IN THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
BEFORE HIS HONOUR JUDGE BOWSHER QC
BETWEEN:
P&O DEVELOPMENTS LIMITED
Plaintiff
-and-
THE GUY'S AND ST THOMAS' NATIONAL HEALTH SERVICE TRUST
Defendant
(by original action)
-and-
THE GUY'S AND ST THOMAS' NATIONAL HEALTH SERVICE TRUST
Plaintiff
-and-
(1) P&O DEVELOPMENTS LIMITED
(2) AUSTEN ASSOCIATES (a firm)
(3) AUSTEN ASSOCIATES LIMITED
Defendants
(by counterclaim)
Case number: 1996 ORB 1491
Dates of trial: 5,6 October, 1998
Date of Judgment: 15 October, 1998
Simon Goldblatt Q.C. and Adam Robb instructed by Rowe & Mawe for the Plaintiffs by Counterclaim. Richard Fernyhough Q.C. instructed by Speechly Bircham for the first Defendants by Counterclaim Andrew Bartlett Q.C. instructed by Berrymans for the second and third Defendants by Counterclaim.Rationale of Biggin v. Permanite:
1. A rule of evidence;
2. An application of the second rule in Hadley v. Baxendale.
JUDGMENT
Dated: 15 October, 1998
1. Official approved Judgment of the Court. No further note or transcript is to be made.
2. The text of the Judgment of His Honour Judge Bowsher Q.C. is as follows:
His Honour Judge Bowsher Q.C.
INTRODUCTION:
1. This is a trial of Preliminary Issues. Upon applications for further and better discovery of documents during preparations for trial of this action, it became clear that issues were raised going beyond discovery to the conduct of the trial of a part of the action.
2. With the agreement of the parties, I therefore ordered the trial of certain preliminary issues with a view to making rulings for the guidance of the parties in preparations for trial and in the conduct of the trial.
3. The parties have agreed certain assumptions of fact for the purpose of the trial of these preliminary issues only, but to understand those agreed assumptions, it is necessary to state something of the background. In giving an account of the background, I shall endeavour to give a simplified account of that part of the background as it affects the issues before me now. I hope that that account will not be so over-simplified as to be misleading. The issues before me now concern only a very small part of the multitude of issues and sub-issues arising in the action as a whole.
THE ACTION AND THE PARTIES
4. This action arises out of a part of a new building development of Guy's Hospital, London SE1. The part concerned is Stage 2 of Phase 3 of Philip Harris House, on the site of the existing main hospital building.
5. The defendants to the main action (Guy's) were the employers. They employed Higgs & Hill Management Contracting Limited (Higgs & Hill) as management contractor pursuant to a Management Contract dated 12 April, 1991. That agreement required Higgs & Hill to enter into contracts employing many Works Contractors.
6. Guy's employed a management team which included the plaintiffs by original action (P&O) as project managers, the second and third defendants by counterclaim (AA) as Mechanical and Electrical Services Engineers, Beard Dove as Quantity Surveyors, and Watkins Gray International as Architects.
7. There were delays to the project in respect of which the Architects granted extensions of time, and the parties to this action seek to cast the blame for those delays in various directions.
8. The action began with a claim by P&O for payments under their contract, including payments related to extensions of time. Guy's counterclaim against P&O and AA for damages for having caused a part of those delays by producing late and inadequate information and otherwise failing adequately to programme and manage the project.
9. A part of the counterclaim brought by Guy's, which is the part with which this preliminary trial is concerned, relates to claims brought by certain Works Contractors.
10. Works Contractors brought claims against Higgs & Hill with whom they had contracted. Those claims were, in part only, brought in respect of the delays which it is alleged can be traced back in part to delays caused by P&O and AA. The Management Contract required Guy's to recompense Higgs & Hill in respect of certain claims made against Higgs & Hill by the Works Contractors.
11. In 1994, the project was in disarray. Completion dates were past. Costs were rising. Guy's were open to liabilities which were difficult to quantify. To resolve their problems, Guy's took advice from distinguished surveyors, Davis Langdon and Everest and others. After consideration, Davis Langdon and Everest made a substantial report in writing in October, 1994 recommending a commercial agreement or "wrap-up deal" with Higgs & Hill. Following that advice, an agreement was made between Guy's and Higgs & Hill on 21 December, 1994.
12. By the 21 December, 1994 agreement, Higgs & Hill agreed amongst other things to complete Stage 2 by a fresh agreed date and to meet their own and the Works Contractors' claims without further recourse to Guy's. By that agreement, Guy's agreed to pay and did pay to Higgs & Hill £83.9 million (somewhat more than had been recommended by Davis Langdon and Everest). There was no agreement with Higgs & Hill as to how the £89.3 million was to be applied by Higgs & Hill. In particular, there was no agreement as to what, if any, sums were to be paid by Higgs & Hill to individual Works Contractors. That was a matter for negotiation between Higgs & Hill and the Works Contractors.
13. In the October, 1994 report, Davis Langdon and Everest made provision of individual sums for the claims made by Higgs & Hill and the individual Works Contractors.
