Strand, London, WC2A 2LL |
||
B e f o r e :
SITTING AS A JUDGE OF THE HIGH COURT
Between :
____________________
GASL IRELAND LEASING A-1 LIMITED |
Claimant |
|
- and - |
||
SPICEJET LIMITED |
Defendant |
____________________
TIMOTHY YOUNG QC and RUPERT HAMILTON (instructed by Reed Smith LLP) for the Defendant
Hearing dates: 17 February 2022
Judgment Approved
____________________
Crown Copyright ©
SIMON SALZEDO QC :
Introduction
Procedural history
"2. The Claimant has permission to file and serve Amended Particulars of Claim in the form of the draft included in the Case Management Bundle.
3. The Defendant has permission to file and serve an amended Defence to respond to the amendments in the Particulars of Claim on or before 26 November 2021.
4. The Claimant has permission to file and serve a Reply in the form of the draft included in the Case Management Bundle, as modified to respond to the Amended Defence, on or before 10 December 2021.
5. The Claimant shall (if so advised) file and serve an amended version of Appendix 2 to its Statement of Case to include further and better particulars of the claims set out therein not later than 31 January 2022.
6. The Defendant shall (if so advised) file and serve a document setting out its defence to any amended version of Appendix 2 by no later than 28 February 2022 (subject to the Defendant's liberty to apply to the Court for an extension of time)."
"9. Any further evidence in respect of the Summary Judgment application dated 5 November 2021 shall be filed and served:
a) by the Defendant in answer no later than 10 December 2021; and:b) by the Claimant in reply no later than 23 December 2021.
10. There shall be a hearing of the Claimant's summary judgment application dated 5 November 2021 as soon as possible thereafter but not before 14 January 2022, with a time estimate of four hours."
Contracts
"8.3 Absolute Obligations
(a) Sub lessee's obligations to pay Rent and to perform any of its other obligations pursuant to this Agreement are absolute and unconditional. Sub lessee may not regard its obligations as terminated, suspended or altered (and waives to the greatest extent permitted by applicable Laws any rights which it may have at any time to terminate, suspend or alter such obligations) by reason of any contingency or circumstance whatsoever, including (but not limited to):(i) any right of set off, counterclaim, recoupment, reimbursement, defence or other right which Sub lessee may have against Head Lessor, Owner Intermediate Lessor, Sub lessor, Manufacturer, any seller or any other person;(ii) any unavailability of the Aircraft after the Delivery Date for any reason or interruption of or interference with Sub lessee's use, operation or possession of the Aircraft;(iii) any defect in title, airworthiness, condition, design, operation of fitness for use of, registration of the Aircraft or any damage to or loss or destruction of the Aircraft;(iv) any insolvency, bankruptcy, reorganisation, arrangement, readjustment of debt, dissolution, liquidation or similar proceedings by or against Head Lessor, Owner, Intermediate Lessor, Sub lessor or Sub lessee or Any other Person; and:(v) any invalidity or unenforceability of or other defect in, this Agreement.(b) The provisions of this Clause 8.3 (Absolute Obligations) shall not be construed to limit Sub lessee's right to take independent legal proceedings against Sub lessor in the event of Sub lessor's breach of the terms of this Agreement or to limit Sub lessee's rights and remedies against any other Person."
"Sub lessor's Determination of Amounts Due
Any certificate or determination by Sub lessor as to any rate of interest (which shall be capped at the Default Rate) or as to any other amount payable under this Agreement shall, in the absence of manifest error, be conclusive and binding on Sub lessee."
"Sub lessor's Rights
(a) Sub lessor Rights and Remedies: If an Event of Default occurs, Sub lessor (unless specified below) may at its option (and without prejudice to any of its other rights or remedies under this Agreement or available under applicable law), at any time thereafter while such Event of Default is continuing (and subject to compliance with any mandatory requirement of applicable Law then in effect):
... (iii) either:
(A) take possession of the Aircraft, for which purpose Sub lessor may enter any premises belonging to or in the occupation of or under the control of Sub lessee where the Aircraft may be located, or cause the Aircraft to be redelivered to Sub lessor at the Redelivery Location (or such other location as Sub lessor may require), and Sub lessor is hereby irrevocably by way of security for Sub lessee's obligations under this Agreement appointed attorney for Sub lessee in causing the redelivery or in directing the pilots of Sub lessee or other pilots to fly the Aircraft to that airport and will have all the powers and authorisations necessary for taking that action; or:(B) by serving notice require Sub lessee to redeliver the Aircraft to Sub lessor at the Redelivery Location (or such other location as Sub lessor may require).
