BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
COMMERCIAL COURT (KBD)
IN THE MATTER OF THE ARBITRATION ACT 1996
AND IN THE MATTER OF AN ARBITRATION
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
THE FRENCH STATE |
Claimant/ Respondent in the Arbitration |
|
- and – |
||
THE LONDON STEAM-SHIP OWNERS' MUTUAL INSURANCE ASSOCIATION LIMITED |
Defendant/ Claimant in the Arbitration |
____________________
Christopher Hancock KC and Alexander Thompson (instructed by Wikborg Rein LLP) for the Defendant
Hearing dates: 8-9 August 2023
____________________
Crown Copyright ©
The Hon Mr Justice Butcher :
(1) Whether the French State needs and should be granted an extension of time to seek leave to appeal the First Partial Award;
(2) To the extent that the French State does not need, or is granted, an extension of time, should the French State be granted leave to appeal the Awards; and
(3) If it is, should the French State's appeals against the Awards succeed.
Background
(1) The French State was one of the claimants in the Spanish proceedings, who, in about June 2010, made a civil claim against the Defendant ('the Club') under Article 117.
(2) The Defendant ('the Club') commenced a different arbitration against the French State from that which it commenced against Spain, by notice of arbitration dated 16 January 2012. Mr Alistair Schaff QC was appointed as arbitrator. Mr Schaff issued his award in the arbitration involving the French State on 3 July 2013. In that award he granted substantially the same relief granted to the Club against Spain in his award of 13 February 2013.
(3) The French State had taken no part in that arbitration. It did, however, resist the Club's s. 66 AA 1996 application in respect of the Schaff award against it, and brought its own application challenging the substantive jurisdiction of the tribunal under s. 67 and/or s. 72 AA 1996. The French State was accordingly a party to and represented at the hearings before Hamblen J in October 2013, and the Court of Appeal in January 2015.
(4) The Spanish proceedings ultimately resulted in an order of the Provincial Court of La Coruña of 1 March 2019 providing, inter alia, that the French State was entitled to seek enforcement against the Club of up to about €117 million, and that the Spanish State was entitled to seek enforcement up to about €2.355 billion and various other Spanish claimants further amounts, subject to the US$1 billion limit in the insurance contract.
(5) On about 11 January 2019 the Club served a notice or further notice of arbitration on the French State. In the absence of any agreement by the French State, the Club issued an Arbitration Claim Form, seeking the appointment of Dame Elizabeth Gloster as sole arbitrator pursuant to s. 18 AA 1996. On 14 February 2020, that application was heard by Foxton J. The French State did not attend that hearing or make any submissions. Foxton J held that the French State was not immune from the proceedings, by reason of s. 9 State Immunity Act 1978 ('SIA'), because it had agreed in writing to refer the Club's claims to arbitration and the s. 18 AA 1996 application related to the arbitration. Further Foxton J held that the requirements of s. 18 AA 1996 were met, and appointed Dame Elizabeth Gloster as the sole arbitrator in the reference.
(6) In the arbitration, in summary, the Club sought declarations that the French State was in breach of its obligations not to pursue the non-CLC claims other than by way of London arbitration, injunctive relief, and an order that the French State pay to the Club such sums as the Club is ordered to pay to the French State in any jurisdiction in which the Spanish Judgment is recognised or enforced, as well as compensation for its costs of defending the non-CLC claims in Spain.
(7) A hearing in the arbitration took place before Dame Elizabeth Gloster on 6-8 and 19-22 July 2021. The French State participated in this hearing. On 20 June 2022 the CJEU handed down its judgment in the Reference. K&L Gates LLP, for the French State, provided a copy of that judgment to Dame Elizabeth Gloster. On 22 June 2022 she said that, having read the judgment, she did not require submissions from the parties to the arbitration to complete her award. Neither party sought to persuade her otherwise. During July 2022 the parties exchanged submissions on a different authority, UK P&I Club v Republica Bolivariana de Venezuela (The 'Resolute') [2022] EWHC 1655 (Comm) and its relevance to the issues before the tribunal. After that there were no further written or oral submissions in the arbitration, and Dame Elizabeth Gloster proceeded to produce her first award.
(8) The French State, unlike Spain, has not sought, or obtained, an order seeking to have the Spanish Judgment registered in England pursuant to the Brussels I Regulation.
