QUEEN'S BENCH DIVISION
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
The Lord Chancellor |
Claimant |
|
- and - |
||
Charles Ete and Co -and- Charles Ete -and- Ratookumar Manorbhai Patel |
Defendant 2nd Defendant 3rd Defendant |
____________________
Mr. Charles Ete for all Defendants
Hearing dates: 18, 19, 20, 21, 22 and 25 January 2016
____________________
Crown Copyright ©
Mr. Justice Holgate:
Introduction
The proceedings and the pleadings
(i) The allegation that there had been a breach of natural justice through the inappropriate composition of the CRB; and
(ii) A failure on the part of the LSC to consider taking corrective action instead of terminating the crime contract.
The Relevant Contracts
The Legal Basis for the Recoupment of Payments on Account
"If a solicitor could defer indefinitely ascertainment of the ultimate liability, the result would be that he or she could keep the payment on account. That would frustrate the clear purpose of the regulations in permitting payments on account which … was to assist lawyers' cash flow. It clearly is facilitative of, and incidental and conducive to, the functions of the Commission in administering the fund to be able to ensure that, where payments on account have been made, they are recouped if the solicitors have expressly, or by conduct, evinced an intention not to submit a claim for their final costs for assessment. Accordingly, section 4(1)(b) must be read as enabling the Commission to assess the final costs at nil." (see paragraph 50).
Section 4(1)(b) of the 1988 Act has since been replaced by section 3(1) of the Access to Justice Act 1999 which is in all material respects to the same effect as the preceding provision.
Relevant contractual terms for civil legal aid work
"- A time recording system for all matters and cases;
- An up to date record of the value of your work in progress (including disbursements shown separately) on each matter and case; and
- An up to date record of the total costs of each matter and case."
Annex E also stipulated that "in order for an IT system to be appropriate the information recorded on it must be capable of being quickly processed and retrieved." Clause 8.2 of the Unified Contract stated (inter alia) "You must maintain an up to date running record of costs and disbursements incurred for each matter and case, otherwise you will be unable to demonstrate compliance with this contract." Clause 7.7 required the Firm to "Record and report all data and information required by the contract promptly and accurately and in accordance with this contract."
"(b) where payment has been made in respect of a matter or case, the amount of any subsequent reduction on assessment;
(c) where payment has been made in respect of a matter or case, any sum which we are not required to pay (or you are not entitled to be paid) for some or all of the work that you have carried out;
(d) any payment specified as such in the Specification."
"(a) three years having lapsed since the date of issue of the funding certificate for the case in respect of which the payment on account was made;
(b) three months have elapsed since the case ended;
(c) we have requested information from you about the case and you have failed to provide it to our reasonable satisfaction within 14 days;
(d) …"
Clause 6.31 provided that if the Firm became aware that any of the events set out in (inter alia) clause 6.30 had occurred, then they should notify the LSC of that within fourteen days so as to enable the latter to adjust the Firm's account and if necessary to require repayment. Clause 6.32 provided that "Before seeking repayment in respect of an overpayment or mispayment under paragraph 6.29, we will give you an opportunity to state why we should not do so. If you have made out good reason why we should not do so, then we shall not seek repayment."
"More than one breach which, together, are so serious that termination is justified."
Fundamental Breach C is defined as:
"One or more breaches, from which we may reasonably infer that performance will continue to be so substandard as to justify termination."
Paragraph 2 of Annex H provided that "termination for Fundamental Breach B will normally be justified in such cases even if the Supplier takes corrective action….".
The Defendants' preliminary legal points on the termination of the civil contract
"Our Legal Director or the CRB's determination (as appropriate) may e.g. allow the formal review, dismiss the formal review, make a different decision, give directions to the Regional Office or recommend that a fresh decision is made after a specified period. For the avoidance of doubt our Legal Director and the CRB's determinations are our decisions."
Events before the audit regarding civil legal aid work
"Using the case lists enclosed please submit your response to me by 5 March 2010. If you fail to do so I will unfortunately have no choice but to close the remaining cases and recoup the outstanding payments on account."
"Further to the previous correspondence regarding your outstanding payments on account I note that we are still waiting to receive your bills on a number of cases. I enclose a copy of the relevant case list. Please can you ensure your bills are submitted by 10 February 2011 or at least provide me with a clear indication as to when they will be sent. It appears that you intended many of these matters to have been billed last year. Unfortunately if I do not hear from you then I will need to start closing some of these cases and make the appropriate recoupments."
"Some of the bills are also still with the costs drafters. The costs drafters have informed us that they currently have backlogs and they are dealing with them. We therefore ask that you allow the revised estimated time. It may be that some of the bills will come before the estimated date."
"Meanwhile we have given mere estimates of the dates below. Therefore, please do not close the files as we are making efforts to get the bills assessed as quickly as possible."
The LSC responded on 10 February 2011 by a letter stating:-
"I note the problems you are having in getting your bills drafted and manoeuvred through the assessment process so I will re-diary your outstanding cases for a few months for the time being. I will recheck the situation periodically to ensure the bills are being received and I note that you will keep me informed."
The Audit
"The Legal Services Commission has a responsibility to ensure that public money is appropriately spent regarding the provision of Legal Aid. Where claims are made upon the Legal Aid Fund, claims have to be made in accordance with this specific requirements of the Contract. Charles Ete and Co Solicitors have Contracts which permit them to provide advice to clients in the family and crime categories of law. The Firm therefore have a responsibility to ensure that clients are eligible to receive publicly funded advice and that all claims by the Firm, on the fund, are accurate."
The purpose of the audit was stated to be:-
"…to seek reassurance that Charles Ete and Co Solicitors are reporting claims accurately and are more generally meeting the requirements of their Contract. The audit will involve discussions with members of staff…, a review of files and a review of standard documentation."
"Due to the Firm's inability to provide accurate and up to date financial information, it was not possible to complete the checks required to gain an assurance that the Firm is complying with Contracts in place. The Firm was unable to demonstrate that the payments on account for which it is responsible had been properly claimed and are being properly retained. For this reason I recommend that a Contract Sanction be applied under Clause 29 of the Unified Contract (Civil) 2007 (Standard Terms 2007), suspending further payments on account of profit costs, for a minimum period of six weeks."
The report added that it had been reviewed by one of the LSC's Audit Managers who had approved that recommendation.
(i) As at 28 September 2011 the LSC data showed that the Firm had received POA to the value of £1,376,565.40.(ii) The Firm was unable to provide an overall figure for work in progress ("WIP") for certificated matters and had stated that their IT system did not make it possible to extract a WIP valuation for that category of work from their running records of costs.
(iii) The Firm provided a total value of work figure amounting to £1,949,620.37. That figure included non-certificated work and it was not possible to readily cross-check the data provided by the Firm against the list of the legal aid certificates currently held by the Firm.
(iv) As for the request for full ledger/account print outs and WIP/Running records of costs for 20 legal aid matters, the Firm provided ledgers for the matters requested but stated that they were not used for accounting purposes but simply as a vehicle for monitoring certificate limits. The Auditor added that the ledgers in the form provided did not make it possible to track profit costs or disbursements.
(v) In any event, the Firm had provided running records of costs for only 3 out of the 20 cases identified in advance of the audit. The total value of work shown in those records did not support the profit cost POAs that had been claimed and in 2 out 3 cases incorrect public funding rates had been used to calculate the value of work done.
(vi) The Firm had been unable to recover from its system running records of costs for other cases requested owing to IT system malfunctions.
(vii) As for files for the 20 cases listed in the Audit Plan, the Firm had stated that files in 11 cases were with the Court or costs draftsman and 1 file had been removed by a previous fee-earner without authority.
(i) As at 28 September 2011, there were 157 certificates on the Firm's account. Of those, 39 were recorded as having been discharged.(ii) Prior to the audit the Firm had been provided with full POA reports prepared by the LSC listing all relevant certificates. The Firm had been asked to review the list and to report on whether matters were ongoing or concluded. For concluded matters, the Firm had been asked to give information on the stage of billing reached and the anticipated date for submission to the LSC of a final bill.
(iii) At the beginning of the audit the Firm stated that they had begun but not completed the review requested. On the second day of the audit, the Firm provided a report which dealt with only 105 cases. Because of the format used by the Firm (client name and short comment only), it had not been possible during the audit to cross reference the list against the LSC's POA report. It was clear that the Firm had not reviewed all matters.
(iv) Of the 105 cases listed on the Firm's review, only 23 were identified as ongoing; all other matters had concluded. The Firm has stated that files for only 48 cases had been sent to costs draftsmen for the preparation of bills.
(v) Mr. Ete had admitted significant delays in the billing out of certificated cases, but said that this was "partly attributable to problems with costs draftsmen but was also caused by cash flow problems, causing difficulties with payment of both costs draftsmen and Court assessment fees".
(i) Within 28 days the Firm had to complete for the Auditor a full and detailed report for all cases listed on the LSC's POA report. That response should identify ongoing cases, distinguishing them from concluded cases.(ii) For each concluded case the Firm had to report the date of the determination which had closed the case, the stage of billing reached and the anticipated date by which a final bill would be submitted to the LSC.
(i) A failure to provide running records of costs for 17 of the 20 matters notified in advance of the audit inspection.(ii) Payments on account exceeding 75% of the profit costs incurred had been claimed and received for 3 of those 20 cases.
(iii) The Firm acknowledged delays in the submission of the final bills.
The contract notice relied upon the audit report for full details of these points. The contract notice specifically warned that the Firm should not repeat the breaches, the LSC would undertake periodic reviews of the Firm's work to ensure ongoing contract compliance and that one or more of the sanctions in the contract might be applied. The notice explicitly stated that if any or all of these breaches were to be repeated, the contract might be terminated.
"Some were produced and more time was requested to produce the others, the Auditor agreed to give more time, these will be provided in the time given."
In the light of that statement, the LSC was entitled to expect that when the Auditor returned to the Firm in December 2011, all the requested details would be provided. The letter accepted the allegations of over-claiming in relation to POA in the following terms:-
"In respect of over-claiming, we believe this to be an error of the system, or a mistake as to the applicable rate; corrective measure will be taken to ensure the correct rates are used and the system updated."
It is to be noted that at no stage did the Firm identify the errors which it had uncovered or the specific corrections it had applied. Nor was this matter covered in the evidence produced by the Firm before this Court.
"We welcome a new date for further audit as the Auditor has stated we welcome dates in December 2011. We ask that we be given adequate time to obtain the information and documents needed and the information and documents needed should be clear and precise and if any alternative is requested this be made clear with proper notice given."
It is apparent that the Firm appreciated the urgency of the situation and did not suggest that a further audit during December would pose problems because of the approaching Christmas period. That contradicts Mr. Ete's evidence during the trial when he relied upon the Christmas period as a reason for the Firm failing supply the information required during the second stage of the audit.
(i) The total value of the POA already provided to the Firm appeared to be "unusually high, relative to the number of solicitors or case workers that are or have been doing civil certificated work". The figure quoted related to 140 out of 157 of the Legal Aid certificates in the Firm's name.(ii) A review of the claims made by the Firm over the previous 12 months indicated that the number of final bills received was negligible in comparison to the number of claims for POA. This billing pattern was unusual and could indicate that the Firm was not closing and billing cases when the cases were concluded.
(iii) The profile of the Firm's case list was unusual and suggested that the Firm was failing to bill cases properly upon the conclusion of work. Of the 140 certificates on which POA had been made, 33 had been discharged but no final bill yet received. Many of the certificates had been discharged some considerable time ago, which made it unlikely that delays in the assessment or taxation processes were responsible for the disparity.
(iv) Of the 107 certificates which had not yet been discharged, 43 had been issued more than 4 years earlier. Even allowing for any complexity in the work undertaken, the profile appeared anomalous and suggested delay on the Firm's part.
(v) Compared to the national average value of POAs outstanding on individual certificates, £4,008 per case, the average amount outstanding in the case of the Firm at £9,116 was high.
(vi) At the previous meeting, the Firm was able to provide up to date running records of costs on only 3 cases and, in 2 out of those 3 cases, the amount claimed on account exceeded the amount properly claimable under the rules of the scheme.
The letter stated that in order to avoid the possibility of the Auditor recommending further sanctions, the Firm would need to be able to provide "a reliable, evidence-based assurance to the Auditors, that the rules of the payments on account scheme have been complied with and that payments outstanding on the certificates ascribed to the Firm do not present a risk to the Legal Aid fund".
"I've written at some length because, as I am sure you realise, I regard the payments on accounts position as being one which poses potentially serious risks to the Legal Aid fund and to the Firm's status as a contracted provider. I hope that at the forthcoming audit you will be able to demonstrate those concerns are unfounded." (emphasis added)
The Court has not been shown any evidence to suggest that the Firm got in touch with the LSC or the Auditor at that point to indicate that it did not understand what information it was required to provide or that it would be unable to comply by the time of the audit in December 2011.
"In order to fulfil our duty to protect public funds I consider that the decision to suspend further payments to you was fair in the circumstances."
The letter also took into account concerns which Mr. Cowley had expressed in his letter of 22 November. It should also be noted that the Firm was informed that the second stage of the audit would take place during the first two weeks of December. I note that it was not suggested by the Firm even at this stage that it would be unable to comply with the LSC's requirements within the timescale given.
(i) During the supplemental audit, the Firm provided a revised total value of work figure in the sum of £1,503,552.12. However, this figure included not only certificated work but also "legal help" matters ("legal help" refers to publicly funded work carried out in bulk before the issue of a Legal Aid certificate for a particular case). The figure also included both historic and closed matters for which the Firm had already been paid and therefore was not a work in progress figure. The value of work figure could not therefore be accepted as a true and accurate reflection of the current value of outstanding work on certificated matters.(ii) The Firm did provide running records of costs and client ledgers for the 20 cases which had previously been identified. Information extracted from these documents was provided by the Auditor in Appendix 1 of her second report. However for 16 out of 20 of the cases, the total value of work did not support the POA claimed, according to the running records supplied by the Firm. Appendix 1 shows that in 80% of these cases, POA had been over-claimed, in the sense that the POA represented more than 75% of the evidence provided to demonstrate work actually carried out. It was also noted that in some instances work carried out even before the issue of a certificate had been included in the total value of work carried out.
(iii) On the running records of costs for some cases, high volumes of file reviews had been recorded. For example, in the case of Jones, 51 file reviews had been claimed by the Firm at 2 hours per review amounting to a total value of nearly £8,000. However, 23 of these file reviews were said to have taken place between December 2009 and October 2011, a period of nearly 2 years when no other activity was recorded as having taken place. In the case of Obialisi, 27 file reviews had been recorded, totalling £4,203.90. When the files for this client were called for, there was no evidence to support the work or time recorded.
(iv) In 6 out of the 20 cases not all POA profit costs values had been credited to client ledgers and in a further 2 matters the VAT element only of the POA figure had been credited (see also Appendix 1 to the Auditor's report).
(v) Disbursement POA figures were credited to the client ledgers but there were no corresponding debit entries to reflect onward payment to relevant third parties.
(vi) At the audit the Firm was asked to provide running records of costs, client ledgers and files for 5 clients in addition to those requested beforehand. The documents were not provided immediately and had to be re-requested during the audit. No running records were provided in respect for 1 of the cases. For others, no evidence could be seen on the files to support the work recorded as "file reviews". In 2 cases, the Auditor had wished to check whether costs had been duplicated but it was impossible to access live computer records for this purpose.
(vii) The Auditor had intended to undertake checks for additional matters directly against live computer records. However when that was attempted, Mr. Ojo was unable to access any live records and the checks had to be aborted. In the alternative, additional checks were carried out for profit costs POA claims using the "total costs all cases information" provided by the Firm. This information was reproduced in Appendix 2 to the Auditor's report. 54 out of 142 of the cases listed in the Firm's information could not be identified so no check was possible. In relation to the remaining 88 cases, profit costs POA claims were not supported by total value of work as at 7 December 2011 in 36 cases, indicating that POA had been over-claimed in 40% of those cases.
(viii) Mr. Ete told the Auditor that because of cash flow issues, the Firm did not have access to support services for one of the software tools used and that running costs records of costs could be inaccurate because of IT system problems. Mr. Ete also said that he had retained a copy of each POA claim submitted in a central record but no supporting information had been attached to any claim, such as a copy of a computer-generated running record or a manual costing. As for the files reviewed during the audit, there was no evidence found by the Auditor of the manual costings which Mr. Ete had said were carried out. The Firm was unable to provide any additional evidence to support POA claims identified as "over-claims". Mr. Ete told the Auditor that the absence of some POA claims attributable to client ledgers was likely to have been an oversight by Mr. Ojo.
(ix) As for the absence of records recording payments to third parties for claimed disbursements, whereas Mr. Ete had said that the Firm had a second IT system used for that purpose, Mr. Ojo told the Auditor that that system was not used for publicly funded work.
(x) The overall conclusion was that the running records of costs included excessive volumes of file reviews not supported by evidence, the Firm could not support the POA claimed in 16 out of 20 cases initially checked or in an additional 36 out of 88 matters subsequently checked, the Firm had not provided a reliable evidence-based assurance to the Auditor that the rules of the scheme had been complied with, persistent breaches of contract requirements had been identified, and the Firm could not demonstrate that the payments outstanding on the certificates attributable to the Firm did not present a risk to the Legal Aid fund.
(i) At the beginning of the second stage of the audit the Firm provided a report detailing the status of 150 certificated cases. Of these cases only 25 were reported as ongoing, 14 were reported said to be lodged with the Court for detailed assessment (but the Courts involved had not been identified by the Firm) and 77 cases were said to be with a costs draftsman for the preparation of a bill. Mr. Ete said that only one costs draftsman was now used by the Firm, Mr. Godrey Odugba. A list of 75 cases said to have been lodged with Mr. Odugba was provided to the Auditor signed by him.(ii) Mr. Ete stated that he anticipated bills would be prepared at the rate of 3 a month, subsequently revising that estimate to 6 a month.
(iii) 9 matters were said to be lodged with the LSC for payment and 4 as closed and paid, 7 cases were reported as case pending, bill to be amended, bill completed or matter not proceeding, and in the case of 6 matters it was said that files had been retained by 2 previous fee-earners and were unavailable for bill preparation.
(iv) For "concluded matters" the Firm had not given the date of the determination which had closed the case in each instance.
(v) The Firm had not provided an anticipated date for submission of a final bill in many cases.
(vi) Because of the Firm's failure to record the dates upon which concluded matters had been determined, it had not been possible to establish the length of the delay in submitting final bills in all cases. However, from the information available it was clear that delays are significant and there had been persistent breaches in contract requirements.
Events after the audit
"To manage that risk I have decided to recover the payments on account made to you on two categories of case; first I intend to make recoveries on a group of seven cases which in February 2011, you told us would be billed before May 2011. Unfortunately your assurance that bills would be forthcoming has not been realised. It is now nearly one year since we received your letter, but bills have not yet been received. Secondly, I intend to recover the payments on account made on those six cases which you were unable to produce at audit, because the files had been removed from the Firm by one or more of your previous employees."
He enclosed a schedule of the 11 cases to which he was referring and said that in these cases the Firm's costs would be provisionally assessed as nil. Nonetheless it was pointed out that if the Firm was able to submit a bill in any of these cases, then the LSC would re-open the matter and assess a claim for costs in the usual way and if any money were found to be payable then at that point the sum would be credited to the Firm's account. Thus, the LSC followed the practice described by Cranston J in the Loomba case.
(i) A letter sent directly to the LSC by the costs draftsman, confirming which cases (with their legal aid certificate numbers) had been lodged with him for billing and when the provisional bill was likely to be drawn;(ii) For cases said to have been submitted to the Court for detailed assessment, details of the Court concerned, the date when the submission had been made and a copy of the bill as drawn;
(iii) For each of the 13 cases cited in the LSC's letter of 19 January, a copy of the bill as drawn or an up-to-date print-out of the ledger in relation to the case showing the activity that had taken place and the value of the work in progress to date calculated at the prescribed legal aid rates. On each file ledger, the total of the Firm's profit costs, the value of any work done by any previous solicitor and the cost of any disbursements were to be highlighted.
"… accepted the contents of the Audit Report (30 October 2011) and the Supplementary Audit Report (7 and 8 December 2011) as accurate in terms of the audit activity and the findings. Their decision was that the Audit Report and the Supplementary Audit Report confirm serious contract breaches over a long period of time which puts the legal aid fund at risk both historically and going forward were the Contract not terminated. In these circumstances they did not accept a central theme of your argument which was to the effect that in terminating the Contract too much emphasis had been placed on technical matters and too little on other factors such as the work undertaken by the Firm. The Contract Review Body considered that termination of the Contract was proportionate and reasonable in all the circumstances. The sum held by you in respect of Payments on Account, in excess of one million pounds, was not properly accounted for and therefore represented a substantial risk to the legal aid fund. The Contract Review Body did not consider that directing corrective action was an appropriate alternative to termination. There was a future risk to the legal aid fund were you permitted to continue because it was clear from the evidence that Work in Progress was not accurately recorded. There was evidence that Work in Progress figures were inflated."
"Your assertion that six weeks between the initial audit and the second audit was inadequate was considered but was not accepted. The contractual requirement was to demonstrate compliance with the Contract at the first audit pursuant to clause 8 of the Contract Standard Terms. In any event the Contract Review Body accepted the evidence of Toni Harvey firstly that six weeks was the maximum period that could be safely allowed given the serious nature of the Contract breaches that had been identified and secondly that the six week period represented a concession because there was sufficient evidence to terminate the Contract following the first audit.
