QUEEN'S BENCH DIVISION
Strand, London, WC2A 2LL |
||
B e f o r e :
(sitting as a Deputy Judge of the High Court)
____________________
Darrell BAKER (a protected party by his Litigation Friend Kerry BAKER) |
Claimant |
|
- and - |
||
BRITISH GAS SERVICES (COMMERCIAL) LIMITED (1) - and - J & L ELECTRICS (LYE) LIMITED (2) |
Defendants |
____________________
Colm Nugent (instructed by Bond Dickinson LLP) for the First Defendant
Shaun Ferris (instructed by Kennedys Law LLP) for the Second Defendant
Hearing dates: 17 to 21 July 2017
____________________
Crown Copyright ©
Amanda Yip QC :
Introduction
The Evidence
The Facts
The happening of the accident
"The next thing I noticed was a noise, a moaning, groaning animal sound. It was a strange noise that I had not heard before. This made me look up and I remember thinking why was there a machine hanging down. I thought he may have been using a testing machine, but I now know that this was the light fitting hanging down. His body looked stiff and stuck in place. I think his right arm and face were in the ceiling hole. The cable from the light fitting was just hanging down. He did not move and the sound just went on. It seemed to go on for a really long time. I thought he was then starting to come down the ladder, but his body fell straight to the floor …"
"It is quite likely that the live casing of the incident light fitting made contact with Mr Baker's chest (through his shirt) while one of his hands or arms was touching the suspended ceiling support structure."
The faulty wiring
"If there had been anything specifically difficult or unusual during the job, I would most likely have remembered. This was not the case and the installation was completely standard."
By contrast, in the witness box, he said that he could remember the job because it was a particularly easy one. That is inconsistent with his statement. He was asked about timings. I note the following relevant evidence in his witness statement:
"The first test is undertaken before the installing electricians start the third fix stage. …. When John Foxall had completed the initial dead testing, I would proceed with the third fix. … Following the connection of the lights and on completion of all remaining third fix items, John Foxall would have proceeded to carry out the live tests."
In his oral evidence, Mr Moule said that he did not have to wait until the testing was completed before starting work on the final fix. Rather, he would start work on one circuit while Mr Foxall was testing another. In my judgment, that is very different from what he describes in his statement. His explanation of the process which he called "conveyor belting" came about in my view when it became apparent that the time Mr Foxall had been on site would not have allowed sufficient time for the processes described in Mr Moule's statement. It is another significant inconsistency between his statement and his oral evidence.
"The results of the tests carried out when the installation was commissioned appear credible, but we cannot be sure where when or how the measurements were made."
a) the ballast in the relevant light fitting was the original one;
b) the light fitting itself had not been moved;
c) there is no other likely explanation for the junction box to have been re-wired.
Liability of the Second Defendant
Liability of the First Defendant
"… maintenance personnel could easily have come into contact with exposed conducting parts (e.g. metal housings) when replacing lamps, ballasts and other components and so in my opinion earth continuity should have been tested during the Periodic Inspection(s)."
"… any act or omission before the transfer is completed, of or in relation to the transferor in respect of [the contract of employment] … shall be deemed to be an act or omission in relation to the transferee."
"It is to my mind significant that by common consent all contractual rights and liabilities are transferred. They are not limited to those which are still contingent. Thus fully accrued rights and liabilities are transferred. That demonstrates the far-reaching effect of the 1981 Regulations. But if such contractual rights and liabilities are transferred it is hard to understand why tortious rights and liabilities are not transferred … It would be very strange if the effect of the 1981 Regulations was that the contractual claim of the employee was transferred so that the transferee alone became liable in exoneration of the transferee employer but that the tortious claim remained enforceable against the transferor."
Contributory Negligence
"Whilst the HSE always recommend that when it is reasonable to do so electrical equipment is made dead before any work is undertaken, it would appear in this case that the electrician was quite reasonably trying to determine if it was possible to disconnect the light fitting from the lighting circuit without having to isolate the complete circuit … I do not believe that the actions being taken by the electrician were, at the time of the incident, unreasonable, unexpected or unsafe."
Conclusions