(1) Set out the factual and procedural background (paras. 6-55);
(2) Identified the issues which arose for decision (para. 56). There were six principal issues: Issue I as to her jurisdiction; Issue II as to the effect, if any, of the Club's participation in the Spanish quantum proceedings; Issue III as to whether there should be the grant of declaratory relief in favour of the Club; Issue IV as to whether there could and should be the grant of equitable compensation to the Club; Issue V as to whether she could and should grant injunctive relief restraining the French State from enforcing any of the judgments of the Spanish Courts anywhere in the world outside Spain; and Issue VI as to whether the Club should be granted damages under s. 50 SCA instead of or in addition to an anti-enforcement injunction;
(3) Resolved the jurisdiction issue (Issue I) in favour of the Club (paras 57-62);
(4) Found (in relation to Issue II) that the Club had not submitted to the jurisdiction of the Spanish Courts by its participation in the quantum proceedings there (paras. 63-81);
(5) Held (in relation to Issue III) that she should exercise her discretion to grant declaratory relief to the effect that the French State, by maintaining direct civil claims in Spain and by taking steps in Spain to enforce the order of the Provincial Court of La Coruña of 1 March 2019 was in breach of its obligations in equity not to pursue such claims other than by way of London arbitration; and that if it took further steps, in Spain or elsewhere, to enforce that order, or any other order of the Spanish Courts upholding or enforcing such claims, it would be in breach of its obligations not to pursue such claims other than by way of London arbitration (paras. 81-85);
(6) Concluded (in relation to Issue IV) that she, as the tribunal, had the power to award equitable compensation to the Club in respect of the French State's past and future breaches of its equitable obligation to pursue direct claims only in London arbitration; and that as a matter of discretion she should make such an order (paras 87-149);
(7) Concluded (in relation to Issue V) that she had jurisdiction to grant an injunction restraining the French State from enforcing any of the judgments of the Spanish Courts, and that as a matter of discretion she should grant such an injunction (paras 150-202);
(8) Said (in relation to Issue VI) that she considered it neither necessary nor appropriate to decide on this, as she had already concluded that it was appropriate to make an order for the payment of equitable compensation (including contingently on future breaches by the French State of its equitable obligation) (paras. 203-204).
'(1) A declaration that the Respondent is, by maintaining the direct civil claims brought against the Claimant in Spain other than under the International Convention on Civil Liability for Oil Pollution Damage 1992 (the "Claims"), and by taking steps in Spain and elsewhere to enforce against the Claimant the order of the Provincial Court of La Coruña dated 1 March 2019 (the "Spanish Order"), in breach of its obligations in equity not to pursue such claims other than by way of London arbitration.
(2) A declaration that if the Respondent takes any further steps in Spain, or elsewhere, to enforce the Spanish Order, or any other order of the Spanish Courts upholding or enforcing the Claims, against the Claimant, the Respondent will be in breach of its obligations not to pursue the Claims other than by way of London arbitration.
(3) An injunction that the Respondent be enjoined from taking any step to have the Spanish Order, or any other order of the Spanish Courts upholding or enforcing the Claims, recognised or enforced in any jurisdiction worldwide, other than in Spain.
(4) A declaration that, as and when France obtains a final monetary judgment (or any enforcement order to similar effect) against the Club in any jurisdiction [outside Spain] arising out of the execution order of the Provincial Court of La Coruña dated 1 March 2019 or any of the preceding judgments of the Spanish Courts, or obtains satisfaction (in whole or in part) in any country in respect of such judgments, France will immediately be obliged to pay equitable compensation in an equal and opposite amount to the Club and/or give credit for such equitable compensation in the amount of the judgment or satisfaction obtained.
(5) An order that, as and when France obtains a final monetary judgment (or any enforcement order to similar effect) against the Club in any jurisdiction [outside Spain] arising out of the execution order of the Provincial Court of La Coruña dated 1 March 2019 or any of the preceding judgments of the Spanish Courts, or obtains satisfaction (in whole or in part) in any country in respect of such judgments, France will immediately be obliged to pay equitable compensation and/or give credit for such equitable compensation in the amount of the judgment or satisfaction obtained.
(6) An indemnity in respect of any amounts awarded to France in any final monetary judgment (or any enforcement order to similar effect) in any jurisdiction [outside Spain] arising out of the execution order of the Provincial Court of La Coruña dated 1 March 2019 or any of the preceding judgments of the Spanish Courts or any satisfaction (in whole or in part) France obtains in any country in respect of such judgments.