14. In this action, Guy's contend that those provisions made by Davis Langdon and Everest are the starting point for the computation of that part of Guy's damages claim which relates to sums paid to Higgs & Hill in relation to delay claims by the Works Contractors.
15. Guy's contend that the Court should take the sums provided for by Davis Langdon and Everest in respect of those Works Contractors alleged to be relevant and decide what proportion of those provisions should be attributed to the delays caused by Guy's and AA. The resultant figures should then be taken to be the sums paid by Guy's to Higgs & Hill in respect of relevant delays suffered by Works Contractors as part of the £83.9 million and recovered as damages from P&O and AA. P&O and AA contend that that is far too simple an approach and that a much deeper enquiry should be made by both discovery of documents and by evidence at the trial into the relevant damage in fact suffered by the Works Contractors.
16. Guy's submit that by arriving at a global settlement with Higgs & Hill, within which were incorporated allocations for the delay and disruption claims of Higgs & Hill itself and the affected works contractors, Guy's established - so long as the global settlement figure itself was reasonable - the actual cost to Guy's of the delay and disruption claims.
17. Guy's contend that the settlement figure was primarily derived from the advice of Davis Langdon and Everest, and Guy's case is that so long as the advice given by Davis Langdon and Everest as to figures was reasonable, that was as far as Guy's needed to go in order to establish the reasonableness of the settlement. The consultants, P&O and AA contend that it is not enough for Guy's to accept and act upon apparently reasonable advice: on the contrary it is necessary to look behind the face of the advice, to examine the workings and the working papers of Davis Langdon and Everest and to investigate whether the advice given was in fact correct.
THE AGREED FACTS
18. The parties have agreed assumptions of fact in the following terms:
3. "These assumptions of fact are made for the purposes of the preliminary issues and are not to be binding upon the parties at any subsequent trial.
4. (1) Guy's entered into a Management Contract with H&H for the construction of Stage 2 of Phase 3 of the Guy's Hospital Project. H&H entered, over a period of time, into a number of Works Contracts with Works Contractors.
5. (2) During the work, construction was delayed and disrupted, with the result that a number of Works Contractors made claims for extensions of time and associated loss and expense and disruption against H&H under the terms of their Works Contracts.
6. (3) H&H made claims for extensions of time and associated loss and expense and disruption against Guy's under the terms of its Management Contract.
7. (4) The Architect granted extensions of time to H&H.
8. (5) H&H granted extensions of time, for varying periods, to a number of the Works Contractors.
9. (6) A negotiation took place between H&H and Guy's as to the sum at which the H&H would be prepared to fix the global cost of the contract, on the footing that H&H would fix the date for completion of the project, accept certain risks and settle the Works Contractors claims.
10. (7) Guy's received advice from Davis Langdon & Everest particularised in the FBPs served 19th May 1998.
11. (8) Guy's settled the dispute with H&H for an overall figure slightly higher than that recommended. That figure was £ 83,876,354. The present claims against P&OD and AA seek to attribute £ 6,720,947 (about 8%) of that sum to the alleged breaches of contract and duty by those consultants towards Guy's. There was no agreement between Guy's, or anyone on behalf of Guy's, with Higgs & Hill, or any of the Works Contractors, as to the breakdown of the overall sum paid or the actual sums payable by H&H to the Works Contractors.
12. (9) As part of the process of advising on the global settlement sum, Davis Langdon & Everest made assessments at the time, providing sums to be allocated to individual works contractors claims. Those assessments are pleaded in Schedule H2 of Guy's Amended Defence and Counterclaim. Guy's contends that it accepted those assessments, so that the global settlement sum incorporated as constituent elements provision for individual works contractors claims of the amounts pleaded in Schedule H2 of Guy's Amended Defence and Counterclaim. AA and P&OD accept that the DLE assessments formed part of the advice that Guy's considered when it reached the global settlement with H&H.
13. (10) In pursuing its present claim for damages from P&OD and AA, Guy's has made a further assessment of the figures allocated to individual works contractors in Schedule H2. That assessment specifies which part of the total figure allocated to the individual works contractor it is alleged was caused by the periods of extensions of time and associated disruption, for which it is alleged that P&OD and/or AA are responsible.
14. (11) For the avoidance of doubt, Guy's do not claim on the basis of what may have been actually paid by H&H to the Works Contractor."
AGREED ISSUES
1. The parties have agreed issues as follows:
15. "The following issues of law are to be decided upon the basis that the agreed assumptions of fact are true.
16. A. If Guy's proves that the sum, £ 83,876,354, at which it reached a global settlement with HH was reasonable:
17. (1) does it follow that the sums in fact allocated by Guy's to individual works contractors claims (as pleaded in Schedule H2 of the Amended Defence and Counterclaim) were also reasonable sums, such that if the reasonableness of the global settlement is established, the sums in fact allocated by Guy's to the individual works contractors represent Guy's actual loss with respect to those works contractors;
18. (2) is it necessary for Guy's to prove that the sums in fact allocated by Guy's to the individual works contractors claims were reasonable sums to allow? and
19. (3) is it material to investigate at what figure H&H themselves settled the individual works contractors claims?
