QUEEN'S BENCH DIVISION
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
ICE ARCHITECTS LTD |
Claimant |
|
- and - |
||
EMPOWERING PEOPLE INSPIRING COMMUNITIES |
Defendant |
____________________
Matthew Finn (instructed by DWF LLP) for the Defendant
Hearing date: 24th January 2018
____________________
Crown Copyright ©
Mrs Justice Lambert :
The Facts
"You will invoice EPIC on a monthly basis for work completed to date. The basis of payment proposed in the appendix to the document described above is acceptable. EPIC Ltd will endeavour to make payment within 30 days of receipt (unless otherwise stated)".
The Preliminary Issue Hearing before HHJ Parfitt
i) on the authority of Coburn v Colledge [1897] 1 QB 702, in the absence of agreement to the contrary, the starting point is that a provider of services is entitled to be paid once the work has been done and so its cause of action for payment arises at that time;ii) the agreement reached between the parties in Henry Boot Construction Ltd v Alstom Combined Cycles Ltd [2005] EWCA Civ 814 provided an illustration of an agreement to the contrary;
iii) in Coburn the Court of Appeal identified a material distinction between (as described by HHJ Parfitt) "facts which are a necessary part of the right to be paid and those matters which might bar that right (such as limitation itself but also facts such as a failure to comply with statutory requirements eg statutes about solicitors bills in Coburn)."
Legal Framework
Arguments on Appeal
i) the Judge's failure to conclude that the terms of the contract in Boot were materially similar to those set out in the letter of 10th July 2007;ii) the Judge's failure to give any reason for distinguishing Boot;
iii) the Judge's error in distinguishing Levin;
iv) the Judge's error in treating the requirement for an invoice to be issued and for 30 days to elapse as similar to the regulatory provisions requiring a solicitor to issue a bill.
Discussion and Conclusions