(7) A declaration and order that France shall in any event pay to the Club its costs of defending the Claims in Spain, or any proceedings taken by France to enforce the execution order of the Provincial Court of La Coruña dated 1 March 2019 or any of the preceding judgments of the Spanish Courts, such sums to be determined in a subsequent Award, if not agreed.
(8) I formally reserve jurisdiction in this arbitration to deal with the precise terms of this order; costs; any other outstanding matters arising out of this Partial Award.'
'NOW I, the said Dame Elizabeth Gloster DBE, having accepted this reference and having carefully and conscientiously considered all the evidence and submissions made to me, DO HEREBY MAKE, ISSUE AND PUBLISH this my SECOND PARTIAL AWARD:
A) I AWARD AND DECLARE that:
1) The Respondent has acted, by maintaining its direct civil claims brought under the Spanish Penal Code against the Claimant in Spain and other than under the International Convention on Civil Liability for Oil Pollution Damage 1992 (the "Non-CLC Claims"), and by taking steps in Spain to enforce against the Claimant the judgment and order of the Provincial Court of La Coruña dated 15 November 2017 and 11 January 2018 and the judgment of the Spanish Supreme Court dated 19 December 2018, those steps having led to the order of the Provincial Court of La Coruña dated 1 March 2019 (the "Execution Order"), in breach of its equitable obligations not to pursue such claims other than by way of London arbitration;
2) if the Respondent takes any further steps, in Spain or elsewhere, to enforce the Execution Order, or any other order of the Spanish Courts upholding or enforcing its Non-CLC Claims, against the Claimant, the Respondent shall be in breach of its equitable obligations not to pursue its Non-CLC Claims other than by way of London arbitration;
3) the Respondent is hereby enjoined from and shall not take any steps to have the Execution Order, or any other order of the Spanish Courts upholding or enforcing its Non-CLC Claims, recognised or enforced in any jurisdiction worldwide, other than in Spain;
4) the Respondent is liable to pay, give credit to, and indemnify the Claimant in Spain in an equal and opposite amount to the sum which the Respondent is entitled to enforce against the Claimant out of the capped total amount of EUR 855,493,575.65 awarded in favour of all claimants under the Execution Order (the "Capped Amount"). That liability is present and existing, but the Respondent shall not be required to make any actual payment to the Claimant in Spain under this paragraph before a Spanish Court has determined the share of the Capped Amount to which the Respondent is entitled. If and when a Spanish Court determines that amount, the Respondent shall in Spain come under an obligation to make actual payment to the Claimant in respect of its aforesaid liability.
5) if and when the Respondent obtains a final monetary judgment (or any enforcement or other order or determination to similar effect) against the Claimant in any jurisdiction outside Spain in respect of and determining the precise sums awarded to it in the Execution Order, or any of the preceding judgments of the Spanish Courts (a "Further Execution Order"), the Respondent shall in that jurisdiction pay, give credit for, and indemnify the Claimant in respect of an equal and opposite amount to that of the Further Execution Order;
6) if and when the Respondent takes steps to and obtains satisfaction (in whole or in part) in any country in respect of any amounts awarded to it by the Execution Order or any of the preceding judgments of the Spanish Courts, or any Further Execution Order which it may in future obtain, the Respondent shall pay to and indemnify the Claimant in an amount equal to the sum obtained; and
7) to the extent not otherwise recoverable under an final costs order made in respect of the proceedings in question, the Respondent shall pay to and indemnify the Claimant in respect of its costs of defending the Respondent's Non-CLC Claims in Spain and/or any proceedings taken by the Respondent to enforce the Execution Order or any of the preceding judgments of the Spanish Courts, such sums and any claim to interest thereon to be determined (including the principle of whether interest is payable) in a subsequent award, if not agreed, and jurisdiction is reserved for that purpose.
B) I further AWARD AND DECLARE that:
1) the Respondent shall bear and pay the Claimant's costs of this reference (to the extent they are reasonable in amount and reasonably incurred) and the Tribunal's costs of this reference, to the date of this Award, and shall reimburse the Claimant for the Tribunal's costs if they have been borne in the first instance by the Claimant, such sums to be determined in a subsequent award, if not agreed, and jurisdiction is reserved for that purpose.; and
2) the jurisdiction of the Tribunal is otherwise reserved generally.'