The Contract Review Body considered your representations in relation to the Work in Progress figures but it was satisfied that you had not been able to provide an accurate figure. They did not accept that there were errors in either Audit Report and considered it was abundantly clear that you held in excess of one million pounds in respect of Payments on Account which you were unable to properly account for pursuant to the terms of your Contract. This, they considered, represents a substantial risk to the legal aid fund and justifies termination.
Your point in respect of payments to other firms was noted but the Contract Review Body accepted the evidence of Toni Harvey that this accounted for a very small proportion of the sum outstanding.
There was further concern that such figures as you did have were not accurate in terms of what would eventually be allowed on taxation or assessment. In this regard it was noted that you did not dispute the inaccuracies identified in 16 out of 20 pre-requested files audited on 8 December 2011 or that 36 files of the 88 files provided contained Payment on Account Claims not supported by the work recorded.
The Contract Review Body did not accept that it was unfair to raise excessive file reviews, which were included as Work in Progress figures, as reason to question the accuracy of the figure for Work in Progress overall. On the file of James referred to in the Supplementary Audit Report 51 file reviews had been recorded at 120 minutes per review. This was clearly charging for time which was not chargeable and which could in no circumstances be reasonable.
The Contract Review Body noted the points you made in relation to individual files but concluded that even if they were accurate they did not assist you. The overall position was clearly one of multiple breaches of Contract which had first been identified in October/November of last year and the position was little improved at the date of the hearing. The Contract Review Body were satisfied the "Outcome" of the audit of "Certificated Matters, Payments on Account… and IT requirements, including Time Recording" detailed in the Supplemental Audit Report was fair, and accurately recorded the position.
In relation to "Certificated Matters, Delays in Billing" in the Supplemental Audit Report the Contract Review Body were satisfied that there had been serious breaches of Contract in this regard which were not adequately dealt with in your representations. There was clear evidence of a substantial failure to bill files in accordance with the Contract over a prolonged period.
Finally, the Contract Review Body considered the position in relation to supervision detailed in the Audit Report dated 30 October 2011 and 1 November 2011. They were satisfied that the breaches of Contract detailed in the Audit Report in this regard were appropriately recorded and that the situation detailed represented a serious breakdown in the arrangements for Supervision." (emphasis added)
"Given the circumstances, the time that has elapsed and the ongoing failure to report, I am now of the view that it would be inappropriate to rely on the assertion that the cases said to be with the costs draftsman are actually resting there and are in the course of being billed, even if a statement to that effect from the draftsman is forthcoming. I intend to ask our payments on account team to recoup the payments on account made."
It is to be noted that the LSC had not been sent any updated information on the timescale for the submission of bills produced by the costs draftsman.
"At present there is a debit balance on the account, reflecting the fact that payments on account as itemised in my last letter have been recouped. The amount shown as being owed to the Commission stands at £534,486.
Since April we have processed only two claims for costs from your Firm arising from work done under civil certificates. The total value of claims processed was under £10,000.
The fact that only two claims have been made does not appear to be commensurate with your earlier assurance that a significant number of claims were being prepared by your costs draftsman or your assertion that you would be able to discharge any liability to the Commission by submitting bills to us. Put bluntly, the assurances you have provided to us, both recently and in the preceding years appear to have been entirely unreliable.
I enclose a report that shows the value of payments on account still outstanding on cases that have not yet been claimed for (in other words, cases where we have not received a final claim for costs nor yet recouped the payments on account made). The total value of the payments outstanding is £524,567 (but of course some of those payments have been made to previous solicitors or to counsel).
To secure the Commission's financial position I now intend to ask our finance team in Leeds to seek to reconcile the finances in these remaining cases, by settling counsel's accounts and those of previous solicitors with them and by recouping from your account the other sums due to us. I will write to you again to confirm the balance due to us when this exercise has been done. After that your correspondence should be with our Debt Recovery Team."
"totally disputed. As I indicated before they contain figures in respect of certificates and files which have been transferred to other providers by the LSC. We were asked to send our files to them which we have done. They are therefore not our responsibility as we have since sent the files to those providers. I note you also carried over amounts which related to those files including amount paid to other former solicitors and counsel totally separate from us. We were never a party to such payments, we never authorised them and are therefore not liable to same".
But, once again, the letter did not give any examples of such files or any specific amounts to illustrate the assertions being put forward. I should also add that during the course of the trial no such material was shown to the Court.
"I think there are a number of ways in which you have misinterpreted my previous letters.
1. I accept (and have always accepted) that you dispute our calculation of the amount owing to us. You have however failed to provide evidence to support your position, despite being given numerous opportunities to do so by the Auditor who carried out the audit of your civil work and the Contract Review Body that heard (and dismissed) your appeal.