20. B. In order to prove that the global settlement was reasonable, is it sufficient for Guy's to prove that:
21. (1) Guy's relied upon advice given by competent advisers; and
22. (2) Guy's acted reasonably in relying upon that advice ?
23. Alternatively, is it necessary to investigate whether the advisers upon whom Guy's relied themselves acted reasonably in giving their advice ?
24. C. If Guy's prove that breaches of contract and/or duty by P&OD and/or AA, as the case may be, caused delay and disruption to works contractors, is the measure of damages recoverable:
25. (1) an amount calculated by reference to the sums incorporated in the global settlement; and/or
26. (2) a sum ascertained by reference to actual amounts recovered or recoverable by works contractors;
27. corresponding with the delay and disruption proved to be attributable to the breaches of contract and/or duty of P&OD and/or AA ?"
THE ISSUES
2. The issues before me concern the assessment of damages, but it has to be remembered that the assessment of damages is preceded by issues of duty, breach, and causation.
3. To the issues agreed between the parties there has to be added an assumption for present purposes that P&O and AA or one of them, are found to be in breach of duties owed to Guy's, otherwise the issues would not arise. (Of course, whether breaches will be proved remains an open question). But it is impossible at this stage to identify the precise duties breached. What is certain only is that the duties are duties owed by P&O and AA to Guy's, not duties owed by P&O and AA to Higgs & Hill or the Works Contractors. The damages under consideration are defined by those duties owed to Guy's and also by different duties owed by Guy's to Higgs & Hill and by yet further different duties owed by Higgs & Hill to various of the Works Contractors, though not to all of them.
4. The breaches assumed to be proved against P&O will clearly be different breaches from the breaches proved against AA and the consequences of those breaches cannot be assumed to be identical. Important questions of causation will arise in assessing damages. What was caused by breaches of each of P&O and AA individually, and what was caused by each individually to the work of each of the Works Contractors selected by Guy's as allegedly affected? It is accepted by Guy's that not all of the Works Contractors were affected, so it will be necessary to prove which ones were affected and how they were affected. Since they were doing different work at different times, those affected (if any) are likely to have been (or at any rate may have been) affected in different ways and to different extents: that is reflected in item (10) of the Agreed Facts.
5. In case authority is necessary to support the approach adopted in the immediately preceding paragraphs, I cite from a discussion of the authorities in my judgment in the British Library Case, Department of National Heritage v. Steensen Varming Mulcahy and ors (1998) Internet Court Service Site, 21 July, 1998:
28. "The governing principles were illustrated by the House of Lords in Banque Bruxelles. v. Eagle Star [1997] AC 191. That was a case of negligent valuation, but the principles are of general application. In many cases, when assessing damages, it is sufficient to consider explicitly what is the correct measure of damages for the loss which the lender has suffered. But in all cases, there is a preceding question, what is the kind of loss to which the wrongdoer's duty relates? The answer to that question is usually so simple that one overlooks the fact that one has tacitly asked and answered that question, and one moves to the next question which was the starting point of the Court of Appeal in Banque Bruxelles, "What is the correct measure of damages for the loss suffered?" In the less usual case, including the valuation cases, and the present case, it is necessary to ask expressly, "What are the duties owed, and do they extend to the kind of loss suffered by the plaintiffs?" The assessment of damages becomes not just an exercise tacked on after consideration of the issues of duty, breach, and causation, it is a part of the consideration of all three of those issues and particularly of the duty.
In Banque Bruxelles at 210, Lord Hoffman said,
29. "Much of the discussion ... has assumed that the case is about the correct measure of damages for the loss which the lender has suffered. The Court of Appeal began its judgment, at pages 401 - 402, with the citation of three well known cases (Robinson v. Harman (1848) 1 Exch 850, 855; Livingstone v. Rawyards Coal Co. (1880) 5 App. Cas. 25, 39; British Westinghouse Electric and Manufacturing Co. Ltd. v. Underground Electric Railways Co. Ltd of London Ltd. [1912] AC 673, 688-689) stating the principle that where an injury is to be compensated by damages, the damages should be as nearly as possible the sum which would put the plaintiff in the position in which he would have been if he had not been injured. It described this principle, at page 403, as 'the necessary point of departure'.
30. I think that this was the wrong place to begin. Before one can consider the principle on which one should calculate the damages to which a plaintiff is entitled as compensation for loss, it is necessary to decide for what kind of loss he is entitled to compensation. A correct description of the loss for which the valuer is liable must precede any consideration of the measure of damages. For this purpose it is better to begin at the beginning and consider the lender's cause of action."
31. Those words lead me to cite that authority at this stage before construing the contracts and considering the common law duties.
32. Later, at page 211, Lord Hoffman said,
33. "A duty of care such as the valuer owes does not however exist in the abstract. A plaintiff who sues for breach of a duty imposed by the law (whether in contract or tort or under statute) must do more than prove that the defendant has failed to comply. He must show that the duty was owed to him and that it was a duty in respect of the kind of loss which he has suffered. ... As Lord Bridge of Harwich said [in Caparro v. Dickman [1990] 2 AC 145] at page 627:
34. 'It is never sufficient to ask simply whether A owes B a duty of care. It is always necessary to determine the scope of the duty by reference to the kind of damage from which A must take care to save B harmless.'