(1) Ground 1: whether the arbitral tribunal had the power to grant an injunction against the French State under s. 48(5) AA 1996;
(2) Ground 2: whether the arbitral tribunal had the power to award equitable compensation for breach of an equitable obligation to arbitrate arising by application of the conditional benefit principle, or whether equitable compensation is otherwise available in these circumstances;
(3) Ground 3: whether an anti-enforcement injunction can be granted where its effect is to restrain enforcement of a foreign judgment which is granted recognition under English law; and
(4) Ground 4: whether equitable compensation can be granted where its effect is to neutralise the effect of a foreign judgment which is granted recognition under English law.
(1) That until the French State received the Club's application pursuant to s. 66 AA 1996, in which the Club did not seek to enforce the injunctive relief granted by Dame Elizabeth Gloster, it was not reasonably possible or practicable for it to advance its s. 66 AA 1996 application as to do so would risk it losing its entitlement to claim immunity under s. 13(2)(a) SIA. Prior to being notified that the Club was not seeking to enforce the injunction, the French State had intended to assert immunity by issuing a Part 11 application in response to the Club's s. 66 AA 1996 application.
(2) That the French State had acted proactively in seeking the Club's agreement to allow it to proceed without the risk of waiving immunity, and had acted promptly to issue its Arbitration Claim Form once such agreement had been secured.
(3) That in all the circumstances, including the length of delay, the actions of the parties, and the lack of prejudice to the Club, an extension of time was justified.
The Issues arising
Does the French State need an Extension of Time?
(1) An appeal under s. 69 AA 1996 can only be made in respect of 'an award'.
(2) The meaning of an 'award' is not defined in AA 1996, although s. 52 AA 1996 sets out a number of formal requirements with which, in the absence of contrary agreement, an award must comply, namely that it should be in writing and signed by the arbitrator, that it contains the reasons for the award, and that it states the seat of the arbitration and the date on which it was made.
(3) An award may be one of a number of kinds. Thus it may be a final and unitary award which disposes of all the issues in the reference. But a tribunal does not need to decide all issues at the same time: it may instead make one or more partial awards, which dispose of some issues and leave other issues to be determined subsequently, as provided for (in the absence of agreement otherwise) by s. 47 AA 1996.
(4) Subject to a successful appeal an arbitration award is final and binding on the parties and on any persons claiming through or under them, as is provided by s. 58 AA 1996; and gives rise to an estoppel on the matters decided. The position was summarised as follows in Emirates Trading at [22]-[26] per Popplewell J:
22. The Jurisdiction Award was an award which was final and binding on the parties as to the matters it decided. This is the effect of section 58 of the Act …
23. This has two consequences. The first is that absent contrary agreement between the parties, the ability to challenge the validity of such an award in this Court is limited by the rights of challenge and appeal conferred by ss. 67-69 of the Act. If no such challenge is made timeously, or is made and rejected, the finality of the award creates an issue estoppel between the parties which precludes either party challenging it before the tribunal or as a ground of challenge to a subsequent decision of the tribunal: see Fidelitas Shipping Ltd v V/O Exportchleb [1966] 1 QB 630 and Westland Helicopters Ltd v Sheikh Salah Al-Hejailan (No 1) [2004] 2 Lloyd's Rep 523.
…
26. The second consequence of an award being binding is that, subject to limited exceptions, the tribunal no longer has power to review or reconsider the subject matter of the award. There is a longstanding rule of common law that when an arbitrator makes a valid award, his authority as an arbitrator comes to an end and, with it, his powers and duties in the reference: he is then said to be functus officio (see Mustill and Boyd's The Law and Practice of Arbitration 2nd Edition pp. 404–405 and Companion Volume 404-414). This applies as much to a partial award as to a final award: see Fidelitas per Diplock LJ at p. 644B-E. Absent agreement of the parties, the tribunal may only reconsider or review its decision if the matter is remitted following a successful challenge to the award in Court, or pursuant to the express powers of correction or reconsideration conferred by section 57 of the Act or by the arbitral rules which the parties have agreed to govern the reference. Otherwise the tribunal has no authority or power to do so. None of these exceptions apply in this case.