2. The recoupment of the payments on account in issue were all made against certificates attaching to your account at the point at which the recoveries were triggered. Put another way, the certificates in these cases had not then been assigned as you suggest, to other providers.
3. Any amount paid to former solicitors on account became your responsibility when the certificate in the case was assigned to you. Under the contract you have a duty to conclude cases properly, which extends to a duty to bill or make reports on each case when the client's retainer ceased.
4. Amounts paid to counsel have not been recouped from your account. We are resolving any issues in relation to these payments directly with counsel." (emphasis added)
The audit of the crime contract
"We request that I be served with the alternative recommendation made by the Auditor, in that during the audit, we were informed that they would recommend that certain corrective measures be carried out by us if their manager recommends our contract to continue". (emphasis added)
The decision to terminate the crime contract had been taken by Mr. Kelly. The informal review was carried out by Mr. Cowley and his decision was given by letter dated 31 July 2013. He said:-
"Your letter suggests that you have been provided with one of two audit reports and that an 'alternative' report makes a different recommendation from that in the report you have. I think there is a misunderstanding here. The report you have is the 'final' report and the report on which we will rely should you wish to make a formal appeal. Mr. Kelly made his decision to terminate the contract on the basis of the evidence in reports sent to him by the Auditor. Having made that decision he sent you the report with his letter of 4 July; taken together the two documents set out the evidence he considered and the grounds for his decision. He will have removed from the report sent to you any reference to 'corrective action' because of course the decision to terminate the contract had the effect of making any such reference redundant."
"Please note at the outset that this was the report that was sent to the audit manager which included possible corrective action if his decision was not to terminate. This was an internal report and in the event he decided to terminate your crime contract and corrective action was deemed not appropriate. As a result, the report you received, which was the final report, confirmed the findings and audit manager's decision to terminate."
(i) Matters covered by the Auditor's reports on the Civil legal aid contract;
(ii) The decision to recoup POAs;
(iii) The Claimant's schedule of loss – "updated Schedule A";
(iv) The decision to terminate the civil legal aid contract;
(v) The Defendants' schedule of damages and loss;
(vi) The non-inclusion of the firm in the Duty Solicitor Scheme rota.
Witness evidence
Matters covered by the Auditor's reports on the Civil Legal Aid Contract
"We had properly run files for each matter, in fact our files were commended by the Law Society Practice Standards Unit and as stated we passed the external peer review organised by the Claimant. These were all reviews based on files we were asked to provide. For the Claimant to then say that we did not have well run files was again misleading. The Claimant merely invented that reason (in addition to its other reasons which were false), in a bid to maliciously, wrongly and unfairly terminate our contracts."
But Mr. Ete there neglected to point out that the peer review to which he was referring was in fact for the Crime Contract and as long ago as 2007. It was not a review in respect of the Civil Contract, nor indeed contemporaneous with the matters which the Auditor was considering. I will return to the other reviews upon which Mr. Ete relied subsequently in this judgment.
"As at initial audit CE stated that there had been problems with … Lawmaster systems, including a system crash in December 2010. Owing to cashflow issues, the Firm do not have current access to Lawmaster support services. CE indicated that running records of costs may be inaccurate because of IT system problems encountered."
Second, Mr. Ojo himself said in cross-examination that the last time he could recall relying upon the assistance of Lawmaster's service department to solve an IT problem was in 2010. So there is no evidence to contradict the statement made by Mr. Ete to the Auditor that there had been a system crash involving the Lawmaster software in December 2010, the Firm did not have access in 2011 at the time of the audit to Lawmaster support services and according to Mr. Ete the running records of costs might be inaccurate because of IT system problems. At one point in his evidence Mr. Ete suggested that because of the difficulties the Firm had experienced with Lawmaster, it had invested in a second piece of software provided by Peapod. However, at page 4 of her second report the Auditor recorded that Mr. Ojo had told her that Peapod was not maintained or utilised for publicly funded work. That statement by Mr. Ojo was not contradicted in evidence before the Court by Mr. Ojo or indeed by Mr. Ete.
The decision to recoup payments on account
The Claimant's schedule of loss – "updated schedule A"
The decision to terminate the civil legal aid contract
"It was apparent that Charles Ete and Co has a strong service ethic. The files I reviewed were, in general, well organised and managed. I would also mention that I was impressed by your attitude and obvious commitment, as well as by the cordiality and helpfulness of all your colleagues."