Each of Sub lessor and Sub lessee acknowledges and agrees that the rights exercisable by Sub lessor under this Clause 20.2(a)(iii) shall also be exercisable by each of Head Lessor, Intermediate Lessor and Owner."
(a) a novation and amendment deed between Airspeed, NOK and the claimant, by which Airspeed's rights and obligations under the Head Lease were novated to the claimant.
(b) a lease security assignment between the claimant and NOK, under which NOK assigned its interest under the Intermediate Lease and the Sub lease to the claimant as security for its obligations under the Head Lease.
"4. Enforcement of Security
4.1 Subject to (i) paragraph 4.2 below and (ii) the terms of the
Security Assignments:
(a) the Lessee may exercise all its rights, powers and discretions under the Sub Lease without the prior written consent of the Head Lessor; and:
(b) the Lessor may exercise all its rights, powers and discretions under the Lease without the prior written consent of the Head Lessor.
4.2 If the Head Lessor issues an Enforcement Notice to the Lessee and Sub Lessee:
(a) all the rights, powers and discretions of the Lessee (under the Sub Lease) and the Lessor (under the Lease and the Sub Lease Security Assignment) will be exercisable by, and notices must be given to, the Head Lessor (or as it directs) to the exclusion of the Lessee and the Lessor;
(b) all money that may be payable by (i) the Lessee under the Lessor Assigned Documents and (ii) the Sub Lessee under the Sub Lease, shall be paid to such account as the Head Lessor may from time to time direct;
(c) the Lessee and the Sub Lessee shall ignore the purported exercise of any such rights referred to in paragraph 4.2(a) above by the Lessee and/or the Lessor (as applicable) unless countersigned by the Head Lessor; and:
(d) such notice shall continue to apply until the Lessee and/or the Sub Lessee receive further notice to the contrary from the Head Lessor."
Other facts
"Via Courier and Email.
22 March 2020.
Spicejet Limited, 319, Udyog Vihar, Phase 4, Gurgaon 122016, Haryana, India.
Attention: Legal Department.
Re: The Sub Lease Security Assignment dated 17 May 2017 between Jabberjay Leasing Limited ("Jabberjay"), as assignor and Nok Airlines Public Company Limited ("NOK"), as assignee, in respect of one (1) Boeing 737 800 Aircraft bearing Manufacturer's Serial Number 29670 (as amended, modified, supplemented and/or novated from time to time, the "Sub Lease Assignment") and Lease Security Assignment, dated 14 January 2019, between GASL Ireland Leasing A 1 Limited, as assignee ("GASL Ireland"), and NOK, as assignor, together with the Notice and Acknowledgement to Security Assignment dated 14 January 2019 (the "Security Notice") acknowledged and agreed by NOK, Jabberjay and Spicejet (collectively, the "Security Assignment").
ENFORCEMENT NOTICE.
Dear Sir
We refer to the Sub Lease Assignment and the Security Assignment. All capitalized terms used herein shall have the meanings ascribed to such term in the Security Assignment, unless otherwise defined herein. We herewith inform you that GASL Ireland has issued a Notice of Default and Demand for Payment to NOK under the Aircraft Lease Agreement dated 10 August 2012, between GASL Ireland, as lessor, and NOK, as lessee. We are sending you this Enforcement Notice in connection the exercise of our rights under the Security Assignment. Pursuant to Clause 4.2 of the Security Assignment, with immediate effect we (a) are exercising all of the rights, powers and directions of Jabberjay (under the Sub Lease) and NOK (under the Intermediate Lease and the Sub Lease Security Assignment) to the exclusion of NOK and Jabberjay and (b) hereby direct you to pay all money that is payable under the Sub Lease to the GASL account (defined below) until further notice. Furthermore, as agreed in the Security Notice, you shall ignore the exercise of any rights of NOK and Jabberjay unless countersigned by us. 'GASL Account' shall mean: Bank: Allied Irish Bank Plc, account Name: GASL Ireland Leasing A 1 Limited. Account No: 25177922. Sort Code: 930067. BIC: AIBKIE2D. IBAN: IE39AIBK93006725177922. This Enforcement Notice shall continue to apply until you receive further written notice to the contrary from us. Enforcement Notices have been sent to NOK and Jabberjay as well. This Enforcement Notice and GASL Ireland's actions hereunder are without prejudice to, and GASL Ireland hereby expressly reserves and does not waive, all other rights and remedies of GASL Ireland under the Security Assignment, at law and at equity, with respect to the Event of Default which is the subject of this Enforcement Notice including, but not limited to, GASL Ireland's right to repossess the aircraft and to recover all past and future damages on account of NOK's defaults. This Notice shall be governed and construed in accordance with Clause 9.1 of the Security Assignment. The omission of a reference to any Event of Default or breach which has also occurred does not and will not prejudice, nor constitute a waiver of, any rights we may have either generally, under the Security Assignment, or in respect of this Enforcement Notice.
Sincerely,
GASL IRELAND LEASING A 1 LIMITED.
Name: Karl Griffin,
Title: Director."
"Re: The Sub Lease Security Assignment dated 17 May 2017 between Jabberjay Leasing Limited ("Jabberjay"), as assignor and Nok Airlines Public Company Limitee ("NOK"), as assignee, in respect of one (1) Boeing 737 800 Aircraft bearing Manufacturer's Serial Number 29670 (as amended, modified supplemented and/or novated from time to time, the "Sub Lease Assignment") and Lease Security Assignment, dated 14 January 2019, between GASL Ireland Leasing A l Limited, as assignee ("GASL Ireland"), and NOK, as assignor, together with the Notice and Acknowledgement to Security Assignment dated 14 January 2019 (the "Security Notice'') acknowledged and agreed by NOK, Jabberjay and Spicejet (collectively, the "Security Assignment").
ENFORCEMENT NOTICE
Dear Sir: We refer to the Sub Lease Assignment and the Security Assignment. All capitalized terms used herein shall have the meanings ascribed to such term in the Security Assignment, unless otherwise defined herein. We also refer to the Enforcement Notice dated 22 March 2020. We herewith inform you that GASL Ireland has issued a Notice of Default and Demand for Payment to NOK under the Aircraft Lease Agreement dated 10 August 2012, between GASL Ireland, as lessor, and NOK, as lessee. We are sending you this Enforcement Notice in connection with the exercise of our rights under the Security Assignment. For the avoidance of doubt, this Enforcement Notice is sent without prejudice to the Enforcement Notice dated 22 March 2020. We reserve the right to rely on the Enforcement Notice dated 22 March 2020 and reiterate that any and all actions taken pursuant to the Enforcement Notice dated 22 March 2020 were and remain valid. Pursuant to Clause 4.2 of the Security Assignment and to the extent required, with immediate effect, we (a) are exercising all of the rights, powers and directions of Jabberjay (under the Sub Lease) and NOK (under the Intermediate Lease and the Sub Lease Security Assignment) to the exclusion of NOK and Jabberjay and (b) hereby direct you to pay all money that is payable under the Sub Lease to the GASL account (defined below) until further notice, including those amounts due and payable and not paid to date. For the avoidance of doubt, this includes unpaid Rent at the Delayed Rent Rate (as those terms are defined in the Sub Lease), and interest on unpaid Rent and Supplemental Rent at the Default Rate. Furthermore, as agreed in the Security Notice, you shall ignore the exercise of any rights of NOK and Jabberjay unless countersigned by us. GASL Account" shall mean: Bank, Allied Irish Bank PIc. Account Name, GASL Ireland Leasing A l Limited. Account No, 25177922. Sort Code: 930067. BIC: IBKIE2D. IBAN: AIBK93006725177922. This Enforcement Notice shall continue to apply until you receive further written notice to the contrary from us. Enforcement Notices have been sent to NOK and Jabberjay as well. This Enforcement Notice and GASL Ireland's actions hereunder are without prejudice to, and GASL Ireland hereby expressly reserves and does not waive, all other rights and remedies of GASL Ireland under the security Assignment, at law and at equity, with respect to the Event of Default which is the subject of this Enforcement Notice including, but not limited to, GASL Ireland's right to repossess the aircraft and to recover all past and future damages on account of NOK's defaults. This Notice shall be governed and construed in accordance with Clause 9.1 of the Security Assignment. The omission of a reference to any Event of Default or breach which has also occurred does not and will not prejudice, nor constitute a waiver of, any rights we may have either generally, under the Security Assignment, or in respect of this Enforcement Notice.
