract sum. Mr Goldstraw's award is final and binding in respect of them.
72) In any event, on the arbitrator's findings all the items (including item 2) are barred by the application of the"extended principle" for the reasons set out above. Even if I leave aside the respondent's solicitor's admission or concession that there were no special circumstances to justify items 2, 8, 9 and 11 (by which he meant they could all have been established with reasonable diligence) the arbitrator's findings establish only those circumstances which do not suffice, since it is not, for example, sufficient in law that it was more convenient for the respondents to withdraw items or not to pursue item with diligence so as to present them together with other items in a new arbitration. I can therefore see no special circumstances available to the arbitrator which in law could justify his conclusion that in law the respondents were nevertheless entitled to bring them forward. In my view therefore this part of the award must also be set aside as Mr Goldstraw's award is equally binding in respect of them.
73) Since no useful purpose would be served by remitting the affected parts of the award to the arbitrator for further consideration there will (subject to submissions) be orders as follows: