QUEEN'S BENCH DIVISION
BIRMINGHAM DISTRICT REGISTRY
MERCANTILE COURT
B e f o r e :
____________________
AXA INSURANCE UK PLC | Claimant | |
- and - | ||
THERMONEX LIMITED (in liquidation) | Defendant |
____________________
Crown Copyright ©
Introduction
(a) Mr Tom Davison of DAC Beachcroft, solicitors for Axa, and accompanying exhibits TD 1 and TD 2;(b) Mr Pierre Johnstone of Axa's large loss unit;
(c) Mr David Aulton, the Managing Director of Thermonex until it went into liquidation;
(d) Mr Mark Docker, a process server.
(a) the four witness statements referred to above;(b) the Particulars of Claim (exhibit to witness statement of Mr Docker);
(c) the following extracts from the Policy (TD 1/29ff)
(i) general insuring clause and choice of law (TD 1/29)(ii) General Conditions 3 and 15 (TD 1/30, 33)(iii) Public Liability section (TD 1/126) and especially clauses 1 and 3 (TD 1/126-7), Exclusions 2, 3 and 6 (TD 1/128-9) and Special Conditions 1 and 4 (TD 1/132)(iv) Contractors All Risks section (TD 1/134) and especially clauses 1 and 2 (TD 1/134-5) and Exclusion 10 (TD 1/135)(d) in the Irish proceedings, the Statement of Claim (TD 2/69-87), the Notice for Particulars (TD 2/158-71), the Replies to Particulars (TD 2/172-81) and Thermonex's Defence (TD 2/535-45);
(e) the correspondence between Gem's solicitors Matheson Ormsby Prentice ('MOP') and Axa: TD 1/5-9, 22, 23 and 2/1-3. Gem is an Irish construction company seeking to claim indemnity from Axa as insurers of Thermonex.
(f) the correspondence between MOP and DAC Beachcroft: TD 1/10-13 and 25
(g) the correspondence between DAC Beachcroft and Foreman & Co: TD 1/1-5
Summary of Axa's Position
(a) in respect of property comprising the permanent or temporary works undertaken by it and would be excluded by virtue of exclusion 2(c) of the PL section (TD 1/128), and/or(b) in respect of the cost or value of the works executed by it or the replacement, repair, rectification or reinstatement thereof and any claim would be excluded by virtue of exclusion 3(a) of the PL section (TD 1/129), and/or
(c) as regards the contractual claims including the claim for breach of warranty, would be excluded by virtue of exclusion 6 of the PL section (TD 1/129).
Position of Thermonex
Position of Gem
Summary Judgment
(a) the Court must consider whether the respondent has a 'realistic' as opposed to a 'fanciful' prospect of success;(b) a realistic claim is one that is more than merely arguable;
(c) in reaching its conclusion the court must not conduct a mini-trial;
(d) this does not mean that a court must take at face value everything that a party says in statements before the court. In some cases it may be clear that there is no real substance in factual assertions made, particularly if contradicted by contemporaneous documents;
(e) however, in reaching its conclusion the court must take into account not only the evidence actually placed before it on the application for summary judgment, but the evidence that can reasonably be expected to be available at trial;
(f) although a case may turn out at trial not to be really complicated, it does not follow that it should be decided without the fuller investigation into the facts at trial than is possible or permissible on a summary judgment hearing. Thus the court should hesitate about making a final decision without a trial, even when there is no obvious conflict of fact at the time of the application, where reasonable grounds exist for believing that a fuller investigation into the facts of the case would add to or alter the evidence available to a trial judge and so affect the outcome of the case;
(g) if one part of the claim is to go to trial it may be more appropriate for the entirety of the claims to go to trial rather than divide the history up and strike out other parts of it.