....
35. There is no reason in principle why the law should not penalise wrongful conduct by shifting on to the wrongdoer the whole risk of consequences which would not have happened but for the wrongful act... But that is not the normal rule. ... Rules which make the wrongdoer liable for all the consequences of his wrongful conduct are exceptional and need to be justified by some special policy. Normally the law limits liability to those consequences which are attributable to that which made the act wrongful. In the case of liability in negligence for providing inaccurate information, this would mean liability for the consequences of the information being inaccurate." "
6. I turn from those considerations to the contentions put forward on behalf of Guy's.
7. As expressed by counsel, Guy's primary case is that:
36. (1) "if Guy's proves that the global settlement with H&H was reasonable, then the sums allocated to H&H and the individual works contractors in the October 1994 report represent Guy's actual loss with respect to each works contractor;
37. (2) in order to prove that the global settlement was reasonable, it is sufficient for Guy's to show that it reasonably relied upon advice given by competent and reputable advisers (in particular DLE in the form of the October 1994 report), such that:
38. (3) the fact that the settlement was reached with H&H "at arm's length" and after taking advice from
8. Guy's also put forward an alternative case,
39. "Alternatively, if the reasonableness of the global settlement does not carry with it, and fix as Guy's loss, the individual allocations with respect to the works contractors, then Guy's will contend that the fact that the allocations in the October 1994 report were made by a competent and reputable consultant (DLE) and that there was nothing obviously wrong with those allocations on their face means that those allocations are themselves
9. Counsel for Guy's adds,
40. "On either approach to the settlement it is open to P&OD and/or AA to adduce evidence to show that the amount allocated by DLE with respect to a particular works contractor was unreasonable. On the higher assumption that Guy's primary case is correct and the reasonableness of the global settlement figure is determinative, then evidence that a particular allocation by DLE was unreasonable may help P&OD and/or AA establish that the global settlement figure was unreasonable.
41. Whether the relevant figure to consider is the global settlement figure or the individual allocations, it is not necessary for Guy's, in order to establish its loss, to prove that DLE themselves acted reasonably in producing the figures in the October 1994 report. This is taken to be no longer in dispute."
10. Both the primary and the alternative cases put by counsel for Guy's are in my judgment wrong in law in that they are contrary to the decision of the Court of Appeal in Biggin v. Permanite [1951] 2 KB 314. In considering that much cited decision, it is always important to bear in mind what it did not decide.
11. A settlement between A and B, however reasonable it may be from the point of view of A and B, cannot determine C's liability to B. A submission to the contrary was firmly rejected by a strong Court of Appeal in Fletcher & Stewart v. Jay & Partners (1976) 17 BLR 38 (Megaw, James and Geoffrey Lane LJJ.). In that case, the Court of Appeal approved the statement of the Official Referee, Sir William Stabb Q.C.:
42. "I am bound to say that I regard the decision in Biggin v. Permanite as being concerned only with the question of whether a reasonable sum paid in settlement of a claim can be regarded as the proper measure of damages in a subsequent action, where liability is not in issue. Where liability is in issue between a defendant and a third party, I cannot think that a defendant can impose liability on a third party by settling a plaintiff's claim against him, where the obligations of the defendant to the plaintiff are the same as those of the third party to the defendant."
43. The case before me is an even stronger case than that before Sir William, because the present is not a case where the obligations of the third party to the defendant are the same as the obligations of the defendant to the plaintiff. As I have already pointed out, the nature of the causes of action and to whom they are owed has to be identified.
12. The arguments and the judgments in Biggin v. Permanite proceeded on the footing that Biggin had settled with the Dutch Government on a basis which broadly sought to include the legal liability of the Dutch Government to others. The transcript of the judgments of the Court of Appeal shows that the Court of Appeal, having rejected the approach of the trial judge to the evidence, itself heard evidence of the amount of the claims and made its own assessment of that evidence. The Court of Appeal decided the case on the basis of that evidence as well as on the evidence of the settlement. Their judgments show that even where a party shows that a settlement with a third party was entered into reasonably, that is not sufficient on its own to prove the amount of damages. At page 321, Somervell L.J. said,
44. "I think that the judge here was wrong in regarding the settlement as wholly irrelevant. I think, though it is not conclusive, that the fact that it is admittedly an upper limit would lead to the conclusion that, if reasonable, it should be taken as the measure. The result of the judge's conclusion is that the plaintiffs must prove their damages strictly to an extent to show that they equal or exceed £43,000; and if that involves, as it does here, a very complicated and expensive enquiry, still that has to be done.The law, in my opinion, encourages reasonable settlements, particularly where, as here, strict proof would be a very expensive matter. The question, in my opinion, is: What evidence is necessary to establish reasonableness? I think it relevant to prove that the settlement was made under advice legally taken. The client himself could do that, but I do not think that the advisers would normally be relevant or admissible witnesses. I say 'normally'. It may be that in special cases they might be. The Plaintiff must, I think, lead evidence, which can be cross-examined to, as to facts which the witnesses themselves prove and as to what would probably be proved if, as here, the arbitration had proceeded, so that the Court can come to a conclusion whether or not the sum paid was reasonable. The Defendant may, by cross-examination, as was done here, seek to show that it was not reasonable. He may do so or call evidence which leads to the same conclusion. He might in some cases show that some vital matter had been overlooked".