(5) If the tribunal makes an award, it must be certain, in the sense that it may be subject to an application under s. 57 AA 1996 and a challenge under s. 68 AA 1996 if it is insufficiently clear in respect of the matters which it decides.
a) The Court will certainly give real weight to the question of substance and not merely to form: Emmott at paragraph 18 (by concession); Russell on Arbitration (24th edition, 2015) at [6-003].
b) Thus, one factor in favour of the conclusion that a decision is an award is if the decision is final in the sense that it disposes of the matters submitted to arbitration so as to render the tribunal functus officio, either entirely or in relation to that issue or claim: Cargill at 5, The Smaro at 247; Enterprise Insurance at [39].
c) The nature of the issues with which the decision deals is significant. The substantive rights and liabilities of parties are likely to be dealt with in the form of an award whereas a decision relating purely to procedural issues is more likely not to be an award. Brake at [25], The Smaro at 247; Emmott at [19-20], Cargill at 5, The Trade Fortitude at 175.
d) There is a role however for form. The arbitral tribunal's own description of the decision is relevant, although it will not be conclusive in determining its status: The Trade Fortitude at 175 Emmott at [19-20].
e) It may also be relevant to consider how a reasonable recipient of the tribunal's decision would have viewed it: Emmott at [18]; Ranko p 4.
f) A reasonable recipient is likely to consider the objective attributes of the decision relevant. These include the description of the decision by the tribunal, the formality of the language used, the level of detail in which the tribunal has expressed its reasoning: Emmott at [19 -20]; Uttam Galva Steels at [29]; The Trade Fortitude at 175; The Smaro at 247.
g) While the authorities do not expressly say so I also form the view that:
i. A reasonable recipient would also consider such matters as whether the decision complies with the formal requirements for an award under any applicable rules.
ii. The focus must be on a reasonable recipient with all the information that would have been available to the parties and to the tribunal when the decision was made. It follows that the background or context in the proceedings in which the decision was made is also likely to be relevant. This may include whether the arbitral tribunal intended to make an award: The Smaro at 247, Ranko p 4.
(1) It is called an award, and it purports to be an award.
(2) It complies with the formal requirements for an award in s. 52 AA 1996.
(3) It deals with the substantive rights and liabilities of the parties, and sets out the reasoning of the arbitrator in detail.
(4) In respect of the matters on which she expressed a concluded view, I consider it clear that Dame Elizabeth Gloster's authority in the arbitration was at an end, in the sense that she could not, having issued the First Partial Award, have revisited the issues which she had decided and reached a different conclusion on them. On those matters, she was not providing a 'provisional view', but was rendering a final decision.
(5) The arbitrator left limited issues for later determination, including the terms of the relief and some other, comparatively minor, issues, including costs. This however meant only that it was, as indeed its title indicated it was, a partial award under s. 47 AA 1996.
(6) I consider that a reasonable recipient of the First Partial Award would have regarded it as an award. Indeed, it is of some significance that the French State does not suggest that either it or its lawyers considered the First Partial Award not to be an award; and in its Arbitration Claim Form it sought to appeal the First Partial Award and an extension of time in which to do so.
Should an Extension of Time be Granted?
(1) That the length of the delay was not significant in the context of the dispute, and given that the same or related grounds of appeal were being advanced by Spain.
(2) That the French State had acted reasonably in not applying for leave to appeal the First Partial Award within 28 days. It relied on the evidence set out in two witness statements of Mr Meredith. It says that it assumed, reasonably, that the Club would seek to enforce the injunctive relief granted by the tribunal. It wished to preserve its right to assert immunity pursuant to s. 13(2)(a) SIA, and that, in the circumstances, it had to act with great care. It was mindful that in The Prestige (No. 2) it was held that the French State and Spain had, for the purposes of s. 2 SIA, submitted to the court's adjudicative jurisdiction by issuing their own claims under the AA 1996. It also considered that there was uncertainty about whether a State which appeals an arbitration award under s. 69 AA 1996 will be taken to have submitted not only to the court's adjudicative jurisdiction, but also have waived its right to assert immunity against injunctive relief under s. 13(2)(a) SIA. Further there was a need to consult with appropriate persons within the French State. The French State had been proactive in seeking an agreement with the Club which would have enabled it to lodge its s. 69 AA 1996 application and deal with the merits of that application without having waived its immunity under s. 13(2)(a) SIA. It was only on 12 May 2023 that the Club had responded to the French State's suggestion; and it was only on the same day that the French State discovered that the Club was not seeking to enforce, pursuant to s. 66 AA 1996, the injunctive relief granted by the arbitrator.
(3) That the Club had to some extent contributed to the delay, by not giving an undertaking regarding the waiver issue prior to the week of 18 May 2023, and by not indicating before 12 May 2023 that it would not seek to enforce the injunction.
(4) That the Club had not suffered any prejudice from the delay.