Negative declaratory relief
The Policy
Your Policy
The Company in consideration of the payment of the premium shall provide insurance against loss destruction damage or liability for injury or damage occurring at any time during the Period of Insurance (or any subsequent period for which the Company accepts a renewal premium) in accordance with the Sections of the Policy shown as operative in the Schedule subject to the exclusions provisions and conditions of the Policy
The law applicable to this Policy
You are free to choose the law applicable to this Policy Your Policy will be governed by the law of England and Wales unless You and We have agreed otherwise
General Conditions
…
3 Claims Conditions
1) In the event of any loss destruction or damage or event likely to give rise to a claim under this Policy the Insured shall
a) notify the Company immediately
…
d) deliver to the Company at the Insured's expense
(i) full information in writing of the property lost destroyed or damaged and of the amount of loss destruction or damage
ii) details of any other insurances on any property hereby insured within 30 days after such loss destruction or damage or such further time as the Company may allow
iii) all such proofs and information relating to the claim as may be reasonably required
…
2) No claim under the Policy shall be payable unless the terms of this condition have been complied with
…
15 Condition Precedent
It is a condition precedent to any liability on the part of the Company under this Policy that a) the terms hereof so far as they relate to anything to be done or complied with by the Insured are duly and faithfully observed and fulfilled by the Insured and by any other person who may be entitled to be indemnified under this Policy …
Public Liability – Building and Allied Trades Section (TD 1/126)
1. Definitions
…
Business
the business stated in the Schedule conducted by the Insured at or form premises in Great Britain Northern Ireland the Channel Islands or the Isle of Man …
…
Territorial Limits
a) anywhere within Great Britain Northern Ireland the Channel Islands or the Isle of Man other than Offshore
b) member countries of the European Community other than Offshore in connection with temporary visits undertaken in the course of the Business by any person normally resident in the territories described in a) above
...
Works Executed
Works executed including goods or materials used by or on behalf of the Insured in the course of the Business
…
3. Indemnity (TD 1/127)
The Company will indemnify the Insured against all sums that the Insured shall become legally liable to pay as damages and costs and expenses in respect of accidental
a) injury to any person
b) loss of or damage to material property
c) nuisance or trespass obstruction loss of amenities or interference with any right of way light air or water
…
occurring within the Territorial Limits during the Period of Insurance and happening in connection with the Business
…
Exclusions (TD 1/128-9)
The Indemnity will not apply to legal liability
…
2. Property under Insureds Control
in respect of loss or damage to
…
c) property comprising the permanent or temporary works undertaken by the Insured in the course of any contract or agreement and which are under the control of the Insured or for which the Insured is responsible
…
3. Rectification Costs
a) in respect of the cost or value of any Works Executed or replacement repair removal rectification or reinstatement thereof where legal liability arises from a defect in or the unsuitability of such Works Executed
…
6. Liability under Agreement
assumed by the Insured under agreement unless the conduct and control of all claims is vested in the Company but indemnity shall not in any event apply to
…
c) liability which attaches solely by reason of an agreement relating to the performance of work outside Great Britain Northern Ireland the Channel Islands or the Isle of Man
…
Special Conditions (TD 1/132)
1. Observance of Terms
It is a condition precedent to any liability on the part of the Company under this Section that the terms hereof so far as they relate to anything to be done or complied with by the Insured shall be duly and faithfully observed
…
4. Notification of Claims
In the event of any occurrence which may give rise to a claim under this Section the Insured shall immediately
a) give written notice with full particulars to the Company
b) forward to the Company upon receipt every letter claim writ summons or process
Contractors All Risks Section
1. Definitions (TD 1/134)
…
Territorial Limits
Shall mean anywhere within Great Britain Northern Ireland the Channel Islands or the Isle of Man
2. Indemnity
The Company agrees (subject to the terms exceptions and conditions contained herein or endorsed hereon) to indemnify the Insured by payment or at its option by reinstatement or repair in respect of loss or damage to the property described in the Schedule to this Section
…
3. The Property Insured
…
The Permanent or Temporary Works
The Permanent or Temporary Works executed in performance of the Contract and Materials for use in connection therewith
…
4. Exclusions (TD 1/135)
This section does not cover
…
10. Defective Design Material or Workmanship
The cost necessary to replace repair or rectify any of the Property Insured which is in a defective condition due to a defect in design plan specification materials or workmanship notwithstanding anything contained herein to the contrary this exclusion shall not apply to the remainder of the Property Insured which is free of such defective condition but is damaged as a consequence of such defect
The Development
(a) as regards Phase 1, by a contract dated 9 December 2004 (TD 2/189) between Swindon Investment Company Limited ('Swindon') as employer and Gem as contractor, Gem agreed to construct 33 Golf Villa residences at the development and by a Purchase Order dated 7 January 2005 (TD 2/351) Gem sub-contracted the design, supply and installation of basements at 23 of these residences to Orchardville Limited trading as Thermonex ('Orchardville'), a company incorporated in Ireland whose registered office was at 39 The Studio, Ballyreddin, Bennettsbridge, County Kilkenny.(b) As regards Phase 2, Gem entered into a further contract with Swindon dated 8 December 2005 (TD 2/250) for the construction of a further 49 villas and Gem sub-contracted the design, supply and installation of basements at 29 of those villas to Orchardville by a Purchase Order dated 3 February 2006 (TD 2/384).