Sincerely
GASL IRELAND LEASING A l LIMITED."
"By Email.
Reed Smith LLP, The Broadgate Tower, 20 Primrose Street, London EC2A 2RS.
FAO: Alexander Sandiforth; Richard Hakes.
Dear Sirs/Madams,
GASL Ireland Leasing A 1Limited ("Claimant") v SpiceJet Limited ("Defendant").
1. We refer to your email dated 16 June 2021. Terms used in this letter have the same meaning as those used in the Particulars of Claim filed and served on behalf of our client dated 22 March 2021.
2. As noted in your email, the parties have been engaged in ongoing without prejudice discussions in relation to the Aircraft since prior to the Scheduled Expiry date of 27 November 2020.
3. Those negotiations have not resolved the dispute between the parties.
4. The Aircraft, in our client's view wrongfully, remains in your client's possession. In the Defence filed on behalf of your client on 10 June 2021, your client has not put forward any defence to the claims for (inter alia) unpaid Rent, Supplemental Rent and Default Interest or to the claims set out in Appendix 2 to the Particulars of Claim.
5. In the circumstances, our client sees that there is nothing to be gained from engaging in any further form of Alternative Dispute Resolution, in addition to the lengthy negotiations between the parties which have to date proved fruitless.
6. However, if your client demonstrates some new good faith commitment resolution of the dispute and is willing to assist our client in the exercise of its rights to repossession the Aircraft and in the provision of all necessary documentation, our client is prepared to consider ADR.
7. Our client requests that your client, as a sign of the good faith required for any successful ADR provides the following documents to our client by 5pm (London) on Thursday 24 June 2020:
(a) a completed GR Waiver form;
(b) a copy of your client's latest Goods and Services Tax returns evidencing payment of Integrated Goods and Services tax (IGST) against the Aircraft;
(c) a completed application for an IGST No Dues Letter from the Central Board of Indirect Taxes and Customs for the Aircraft;
(d) a letter from a chartered accountant confirming that IGST has been paid against the Aircraft.
(e) a Letter undertaking to pay any taxes, if any, that remain unpaid in respect of the Aircraft prior to export;
(f) evidence of payment of all airport charges in respect of the Aircraft to date; and:
(g) a Letter confirming that the Aircraft has been used for scheduled services as required for import.
8. If all of the above documents are not received by the time stated above, our client is minded to take such steps as are necessary to exercise its Irrevocable De Registration and Export Request Authorisation rights without further notice.
9. Our client reserves all its rights. Yours faithfully." "Watson Farley & Williams LLP."
"Dear Sirs,
We refer to your letter of 18 June.
Our clients remain willing to return the aircraft and can provide the documents requested. However, their position is that any agreement over redelivery should also take account of the claims made by your client against SpiceJet in the above captioned court proceedings, which should all be wrapped up in one overarching settlement agreement provision of the requested documents and redelivery of the aircraft should not be a precondition to mediation (or to considering mediation, as stated in your letter). The point made in your letter about demonstrating good faith commitment to the resolution of the dispute works both ways especially when there is no commitment to mediation even were the aircraft to be returned.
Therefore it seems to us that if progress is to be made, it makes far more sense for your clients to agree to mediation. Just because negotiations have not yet resulted in a commercial resolution does not mean that a Mediation could not break the impasse. The presence of a mediator may well make all the difference and the parties can of course speak to a mediator confidentially on an individual basis and be more open than they can in commercial discussions, such that the mediator may well be able to assist the parties in making progress.
Our clients remain willing to mediate and it is up to your clients to decide whether they wish to engage in that process. If not, then our clients cannot force them to do so, but we do consider mediation is in the best interests of both parties given the current state of the aviation industry. We hope your clients will be willing to reconsider their position.
Yours faithfully,
Reed Smith LLP."
History of this application
Legal test
Issues for determination
(i) Is the defendant estopped from relying on any ineffectiveness of the First Enforcement Notice?
"9A. It is admitted that what purported to be an Enforcement Notice dated 15 October 2021 was sent by courier and by email to the Defendant, but no admission is made as to whether it was
sent by facsimile or to the facsimile number designated as pleaded above, or as to its validity or effects or the correctness of the assertions made therein. To that extent, but that extent only, paragraph 19A of the Amended Particulars of Claim is admitted but it is otherwise denied. For the avoidance of doubt, it is denied that it was a contractual notice as alleged or at all."