45. In the event, the Court of Appeal had heard evidence and as a result of that evidence concluded that the Dutch Government would probably have recovered in an arbitration more than the amount of the settlement of £43,000. That evidence heard by the Court of Appeal was on broad lines and did not go into every detail which would have been canvassed in an arbitration. It was on that basis that the settlement was held by the Court of Appeal to have been reasonable in amount. Reasonableness was there related to what was reasonable in relation to a potential finding by an arbitrator.
13. In the same case Singleton L.J. said, at page 324 ff:
46. "The claim of the plaintiffs was for damages. They said that the damages should be the sum of £43,000, the amount of the settlement, which they claimed was reasonable. They did not ask for more. The plaintiffs must prove their damages. It is not enough for them to say: 'We were advised to settle for £43,000, we did so, and we now claim that sum'. Before the court can award a sum as damages, there must be evidence on which it can act. Therefore, in a case such as this, the plaintiffs must call evidence to establish their case. If the evidence which they call satisfies the judge or jury that the settlement was a reasonable one, the damages awarded will be the amount of the settlement and the costs reasonably incurred. I do not think that any good purpose is served by calling counsel who advised the settlement to say that he did so advised, even if the evidence is admissible. It could only be followed by questions why he so advised, and that would be asking him to do the work of the judge. Moreover, the duty of the judge at the trial is to determine the damages; and the facts proved before him might be quite different from those known to counsel at the time of his advice to settle for so much. The trial judge must make up his own mind on the facts he finds proved before him.
47. At the same time I am far from saying that the settlement ought to be disregarded. No-one can think that a person or a company will agree to pay £43,000 damages lightly. It is a matter for consideration that the settlement was arrived at under advice, even more so as the parties settling may be quite uncertain as to whether he can recover anything against someone else. If, upon the evidence, the Judge is satisfied that the damages would be somewhere around the figure at which the Plaintiffs had settled, he would be justified in awarding the settlement figure. I do not consider that it is part of his duty to examine every item in those circumstances. The Plaintiffs put forward their claim and call evidence to establish it. The Defendants have an opportunity of cross-examining the Plaintiffs witnesses and of calling evidence themselves. The Plaintiffs must establish a prima facie case that the settlement was a reasonable one. If the Defendants failed to shake that case, the amount of the settlement can properly be awarded as damages. ..... After full examination of all the evidence, I do not think it was sufficient to displace the case which the plaintiffs had set up, that this was a reasonable settlement. The question is not whether the plaintiffs acted reasonably in settling the claim, but whether the settlement was a reasonable one;..."
14. By way of explanation of Biggin v. Permanite, counsel for Guy's relies on certain authorities which, upon examination, I do not find helpful in the circumstances of this case.
15. Counsel for Guy's submits that his primary contention is supported by the decision of His Honour Judge Esyr Lewis Q.C. in Oxford University Press v. John Steadman Design Group (1990) 34 Con LR 1. In that case, the judge found that a global settlement was reasonable and then went on to make an apportionment of the global figure to various heads. That decision does not assist Guy's. The apportionment made in that case was made pursuant to the provisions of the Civil Liability (Contribution) Act, 1978 and totally different considerations arose which do not arise in this case. There is no question of any statutory right of contribution in the present case. The nature of the cause of action is an essential feature of the assessment in each case.
16. Counsel for Guy's also relies on the decision of the Court of Appeal in Comyn Ching & Co. (London) Limited v. Oriental Tube Co. Limited (1979) 17 BLR 86. Here again, an examination of the cause of action shows that the decision is not relevant to the present case. There the plaintiffs relied on a contractual indemnity. The difference in approach is demonstrated most succinctly by some words of Brandon L.J. at page 92:
48. "The indemnity relied on by the plaintiffs is an indemnity against claims. That expression is somewhat telescopic; what it means is an indemnity against loss sustained in consequence of claims. A loss will be sustained in consequence of a claim if it arises from a reasonable settlement of a claim which had some prospect or a significant chance of success.
49. The indemnity against claims concerned in this case should be construed accordingly. And if it is so construed, then the argument that the only claims covered are those in respect of which there is proven legal liability is bound to fail."
17. Anything said by the Court of Appeal in Comyn Ching which might be thought inconsistent with the decision of the Court of Appeal in Biggin v. Permanite is explicable simply by the fact that the two decisions concerned totally different causes of action. That consideration explains, amongst other matters, a point taken by counsel for Guy's labelled by others "the hindsight point". For Guy's it is submitted that it is irrelevant to hear evidence of what has been learnt about the matter which was not before the advisers advising the settlement. Counsel relies on a passage in the judgment of Goff L.J.at page 78. Goff L.J. said that one of the questions before the court was to decide, "Whether what went wrong was something for which Ching were or at the date of the compromise might reasonably be expected to be found liable". But that question is related to the terms of the indemnity then before the court. In the present case, what is to be considered is not what at the date of the compromise might reasonably be expected, but what ought to have been in the contemplation of the parties at the time of the breach, namely, a reasonable settlement.
