QUEEN'S BENCH DIVISION
Strand, London, WC2A 2LL |
||
B e f o r e :
(Sitting as a Deputy Judge of the High Court)
____________________
ANTHONY D. MARTIN |
Claimant |
|
- and - |
||
MICHAEL POSENER NICHOLAS POSENER |
Defendants |
____________________
Clifford Darton and George Woodhead for the Defendant
Hearing dates: 3, 4 and 5 July 2017
____________________
Crown Copyright ©
His Honour Judge Simpkiss :
Introduction
The background facts
i) the Good Will Fund, which was expected to pay out some 80% on any admitted claim. Time for making applications under this fund had expired by November 2014;ii) the Late Applicant's Fund for which final claims had to be made by 31st December 2014. This would pay out 50% of the claim;
iii) the Third Claim Programme which gave no guarantee of the percentage payment to be made.
"It is necessary, whether claims are with the Bundesamt or with the JCC that you, Michael and Nicholas, contact cousin Tony (the Claimant) to both protect your highest compensation payment rights with the JCC (if the Siegbert Posener family have never filed before) as well as with the Bundesamt without extended delays because of the JCC time limit in December 2014".
"it appears if they are open Claims, they would be for Heinrich Posener's portion of the business as Mortiz Falk's portion of the business was paid out in the 1990's to the Falk sisters in the opinion of the JCC. The Bundesamt however thinks maybe real estate claims in the old 1991-1992 programme, which is also included in the JCC website as these open claims under the name "gebr. Posenerr Dresden in error".
The issues
i) The construction of the contract. It had been argued that the contract did not cover compensation paid under claims to the BADV, but in his final submissions Mr. Darton, rightly in my judgment, conceded that he could not argue this point.ii) The contract was "barred under the doctrine of clean hands. The Agreement the Claimant seeks to enforce is contrary to Rule 1.8 of the RPC [Massechusetts Code of Professional Conduct] and unenforceable" (paragraph 37 if the Defence) ("the Code 1.18 issue").
iii) The Claimant was in repudiatory breach of contract by refusing to fund Mr. Chudson's trip to Berlin in July 2015 and this breach was accepted, relieving the Defendants from performance of the contract.
iv) The award was not made as a result of any research carried out by Mr. Chudson and therefore no sums are due to the Claimant.
v) The amount claimed has not been proved or adequately accounted for.
The witnesses
The construction of the contract
WHEREAS, Tony [Claimant] has engaged ….. "Lee" [Chudson] of ….., to research German and US archives for documentation ("Claim Documents") needed to support claims ("Claims") to be made to the Conference on Jewish Material Claims Against Germany ("JCC") and/or the German courts for award of compensation ("Awards") for German property that was confiscated directly or by forced sale by the Nazi regime ("German Property"); and
WHEREAS, Tony has also engaged Attorney ARNDT SURNER ("Surner") of the Dresden office of Hirsch, Thiem & Collegen to prosecute Claims at the JCC and in the German courts, for which purpose Tony has delivered to Surner a German power of attorney known as a "Vollmacht";
WHEREAS, Lee has reported to the parties that the JCC may hold property of Heinrich ("Posener Property") including without limitation Palaistrasse 15 Dresden and Hienrich's interest in the Falk and Posener partnership;
WHEREAS, the JCC has declared that Claims for German Propertey held by the JCC must be submitted to their Late Application/Second Heirs Fund prior to 12/31/14; and
WHEREAS, Mike [First Defendant] and Nicky [Second Defendant] have not yet registered with the JCC, nor made Claims for the Posener Property, nor have they obtained the necessary Claim Documents to support any such Claims; and
WHEREAS, Mike and Nicky wish to obtain Tony's assistance in making Claims in the Late Application Fund at the JCC for the Posener Property and for any other German property for which Lee may be able to produce Claim Documents; and
WHEREAS, Tony is willing to assist Mike and Nick in making Claims for the Posener Property on the terms and conditions hereof;
Clause 1 provides for the Defendants to deliver a Vollmacht to Dr. Surner authorising him to represent them at the JCC for the prosecution of the Claims for the Posener Property.
By clause 2 the Claimant agrees to obtain Claim Documents by paying Mr. Chudson's charges and out of pocket expenses for obtaining the Claim Documents and Surner's charges and disbursements for prosecuting Claims for the Posener Property.
By clause 4 the Defendants acknowledged that there were "no guarantees that sufficient Claim Documents may be found as may be required by the JCC in order to obtain Awards to them for the Posener Property". In those circumstances the Defendants would be under no liability for the costs and expenses incurred by the Claimant.
By clause 6 the Claimant will account for the payment of Expenses (defined in Clause 5) including by the delivery of receipts and other evidence of payment of Expenses as the Claimant receives from Mr. Chudson and Dr. Surner.
By clause 7 the Claimant agreed to allocate the Expenses between researches and prosecution of Claims for Posener Property and any Claims that did not involve the Defendants.