"As to paragraph 9 in respect of the Enforcement Notice and paragraph 9A the Defendant in respect of the Further Enforcement Notice purports to plead a denial that it neither 'was a contractual notice as alleged or at all'. Neither is a proper pleading because in neither case does the Defendant state its reasons for the denials contrary to the mandatory provisions of CPR 16.1 and 16.2 that states that:
'16.5 (1) In his defence, the defendant must state:
(a) which of the allegations in the particulars of claim he denies;
(b) which allegations he is unable to admit or deny, but which he requires the claimant to prove; and (c) which allegations he admits.
(2) Where the defendant denies an allegation:
(a) he must state his reasons for doing so ..'
The Claimant will contend that such a defective pleading debars the Defendant from putting forward any case as regards the Enforcement Notice or the further Enforcement Notice. The Claimant does not know because the Defendant has failed to plead the case that the Claimant has to meet in this respect. The Claimant repeats paragraphs 19 and 19A of the Amended Particulars of Claim."
"The Defendant is estopped from alleging that the Enforcement Notice referred to in Paragraph 19 was not effective as a contractual notice, notwithstanding any deficiency (which are all denied) in its method of delivery or otherwise, by reason of the following:
PARTICULARS OF CONDUCT RAISING ESTOPPEL:
(a) On 19 March 2019, the Claimant sent an enforcement notice to the Defendant ('2019 Enforcement Notice'), requiring it to pay Rent and Supplemental Rent directly to the Claimant. Prior to 19 March 2019 the Defendant made no payments of Rent or Supplemental Rent directly to the Claimant and made all such payments to JLL or Nok. Between 19 March 2019 and 8 November 2019, the Defendant paid Rent and Supplemental Rent directly to the Claimant.
(b) On 13 November 2019, the Claimant revoked the 2019 Enforcement Notice directing the Defendant to resume paying Rent and Supplemental Rent in accordance with the terms of the sublease. On and after that date, and until the payment referred to in sub paragraph (e) below, the Defendant did not pay Rent and Supplemental Rent to the Claimant and made all such payments to JLL or Nok.
(c) On 22 March 2020, the Enforcement Notice was delivered by the Claimant to the Defendant.
(d) The Defendant raised no question as to whether the Enforcement Notice was intended to have contractual effect and/or the effects pleaded in Paragraph 19, until the Defence was filed on 11 June 2021.
(e) On 27 May 2020, the Defendant paid directly to the Claimant $US50,000 in Rent in relation to the Aircraft to account number 25177922 Sort code 93 00 67, IBAN IE39 AIBK 9300 6725 1779 22. Confirmation of that payment was provided in an email from Ms Ashima Arora on behalf of the Defendant to Mr Pat Madigan on behalf of the Claimant dated 27 May 2020 with the subject 'Rent payment'.
(f) On 29 May 2020, the Defendant paid directly to the Claimant $US30,000 in Rent in relation to the Aircraft to account number 25177922 Sort code 93 00 67, IBAN IE39 AIBK 9300 6725 1779 22. Confirmation of that payment was provided in an email from Ms Ashima Arora on behalf of the Defendant to Mr Pat Madigan on behalf of the Claimant Dated 1 June 2020 with the subject 'Re: Rent payment'.
(g) On 18 June 2020, the Defendant paid directly to the Claimant $US133,875 in Rent in relation to the Aircraft to account number 25177922, sort code 93 00 67, IBAN IE39 AIBK 9300 6725 1779 22. Confirmation of the intention to make that payment was provided in an email from Ms Ashima Arora on behalf of the Defendant to the Claimant dated 18 June 2020 with the subject 'Re: Rent & Maintenance Payment MSN 29670'.
(h) On 23 July 2020, the Defendant paid directly to the Claimant $US101,085 in 'Rent' in relation to the Aircraft to account number 25177922, sort code 93 00 67, IBAN IE39 AIBK 9300 6725 1779 22. Confirmation of the payment was provided in an email from Ms Ashima Arora on behalf of the Defendant to Mr Pat Madigan on behalf of the Claimant dated 23 July 2020 with the subject 'Re: Rent & Maintenance Payment MSN 29670'. In that email, Ms Arora stated that the Defendant had 'released another rent payment as per utilization [sic]'. (Emphasis added)."
