QUEEN'S BENCH DIVISION
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Oxfordshire County Council |
Claimant |
|
- and - |
||
(1) Wyatt Bros (Oxford) Ltd (2) Michael Wyatt (3) Ronald Charles Wyatt |
Defendants |
____________________
Mr A Alesbury (instructed by Morgan Cole) for the Defendants
Hearing dates: 29-30 September 2005
____________________
Crown Copyright ©
Mr Justice Beatson :
Introduction
"(1) Where a local planning authority consider it necessary or expedient for any actual or apprehended breach of planning control to be restrained by injunction, they may apply to the court for an injunction, whether or not they have exercised or are proposing to exercise any of their other powers under this Part.
(2) On an application under sub-section (1) the court may grant such an injunction as the court thinks appropriate for the purpose of restraining the breach."
The legal principles
"1) section 187B confers on the court an original and discretionary, not a supervisory, jurisdiction, so that a defendant seeking to resist injunctive relief is not restricted to judicial review grounds; 2) it is questionable whether Article 8 adds anything to the existing equitable duty of a court in the exercise of its discretion under section 187B; 3) the jurisdiction is to be exercised with due regard to the purpose for which [it] was conferred, namely to restrain breaches of planning control, and flagrant and prolonged defiance by a defendant of the relevant planning controls and procedures may weigh heavily in favour of injunctive relief; 4) however, it is inherent in the injunctive remedy that its grant depends on a court's judgment of all the circumstances of the case; 5) although a court would not examine matters of planning policy and judgment, since those lay within the exclusive purview of the responsible local planning authority, it will consider whether, and the extent to which, the local planning authority has taken account of the personal circumstances of the defendant and any hardship that injunctive relief might cause, and it is not obliged to grant relief simply because a planning authority considered it necessary or expedient to restrain a planning breach; 6) having had regard to all the circumstances of the case, the court will only grant an injunction where it is just and proportionate to do so, taking account, inter alia, of the rights of the person or persons against whom injunctive relief is sought, and of whether it is relief with which that person or persons can and reasonably ought to comply."
The Evidence
The planning and enforcement history
"11. The eastern part has been the subject of the greatest activity. The landform as it now exists is the combined result of a number of actions. ..A lake has been excavated and blue clay exported. This was the subject of consents both from SODC and OCC. Overburden of brown clay has been deposited elsewhere on the eastern part. Topsoil has been stripped and formed into several mounds. In the centre next to the River Thame what Mr Lyne describes as a fairway has been created. Mr Lyne states that this was raised by about 1 m in 1994 and 1995 and consists of builders' rubble overlain with some brown clay. This is now grass covered with no visible evidence of tipping. The land was wet at the time of my visit.
12. There is a mound next to the 10th fairway which defines the edge of the existing course (sometimes described as a demarcation bund). Mr Lyne says that this was formed during 1993-1994 and includes builders' rubble and soil from within the site. To the east of the lake there has been a substantial raising of the land above original levels. Mr Tyce states that there was substantial tipping from November 1996 until September 1997, prior to the commencement of the MSA contract in October 1997. That would be consistent with the authorisation of enforcement action in June 1997, leading to the issue of Notice A in September. My Lyne visited the site in June 1997 and accepts that there was builders' rubble and the beginnings of a mound in the north-east corner of the land. From my site visit the presence of substantial amounts of brick, hardcore, concrete and excavated subsoil which is not part of the MSA contract is apparent.
13. Invoices submitted by WB show that MSA material was deposited between 20th October and 14th November 1997, 2nd -5th December 1997 and 21st-25th February 1998. This was excavated subsoil arising in the first instance from construction of the M40 in about 1989. This has been deposited on land nearby where a MSA was subsequently permitted. WB entered into a contract to take the material, with 120,000 cubic metres said to be available. Part of this material was used to infill the lake and a substantial quantity can be identified to the east of the lake.
14. A bund has been formed on the eastern side of the driving range. A bund is required as a condition of a PP granted on appeal for the retention of the safety netting, which is shown in the relevant plan to be 2-2.5 m high and narrow, perhaps 4.5 m wide. In its present state the bund is of greater width and in part does not achieve the required height.
15. A haul road has been constructed from hardcore and builders' waste between the lake and the roundabout on the A418. This was permitted in conjunction with the clay extraction and a condition of that consent requires its removal. To the north-west of the driving range between the haul road and a public footpath which crosses the appeal land is a level area. There is a small store of stone and hardcore on this but looking from the footpath, which is at a lower level, it appears that the levelled area has been formed by the tipping of material including hardcore and builders' waste."
Attempts to reach a settlement
"9. Since 1999 there have been negotiations between the appellants and the council to find a compromise solution that will allow the construction of a 9 hole golf course without full compliance with the enforcement notice. At the outset, the council indicated by letter dated 13 October 1999 that removal of a substantial proportion of the waste material from the area to the east of the irrigation lake would be required.
10. Another guiding principle was the need to reflect very closely the underlying land form prior to depositing the waste, using the existing 18 hole golf course as an example of what might be acceptable. A layout that was elevated well above the pre-existing contours would not be acceptable, even if it resulted in an attractively designed landscape. But it was also made clear that there may be a case for some of the waste material to remain in certain areas of the site.
.
