QUEENS BENCH DIVISION
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Great North Eastern Railway Limited |
Claimant |
|
- and - |
|
|
Gary Neil Hart And Secretary of State for Transport, Local Government and the Regions And Network Rail Infrastructure Limited (and consolidated proceedings commenced by Network Rail Infrastructure Limited Action HQ02X00890) |
Defendant/Part 20 Claimant First Part 20 Defendant Second Part 20 Defendant |
____________________
Mr I. Burnett QC and Mr W. Hoskins and Mr A. Edwards (instructed by The Treasury Solicitor) for the First Part 20 Defendant
Hearing dates : 6th – 15th October 2003.
____________________
Crown Copyright ©
Mr Justice Morland : Judgment
"The path of the Land Rover on leaving the motorway can be very accurately determined from a series of tyre marks which ran from a shallow angle along the embankment backing the southern side of the road.
The first point at which the vehicle struck the kerb at the edge of the hard shoulder was around 50 metres east of the beginning of the safety barrier. Logically, the first tyre to strike the kerb would have been the front nearside tyre of the land Rover.
The angle at which the Land Rover/trailer combination moved along the embankment did not vary to a great extent. This is surprising given the steepness of the slope. What is even more remarkable is the fact that the Land Rover did not roll over. This vehicle has a very high centre of gravity and is far less stable than a conventional motorcar. It may well be that the presence of the trailer played some part in preventing roll over taking place, particularly if the trailer swung round and was literally crabbing along the embankment.
At the outset the tyre marks were fairly closely grouped together consistent with the vehicle/trailer running parallel to each other and without any significant rotation. As the combination moved down the embankment the distance separating the marks increased. It is probable that the combination began to jack-knife at that point.
The position of the Land Rover at the point of impact with the GNER train can be precisely determined.
The evidence indicates that the tailgate of the Savannah estate opened as the combination came to rest. That tailgate was struck a glancing blow by the passenger train and the whole assembly was then distorted and displaced in a southerly direction.
A large proportion of the Land Rover came to rest clear of the actual railway line. The front of the Land Rover overhung the eastern rail line."
"The Land Rover's nearside front wheel appears to have struck the kerb on the nearside edge of the westbound carriageway at a point approximately 50 metres in advance of the terminal end of a safety fence that is connected to the parapet of Little Heck Bridge.
The vehicle then appears to have proceeded at a shallow angle to the kerb before the offside wheels struck the kerb approximately 24 metres in advance of the safety fence terminal.
From each point of contact, rolling wheel tracks through the grass on the verge identify the subsequent course of travel. These marks were very clear at the time of my site inspection and are readily observable in the data obtained by the three dimensional scanning laser system, as well as in photographs taken of the scene around that time.
The wheel tracks were remarkably straight as they crossed the verge at a shallow angle (measured as being between 5 and 6 degrees to the normal direction of travel along the motorway).
Due to its shallow angle of travel, the vehicle combination passed by the terminal end of the safety fence relatively close to it. Had the safety fence been approximately 7 metres longer or more, then the vehicle combination would have struck it.
After passing by the end of the safety fence and travelling behind it, the vehicle combination descended the highway embankment, which is approximately 3.5 metres high at this point.
The vehicle combination broke through the wooden post and rail boundary fence between the highway and adjacent private land at the foot of the motorway embankment approximately 17 metres before the intersection of that fence with the similarly constructed boundary fence of the East Coast Main Line (ECML) railway, which passes beneath Little Heck Bridge.
The vehicle combination continued through the boundary fence of the railway, dropped down into the railway cutting and finally came to rest fouling the ECML, where it was struck by a passenger train travelling south to London.
In all, the vehicle combination travelled approximately 95 metres between leaving the carriageway and coming to rest on the railway.
In my opinion and experience there is nothing at all unusual in the design and layout of the pertinent section of the M62 Motorway and there is little to distinguish it from many other lengths of motorway and/or many other motorway bridges over railways elsewhere in the UK.