(5) That the French State's application for leave, and the appeal itself, have strong merits.
(6) That, looking at the matter more generally, it would occasion substantial injustice to deprive the French State of the opportunity to pursue a meritorious appeal against the First and Second Partial Awards.
26. There was no significant dispute as to the principles applicable to an application for an extension of time such as this. They were set out in Kalmneft v Glencore and further elaborated in Terna Bahrain Holding Company WLL v Al Shamshi [2012] EWHC 3283 (Comm) where, at [27]-[32] Popplewell J said:
27. The principles regarding extensions of time to challenge an arbitration award have been addressed in a number of recent authorities … from which I derive the following principles:
(1) Section 70(3) of the Act requires challenges to an award under sections 67 and 68 to be brought within 28 days. This relatively short period of time reflects the principle of speedy finality which underpins the Act, and which is enshrined in section 1(a). The party seeking an extension must therefore show that the interests of justice require an exceptional departure from the timetable laid down by the Act. Any significant delay beyond 28 days is to be regarded as inimical to the policy of the Act.
(2) The relevant factors are:
(i) the length of the delay;
(ii) whether the party who permitted the time limit to expire and subsequently delayed was acting reasonably in the circumstances in doing so;
(iii) whether the respondent to the application or the arbitrator caused or contributed to the delay;
(iv) whether the respondent to the application would by reason of the delay suffer irremediable prejudice in addition to the mere loss of time if the application were permitted to proceed;
(v) whether the arbitration has continued during the period of delay and, if so, what impact on the progress of the arbitration, or the costs incurred in respect of the arbitration, the determination of the application by the Court might now have;
(vi) the strength of the application;
(vii) whether in the broadest sense it would be unfair to the applicant for him to be denied the opportunity of having the application determined.
(3) Factors (i), (ii), and (iii) are the primary factors.
28. I add four observations of my own which are of relevance in the present case. First, the length of delay must be judged against the yardstick of the 28 days provided for in the Act. Therefore a delay measured even in days is significant; a delay measured in many weeks or in months is substantial.
29. Secondly, factor (ii) involves an investigation into the reasons for the delay. In seeking relief from the Court, it is normally incumbent upon the applicant to adduce evidence which explains his conduct, unless circumstances make it impossible. In the absence of such explanation, the Court will give little weight to counsel's arguments that the evidence discloses potential reasons for delay and that the applicant "would have assumed" this or "would have thought" that. It will not normally be legitimate, for example, for counsel to argue that an applicant was unaware of the time limit if he has not said so, expressly or by necessary implication, in his evidence. Moreover where the evidence is consistent with laxity, incompetence or honest mistake on the one hand, and a deliberate informed choice on the other, an applicant's failure to adduce evidence that the true explanation is the former can legitimately give rise to the inference that it is the latter.
30. Thirdly, factor (ii) is couched in terms of whether the party who has allowed the time to expire has acted reasonably. This encompasses the question whether the party has acted intentionally in making an informed choice to delay making the application. In Rule 3.9(1) of the Civil Procedure Rules, which sets out factors generally applicable to extensions of time resulting in a sanction, the question whether the failure to comply is intentional is identified as a separate factor from the question of whether there is a good explanation for the failure. This is because in cases of intentional non compliance with time limits, a public interest is engaged which is distinct from the private rights of the parties. There is a public interest in litigants before the English Court treating the Court's procedures as rules to be complied with, rather than deliberately ignored for perceived personal advantage.
31. Fourthly, the Court's approach to the strength of the challenge application will depend upon the procedural circumstances in which the issue arises. On an application for an extension of time, the Court will not normally conduct a substantial investigation into the merits of the challenge application, since to do so would defeat the purposes of the Act. However if the Court can see on the material before it that the challenge involves an intrinsically weak case, it will count against the application for an extension, whilst an apparently strong case will assist the application. Unless the challenge can be seen to be either strong or intrinsically weak on a brief perusal of the grounds, this will not be a factor which is treated as of weight in either direction on the application for an extension of time. If it can readily be seen to be either strong or weak, that is a relevant factor; but it is not a primary factor, because the Court is only able to form a provisional view of the merits, a view which might not be confirmed by a full investigation of the challenge, with the benefit of the argument which would take place at the hearing of the application itself if an extension of time were granted.