(i) In reliance on the above pleaded words and conduct, the Claimant:
(i) believed that the Defendant had accepted that the enforcement Notice had the effects set out in paragraph 19 of the Amended Particulars of Claim; and:(ii) did not re deliver the Enforcement Notice or issue a further Enforcement Notice at any time prior to the Defendant taking issue with the Enforcement Notice in the Defence filed and served on 10 June 2021.(iii) Had the Defendant raised any point as to the validity of the Enforcement Notice at about the time of service the Claimant would have investigated the issue at that time and if necessary have re served the same but did not do so until the Defendant did not admit the validity of the method of service in the Defence."
"5. On 22 March 2020, the Claimant issued and served an Enforcement Notice on the Defendant. [JLR1/1]. The Enforcement Notice was sent by me. The Enforcement Notice was issued by the Claimant in order to trigger the Defendant's obligation to pay rent in respect of the Aircraft directly to the Claimant, as a result of the Sub Lease Assignment Deed, the Security Assignment Deed and the Notice and Acknowledgement.
6. I emailed the Enforcement Notice to the Defendant on 22 March 2020 [JLR1/3]. My team has been unable to find any evidence that the Enforcement Notice was faxed or couriered to the Defendant at the same time and, for the purposes of this summary judgment application, the Claimant is prepared to progress on the basis that it was neither faxed nor couriered.
7. The Defendant made part payments of Rent directly to the Claimant in May, June and July 2020 on the dates and in the amounts set out below:
8. Confirmations of these payments are provided with this witness statement [JLR1/4]. I understand, and am informed by Mr Pat Madigan, Senior Vice President of Genesis, that the Defendant informed Genesis's commercial team at the beginning of May 2020 that it was unable to pay the full amount of Rent and Supplemental Rent due and payable to the Claimant but that these pro rata payments of Rent to the Claimant were based on its utilisation of the Aircraft. This is confirmed in emails from the Defendant to the Claimant between May 2020 and July 2020, which are provided with this witness statement [JLR1/7]. The Claimant accepted these part payments of Rent, but did not waive, and indeed maintained, its rights to full payment from the Defendant."
"8. In relation to the Enforcement Notice [AJW1/561], I note that Mr Ward and Ms Reimers both acknowledge (at paragraphs 33 and 6 of their respective statements) that there is no evidence that the Enforcement Notice was faxed or couriered to SpiceJet, in accordance with the notice requirements of clause 7.2 of the Notice and Acknowledgement (assuming this was valid and effective in the first place).
9. SpiceJet does not accept that either the Enforcement Notice or the Further Enforcement Notice [AJW1/565] were properly served or entitled the Claimant to demand payment of the amounts claimed (or indeed any amounts) directly from SpiceJet. Nor does SpiceJet accept that the Letter of Demand [AJW1/563] or the further Letter of Demand [AJW1/567] took effect as Lessor Determinations of Amounts Due pursuant to clause 8.7 of the Sublease."
"Perhaps acknowledging the technical correctness of SpiceJet's point on the purported first Enforcement Notice, the Claimant then invokes an alleged waiver or an estoppel (see paragraphs 3 5 of its Reply at Tab 7, pp.97 100). They are arguments ill adapted to a Part 24 application. They are critically factual and fact sensitive. The Claimant asserts both representation and reliance and perhaps detriment, but Ms Reimers' evidence on this issue is startlingly brief, given the factual issues involved, and adds little to the Claimant's pleaded case. Waiver/estoppel arguments are simply not appropriate to be dealt with on the present application. Let us see if, at the hearing, the Claimant maintains these arguments as being apt for summary judgment."
(ii) Were the First Enforcement Notice and the Second Enforcement Notice ineffective?
"19. The Claimant's Skeleton criticises SpiceJet for having failed to admit various facts when the Claimant thinks SpiceJet ought to have admitted them, although they are facts of which the Claimant formally bears the onus of proof. It is not the undersigneds' understanding of the law that a party is legally obliged to admit facts simply because the party asserting those facts thinks it ought to. If a party making an allegation thinks that there are facts which should be admitted, it can always serve a Notice to Admit and in due course secure an appropriate costs Order when it is otherwise appropriate. If they are facts which are easy for the Claimant to prove, then so be it and the costs of such proof will be minimal.