When considering the 6 year PIA data for the westbound carriageway between Marker Posts 147/0 and 148/0 only (i.e. the 1 kilometre length including Little Heck Bridge, which is adjacent to Marker post 148/1), it can be seen that no PIAs are recorded.
Therefore, it can be concluded that the PIA rate for the section of the westbound carriageway of the M62 Motorway around Little Heck Bridge during the 6 year period up to 31 December 2000 (i.e. up to two months prior to the material incident occurring) is significantly less that the national average for motorways and, in my opinion, does not warrant any cause for concern. "
"Definitions, types and uses of Safety Fences and Barriers
3.1 The objective of installing safety fences and barriers within a highway is to reduce the consequences of vehicles leaving the carriageway and entering areas where it would be unsafe to travel.
3.2 A safety fence is intended to absorb some of the energy impact caused by an errant vehicle striking it and to redirect the vehicle within a narrow angle to follow the line of the fence so that it does not gyrate or overturn
A safety barrier is intended to provide containment without significant deflection or deformation under impact, and to redirect errant vehicles along the line of the barrier in the direction of traffic movement.
3.3 Tensioned Steel Beam.
3.3.1 Tensioned Corrugated Beam (TCB).
3.3.1.1 This consists of "W" section beams, used single or double sided, attached to "Z" section posts by shear bolts and tensioned between anchorages. These safety fences may also be attached to angled brackets. This type of safety fence shall be used on central reserves and where other than short lengths are necessary on verges.
3.3.1.2 A TCB safety fence shall not be used:-
(a) Where the length of fence between anchorages is less than 45m,
3.4 Untensioned Steel beam
3.4.1 Open Box Beam (OBB)
3.4.1.1 This is a trapezoidal section beam, 150mm x 200mm and may be used either single- or double-sided attached to stronger "Z" section posts than those used in tensioned systems. OBB safety fences shall be used for providing protection at obstructions over short lengths and/or where space for deflection is limited.
Criteria for Provision of Safety Fences and Barriers.
4.1 General.
4.1.1 Safety fences shall be installed on all new trunk roads where speeds of 50 mph or above are allowed and for which the circumstances described in Paragraphs 4.2, 4.3.1 and 4.3.2 herein apply.
4.1.2 Where there are exceptional local hazards, involving either layout or the roadside, safety fences may be needed as described in Paragraphs 4.2 and 4.3.2.
4.2 Verges
(a) On embankments 6m or more in height;
(b) On other embankments where there is a road, railway, water hazard or other feature (e.g. a subway entrance) at or near the foot of the slope"
"To prevent direct impact between a vehicle and the end of the vehicle parapet facing the traffic on the nearside, a safety fence shall be provided on each approach towards the bridge.
The safety fence shall be at least 100 ft long and shall continue the line of the traffic face of the parapet."
and of which 205(ii) says:-
"Where no effective alternative arrangements exist to prevent a vehicle from leaving the bridge approach and falling onto the railway below, a safety fence shall be provided on each approach towards the bridge, as in the cases of Group P.1 and P.2 parapets."
"Criteria for the Provision of Safety Fences.
2 Safety fences are normally recommended only on major roads where speed restrictions permit 80km/h (50 mph) or above and for which the circumstances below apply
A. Verges.
a. On embankments 6.0m or more in height.
b. On embankments where there is a road, railway, river, or abnormal hazard at the foot of the slope.
7. Tensioned beam safety fences are to be used in preference to untensioned types except: -
a. Where the length of fencing is less than 45m between anchorages
There are 2 approved types: -
1. The tensioned corrugated beam (TCB) developed by the Transport and Road Research Laboratory."
"3.17 Safety Fences.
Safety fences are needed where it would be particularly hazardous for vehicles to leave the road…
They are necessary on both sides of roadways on embankment, where the height is 20ft or more, or where there is a road, railway or river at the foot of the slope…..
Safety fences should be designed to redirect a colliding vehicle without overturning, and to minimise the risk of rebounding with obvious danger to following traffic...
It is important that the ends of safety fences should be carried into the ground or turned away from the line of approaching traffic."