(c) As regards Phase 3 Gem entered into a contract with Carton Residential Developments Limited ('Carton Developments') dated 3 November 2006 (TD 2/295) for the construction of a further 36 villas and Gem sub-contracted the design, supply and installation of basements at 26 of those villas to Orchardville by a Purchase Order dated 3 November 2006 (TD 2/386).
The Irish Proceedings
(a) In or about 2004 Gem entered into discussions and correspondence with Orchardville and Thermonex in the course of which Orchardville and Thermonex proposed the use of the ThermoneX X-Concrete system for the basements at the site and represented that the system was independently certified and accredited by the Building Research Establishment and that each basement carried a 10 year structural waterproofing guarantee. Gem understood that the product would be supplied by Orchardville and Thermonex and it liaised with Mr Mulligan of Orchardville and Mr Burr of Thermonex in relation to the design of the basements (SoC paragraphs 7-8).(b) Gem appointed Orchardville and Thermonex as its sub-contractor in relation to the design, fabrication and installation of the basements at the site for each of Phases 1-3 and to provide a 10 year guarantee. Both Orchardville and Thermonex were therefore responsible for the entire design of the basements (SoC paragraphs 11-12).
(c) On the basis of prior discussions and representations, in January 2005 Gem gave a purchase order to Orchardville in respect of phase 1. Although Gem constructed the basement slab all other design and works in respect of the basements was done by Orchardville and Thermonex or their sub-contractors (SoC paragraphs 15-17).
(d) Gem believed that it was contracting with Orchardville and Thermonex. Further Orchardville and Thermonex owed Gem a duty of care in tort in respect of the design and works, and/or Orchardville acted as agent for Thermonex and/or Thermonex acted as a sub-contractor to Orchardville (SoC paragraphs 18-21).
(e) On the basis of prior discussions and representations, in February 2006 and November 2006, Gem issued purchase orders to Orchardville in respect of phase 1 and 2. Gem says that Orchardville and Thermonex owed it the same duties as pleaded in respect of phase 1 and/or that the relationship between Orchardville and Thermonex was the same as for phase 1 (SoC paragraphs 24-29 and 32-37). As regards phase 3 Gem specifically requested that a collateral warranty be issued on a basement by basement basis (SoC paragraph 33).
(f) In May 2006 a leak was reported to Orchardville and Thermonex in relation to one of the phase 1 basements (SoC paragraph 30). Thereafter further leaks were reported (SoC paragraph 40). Gem required Orchardville to carry out remedial works but it was unable to so satisfactorily and Gem took over the remedial works (SoC paragraph 39).
(g) Thermonex provided the warranties in relation to each basement and each warranty was signed by an authorised signatory of Orchardville (SoC paragraph 41).
(h) As a result of the defective works and/or design conducted in respect of the basements, they suffered from extensive leaks which caused loss and damage to Gem and exposed it to claims by Carton Developments and/or purchasers (SoC paragraph 42).
(i) The structural design of the basements alternatively the ThermoneX X-Concrete basement units was flawed on several grounds including 11 grounds set out in the pleading (SoC paragraph 42).
(j) The workmanship on the basements alternatively the ThermoneX X-Concrete basement units was flawed on several grounds including three set out in the pleading (SoC paragraph 42).
(k) Each of Orchardville and Thermonex was in breach of contract in failing to ensure that the design, fabrication, supply, works supervision and installation of the basements alternatively the ThermoneX X-Concrete basements units was carried out competently and in a workmanlike manner using specified and proper materials, in accordance with the contract and the relevant designs and industry guidelines and to the standard that had been represented so that the basements were fit for purpose and suitable for the relevant conditions (SoC paragraph 43).
(l) Each of Orchardville and Thermonex was in breach of the warranties in failing to execute remedial works to eradicate water penetration at basements affected by leaks (SoC paragraph 43).
(m) Each of Orchardville and Thermonex was guilty of negligence and breach of duty (including statutory duty) in failing to ensure that the design, fabrication, supply, works supervision and installation of the basements alternatively the ThermoneX X-Concrete basements units was carried out in the same manner and to the same standard as alleged in relatiin to the contractual claim above (SoC paragraph 44).