8. "The parties agree that in the event that the JCC, any German court or any German agency (including without limitation the Bundesamt) makes any award for Claims for Posener Property supported by Claim Documents and/or prosecuted by Dr. Surner, the parties shall not direct the JCC or any German court or German agency to pay the Awards directly and that all Awards shall be paid to Surner out of which he shall pay his fees and shall then allocate the balance of the Awards (if any) as follows:
(a) Surner shall first remit to Tony out of the Awards sufficient funds to reimburse him for the Expenses he has incurred with respect to such Claims;
(b) Surner shall pay the remainder of the Awards with respect to such Claims, if any (the Net Awards), in the following percentages: 30% to Tony ("Tony's Percentage"); and 70% to Nicky and Mike to be apportioned among all heirs of Siegbert."
9. "In the event that Mike and/or Nicky breach their obligations under this Agreement, including without limitation, their obligation not to seek direct payment of any Awards for Claims for Posener Property and fail to reimburse Tony in full for his Expenses and/or for Tony's percentage, Mike and Nicky, jointly and severally, hereby agree to indemnify and hold Tony harmless from and against all losses, liabilities, costs and expenses, including without limitation legal fees and disbursements, that relate to or arise out of such breach."
Clause 10 provides that the contract is governed by the laws of the Commonwealth of Massachusetts and that may not be waived, amended or the obligations in the contract terminated in whole or in part except by a writing executed by all parties.
Clause 11 provides that the contract is an entire agreement and supersedes any prior understanding or agreements of the parties.
i) Where the words of the contract are clear, they alone determine the meaning of the contract and the court should only consider extrinsic evidence when a term in a contract is ambiguous.ii) Contract language must generally be construed in its usual and ordinary sense.
iii) Contract language is ambiguous only if it is susceptible of more than one meaning and reasonably intelligent persons would differ as to which meaning is the proper one.
iv) It is not the role of the court to alter the parties "agreement".
v) If the court determines that there is an ambiguity, there are a number of factors to consider:
a) whether the ambiguous language is material to the intent of the parties;b) who drafted the ambiguous language;c) whether the contract has an integration clause, and if so its effect on the ambiguous language;d) whether the language used has a special meaning in the industry, circumstances or situation in which it is used;e) to the extent that there is an ambiguity, the court should construe it against the drafter (the contra preferentem rule);f) the language of Clause 11 of the contract (the entire agreement clause) would generally be considered to prevent the admission of any evidence of the parties' negotiation of the agreement prior to its execution.
i) a court would not favour a reading of one clause that undermines explicit provisions elsewhere in the contract and will look at the fair construction of the contract as a whole.ii) Although as a general principle a court considers extrinsic evidence to discern intent only where there is an ambiguity, there is an exception to that general rule and a court may consider parol and extrinsic evidence "for the very purpose of deciding whether the documentary expression of that contract is ambiguous".
iii) If there is an ambiguity, then the circumstances surrounding the making of the agreement must be examined to determine the objective intent of the parties "the practice is to impute to the parties a solution that best carries out the logic and purpose of their agreement". The search is for "manifest meaning" and not "privately held belief", therefore subjective evidence of intent is not admissible.
The Code 1.18 issue
i) the terms of the contract giving rise to liability on the part of the Defendants to pay him a percentage of any award were not disclosed to them in a manner that could reasonably be understood by them;ii) the Claimant failed to advise them in writing or orally, that they should seek independent advice before entering into the contract;
iii) as a result, the Claimant's claims are barred under the doctrine of unclean hands and the agreement is contrary to Rule 1.8(a) of the Code and unenforceable;
i) In evidence the First Defendant, who played the lead role on the Defendants' side in the negotiations, accepted that he had not sought any legal advice from the Claimant;ii) He accepted that advice given in relation to the subject matter of this case was not within the competence of the Claimant, as it involved German law and a claim in Germany;
iii) He accepted that no legal advice was in fact given by the Claimant.
Repudiatory Breach
i) How does the court determine what is a repudiatory breach?ii) He quoted an extract from Burlington Landmark Associates v RHIHoldings Inc 27F. Supp. 2d 95,99, which shows that mere expression of doubt by the obligor as to his willingness or ability to perform is not enough to constitute repudiation. There must be language that is sufficiently positive to be reasonably interpreted to mean that the party will not or cannot perform the contract. He explained that the court must determine, from the evidence, whether some statement made by a party that the party will commit a breach is required. That statement or act must be either with respect to the entire performance that was promised or with respect to so material a part as to go to the essence of the contract.
iii) The court may determine that a breach is not material if the other party suffers no loss or damage as a result of the breach.
iv) Where there is a repudiatory breach, and it is accepted by the other party, then unless the parties agree in writing otherwise, their rights and obligations accumulated up to the breach remain extant.
v) If there is a repudiatory breach, the contract is not automatically determined. It may be affirmed by acts of the party claiming repudiation, although he doubted whether it could be implied by conduct because of Clauses 10 and 11 of the contract. In his response to the Claimant's part 35 request, Judge van Gestel said that there may be circumstances - acts or failures to act – that have the effect of affirming the existence of a contract despite there having been one or more repudiations.