"Guard Fences
1. It has now been agreed that at points of special hazard, guard fences (which should not be confused with pedestrian guard rails between carriageway and footpath) maybe provided…
4. Guard fences may also be used at points of special danger, e.g. where there is a road, railway or river at the foot of the embankment,…
5. The precise length of guard fence should be decided from site inspection but the installation should commence sufficiently in advance of the hazard to give protection to vehicles leaving the road at a narrow angle. Short lengths of guard fence should be avoided."
"Q. You do not mention in your qualifications and professional experience any direct experience of designing bridges over railways?
A. No, I do not have any direct experience of designing bridges over railways.
Q. Or safety fencing leading up to them?
A. I have been involved in the design of safety fences on a number of occasions, but just over the years, as I have said, my involvement in detailed design has diminished.
Q. But my question was whether you had any direct experience of designing safety fences leading up to bridge parapets.
A. Yes, I have done that but not on a trunk road.
Q. Have you at any time been concerned to look directly at the standard applying to bridges and bridge parapets, that is BE5 and its successor?
A. I think this is the first time that I can recall of where it has been particularly associated with the approach of a bridge parapet."
"As to the hypothetical case against the county council, there is, as we have said, authority for the proposition that a highway authority constructing a road for the public use under statutory powers owes a duty to the public to take reasonable care to construct the road properly, so that it will be reasonably safe for the purposes for which it is intended to be used"
and at page 460
"It would not have sufficed for the purposes of a charge of negligence against the county council merely to show that the system of traffic signs or the lighting arrangements might have been improved upon."
"Q. Would you agree that the precise length of the safety fence must be determined by the prevailing circumstances at the individual location?
A. Yes, indeed.
My experience really starts in the early 1970s and certainly we would not design a bridge in my experience, since I have been involved, purely by reference to drawings in the office. That is not my experience"
"I have expressed my concern over the adequacy of the containment standards for crash barriers and bridge parapets where motorways and highways run close to, or cross over, railway tracks.
At Leyland, a car travelling along the M6 left the roadway, travelled down the motorway embankment and across the high speed electrified main lines before coming to rest on the slow lines. The point where the car left the road was some 60 yards short of the crash barrier erected at bridge No. 95 between Euxton Junction and Leyland Station. The incident, which, as you will appreciate, could have had very serious consequences, has raised the whole question of the extent of the crash barriers. So far as I am aware, there are no statutory obligations placed upon the D.o.E in respect of the provision of crash barriers which is apparently left to the discretion of individual highway engineers. I should be grateful for information as to the standards which are applied or the guidance given to these engineers to ensure a consistently acceptable level of protection."
"The extent of the safety fence is a matter for the decision of the responsible Highway Engineer and the recommendation quoted as you imply, is advisory and not statutory."
"Mr Montague also contended that the failure to erect crash barriers at a roundabout would be evidence of negligence by the DOE, since it was foreseeable that road users could leave the road at this point. Once that factual proposition is accepted (and if the presence of a suitable barrier would have prevented this accident), the difficulty of foreseeing the precise way in which the injury was caused does not bar the plaintiff: Hughes .v. Lord Advocate [1963] AC 837, Harvey .v. Singer [1990] SC 155. Although this alleged failure is a fault of omission, the highway authority would not, if otherwise found negligent, escape under the cloak of non-feasance, provided it was responsible for introducing the roundabout."
"All motorists are guilty of errors of one kind or another, and I think it would be quite unreal if roads were designed on the assumption that no driver would ever err. Indeed, as Lord du Parq put it in London Passenger Transport Board v. Upson [1949] AC 155, where the quotation appears at p.176: "A prudent man will guard against the possible negligence of others when experience shows such negligence to be common"."