20. A defendant is still entitled to require a claimant to prove its case, and many of the documents relied upon by the Claimant are agreements to which SpiceJet was not party. The relevant facts that the Claimant asserts should have been admitted in SpiceJet's Amended Defence include facts in relation to agreements to which SpiceJet was not itself a party.
21. In any case, SpiceJet now accepts that such documents accurately reflect the terms agreed between the parties to them. It also accepts that the Further Enforcement Notice (dated 15th October 2021) was properly served and that the second Letter of Demand was an effective determination under clause 8.7 of the Sublease. SpiceJet also no longer maintains any case requiring expert evidence of Indian law and the restrictions imposed by the Indian government, which speak for themselves. The issues that are still 'live' and are relevant to the Summary judgment Application are addressed below.
41. Until a valid Enforcement Notice was properly served in accordance with clause 7 of the Notice and Acknowledgement (Tab 18, pp.737 739), there was no legal obligation on SpiceJet to pay Rent to the Claimant at all. Until that important stage was reached, Rent and Supplemental Rent were payable only to the sub sub lessor (Jabberjay). Thus the service of a valid Enforcement Notice is critical to the Claimant being able to establish that SpiceJet owed any legally enforceable obligation to the Claimant to pay Rent. By parity of reasoning, the same applies to Default Interest considered further below.
42. The Claimant still relies on the purported service of its first Enforcement Notice by a non contractual method. For such contractually important notices technical precision is required. Thus in Trafigura Beheer BV v Ravennavi SpA (The Port Russel) [2013] EWHC 490 (Comm); [2013] 2 Lloyd's Rep 57 Popplewell J (as he then was) held that a clause which stipulated that NOR 'may be given either by letter, fax, telegram, telex, radio or telephone' was an exclusive provision and that a notice given by email was invalid and laytime accordingly did not commence.
43. For reasons spelt out above, it is unsurprising in the present circumstances that SpiceJet has taken what might be characterised by the Claimant as a 'technical' point. Apparently, the Claimant is entitled to rely on technical points, but not SpiceJet. On a Part 24 application that is not appropriate."
"In any case, SpiceJet now accepts that such documents accurately reflect the terms agreed between the parties to them.
It also accepts that the Further Enforcement notice (dated 15th October 2021) was properly served but SpiceJet does not accept that the second Letter of Demand was an effective determination under clause 8.7 of the Sublease. SpiceJet also no longer maintains any case requiring expert evidence of Indian law and the restrictions imposed by the Indian government which speak for themselves. The issues that are still 'live' and are relevant to the summary Judgment Application are addressed below."
"The clause does not require the tenant to use any particular form of words. He must use words which unambiguously convey a particular meaning, namely an intention to terminate the lease on 13 January."
(iii) Duration of rent payments: redelivery date
"11. The question of whether the Aircraft was redelivered, or should be treated as having been redelivered, on the Scheduled Expiry Date, or what date should be treated as the actual Expiry Date, is of course relevant to the question of whether SpiceJet continued to be liable to pay Rent or Supplemental Rent beyond the Scheduled Expiry Date of 27 November 2020 and is therefore relevant to all claims for rent relating to periods after that date.
12. Furthermore, in relation to the claim for Supplemental Rent (for periods both before and after the Scheduled Expiry Date) the Claimant has provided no explanation or evidence to support the amounts claimed, including (for example) of the Engine Flight Hours or Engine Cycles or APU Operating Hours during the relevant periods (which information is required to calculate the elements of Supplemental Rent payable under paragraphs 1(b), (c) and (e) of Schedule 7 to the Sublease Agreement). It is therefore not possible to assess whether the amounts of Supplemental Rent claimed have been correctly calculated or whether there is any factual dispute in relation to the figures underlying any calculations.
13. Otherwise, while the amended Appendix 1 to the Amended Particulars of Claim has corrected the obvious errors that appeared in the original version, there nevertheless appear to be errors in relation to (at least) the interest calculations, which appear not to take into account changes in the alleged default interest rate over time so that, for example, it seems that default interest is charged on rent said to be due from 15 March 2020 at a rate of 2.61% for the whole period from that date to the date of the pleading notwithstanding the variations in Libor over this period. There is no explanation or evidence to support the interest rate figures used in the calculations."