(n) Each of Orchardville and Thermonex was guilty of negligent misrepresentations in relation, inter alia, to the performance of the ThermoneX X-Concrete system and/or as to the manner in which the works would be done and principally because the basements designed and provided by them did not meet the standard represented by Orchardville at the outset of the development (SoC paragraph 45).
(o) Each of Orchardville and Thermonex made an unjustified gain at the expense of Gem in that they have not provided the design and system which they were obliged to provide and/or failed to carry out their obligations under the warranties (SoC paragraph 46).
(p) By reason of these breaches of contract, negligence, breaches of duty and misrepresentations on the part of Orchardville and Thermonex Gem has suffered loss and damage in the sum of €3,817,656.06 plus general damages measured by reference to potential claims by third parties (SoC paragraph 47). The special damages claimed by Gem included a total sum of €1,952,405.08 in respect of remedial works to the basements (SoC paragraph 42).[15]
(q) The relief sought included declarations that Orchardville and Thermonex were obliged to indemnify Gem in respect of all losses etc arising from the design, supply and installation of the basements including the costs of all remedial works executed and compensation paid by Gem as well as damages for breach of contract, negligence, breach of duty (including statutory duty) and negligent misrepresentation and restitution (SoC prayer).
(a) was appointed by Gem as a sub-contractor on the development to design, fabricate or install the basements and/or to provide the warranties;(b) was responsible for the design of the basements;
(c) owed any duty of care to Gem in respect of the design and works;
(d) had ever been a sub-contractor to Orchardville.
Axa's Case
(1) The PL insuring clause(2) Restitutionary Claims
(3) PL Territorial Limits
(4) PL Exclusions
(5) CAR Exclusions
(6) Non/late Notification
(1) The PL insuring clause
'A public liability policy provides cover against liability to the public at large. By contrast private liability arises from contracts entered into between individuals. Public liability in this sense arises in tort; it does not and cannot arise only in contract. As a general rule a claim in tort cannot be founded upon pure economic loss. So the judge was right to say that the fact that this was public liability insurance was important and that such policies do not generally cover liability in contract for pure economic loss. It is a strong pointer to the meaning of the words used. Of course it is not conclusive: the wording may extend cover to third party claims in contract even for pure economic loss although one would expect it to say so clearly and for such insurance to be described as contract liability, financial or consequential loss cover.
…
Looking at the insuring clause it is common ground that the words "shall be liable at law" are wide enough to include liability in contract. But it is the following words which make clear that the cover is against liability in tort; there is nothing in the wording to indicate that liability in contract under a contract of indemnity such as this was intended to be included. A tort gives rise to a liability "at law for damages". Although a breach of contract does give rise to a liability at law for damages the critical question is what the liability must be for. The answer to this question is that the damages must be "in respect of" one or more of the classes of liability set out in (a) to (c). Each class of liability corresponds with a familiar class of liability arising in the law of tort, or its effect, from physical interference with a third party's person, property or property rights and is typical of the harm associated with a project of this kind.
'It therefore appears clear in respect of claims relating to construction projects that in order to bring a claim within a public liability policy it is necessary to show physical damage to property other than the property which is being constructed. Mere economic loss does not fall within the policy, nor does the cost of making good defects.'
(2) Restitutionary Claims
(3) Territorial Limits
(4) PL Exclusions
(a) it is a legal liability for loss or damage to property comprising the permanent or temporary works undertaken by Thermonex in the course of a contract with Gem where the works were under the control of Thermonex and it was responsible for them.(b) To the extent that Gem has particularised its claim for loss and damage, it is a claim for the costs of remedial or rectification works to the basements themselves. If Thermonex has any liability to Gem in respect of the costs of remedial or rectification works to the basements themselves, such liability arises from defects in works executed by Thermonex at the site and/or goods or materials used by Thermonex or from the unsuitability of works executed by Thermonex at the site and/or goods or materials used by Thermonex.
(c) To the extent that Thermonex has any liability to Gem by virtue of any agreement entered into by Thermonex and Gem, including the warranties, by reason of exclusion 6 of the PL section of the Policy Axa is not liable for any liability so assumed by Thermonex.
