QUEEN'S BENCH DIVISION
Strand, London, WC2A 2LL |
||
B e f o r e :
(SITTING AS A JUDGE OF THE HIGH COURT)
____________________
J Browne Construction Company Ltd |
Claimant |
|
- and - |
||
(1) Chapman Construction Services Ltd (2) Andrew Chapman (3) Barry Chapman |
Defendants |
____________________
Philip Williams (instructed by Railton Law) for the 1st & 2nd Defendants
Giles Mooney (instructed by Regulatory Legal Solicitors) for the 3rd Defendant
Hearing dates: 19th – 24th January 2016
____________________
Crown Copyright ©
Her Honour Judge Taylor:
Introduction
i) The Claimant, J Browne Construction Company Limited as JB;ii) The First Defendant Chapman Construction Services Limited as CCS;
iii) The Second Defendant Andrew Chapman as Andrew;
iv) The Third Defendant Barry Chapman as Barry;
v) South East Water Limited as SEW.
Background
The Claim
i) CCS, Barry and Andrew Chapman are liable for unlawful means conspiracy;ii) Barry and Andrew Chapman are liable in deceit;
iii) Barry and Andrew Chapman are liable for procuring or inducing breach of the contract between JB and CCS;
iv) CCS are in breach of contract in failing to provide timesheets with invoices, a condition precedent to payment, and are not entitled to overtime as this was not authorised in writing.
The Contract
Labour & Plant Only Shift Rate Sub-Contract
Sub-Contract Order No. SC002765/1305BC
….
Sub-Contract Summary of Particulars
1. Contract/Site Address: Various sites across the SE Water region
2. Rates or Prices for the Sub- Contract Works (exc of VAT)
In accordance with the following Schedule of 'Daily Shift Rates':
Ganger@ £160 per shift
Skilled Operative @ 150 per shift
Unskilled Operative @ £110 per shift
Signed time sheets by a member of J Browne site management team are to be attached to each invoice submitted
4. Normal working hours
Monday to Friday 0.7.30 am to 17.30 pm ….( 9.5 hour shift) with additional unpaid lunch and working breaks to be taken accordingly
Any overtime working outside of these hours must be instructed in writing by the Contractors Authorised Representative in accordance with clause 5.15 of the Appendix to Sub Contract Order.
5. Payment
5.1. The first and subsequent interim sums for payment shall be due to the Sub-contractor 28 days after the date of receipt by the Contractor of a valid application for payment from the Sub- Contractor (the "due date for payment"). Applications for payment are to be submitted at 14 day intervals. The first submission being the Friday 14 days after the date for commencement of the Sub-Contract Works.
…
5.2. The sub-contractor shall submit to the Contractor with its application for payment a written statement in such form and containing such detail as the Contractor may reasonably require, showing the total value of the Sub-Contract Works that the Sub-Contractor considers it has properly executed up to the date of the application for payment and identifying the names dates and shifts worked by each individual on the project to which the Sub-Contract Order relates.
5.3. It shall be a condition precedent to any sum being due for payment that the Contractor shall have received from the sub-contractor an application for payment and a written statement in respect of that interim sum complying with clause 5.2 above by no later than the corresponding Application submission date. For the avoidance of doubt, if the Contractor does not receive an application for payment of an interim sum from the Sub- Contractor by the corresponding Application Submission Date, no sum shall become due to the Sub-Contractor in respect of the work for which payment is requested in that application for payment.
…
5.15. It is a condition precedent to payment for overtime that prior written authorisation is obtained from the contractors project manager or site manager.
5.16. Overtime Monday to Friday shall be paid at the Hourly Shift Rate divided by 9.5 hours for each hour worked. Saturdays shall be paid at the Hourly Shift Rate divided by 9.5 hours for each hour worked. Sundays shall be paid at the Hourly Shift Rate divided by 9.5 hours multiplied by 1.5 time for each hour worked .Overtime enhancements will only be paid if a full week has been worked (5 days).
Taking the provisions as a whole, the form of document required under paragraph 5.2 is therefore time sheets signed by a member of JB site management team and attached to each invoice submitted.
Disclosure and alteration of case
i) CCS or Andrew Chapman destroyed hand written notes ... if they ever existed) of information he says was provided over the phone by CCS worker which formed the basis of the timesheets prepared initially by him, and subsequently by his wife or Clare Bryan, an Administrator working for CCS.ii) CCS has disclosed no records of hours or pay of its workers; JB maintain that CCS have not given disclosure of any payroll records. CCS say that they were given access to the SAGE computer payroll system.
iii) Barry Chapman destroyed his laptop computer by putting it through a recycling crusher.
iv) Barry Chapman has not produced the original of the 2 July letter.
i) The claim was originally based upon Mr Dodd's analysis of PCWs against JB weekly records of directly employed employees with which they were said to tally, and against CCS invoices which showed discrepancies, What was disclosed was a sample of 15 weekly records for directly employed workers records for comparisons which Mr Dodd said had been picked at random, but showed overcharging by CCS. The remainder of the directly employed worker records (which Mr Dodd estimated were a further 40) were not disclosed until after the evidence was completed at the end of the trial. They were then disclosed with schedules prepared by Mr Dodd which purported to show that the PCWs were more accurate than emerged after he was cross examined about his analysis of the sample of 15.ii) Billing records from SEW other than those relied on by Mr Dodd were not disclosed until very close to the end of the trial. This was only after an application by Barry Chapman to call a witness from SEW on the clawback of sums paid during his control of the contract was granted. Mr Dodd claimed during his evidence that SEW had clawed back money paid because Barry Chapman had authorised work which had not been done. Subsequently some documents were disclosed.
iii) The time sheets for directly employed workers have not been disclosed.
iv) On the first day of trial , with no prior notice, JB dropped the majority of the claim for plant, disclosed documents having undermined the claim that some items were in the possession of CCS rather than lost or stolen or indeed located elsewhere.
v) When Mr Dodd entered the witness box he withdrew a very significant part of his evidence, again without notice. That evidence at paragraph 30 of his statement was that the PCWs were accurate when he compared them with the JB directly employed worker records on two occasions. Whilst JB did not abandon the claim in deceit, the emphasis shifted to those parts of the claim which did not rely on Mr Dodd, such as breach of contract. A claim for wasted management time in investigating the false invoices was dropped at the outset of the trial prior to Mr Dodd's evidence, but presumably based upon knowledge of the withdrawal of the evidence about checking the invoices.
Mr Dodd's approach and evidence
The Timesheets
Overtime
"Weekend working at the moment we just get standard rate".
"Further to our discussion yesterday as per your subcontract terms and conditions (see attached) you are entitled to overtime at time and a half work at weekends and time and a quarter at evenings, This will need agreeing with J Brownes prior to carrying out overtime and is applicable to work carried out beyond the usual 9.5 hour shifts".
Was there a fraud or conspiracy or deceit?
Damages