"15. As to paragraph 26 of the Amended Particulars of Claim, the express terms of the said Lease are admitted but that paragraph is otherwise denied. In particular it is denied that the Defendant has failed to redeliver the Aircraft in any material respect. The Aircraft is at an FAA approved location and no other location has been agreed by the defendant. The operation of Indian Covid-19 legislation has made it impossible and illegal to do more than have the Aircraft (which is based in India) ready for the taking of possession by its lawful owner (as to whose identity no admissions are made) as and when such lawful owner sees fit to do so. The Defendant has done all it lawfully can and must to permit this."
(iv) Supplemental Rent
(v) Points not pursued
(vi) "Other compelling reasons" / adjournment / stay
"11. SpiceJet's Unaudited Standalone and Consolidated Financial Results for the quarter and nine months period ended 31 December 2021 (the 'December 2021 results') are at [CS/20 31]. Note 8 of the standalone accounts states, 'The Company has earned a net profit (after other comprehensive income) of Rs. 230.30 million for the quarter ended 31 December 2021 and incurred a net loss of Rs. 12,627.67 million for the nine months period ended 31 December 2021, and as of that date, the Company has negative retained earnings of Rs. 54,534.32 million and negative net worth of Rs. 38,307.10 million'. SpiceJet's negative net worth as at 31 December 2021 was therefore approximately £381.175 million. Not only is the negative net worth significant, so also is the lack of cash flow and the ability to service debts as they fall due. The Claimant's present claims, if enforced at the present time, are likely to cause significant potential cross defaults under other agreements, as I describe at 17 below, and thus imperil the very existence of the company."
"21. Given SpiceJet's financial position as outlined at paragraphs 8 to 17 above and the difficulties in raising additional financing, I am of the view that a commercially negotiated resolution between the parties would facilitate the best outcome for all involved and in particular the best outcome for the Claimants. Any other outcome would be negative for them as well as all other creditors of SpiceJet.
22. As I outline above, if the Claimants persist in their claims SpiceJet may have no alternative but to seek insolvency relief and that would cause potentially fatal damage to SpiceJet without benefiting the Claimants in any material or financial sense. The only realistic possibility of meeting some or all of the Claimants' claims is if SpiceJet has time to recoup its enormous losses by trading out of the hole it currently finds itself in. Trading out, if time is given, is a very real possibility, but time is all important."
"So in one sense, it is true that SpiceJet does have a general commercial strategy of trying to get itself into a position to honour its proper obligations. Delay is a significant, but not the only, aspect of that. It is not a dishonourable delay, but rather the reverse. Sometimes creditors, who wish their due, must appreciate this and it is no use saying there is a 'hell and high water' obligation if there is no financial ability to satisfy it."
(Dublin) Limited v SpiceJet Limited [2021] EWHC 1117 (Comm) in which he had persuaded that judge to stay certain other claims against SpiceJet.
"I deal first with the claims relating to MSN 64507 and MSN 64509. My conclusion is that it would be appropriate to grant a stay of execution in relation to these claims. This is for the following reasons:
i) There is no evidence before me as to the financial standing of the Second and Third Claimants. Accordingly, their ability to repay should the contracts
become frustrated at a future date cannot be assured.
ii) By contrast, the evidence suggests that the Defendant is currently in a parlous financial state and that being required to pay all outstandings now may well tip it over the edge into insolvency at the very time that there is some small indication that it may be able to trade its way out of difficulty if given enough time.
iii) As argued by the Defendant, insolvency would be contrary to the Claimants' own interests as it would inevitably result in them only receiving a dividend when, with patience, they might recover a larger payout in due course. In other words - and somewhat counter-intuitively - the risk of prejudice to the Claimants will in fact be minimised by not permitting them to enforce any judgment.
iv) The obvious riposte to this latter argument is two-fold. First, the whole purpose of a "no set-off" clause is to assure payment to the creditor even where (or perhaps especially where) the debtor is in financial difficulties. Secondly, it is a matter for the Claimants. If they take the view that their interests are best served by seeking to enforce a judgment which they have no hope of being paid in full, it is not for the court to say otherwise. That said, I accept that this is more than simply a question of financial difficulty for the Defendant; its continued existence is at stake. Its ability to pay rent under the Lease Agreements was wholly dependent on its ability to operate the aircraft and, through no fault of its own, the wholly unforeseeable "double whammy" of Covid and the MAX 8 tragedies now renders it unable to fly MSN 64507 and MSN 64509 at all and able to operate MSN 41397 only to a very limited and unprofitable extent."
Conclusions