32. The position, however, is different where, as has happened in the current case, the application for an extension of time has been listed for hearing at the same time as the challenge application itself, and the Court has heard full argument on the merits of the challenge application. In such circumstances the Court is in a position to decide not merely whether the case is "weak" or "strong", but whether it will or will not succeed if an extension of time were granted. The Court is in a position to decide whether the challenge is a good or a bad one. If the challenge is a bad one, this should be determinative of the application to extend time. Whilst it may not matter in practice whether the extension is allowed and the application dismissed, or whether the extension is simply refused, logical purity suggests that it would be wrong to extend time in those circumstances: there can be no justification for departing from the principle of speedy finality in order to enable a party to advance a challenge which will not succeed.
Should permission to appeal be granted?
Should the appeal succeed: Grounds 1 and 2?
Ground 1: Injunction against the French State
(1) She agreed with the view expressed by Henshaw J in The Prestige (No. 3) that s. 13(2) SIA governs the exercise but not the existence of the court's power to grant an injunction against a State (para. 170);
(2) An arbitral tribunal is in a significantly different position from a court, and the par in parem principle is not applicable to the former (para. 173);
(3) S. 48(5) AA 1996 confers on arbitrators the same 'types or classes' of powers as the court has, but not subject to the same restrictions (para. 174);
(4) The courts could, before the passage of SIA, grant injunctions against States; and the wording of s. 13(2) SIA, being cast in terms of 'relief shall not be given', and the terms of s. 13(3) SIA, recognise a power in the court but curtail its exercise (para. 175);
(5) That an arbitral tribunal's powers to grant an injunction may be more extensive than a court's is exemplified by the fact that, in relation to anti-suit injunctions restraining proceedings in other EU Member States, an arbitral tribunal could, but a court could not, have granted such relief (para. 176).
Ground 2: Equitable Compensation
'[95] … I see no logical, or principled, argument which could be derived from Airbus, or the cases which preceded it, to support Ms Dilnot's thesis that a distinction should be drawn between, on the one hand, the obligations of B1, who is exercising "transferred" rights of action against A pursuant to a direct action statute and, on the other hand, the obligations of B2 who is exercising "transferred" rights of action against A, pursuant to rights of subrogation or assignment. In my judgment the distinction drawn is clearly unfounded, since the same point applies: on Ms Dilnot's approach the third party would be taking the benefit of the contract (to which he is not a party) without its burdens. Moreover, Ms Dilnot was not able to provide any logical, or principled, explanation as to why, where there was an equitable obligation, there was no correlative obligation to comply with relief sought for breach of that obligation. In the circumstances, it is not surprising that the cases have treated the two classes of "derived rights" interchangeably, drawing on the earlier case law without distinction. Indeed, direct action statutes are often referred to as a form of "statutory subrogation", which in a sense they are.
…
[98] Nor do I think that Ms Dilnot derives any support for her argument from the decision in Yusuf AS (The 'Yusuf Cepnioglou') [2016] EWCA Civ 386… On the contrary, the passages … at 47-49 are contrary to her argument that there is a distinction between derived rights obtained through assignment or subrogation and rights obtained under a direct action statute. In the emphasised passages below from [Yusuf AS], Moore-Bick LJ (with whose judgment MacFarlane LJ also agreed) clearly rejected the argument that there is a distinction between the two types of cases:
47. Mr. Lewis sought to distinguish the position of a person who becomes entitled to enforce an obligation by virtue of an assignment or other transfer (as was the case in the 'Jay Bola') from that of a claimant who obtains a statutory right to recover damages direct from an insurer. In my view, however, there is no real distinction. As was made clear in the 'Jay Bola', the arbitration agreement becomes binding on the claimant because it forms an integral part of the contract giving rise to the obligation, a circumstance which is not affected by the manner in which the claimant obtained the right to enforce it. Accordingly, if it becomes necessary to enforce the obligation by proceedings, that must be done by arbitration. Although the 'Jay Bola' was not cited in either the 'Hari Bhum' (No.1) or the 'Prestige' (No. 2), the principle that a claimant seeking to enforce a claim direct against an insurer must comply with an arbitration clause in the contract of insurance was recognised and applied in both cases.
Are there sufficient grounds for granting an anti-suit injunction?
48. In the light of the decision of this court in Aggeliki Charis Compania Maritima S.A. v Pagnan S.p.A. (The 'Angelic Grace') [1995] 1 Lloyd's Rep. 87 Mr Lewis accepted that in the ordinary way it is right for the court to grant an injunction to restrain a claimant from seeking to enforce by proceedings abroad an obligation subject to an English arbitration agreement. He submitted, however, that a distinction is to be drawn between a party to a contract containing an arbitration agreement who seeks to enforce that agreement by proceedings abroad and a party in the position of the claimant, which has not entered into an agreement to arbitrate and whose conduct in commencing proceedings in its own jurisdiction pursuant to its own domestic legislation could not properly be regarded as vexatious or oppressive so as to support the grant of an injunction.
