SCCO reference: SC-2020-APP-000327 |
SENIOR COURTS COSTS OFFICE
Royal Courts of Justice Strand, London WC2A 2LL |
||
B e f o r e :
____________________
Mr Sharifah Masten |
Claimant |
|
- and - |
||
London Britannia Hotel Ltd |
Defendant |
____________________
Stephen Innes (instructed by QM Legal Costs Solutions Ltd) for the Defendant
Hearing date: 8 October 2020
____________________
Crown Copyright ©
Master Leonard:
The Rules
" 47.9
(1) The paying party and any other party to the detailed assessment proceedings may dispute any item in the bill of costs by serving points of dispute on –
(a) the receiving party; and
(b) every other party to the detailed assessment proceedings.
(2) The period for serving points of dispute is 21 days after the date of service of the notice of commencement.
(3) If a party serves points of dispute after the period set out in paragraph (2), that party may not be heard further in the detailed assessment proceedings unless the court gives permission…
(4) The receiving party may file a request for a default costs certificate if –
(a) the period set out in paragraph (2) for serving points of dispute has expired; and
(b) the receiving party has not been served with any points of dispute.
(5) If any party (including the paying party) serves points of dispute before the issue of a default costs certificate the court may not issue the default costs certificate.…"
" (1) The court will set aside a default costs certificate if the receiving party was not entitled to it.
(2) In any other case, the court may set aside or vary a default costs certificate if it appears to the court that there is some good reason why the detailed assessment proceedings should continue.
(Practice Direction 47 contains further details about the procedure for setting aside a default costs certificate and the matters which the court must take into account)…"
"(1) An application for an order under rule 47.12(2) to set aside or vary a default costs certificate must be supported by evidence.
(2) In deciding whether to set aside or vary a certificate under rule 47.12(2) the matters to which the court must have regard include whether the party seeking the order made the application promptly.
(3) As a general rule a default costs certificate will be set aside under rule 47.12 only if the applicant shows a good reason for the court to do so and if the applicant files with the application a copy of the bill, a copy of the default costs certificate and a draft of the points of dispute the applicant proposes to serve if the application is granted.
The Denton Test
"(1) On an application for relief from any sanction imposed for a failure to comply with any rule, practice direction or court order, the court will consider all the circumstances of the case, so as to enable it to deal justly with the application, including the need –
(a) for litigation to be conducted efficiently and at proportionate cost; and
(b) to enforce compliance with rules, practice directions and orders…"
The Facts
The Defendant's Submissions
"… because the availability of a judgment under Part 12 carries with it the availability of an order under Part 13 setting such judgment aside. That is to say, the burden, by way of sanction upon the defendant, of a default judgment regularly entered, is the obligation to persuade the court that there is a real prospect of successfully defending the claim (or other good reason for there not to be summary disposal), and that the just result is therefore that the default judgment be set aside. In the latter respect, the discretion is unfettered, except (if this be a fetter) that CPR r 13.3(2) enjoins the court to consider as one relevant factor whether the application to set aside was made promptly. To make an application to set aside under CPR r 13.3, accepting and seeking to discharge that burden, to my mind is to accept and operate under the CPR sanction for the original procedural default, not to ask for relief from it."
(a) in the first budgeted period of 10 November 2017 – 5 February 2019 the Claimant exceeded the budgeted costs of £56,143.67 by £27,102.04. Further, the Defendant submits that there is good reason to depart downwards from the costs budget in some phases because a significant element of the budgeted work had not actually been undertaken;
(b) in the second budgeted period, the Defendant submits that the Clamant is 127% over budget for the ADR phase, as the Claimant has incorrectly excluded from that phase £18,599.32 for a Joint Settlement Meeting. It follows that there is good reason to depart downwards from the budget because very little of the budgeted work was undertaken;
(c) the Claimant instructed solicitors in the City of London; this was not City work and the rates of up to £476 for a partner were excessive;
(d) the costs claimed incorporate significant irrecoverable duplication between a US attorney and the Claimant's UK solicitors;
(e) the bill includes costs of travel to the United States of approximately £29,000. A costs management order of Master Thornett of 15 February 2019 recorded that the court was not persuaded as to the need for attendance on the Claimant in the United States by legal advisers in this jurisdiction but noted that this was a matter for detailed assessment.
The Claimant's Submissions
Conclusions: Some Points of Principle
Conclusions on the Application of Practice Direction 47 Paragraph 11.2
Conclusions on the Application of the Denton Criteria
Conclusions on Setting-Aside
"Factor (a) makes it clear that the court must consider the effect of the breach in every case. If the breach has prevented the court or the parties from conducting the litigation (or other litigation) efficiently and at proportionate cost, that will be a factor weighing in favour of refusing relief. Factor (b) emphasises the importance of complying with rules, practice directions and orders. This aspect received insufficient attention in the past. The court must always bear in mind the need for compliance with rules, practice directions and orders, because the old lax culture of non-compliance is no longer tolerated."