QUEEN'S BENCH DIVISION
LONDON CIRCUIT COMMERCIAL COURT
Rolls Building Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
SITTING AS A DEPUTY JUDGE OF THE HIGH COURT
____________________
SETHIA LONDON LIMITED |
Claimant |
|
- and - |
||
(1) MR AJAY SETHI (2) MRS DEEPNA SETHI |
Defendants |
____________________
DUNCAN MACPHERSON (instructed by Zaiwalla & Co) for the Defendants
Hearing dates: 29, 30 September and 1 October 2020
____________________
Crown Copyright ©
Covid-19 Protocol: This judgment was handed down by the judge remotely by circulation to the parties' representatives by email and release to BAILII. The date and time for hand-down is deemed to be 22 February 2021 at 3pm
Contents
The criminal proceedings in Dubai
The civil proceedings in Dubai
The law in relation to summary judgment
The applicable principles when considering whether to grant permission to amend a statement of case
The Contractual and Double Recovery Defences - Mr Sethi's submissions
SLL's submissions on the Contractual and Double Recovery Defences
Discussion and conclusion on the Contractual and Double Recovery Defences
SLL's submissions on the application of Section 34 of the CJJA
Discussion and conclusion on Section 34 of the CJJA
Mr Sethi's submissions on the breach of the principle in Henderson v Henderson
SLL's Submissions on the principle in Henderson v Henderson
Discussion and conclusion on the principle in Henderson v Henderson
Conclusion on the draft amendments
Is SLL entitled to default interest?
Conclusion on default interest
Is there some other compelling reason why the matter should go to trial?
MR ANDREW HOCHHAUSER QC :
Introduction
Representation
The evidence
(1) The second witness statement of Abhijit Kandeparkar, a solicitor and director in CND Parker, SLL's solicitors representing SLL, dated 3 March 2020 ("Kandepakar 2") and exhibit AK-2, in support of SLL's summary judgment application;
(2) The first witness statement of Leigh David Crestohl, a partner in Zaiwalla & Co, the Defendants' solicitors, dated 25 July 2020 ("Crestohl 1") and exhibit LC-1, in support of an adjournment, alternatively a stay of SLL's application;
(3) The first witness statement of Ajay Sethi Shakti Chand Sethi dated 25 July 2020 ("Sethi 1") and exhibit AS-1, in support of an adjournment, alternatively a stay of SLL's application;
(4) The second witness statement of Leigh David Crestohl dated 18 September 2020 ("Crestohl 2") and exhibit LC-2, in opposition to SLL's summary judgment application;
(5) The second witness statement of Ajay Sethi Shakti Chand Sethi dated 18 September 2020 ("Sethi 2") and exhibit AS-2, in opposition to SLL's summary judgment application
Parties
Background
(1) Clause 1 contains the following definitions:
"Default Interest Period: each period of days the Lender selects under clause 7.2 to calculate interest on Unpaid Amounts under clause 7.
Event of Default: any event or circumstance listed in Schedule 7
Repayment Date: 06 months from the first Drawdown Date specified in paragraph 1 of Schedule 3 for repaying the Loan
Clause 1.21: Clause, schedule and paragraph headings shall not affect the interpretation of this agreement."
(2) Clause 6 provides for the payment of interest, as follows:
"6.1 The interest rate on the Advance for each Interest Period is 15% (fifteen percent) per annum (360 days).
6.2 The Borrower shall pay interest on the Advance in arrears on the Interest Payment Date for the Interest Period applicable.
6.3 The length of the Interest Period shall be one month.
6.4 The initial Interest Period for the Advance shall start on the Drawdown Date of the Advance.
6.5 If an Interest Period would otherwise end on a day which is not a Business Day, that Interest Period shall, instead, end on:
(a) the next Business Day in that calendar month, if there is one; or
(b) the preceding Business Day, if there is not."
(3) Clause 7 is entitled Default Interest and provides as follows:
"7.1 If the Borrower does not pay any sum it is obliged to pay under the Finance Documents when it is due, the Borrower shall pay interest under this clause 7 on that Unpaid Amount from time to time outstanding for the period beginning on its due date and ending on the date the Lender receives it, both before and after judgment.
7.2 Interest under this clause 7 shall be calculated by reference to successive Default Interest Periods. The duration of a Default Interest Period shall be seven days or less, as selected by the Lender on or before the beginning of each Default Interest Period.
7.3 The first Default Interest Period shall begin on the due date for payment of the relevant Unpaid Amount and each succeeding Default Interest Period shall begin on the last day of the previous Default Interest Period.
7.4 The rate of interest applicable to any Default Interest Period shall be the rate per annum which is 5% higher than the rate of interest which would have applied under clause 6.1, had the Default Interest Period been an Interest Period.
7.5 The Lender shall promptly notify the Borrower of the amount of interest payable and the Interest Payment Date for that Default Interest Period.