18. The decision of His Honour Judge Newey Q.C. in The Board of Governors of the Hospitals for Sick Children and another v. McLaughlin Harvey PLC and ors (1987) 19 Con LR 25 (The Great Ormond Street Hospital Case) also was relied on by Guy's. The question at issue in the part of the judgment relied on (pages 94 - 99) was quite different from the question in issue before me. In that part of his judgment, Judge Newey was considering what method of repair of the building could be regarded as reasonable for the purpose of computing damages, a quite different question.
19. Why is an agreement made with a person not a party to the action relevant or admissible at all? Biggin v. Permanite provides two answers to that question.
50. (a) A rule of evidence. The Court of Appeal in Biggin v. Permanite stressed that it is the policy of the Court to encourage settlements. For that reason, there may be a readiness to accept that individuals settling a claim between them may be taken to have as their purpose trying to reach a settlement at a fair figure related to the claim. The extent to which the settlement may be taken as a matter of evidence to be in the right area will depend on all the circumstances. Sometimes it is not the main purpose of the parties to agree upon a figure which is related to an assessment of legal liability. A settlement may be made on over-generous terms for the sake of future business. Sometimes, the bargaining capacity of the parties will have been so uneven that the evidential value of the settlement will be of little weight - for example, where a defendant settles with a Legally Aided litigant with a nil contribution. In those circumstances, a settlement might be reasonable in the sense that it could be justified to the shareholders of the paying company, but it would not be reasonable as regards third parties to the agreement. But in many cases, it is inherently unlikely that businessmen, particularly those acting on competent advice, would settle a third party's claim at a figure significantly in excess of its true value. As Singleton L.J. said in Biggin v. Permanite at page 325, "No one can think that a person or a company will agree to pay £43,000 damages lightly," but I would add that the reason for the paying party agreeing to make the payment has to be examined. So if a third party's claim is settled, proof of the settlement may be some evidence of its true value, though not conclusive. The settlement sets a maximum to the claim, and depending on the weight to be attached to it as evidence, it may reduce the degree and detail of evidence required to prove the claim in the action.
51. (b) The second rule in Hadley v. Baxendale. The reasonable settlement of claims may be a matter which parties may be held to have had in reasonable contemplation under the second rule in Hadley v. Baxendale (1854) 9 Ex 341. At pages 318, 319 of his judgment in Biggin v. Permanite, Somervell L.J. cited a passage from the judgment of Bowen L.J. in Hammond & Co. v. Bussey (1887) 20 QBD 79. Bowen L.J. referred to the possibility of the plaintiff purchasers of coal being sued by sub-purchasers and if they failed in their defence,
52. "the defendant must in reason be taken to have contemplated that they would have to pay damages and costs. All these matters ... seem to me to be matters that may reasonably be supposed to have been within the contemplation of the parties at the time they made the contract, and therefore the question whether the case comes within the second branch of the rule in Hadley v. Baxendale seems to me to be answered ...".
53. Somervell L.J. commented at pages 321, 322:
54. "Parties, Bowen L.J. said, have been held to contemplate litigation in the sort of circumstances which have arisen here. It would, I think be unfortunate if they were not also held to contemplate reasonable settlements in the type of circumstances which have arisen here."
20. To regard Biggin v. Permanite as applying both an evidentiary rule and the second branch of the rule in Hadley v. Baxendale is workable and sensible, and I intend so to apply that authority. The application of both aspects of that authority, the evidentiary rule and the Hadley v. Baxendale approach must be fashioned to the facts of the individual case.
21. When it is said that a party may be held to have contemplated a reasonable settlement, it is important that one should be clear what is meant by a reasonable settlement. In some exceptional cases, the anticipated consequences of a breach might be so extreme that a party might be taken to have contemplated a settlement at a sum avowedly in excess of what might normally be regarded as the expected legal liability: for example, where completion of a project was planned to meet some immovable event such as the Millennium, a party who delayed the project might be taken to have contemplated that any settlement with sub-contractors might have to made at grossly inflated rates. I would not rule out the possibility that in some very exceptional cases, the law might impose on a wrongdoer liability computed by reference to a settlement which in the eyes of the law is unreasonable. But as a general rule, a party would be taken to have in contemplation a settlement which is reasonable in the sense that it is based on an assessment of what is legally due from the plaintiff to the third party. That was certainly the approach of the Court of Appeal in Biggin v. Permanite.
22. What the parties should be held to have contemplated, and whether they should be held to have contemplated a reasonable settlement at all, must depend on the facts of each case. On the facts of Biggin v. Permanite, a sale of goods case with sub-sales in contemplation, Somervell L.J. considered that the parties should be "held to contemplate reasonable settlements in the type of circumstances which have arisen here". For the "type of circumstances" which Somervell L.J. had in mind on the facts before him, one has to look at the transcript of the full judgments of the Court of Appeal in that case.