"The risk-ranking tool developed for use on high-speed roads was used to rank the M62 Little Heck Bridge. It was decided to ignore the protective gabion walls alongside the toe of the embankment for the purpose of the ranking. The Highways Agency's Maintaining Agents, WSP Civils, have reported a risk-ranking score of 62 for this site. The low score, well below the agreed advisory threshold score of 70 (see paragraph 6.12 above), confirms that the scale of the Selby incident and the extensive media coverage which has raised the public expectation of some additional preventative measures being required at this site, the Highways Agency has decided to subject the site to a detailed site-specific risk assessment. Notwithstanding the low score of the risk-ranking tool the site was reassessed using the assessment procedure described above. The results did not justify any additional preventative measures either in safety or cost terms. The risk assessment procedure lists bands of scores based on the risk-ranking score set against a guideline of the indicative expenditure, that is, the spend that could typically be justified for a site with a score in that band. The guidance suggests that for sites other than those with very high risk-ranking scores, of 100 or more, expenditure should be assessed alongside other road and rail safety needs. For sites with risk-ranking scores between 80 and 99 the indicative expenditure that might typically be justified ranges from £200 to a maximum of £5000 at any one site. Typically for sites scoring less than 80 there is no indicative expenditure justified. However, the notes for guidance encourage engineers to use their discretion and go beyond the suggested indicative expenditure if there is a simple, cost effective safety benefit that could be provided.
The risk ranking process has confirmed the findings of the Highways Agency Working Group (HAWG) and the Health and Safety Commission's Working Group (HSCWG) that the M62 Little Heck Bridge site was typical of a site with a very low risk of a vehicle leaving the nearside and accessing the railway. The HSCWG commented in their report that the risk of a death caused by a vehicle leaving any road and being struck by a train was small compared to other railway risks and tiny compared to other road risks. The accident was caused by an extremely unlikely series of events that was initially triggered by a driver who fell asleep whilst driving. The incident has served to identify a far more significant problem at sites where single carriageway local roads cross railways and where accident records demonstrate the risk of incursion is appreciably greater than that for trunk roads and motorways.
The risk-ranking and further assessment of the Highways Agency's railway bridge sites was carried out as a direct result of and in the aftermath of the Selby Rail crash. There is no evidence of any particular concern being expressed about the safety of the Highways Agency's railway bridge sites or any specific accident data that pre-existed these tragic events. I believe that the results of the risk-ranking and second stage risk assessment procedure that have been used to assess the risk of errant vehicles accessing the railway line at Little Heck Bridge demonstrate that there is no justification in safety or cost terms for any additional protection measures. Therefore, it follows that the current length of safety barrier in advance of the parapet reduces the risk of an errant vehicle accessing the railway line to an acceptably low level for both road and rail users. Any additional protection measures would have to be justified on the basis of the need to allay understandable public concern following the tragic events at this site."
"there would be an overall reduction in safety if funds were diverted from other safety measures to safety barrier extensions with a lower NPV" (Net Present Value)"
"At various stages throughout the development of the risk ranking tool trials took place at several overbridge sites to check that the tool was providing meaningful results when comparing one bridge site with another. The tool was applied to Little Heck motorway bridge and the risk at that site was found to rank at or near the bottom of the list when compared with other bridges. For example, I applied version 3 of the risk-ranking tool to 25 sites in North Yorkshire and summarised the results on 3 September 2001. Bridge 8A came 24/25 in risk ranking. I then also applied the Durham County Council developed tool (as it then was) to the same 25 bridges and Bridge 8A came out bottom of the list. In October 2001, version 7 of the combined tool was applied to the same 25 bridges plus 3 Durham sites to come up with a ranked list. On that occasion, Bridge 8A came out 25th of 28. I consider this to be consistent with my judgement of the relative levels of risk at a large number of overbridge sites that I have seen. Even if the risk ranking tool had been in use prior to the accident at Great Heck, I do not believe that any physical works would have been deemed necessary at Little Heck motorway bridge."
"During 2001, Railtrack, in conjunction with the County Surveyors' Society (CSS) (represented by Durham and North Yorkshire County Councils), developed a tool for the ranking of rail overbridges according to incursions risk. This tool. which comprises a set of 14 questions about the road, rail and road/rail interface elements of the bridge site, is currently being applied to all rail overbridges on the national rail network by teams from Network Rail and local highway authorities.