7.6 Interest accrued under this clause 7 shall be due on demand by the Lender, but:
(a) if not previously demanded, shall be paid on the last day of each Default Interest Period; and
(b) if the Borrower does not pay that interest when due, it shall be added to the Unpaid Amount and compounded at the end of each Default Interest Period."
(4) Clause 8 is entitled "Repayment, Prepayment and Cancellation" and states:
"Schedule 3 shall apply to repayment, prepayments and cancellation of the Facility."
(5) Schedule 3 paragraph 2 provides that:
"2.1 The Borrower may prepay part or all of an Advance, without any premium or penalty, by notifying the Lender 5 Business Days in advance. The Borrower may only do this if:
(a) the notice specifies the amount of the prepayment.
(b) the date of the prepayment is at least 5 Business Days from the date of the notice…."
(6) Clause 9.1 and 9.2 form part of the payment obligations:
"9. PAYMENTS
9.1 Subject to satisfaction of all the applicable conditions in clause 4, the Lender shall pay each Advance to the Borrower in immediately available cleared funds on the relevant Drawdown Date to, or for the account of, the Borrower as specified in that Drawdown Request.
9.2 Subject to clause 9.6, the currency of account shall be US Dollar and all payments that the Borrower makes under this agreement shall be made:
(a) in full, without any deduction, set-off or counterclaim; and
(b) in immediately available cleared funds on the due date to an account which the Lender may specify to the Borrower."
(7) Clause 14 concerns Events of Default:
"14.1 Each of the events or circumstances set out in Schedule 7 is an Event of Default.
14.2 At any time after an Event of Default has occurred and is continuing, the Lender may, by notice to the Borrower, declare:
(a) all outstanding Commitments immediately cancelled; and/or
(b) all outstanding Advances, accrued interest and all other amounts accrued or outstanding under the Finance Documents:
(i) immediately due and payable; or
(ii) payable on demand.
(c) the Security Document to be enforceable.
14.3 If the Lender gives notice under clause 14.2(b) then the Advances and other amounts shall be immediately due and payable by the Borrower."
(8) Non-payment is an Event of Default under paragraph 1 of Schedule 7.
(9) Clause 24.2 states: "The lender is neither precluded from taking proceedings against the borrower in any other court of competent jurisdiction, nor shall the taking of proceedings in one or more jurisdictions preclude the taking of proceedings in any other jurisdictions, whether concurrently or not, to the extent permitted by the law of such other jurisdiction."
"the Borrower agrees that his property at Villa No. W-43, AI Tlianayah Fourth Emirates Hill, Dubai, United Arab Emirates (Premise Number: 394922018) shall immediately stand charged to the Lender upon the occurrence of an Event of Default and the Borrower unconditionally and irrevocably agrees that the property may be sold immediately by the Lender for the recovery of the Loan together with interest, default interest, costs and charges as applicable."
"all monies, debts and liabilities of any nature from time to time due, owing or incurred by the Borrower to the Lender under or in connection with the Loan Agreement."
"2.1 In consideration of the Lender making or continuing loans to, giving credit, accommodation or time to the Borrower at the Lender in its absolute discretion sees fit, the Guarantor guarantees to the Lender to pay on demand the Guaranteed Liabilities.
2.2 If the Guaranteed Liabilities are not recoverable from the Borrower by reason of illegality, incapacity, lack or exceeding of powers, ineffectiveness of execution or any other reason, the Guarantor shall remain liable under this Guarantee for the Guaranteed Liabilities as if she was a principal debtor.
2.3 The Guarantor as principal obligor and as a separate and independent obligation and liability from her obligations and liabilities under clause 2.1 agrees to indemnify and keep indemnified the Lender in full and on demand from and against all and any losses, costs, claims, liabilities, damages, demands and expenses suffered or incurred by the Lender arising out of, or in connection with, any failure of the Borrower to perform or discharge any of her obligations or liabilities in respect of the Guaranteed Liabilities."
"The liability of the Guarantor under this Guarantee shall not be reduced, discharged or otherwise adversely affected by:
(a) any intermediate payment, settlement of account or discharge in whole or in part of the Guaranteed Liabilities; or
(b) any variation, extension, discharge. compromise, dealing with, exchange or renewal of any right or remedy which the Lender may now or after the date of this Guarantee have from or against any of the Borrower and any other person in connection with the Guaranteed Liabilities; or
(c) any act or omission by the Lender or any other person in taking up, perfecting or enforcing any Security, indemnity, or guarantee from or against the Borrower or any other person; or
(d) any termination, amendment, variation, novation or supplement of or to any of the Guaranteed Liabilities; or
(e) any grant of time, indulgence, waiver or concession to the Borrower or any other person; or
(f) any insolvency, bankruptcy, liquidation, administration, winding up, incapacity, limitation, disability, the discharge by operation of law, or any change in the constitution, name or style of the Borrower or any other person; or
(g) the death or incapacity (whether mental or physical) of the Guarantor, or any notice of her death or incapacity; or
(h) any invalidity, illegality, unenforceability, irregularity or frustration of any actual or purported obligation of, or Security held from, the Borrower or any other person in connection with the Guaranteed Liabilities; or
(i) any claim or enforcement of payment from the Borrower or any other person; or
(j) any act or omission which would not have discharged or affected the liability of the Guarantor bad it been a principal debtor instead of a guarantor, or indemnifier or by anything done or omitted by any person which but for this provision might operate to exonerate or discharge the Guarantor or otherwise reduce or extinguish its liability under this Guarantee."