23. The transcript of the judgments of the Court of Appeal in Biggin v. Permanite shows that the settlement was based on the sort of evidence which might normally be accepted by businessmen negotiating settlement of a commercial claim. About half of the claim of the Dutch Government was in respect of unsold material left on its hands. As to that, without going into all the details, it is enough to say that there was evidence to support a loss of profit claim to the extent of £24,600 by reference to the sale price of some of the material before the defective nature of the material became known and evidence of the price obtainable after the defect was known. The balance of the claim of the Dutch Government related to claims made against the Government by others. As to £1,000, the amount of the claim was supported by an arbitration award (not conclusive) in favour of a Mr. Boll. £8,000 was supported by an actual payment to a Mr. Kramer. £23,000 was supported by invoices submitted by contractors for remedial works supported by the evidence of the Director of the Bureau of Tar Products of the Dutch Government and other claims amounting to £10,000. Somervell L.J. considered that it would be safe to conclude that the Dutch Government would have been able to recover at least half of the £23,000 invoiced, and disregarding the other claims for £10,000, the aggregate was substantially in excess of the sum for which Biggin settled. It is to be noted that firstly, the Court of Appeal did not find that the settlement proved that the amount of each claim by contractors was reasonable (in fact quite the contrary); and secondly, the Court of Appeal (reversing Devlin J.) did not require that the amount of each contractor's claim be proved strictly.
24. Whether it was reasonable to enter into a settlement may raise quite different issues. A businessman asking himself whether it is reasonable to enter into a proposed settlement with another businessman with whom he is engaged in an ongoing project, is unlikely to limit himself to asking himself the same question as a judge considering whether a proposed settlement of litigation brought on behalf of an infant is reasonable, even supposing the businessman asks himself a question of the latter type at all. Circumstances may dictate to a businessman that it is reasonable to enter into an overall settlement even though some of the details are unreasonable. There, the overall settlement may be reasonable even though the details are not. In such a case (which according to P&O and AA may well be the present case), it would be wrong to pick out the details and rely on them against the wrongdoer. No doubt, it was that sort of consideration which Singleton L.J. had in mind when he said in Biggin v. Permanite at page 326:
55. "The question is not whether the plaintiffs acted reasonably in settling the claim, but whether the settlement was a reasonable one."
56. But (contrary to the view expressed by Judge Hicks Q.C. in DSL Group v. Unisys International (1994) 67 BLR 127 at 136) I take the view that advice received by the plaintiffs might go either to the question whether the plaintiffs acted reasonably or to the question whether the settlement was reasonable, or both. Moreover, whether the plaintiffs acted reasonably may have an evidential bearing on whether the settlement was reasonable.
25. Without having heard the evidence, it would be wrong for me to determine in advance what the parties ought reasonably to have contemplated as the likely consequence of breach in this case because that question must depend on the facts of the case. But it may assist the parties if I express a purely provisional view, based on the documents I have seen in this case, and my experience of building litigation. As a purely provisional view, it seems to me at this stage in the action that it is likely to be decided that the parties ought reasonably to have contemplated that if Guy's had settled with Higgs & Hill for the claims made by the Works Contractors alone, they would have settled in reliance on advice by competent and reputable advisers who would require the production of the sort of documents which would normally be required by competent quantity surveyors to "vouch" the claims of the Works Contractors and would advise on the basis of that material so as to produce figures representing what was legally due to the Works Contractors. A settlement of the Works Contractors' claims reached in that way would be reasonable, but it would only be evidence of the amount of the claim of any one Works Contractor if the adviser considered each Works Contractor individually rather than considering the Works Contractors generally so as to make an overall judgment.
26. On the facts of this case, the argument of Guy's is as follows. Suppose that critical delays did occur and those critical delays entitled Higgs & Hill and the Works Contractors to make claims. The Works Contractors could claim against Higgs & Hill under individual works contracts and Higgs & Hill could claim against Guy's under the Management Contract. Higgs & Hill could claim against Guy's the value of their own legitimate delay and disruption claims and the total of their exposure to similar claims from Works Contractors. The argument for Guy's continues, that the effect of the wrap up deal was to discharge any obligation of Guy's to Higgs & Hill in respect of the entirety of the delay and disruption claims. So far, the argument follows a logical progression, but it omits any reference to cause of action, breach or causation and hence fails to deal with any legal responsibility of P&O or AA. The argument then concludes with the question and answer,
57. Q: How much did that cost Guy's?
58. A: The sums allocated to the delay/disruption claims by DLE.
59. That is the wrong question, and it is doubtful whether the answer is correct.
27. Having regard to the high reputation of Davis Langdon and Everest, I am more than ready to assume, unless and until the contrary is proved, that they are competent and reputable advisers who in this case acted reasonably in producing the October, 1994 Report. One would expect that the advice given in a report produced by such advisers would be reasonable. But, in using the word "reasonable" there, I mean reasonable in the light of the brief given to Davis Langdon and Everest by Guy's, which is not the same as advice producing figures which are reasonable in law. One has to ask, "For what purpose are the figures and allocations to be considered reasonable?" The Report, which is before me, shows on its face that it was produced to enable Guy's to make with Higgs & Hill a "commercial agreement", which became accurately known as a "wrap-up deal" to secure a fresh start to the project.