No further details were produced to the Court from this report in order to enable a better understanding to be gained as to the purpose and scope of this monitoring exercise. When Mr. Ete gave evidence in chief, he referred to a letter from the Law Society of 27 July 2005 (in his additional bundle E). Perhaps the letter was in fact sent on 27 August 2005 because it responded to a letter from the Firm dated 18 August relating to the monitoring visit in July of that year. The letter stated:-
"I was pleased to learn that you have taken all the steps necessary to address the required actions in my visit report. Thank you for doing that promptly."
The Defendants have not produced the letter of 18 August or any evidence as to what those actions were or why they were necessary. It is difficult for the Court to give any significant weight to material of this kind without the Defendants producing material to show what the ambit and purpose of the inspection was and the extent to which, if at all, it relates to the matters which were investigated during the audit in 2011.
"5. The books of account were in compliance with the solicitors' account rules in all material respects".
In his new bundle E Mr. Ete included a letter from the Solicitors Regulation Authority dated 17 August 2011 which related to the 2011 "investigation under the Solicitors Accounts Rule 1998 and the Solicitors Code of Conduct 2007". The extract from the letter states:-
"I refer to my attendance at your offices on 10 February 2011 and on subsequent occasions. I have now concluded my report which I am enclosing."
The following text has been obscured and Mr. Ete has not produced the entire letter or report. The subject matter of the investigation has not been properly revealed.
The Defendants' schedule of damages and loss
The non-inclusion of the Firm in the Duty Solicitor Scheme rota
"Please also note that where you have been awarded membership of any Duty Schemes, you will need to complete a CDS12 form(s) and return these to us by 4pm on 30 April 2010." (emphasis added)
"… please remember to include me in the new rotas as I was missed out on the last one. This has caused our Firm grave financial hardship, I have since sent in my CDS 12 on time as was requested. The new ones were sent since 11 October 2010. Far before the November 2010 dateline." (emphasis added)
I infer from that that by December 2010 the Firm had been accepted as a member of the duty solicitor scheme, albeit that the manner in which that was achieved has not been dealt with in evidence produced by either side. More to the point, this e-mail confirmed Mr. Ete's acceptance at the time that he needed to complete a CDS 12 form in accordance with the explicit requirement to that effect contained in the LSC's letter of 26 March 2010 to the Firm.
"You must apply for your Duty Solicitors to undertake Duty Solicitor Work on a Scheme by completing a CRM12 form for each of them by the deadline notified by us on our website. A properly completed CRM12 will allow that duty solicitor's name to be entered on the Rota or Panel of the Schemes you are a member of and will result in your being allocated duty slots on that scheme."
Given that the term "duty solicitor" was defined specifically to mean a person who had previously been a member of a scheme under the earlier 2008 Arrangements, it is plain that 6.10 required the appropriate forms to be submitted to the LSC for approval in respect of such solicitors, who would have included Mr. Ete. In addition it is to be noted that Clause 6.2 provided: "you may only apply to join Duty Solicitor Schemes when you submit an application as part of the Tender Document for Contract Work".
Conclusions
The claim to recover POAs
The Claim that the Civil Contract was wrongfully terminated
(i) The adverse findings set out in the Auditor's first and second reports were well justified as regards (at the very least): -(a) The Firm did not have an IT system giving up-to-date and reliable records of works in progress and total costs on certificated cases, both as a whole and individually, and which could be accessed quickly (Annex E of the Unified Contract and Clause 8.2 of the Standard terms);(b) The Firm was unable to provide a reliable and up-to-date figure for works in progress on certificated cases;(c) The Firm had overclaimed POA in breach of clause 17(6)(c) of the Standard Terms in a very substantial proportion and number of the cases examined;(d) There had been a very high number of file reviews which could not be justified and this amounted to over-claiming;(e) There were substantial and unjustified delays in submitting final bills for concluded matters in breach of 8.17 of the Specification.(ii) The Defendants made no effective challenge to those findings before the decision to terminate or before the CRB or before the Court;
(iii) The CRB was entitled to uphold the Auditor's findings and to conclude that there had been "multiple breaches of contract" and "a substantial failure to bill files in accordance with the contract over a prolonged period.
Other points raised by Mr Ete on the auditor's conclusions and the review before the CRB have been dealt with in my earlier findings.
The Claim that the Crime contract was wrongfully terminated
Non-inclusion of the Firm in the Duty Solicitor Scheme
The Defendants Schedule of Loss
Decision
Application for permission to appeal