These bridges that achieve a score of 90 or more in the risk ranking exercise will be subjected to a second stage assessment to identify the costs and benefits of risk mitigation options. The figure of 90 was chosen after some research was undertaken by Railway Safety, indicating that 98% of the risk from incursions occurred at sites scoring 90 or more. The highest figure that I am aware of for any bridge risk ranked to date is 121. I understand from WS Atkins that the Highways Agency have provided a ranking score for Bridge EC2M/BA at Heck of 62, which suggests that no further work is required. The individual factor scores for factors 1 to 14 are 6, 1, 1, 6, 4, 1,5, 1, 1, 1, 2, 16, 5, and 12. From factor 5, it appears that the bridge has been scored with reference to the gabions put in place by the Highways Agency after the accident. The score for factor 5 could not exceed 10, so that an increase to the maximum of 10 for this factor would give a total of 68, still well below the level where we would be considering action was required."
"The principal numerical conclusions in this report are that in Great Britain as a whole there are estimated to be an average of about 0.1 rail occupant fatalities and 0.5 road vehicle occupant fatalities per year in collisions between trains and road vehicles not at level crossings. This risk is distributed over many thousands of sites where such collisions are possible. Some sites will present greater risks than others, but it is clear that the risk at any one site must be very small."
"It is my opinion that overbridge EC2/8A, with the level of protection provided at the time of the Great Heck accident, poses a low risk relative to other overbridges on the network".
"Overbridge EC2/8A has been allocated a low relative risk score using both the original Defendant risk ranking methodology and my revised version (see Section 7.3 and 7.4.2)."
"The risk at overbridge EC2/8A is less than one hundredth of the risk at overbridges where action is recommended (based on my version of the Defendant scoring methodology – see Section 7.4.1)."
"In my opinion, the site would not have been identified for further action as a result of more detailed risk ranking;"
"And therefore no further action would have been taken at this site."
"In my view the creation of a duty of care upon a highway authority, even on grounds of irrationality in failing to exercise a power, would inevitably expose the authority's budgetary decisions to judicial inquiry. This would distort the priorities of local authorities, which would be bound to try to play safe by increasing their spending on road improvements rather than risk enormous liabilities for personal injury accidents. They will spend less on education or social services. I think that it is important, before extending the duty of care owed by public authorities, to consider the cost to the community of the defensive measures which they are likely to take in order to avoid liability. It would not be surprising if one of the consequences of the Anns case and the spate of cases which followed was that local council inspectors tended to insist upon stronger foundations than were necessary. In a case like this, I do not think that the duty of care can be used as a deterrent against low standards in improving the road layout. Given the fact that the British road network largely antedates the highway authorities themselves, the court is not in a position to say what an appropriate standard of improvement would be. This must be a matter for the discretion of the authority. On the other hand, denial of liability does not leave the road user unprotected. Drivers of vehicles must take the highway network as they find it. Everyone knows that there are hazardous bends, intersections and junctions. It is primarily the duty of drivers of vehicles to take due care. And if, in the case of Mrs. Wise, they do not, there is compulsory insurance to provide compensation to the victims. There is no reason of policy or justice which requires the highway authority to be an additional defendant."
"The starting point is that the council did not create the source of danger. This is not a case of a highway authority carrying out road works carelessly and thereby creating a hazard".
Lord Hoffmann said at page 943E:-
"The judge made no express mention of the fact that the complaint against the council was not about anything which it had done to make a highway dangerous but about its omission to make it safer."
"28 Here, by contrast, the starting point must surely be that the defendants did create the source of danger. They it was who required this footpath to be constructed. I cannot accept that in these circumstances they were entitled to wash their hands of that danger and simply leave it to others to cure it by improving the sightlines. It is one thing to say that at the time when the defendants required the construction of this footpath they had every reason to suppose that the improvements along The White Cottage frontage would ultimately allow it to be safely opened and used: quite another to say that they were later entitled to stand idly by whilst, as they must have known, the footpath lay open to the public in a recognisably dangerous state."
"The footpath was not dangerous per se. The danger lay in conjunction of the end of the footpath and a blind bend on to which it exited, just as in the present case the danger lay in the conjunction of the motorway and the railway line. In both cases the danger had been created by the relevant public authority."