49. In my view the distinction which Mr Lewis sought to draw between the position of an original party to an arbitration agreement and that of what might be called a "remote" party (i.e., a claimant who has become entitled to enforce an obligation but is not a party to a contract of any kind with the defendant), is not well founded, because the basis for the court's intervention is the same in each case. In the 'Jay Bola' Hobhouse LJ and Sir Richard Scott V-C explained, in the passages to which Longmore LJ has referred, why the court will intervene by granting an anti-suit injunction to restrain the claimant from enforcing the obligation by proceedings abroad instead of by arbitration. It will do so, not because the claimant is party to a contract containing an arbitration agreement (which it is not), but because enforcement by arbitration alone is an incident of the obligation which the claimant seeks to enforce and because the defendant is therefore entitled to have any claim against him pursued in arbitration. It is the right not to be vexed by proceedings otherwise than in arbitration that equity will intervene by injunction to protect.' (bold emphasis supplied by Dame Elizabeth Gloster)
Grounds 3 and 4
'In this sense the mutual obligations assumed to each other are separate and quite distinct from the external, jurisdictional impact of the contract. The fact that a court is called upon to recognise a judgment, whether under the Convention, Regulation, or otherwise, is irrelevant to the separate question whether the party who obtained that judgment, whether or not it is entitled to recognition, did so in breach of contract.'
'I accept that, if they were successful, the English indemnity and damages claims could be fairly said to neutralise, at any rate in commercial terms, any benefit to Starlight and OME of a judgment in the Greek claims. However, crucially in my view, success for LMI and CMI in the English indemnity and damages claims would not be logically inconsistent in any way with success for Starlight in the Greek claims. It is not inconsistent (although it is commercially pointless) to say that a defendant is liable to pay a claimant a sum by way of damages, while the claimant is bound to indemnify the defendant in respect of the whole of that sum (or is bound to pay an equivalent sum to the defendant). Indeed, the indemnity is not merely logically consistent with the liability: it is positively meaningless without the liability for damages, and the liability for damages, though rendered nugatory by the indemnity, is not logically inconsistent with the indemnity.'
'[114] Nor am I impressed by Ms Dilnot's argument that "there has never been an award of equitable compensation… in the amount of a foreign judgment". As Mr Hancock rightly submitted, a claim for equitable compensation in a case such as the present is the equitable equivalent to the claim in contract for damages for breach of an exclusive jurisdiction or arbitration clause. In the contractual context, damages have been awarded in the amount of, or by way of an indemnity in respect of, a foreign judgment obtained in breach of an exclusive jurisdiction or arbitration clause: see e.g. The Alexandros T [2012] 1 Lloyd's Rep 162 (Burton J); [2014] 2 Lloyd's Rep. 544 (CA); CMA CGM SA v Hyundai Mipo Dockyard Co Ltd [2009] 1 Lloyd's Rep 213 (where Burton J upheld an award of damages in Hyundai's favour, made by the arbitrators in respect of inter alia the judgment sums which it was ordered to pay, and did pay, in the French proceedings to CMA, together with compensation in respect of lost management time and their own French legal costs, and interest); and Compania Sud Americana de Vapores v Hin-Pro International Logistics [2015] 1 Lloyd's Rep 301 [AB5/58], [37]-[40] where damages were awarded in respect of judgment sums awarded against the claimant in the foreign proceedings, but also in respect of sums which it might yet have to pay…'
Overall Conclusions
(1) That the French State requires an extension of time to bring its s.69 AA 1996 application in respect of matters decided in the First Partial Award;
(2) That there should be an extension of time for the French State to bring its application on Grounds 1 and 2, but not on Grounds 3 and 4.
(3) That there should be permission to appeal on Grounds 1 and 2, but there would not have been such permission on Grounds 3 and 4.
(4) Subject to the 'Resolute' point, on which I will defer my decision until after the decision of the Court of Appeal in that case, that in relation to Ground 1 that Dame Elizabeth Gloster did not have jurisdiction to grant an injunction against the French State.
(5) That the appeal on Ground 2 is dismissed.