"Mike and Nicky, I have advanced over $40,000 for Lee's research efforts, by far most of them have been for your benefit. I understand his trip to the Bundesamt is the last step in determining if there are any recoveries for you. If you are not willing to risk 1.25% of my advance by advancing the last $500, I have advised that I will not advance another dollar and he should cancel his trip
If you do advance the $500 ASAP, I will reduce the amount I collect post expenses from your recoveries dollar for dollar against my advances for your benefit – after repayment of course of your advance. I suggest you make a decision on this immediately".
Conclusion on liability
i) a sum to represent the expenses that he has paid to Mr. Chudson or is liable to pay him;ii) 30% of the net compensation received from the BADV, after discounting Dr. Surner's fees and the sum under (a);
iii) His own expenses and costs incurred as a result of the Defendants' breach of contract.
i) $71,377 between 30th October 2014 and 11th August 2016 to or for the benefit of Mr. Chudson in researching the archives or prosecuting the claims;ii) $1,962 to Brazilian counsel and Dr. Plagemann to obtain a relevant Vollmacht and for information;
i) counsel's fees in Germany, Ireland and the UK totalling $9,400;ii) $2,600 payments from Mr. Chudson to obtain documents to support his claim against the Defendants;
i) The Claimant is entitled to be indemnified for any expenses he has incurred with lawyers and others in order to recover the moneys due to him under the Contract, including the prosecution of this claim. He must establish that the various sums claimed were incurred to that end. This should be dealt with by an inquiry as he is entitled to damages equivalent to those sums;ii) He is not entitled to be indemnified in respect of his own time under Clauses 9 (as set out in Judge van Gestel's opinion);
iii) If an order for costs is made in favour of the Claimant at the conclusion of the trial (and I cannot make such an order at this stage as there may be relevant matters of which I am presently unware) then he may be able to recover sums to reflect his own time spent on the case in the usual way. This will be a matter for the costs judge on the assessment.
i) In the letter before action dated 1st March 2016 the sum claimed was 50,000 euros already paid and a further estimated 26,000 euros. A further sum of 20,000 euros for the Claimant's services and expenses. It is to be noted that all that the Claimant is saying at that stage is that a sum has been paid and that further sums are due which is, at that time, only an estimate. It is not therefore reasonable to criticise the Claimant for misstating the sum due.ii) In the original Particulars of Claim it is pleaded that the Claimant has made payments of $38,338.31 between 30th October 2014 and 24th November 2015. Mr. Darton submitted that this was "a lot less than 50,000 euros" and that the Claimant and Mr. Chudson had not settled the sum due. That is correct, but the pleading says no more than that the Claimant has paid this sum. It is however clear from the documents that significant payments were made by the Claimant to Mr. Chudson in January and February 2015 (I have identified at least $5,000, and other direct expenses were incurred). The pleading and the letter before action are dealing with different periods. If this allegation was to be made good as an indication that the Claimant's case is not credible or honest, then it is not enough to make the assertion without doing the sums and the currency computation. In any case I find that it is improbable that there is any significant discrepancy and therefore that this allegation is not proved.
iii) Mr. Darton said that the statement of $50,000 in the letter before action was a deliberate untruth by the Claimant. He relied on an email from Mr. Chudson dated 16th February 2015 in which he said that he had never been paid a penny for his work. The documents produced by the Claimant clearly show that this is not correct and I think it is another example of Mr. Chudson's emotional and colourful way of dealing with matters which he is not happy with. The documents show that he had been paid, but the final bill had not been agreed with the Claimant.
Conclusion
i) The Contract is to be construed as covering the BADV claim and Clause 8 is triggered;ii) The contract is not void or unenforceable by reason of the alleged breach of Code 1.18;
iii) The contract is not repudiated and remains on foot;
iv) The Claimant is therefore entitled to the following:
a) Reimbursement of the sum of $61,666.45 which I find he has paid to Mr. Chudson for his researches under the Contract;b) Payment of the 30% of the net sum to be computed on the sum received by the Defendants from Dr. Surner whose fees had already been deducted, (385,175 euros) less the amount to be reimbursed under (i). The precise amount is to be fixed at a further disposal hearing.v) An indemnity for sums actually paid or incurred by the Claimant to third parties (including legal fees paid or incurred to third parties) following the refusal of the Defendants to honour the Contract and in order to enforce the Contract and recover the moneys due. This sum is to be ascertained by an order for an inquiry.
vi) The Claimant is not entitled to compensation for his own time under the indemnity provision in the Contract, but may be entitled to some compensation on an assessment of the costs of these proceedings in the usual way (having regard to his being a litigant in person). Such matters are to be dealt with by the costs judge but will be subject to an order for costs being made which I cannot do until I have heard further argument as there may be matters of which I am presently unaware that are relevant.