"There are also areas in the carriageway face of the south parapet where the coating has been "pushed" outwards by the concrete (areas 25mm diameter approx.). This could be due to the continued expansion of the gelatinous silica gel disrupting the concrete (see photo ref. K). The situation does not appear to have deteriorated significantly since the previous principal inspection.
The connecting plates of the safety fencing to the parapets are all severely corroded and require attention. This work will be carried out as part of a major maintenance roadwork scheme programmed for early 1993. The south west corner of the concrete parapet has been damaged exposing a fixing bolt and requires repairing (see photo ref. M and N).
The safety fence adjacent to the parapet connector NW corner has been slightly damaged by vehicle impact and there is slight damage to the concrete parapet below the connector at this point. This damage consists of spalled concrete although there is no reinforcement exposed.
There is a section of solid aluminium infill panel missing (south west end) due to accident damage by an unknown vehicle (see photo ref. L.). This damage has been repaired since the inspection was carried out.
The steel parapet paint system and galvanising is breaking down in some areas and corrosion is in evidence and some localised remedial work is required
The addition of the solid aluminium panels will cause maintenance problems to the "hidden" sections of parapet and full inspection of these areas was not possible.
The base plates of the parapet posts appear to be the source of rust staining to the parapet plinths and, as such, require attention."
"I discussed the problem with safety fence either side of gravel Pit and Little Heck bridges verges. Our site instruction asked for corrugated either side with a full height anchor at the parapets. Colin Philipson stated that tension corrugated beam must be a minimum of 45m long which is much longer than the original open box design. It was agreed with consultation with Andy Arendal to change the safety fence to open box but still have a full height open box anchor. Colin informed me later it would take 6 weeks to obtain the full height anchors to the new specification. It was agreed to heed the full height anchors specified in the old specification which there are in stock. The only difference is that the posts are socketted."
"I have, however, spoken to John Wharton who was Contracts Manager for Tarmac during the period of time when that company carried out all maintenance and repair work to safety fencing on behalf of Humberside County Council. He remembers an accident in which a heavy goods vehicle carrying a large electrical generator left the westbound carriageway of the M62 and struck the ramped terminal of the approach safety fencing to the Little Heck Bridge. The vehicle sustained a broken front axle but he believes that the driver was unhurt. Tarmac were required to remove part of the existing safety fencing to enable the vehicle to be pulled back up the embankment and removed from the highway by a recovery contractor probably acting on instructions from the Police. Following removal of the vehicle Tarmac repaired the safety fencing. Mr Wharton told me that all records from this time have been destroyed so he is unable to be more precise about the date of the repair. He was, however, sure that it was after the completion of the major maintenance work carried out by Tarmac on the eastbound carriageway. This therefore puts the date some time after April 1995 but before April 1996 when Amey Construction took over as maintenance contractor for the motorway.
A further source of information I have checked is the accident record for the period 1994 to 1996 and there are no recorded accidents (that is personal injury accidents) within 1.2 km of the bridge within the period. This is consistent with the fencing being damaged as a result of an accident in which there were no injuries that would have to be reported through the "Stats 19" procedure."
"(2) A highway authority may provide and maintain in a highway maintainable at the public expense by them which consists of or comprises a carriageway, such raised paving, pillars, walls, rails or fences as they think necessary for the purpose of safeguarding persons using the highway.
(4) The powers conferred by the foregoing provisions of this section to provide any works include power to alter or remove them."
"In my judgment the ex turpi causa defence is not available as an answer to a claim for contribution under the Act of 1978. The specific purpose of that Act, as of the Act of 1935 before it, was to enable claims for contribution to be made as between parties who had no claim to contribution under the general law. To permit the ex turpi causa defence to be relied upon as an answer to such a claim would, in my view, narrow to a substantial extent the deliberately wide wording of section 6(1) of the Act of 1978 and would, in effect, make a claim for contribution subject to a condition precedent which is not to be found in the Act. Moreover, section 2(1) and (2) give the court ample power to fix the amount of the contribution at a level, including a zero level, which takes account of all the factors which, in relation to common law claims, are relevant to the ex turpi causa defence."