28. The Report began with a Preface
60. "This report has been commissioned by Rowe & Mawe, legal advisers to the Trust [Guy's], who are advising the Trust on litigation which is likely to ensue from the Philip Harris House project. Further to the issue of our Independent Report on the Philip Harris house Phase III Contract (August 1993), we have been instructed to undertake a review of the overall project costs to ascertain the Trust's current contract liability and to provide a backdrop against which the reasonableness or otherwise of the amount of the commercial settlement may be set."
61. There was then a Preamble reciting that since the original draft of their report certain major developments arose "creating a large degree of uncertainty with regard to the outturn costs". Those developments included (a) the insolvency of the mechanical and electrical services package contractor, Kentz; (b) disputes over the legal interpretation of the contract between Guy's and Higgs & Hill regarding liabilities arising on such an insolvency; and (c) "the Trust's initiative to settle the Stage 2 building costs in the form of a commercial settlement i.e. an amount which prospectively determines what the final certificate shall be for, notwithstanding the fact that the effects of relevant events continue to unfold".
29. The intention of the parties in entering into the "wrap-up agreement" was stated in a recital to that agreement as follows:
62. "The parties have executed Heads of Terms dated 20th September, 1994 setting out the intention of the parties which is to secure on clear, fair and acceptable terms, the completion of the Project in accordance with the terms of the contract save where varied by this Agreement and in particular within an agreed period of time and for an agreed final account sum."
30. In the Report, the figures and allocations relating to the Works Contractors (which form a very small part of the monetary considerations) are said by Davis Langdon and Everest to be based in many cases on inadequate information: in some cases the Works Contractor itself had not properly formulated its claim. The impression given by the Report (which may be contradicted by evidence) is that Davis Langdon and Everest were not able for the most part to collect the sort of material which would normally be relied on by quantity surveyors in valuing claims but rather were collating the claims and assessments made by various bodies and using their experience to make provisions rather than assessments for various claims. The Report expressly refers in many places to "provisions". I take it (again subject to any evidence other than a reading of the Report) that Davis Langdon and Everest were in many instances applying a process similar to an insurer who receives a claim and is able, using his experience, to make a provision in his accounts for that claim before full investigation: some provisions may be right and others not even in the right area, but by and large, the overall figures in his books will relate to his overall liability. If that was the approach, it was a perfectly reasonable one for Davis Langdon and Everest to take within their brief, but it would not be expected to produce accuracy even "within the right area" for all the individual items of 5 or 6 figure sums or less in the context of an overall recommended settlement in excess of £83 million.
31. It is a matter for evidence whether and to what extent Davis Langdon and Everest were able to and did make a reasonable assessment of legal liability in the circumstances and under the constraints under which they were acting.
CONCLUSION
32. I therefore answer the questions before me as follows:
QUESTION A:
63. If Guy's proves that the sum, £ 83,876,354, at which it reached a global settlement with HH was reasonable:
64. (1) does it follow that the sums in fact allocated by Guy's to individual works contractors claims (as pleaded in Schedule H2 of the Amended Defence and Counterclaim) were also reasonable sums, such that if the reasonableness of the global settlement is established, the sums in fact allocated by Guy's to the individual works contractors represent Guy's actual loss with respect to those works contractors;
65. (2) is it necessary for Guy's to prove that the sums in fact allocated by Guy's to the individual works contractors claims were reasonable sums to allow ? and
66. (3) is it material to investigate at what figure H&H themselves settled the individual works contractors claims ?
ANSWER A:
67. I am not sure what is meant by the word "reasonable" applied to the global settlement here, but on any meaning of that word, my answers are:
(1) No.
(2) Yes.
68. (3) Yes, but only in the sense that evidence of the figures at which Higgs & Hill settled with individual Works Contractors might (or might not) be helpful evidence of reasonableness or unreasonableness.
QUESTION B:
69. In order to prove that the global settlement was reasonable, is it sufficient for Guy's to prove that:
70. (1) Guy's relied upon advice given by competent advisers; and
71. (2) Guy's acted reasonably in relying upon that advice ?
72. Alternatively, is it necessary to investigate whether the advisers upon whom Guy's relied themselves acted reasonably in giving their advice ?
ANSWER B:
(1) and (2): It is not sufficient, but it might be relevant. Again, I am not sure what is meant by the word "reasonable" applied to the global settlement.
73. B Alternative: No. It is not necessary but it might be relevant.
QUESTION C:
74. If Guy's prove that breaches of contract and/or duty by P&OD and/or AA, as the case may be, caused delay and disruption to works contractors, is the measure of damages recoverable:
75. (1) an amount calculated by reference to the sums incorporated in the global settlement; and/or
76. (2) a sum ascertained by reference to actual amounts recovered or recoverable by works contractors;
77. corresponding with the delay and disruption proved to be attributable to the breaches of contract and/or duty of P&OD and/or AA ?
ANSWER C:
78. Both (1) and (2) may be relevant but not to the exclusion of other evidence.
HIS HONOUR JUDGE BOWSHER Q.C.