12. Essentially the current proposal is based on re-shaping the inert waste material, in particular by removing some of the material from the east side of the irrigation lake to its west side, thereby smoothing out the steeper contours in that area an lowering the profile to the east. The material deposited on the flood plain within the site would also be moved.
13. The proposal is not therefore based on removing the waste material from the site, other than incidentally during the course of construction as a result of finding, say, large lumps of concrete and tarmac. The small amounts of wood, metal and plastic encountered during the Environmental Agency's inspection of the site in August 1997 would also be removed, if unearthed."
"(i) The Inspector's report confirmed the enforcement notice which requires the removal of practically all the waste material with the exception of some bund material along the southern and western boundaries of the tipped area.
(iii) There is thus a need to return the land form to something very close to the pre-existing contours. An application which proposes anything less is likely to result in a recommendation of refusal.
(iv) Within this context, any plans which you prepare should take into account the following principles:
(a) Softening the contours and reducing the height of the bunds in part along the southern and western boundaries.
(b) Removal of a substantial proportion of the material from the area to the east of the lake where the mounding is excessively high.
(c) the need to reflect the underlying land form and using the existing golf course as an example of what might be acceptable to the planning authority.
(v) A layout which results in a landscape, however attractively designed, which is elevated well above and therefore does not reflect the pre-existing land form will not be acceptable."
"demonstrate that the intention was to base an acceptable scheme on the contours shown on the plan provided by Ms Coyne for the western part of the site. On the eastern part of the site I agreed with Ms Coyne that an average of 1 metre depth of on site material could be used to shape the golf course. The eastern part of the site is about 4 hectares in site so an average of 1 metre over this area could amount to up to 40,000 cubic metres of material. This agreement demonstrates the willingness of OCC to retain a substantial amount of imported, or technically 'waste', material on site."
"1. It was agreed that your landscape architect would within about 2 weeks provide a revised scheme for construction of the proposed new 9 hole course using waste material already deposited on the course. Within the 65 and 60 contours on the land to the east of the lake the scheme would use up to a 1 metre depth of material over agreed pre-existing contours (as shown on March 2000 plan 5 alternative contours version) to shape the course.
2. The scheme would provide details of where the surplus spoil would be disposed of.
3. I do not consider that the current proposed driving range bund is strictly necessary for screening the lights. Planting would be equally if not more effective and more in keeping. However, given that planting has not been done, a bund could give an earlier screening effect. Consequently I would be prepared to consider a proposal to extend the bund around the north eastern corner only of the driving range as part of any revised scheme submitted to the County Council. However you would have to demonstrate how this would mitigate the effect of the driving range on nearby properties and include suitable planting measures. It must be limited in scale to what is necessary to achieve screening and must not be simply a means of retaining waste material on the site."
"The County Council's preferred option would be for all the unauthorised deposited waste to be removed from the site, as required by the enforcement notices. However, in the interests of a pragmatic solution, and provided very special circumstances for overriding green belt and other planning policy can be demonstrated, there may be a case for retaining some of the waste if the landscape solution is acceptable."
" ..I can reiterate the key points that would have to be met by a proposal before officers could recommend it for approval. I should however stress that the recommendation to be made on any proposal would depend on the overall scheme and the results of consultations. The starting point would of course be the extent to which any proposal was in accordance with the development plan, in line with section 54A of the 1990 Act.
The key points are set out below.
1. The existing high, steep sided mounding must be altered so as to successfully integrate with the existing land form and return the overall land form to something closer to the pre-existing contours by:
(a) Softening the contours and reducing the height of the bunds in part along the southern and western boundaries.
(b) Removal of a substantial portion of the material from the area to the east of the lake where the mounding is excessively high.
.
4. No further import of material should be involved.
.
You will note that no reference is made in these key points to a limit of 1 metre of material over pre-existing contours. I should stress that this is not to say the depth of fill of greater than this would be acceptable. That limit was put forward by David Young in February 2001 as a potential pragmatic compromise. Given the present position, however, it is felt that the key points should go back to first principles."
The decision to institute proceedings
"In addition the difference between some of the waste and all of it remaining is significant and the two alternatives have different planning consequences. Quite apart from the large-scale landscape change that the considerable volumes of deposited waste have caused, there are issues to be resolved such as waste planning policy which does not support landraising such as this, the effect on the openness of the green belt and removal of waste from the flood plain. If nevertheless only small amounts of waste are retained for example to create essential golf course features, then these policy and other issues may not be breached. Consequently in the absence of an acceptable scheme that follows the principles set out in the letter of 18 October 2002 (which do not rule out the retention of some of the waste in a suitable landscape form) the Council has to rely on the requirements of the enforcement notice to achieve an appropriate planning solution."
"it is far more acceptable than any other scheme that has been put forward by Wyatt Bros over the years. It shows the overall pre-existing gently sloping contours and if complied with the site would be readily assimilated into the river landscape."
The submissions of the parties
The Issues
Conclusions on the issues
(1) The extent of the breach
(2) The nature of the breach
(3) Do the dealings between the parties make it inappropriate to grant the claimant an injunction?
(4) Has the claimant considered all material circumstances in deciding to seek an
injunction?
(5) Will the defendant comply with the enforcement notice without an order?
(6) Should relief be deferred pending the outcome of the planning appeal?
(7) Proportionality
(8) Should relief be given against the second and third defendants?
(9) The period within which there should be compliance.