(5) CAR Exclusion
(6) Non/Late Notification
Conclusion
His Honour Judge Simon Brown QC
Specialist Mercantile Judge
Birmingham Civil Justice Centre
Clerks: Alison Wood & Caroline Norman
birmingham.mercantile@hmcts.gsi.gov.uk
Tel: (0121) 681 3035
Website: http://www.justice.gov.uk/courts/rcj-rolls-building/mercantile-court
8th August 2012
Note 1 See Mr Aulton’s witness statement at paragraphs 34-44 [Back] Note 2 At paragraphs 16-19 [Back] Note 3 The policy wording at TD 1/26ff was in fact issued in May 2006 after the renewal of Thermonex’s policy in April 2006 for the 2006/07 year. Axa has obtained the wordings which would have applied in the previous years and these are exhibited to the witness statement of Ms Pilkington. For the purposes of this application there are no material differences between the policy wordings at any time. [Back] Note 4 Still in force despite the passing of the 2010 Act which has yet to come into force. [Back] Note 5 See James Longley & Co v. Forest Giles Ltd [2002] Lloyds Law Reports (Insurance and Reinsurance) 421 [CA] and Tesco Stores Ltd v Constable [2008] Lloyd’s Rep IR 636 [Back] Note 6 See the witness statement of Mr Docker [Back] Note 7 The liquidator could have applied to stay the proceedings but chose not to do so. [Back] Note 8 In the interim Thermonex had set out its position in correspondence with the Court in January and February 2010 (TD 2/36-37) [Back] Note 9 See the witness statement of Mr Davison at paragraph 69 [Back] Note 10 See White Book volume 1 40.20.3 and Hayim & Ors v Couch [2009] EWHC 1040 at paragraphs 13– 18 [Back] Note 11 Padden v Arbuthnot Pensions [2004] EWCA Civ 582 [Back] Note 12 See, for instance, in an international context, Messier-Dowty v Sabena [2000] 1 WLR 2040 [Back] Note 13 See, for instance, Colinvaux & Merkin’s Insurance Contract Law paragraphs C-0700ff and D-0632 [Back] Note 14 See the Cyril Sweett report at TD 2/50. The remedial works were done in three phases between these dates. [Back] Note 15 As indicated above, by a subsequent report, dated 18 March 2011 (TD 1/47), commissioned on behalf of Gem by MOP in order to provide a valuation of the quantum of the works undertaken by Gem in connection with the remedial works required to the basements, Cyril Sweett concluded that the direct costs incurred by Gem up to July 2010 was €2,877,641.52 and that the entire costs incurred were €4,092,641.52.
[Back] Note 16 As a matter of English law the Court of Appeal has recently re-affirmed in Robinson v PE Jones (Contractors) Ltd [2011] 3 WLR 815 the general principle that the relationship between a builder and its immediate client is primarily governed by the contract between them and, absent any assumption of responsibility, the only tortious duty owed by a builder to its client is to take reasonable care to prevent any defect in the work causing personal injury or damage to other property of the client. However, it recognised that there may be circumstances where the builder assumes a responsibility to the client so as to give rise to a tortious duty of care in respect of economic loss. [Back] Note 17 James Longley & Co v. Forest Giles Ltd [2002] LLR (Insurance and Reinsurance) 421 per Potter LJ paras 17 -19. [Back] Note 18 See Goff & Jones: The Law of Unjust Enrichment (8th ed, 2011) paragraph 36-02ff [Back] Note 19 See Pilkington United Kingdom Ltd v CGU Insurance Plc [2004] Lloyd’s Rep IR 891 at paragraphs 63-65 per Potter LJ. [Back] Note 20 For a clause to have the effect of a condition precedent, it does not have to use those words but it does require wording which makes clear‘a conditional link between the assured’s obligation … and the underwriter’s obligation to pay the claim’, see Aspen Insurance UK Ltd v Pectel Ltd [2009] Lloyd’s Law Rep 440 at paragraphs 62-64 per Teare J andGeorge Hunt Cranes Ltd v Scottish Boiler & General Insurance Co Ltd [2002] Lloyd’s Rep IR 178.
[Back] Note 21 Barrett Bros v Davies [1966] 1 WLR 1334 is sometimes relied upon in this context. In that case insurers happened to have got notice from the police and the majority of the Court of Appeal held that the insured was therefore absolved from giving notice personally. The minority held that there was still a clear breach of the condition precedent but that insurers had waived the breach. See also MacGillivray para 19-043
[Back] Note 22 See Kidsons v Lloyds [2009] Lloyd’s Rep IR 178 at paragraph 72 as regards notification of circumstances and paragraph 86 as regards formal requirements. [Back]