"RECITALS
C. For the avoidance of any doubt, the ultimate beneficial owner of SLL and NSIL is [Mr Sethia].
1. The Parties have agreed that if [Mr Sethi] fails to repay the Loan Amount to SLL by 30 September 2019 ("Deadline"), [Mr Sethi] undertakes to transfer the [Villa] as settlement of the loan to [Mr Sethia] or his nominee ("Future Buyer") no later than the Transfer Date ("Transaction") …
1. Interpretation
In this Agreement, except where the context otherwise requires, the following word shall have the following meanings:
"Applicable Law" means any law in the United Arab Emirates either as federal law or as law, order or regulation in the emirate of Dubai that requires the relationship between the parties in respect of the Property….
3. Transaction
3.2 Prior to the Effective Date of this Agreement, [Mr Sethi] has handed over an original undated personal cheque drawn in favour of NSIL in an amount of AED 7,900,000 ("Supplementary Cheque") ….
3.3 In the event that [Mr Sethi] fails to settle the Loan Amount by the Deadline, the Parties agree that [Mr Sethia], SLL and NSIL have the following remedies which they can exercise at their sole discretion, in any order:
(a) the Parties agree that [Mr Sethi] must transfer the [Villa] to the Future Purchaser before Dubai Land Department on a date nominated by [Mr Sethia] in his sole discretion ("Transfer Date"). For purposes of transfer, [Mr Sethi] irrevocably authorizes [Mr Sethia], SLL and NSIL to utilize the power of attorney and submit Contract F pursuant to Clause 3.1 of this Agreement. [Mr Sethi] further authorizes [Mr Sethia], SLL and NSIL to approach Dubai Islamic Bank for settlement of the Loan Amount and obtain their no objection certificate and to approach the master developer of the Property (i.e. Emaar Properties PJSC) for their no objection to complete the title transfer; and/or
(b) if the Future Purchaser is unable to acquire the Property on the Transfer Date due to any reason, [Mr Sethi] irrevocably authorises and directs NSIL to immediately date and encash the Supplementary Cheque towards the settlement of the outstanding Loan Amount …
5. Default
5.1 [Mr Sethi] and [Mrs Sethi] how be considered in the fault of its obligations under this agreement in any of the following events:
(a) [Mr Sethi] or [Mrs Sethi] fail to perform any of its obligations under this agreement;
(d) [The Cheque] is dishonoured at the time of encashment by NSIL …
5.2 Upon the happening of any event of default pursuant to clause 5.1 of this Agreement, the Parties agree and acknowledge that SLL NSIL and [Mr Sethia] reserved their legal rights under the applicable law to take the necessary civil and criminal actions against [Mr Sethi] and [Mrs Sethi] to protect their rights under the Applicable Law (defined as and pursuant to this agreement….
9. Governing Law and Jurisdiction
This Agreement and the rights of the Parties shall be governed by the laws of Dubai and the Federal Laws of the United Arab Emirates and the Parties agree that any legal action or proceeding with respect to this agreement shall be subject to the exclusive jurisdiction of the Courts of Dubai.
This Agreement does not affect the rights, powers and interests of the parties under this Agreement under any other law or jurisdiction for the time being in force."
"(v) the original undated personal security cheque no. 401622 of Bank of Baroda, Dubai issued and already handed over by the Borrower ("Borrower Cheque") drawn in favour of NS Investments Limited, ("NSIL") in an amount of AED 7,900,000 to the Lender, and in case Borrower didn't transfer the property W43, Emirates Hills, Dubai to the Lender.
(vi) the original undated personal cheque issued by the Personal Guarantor ("Guarantor Cheque") drawn in favour of NSIL in an amount of AED."
"3. EFFECT OF AMENDMENT-III
Except as expressly amended, restated or agreed in this Amendment-III, the Facility Agreement and the security provided by the Borrower and the Personal Guarantor shall continue in full force and effect. Default interest (at the rate of 20% per annum) till August 2019 shall be paid by the Borrower on or before 10th September 2019 and remainder default interest (at the rate of 20% per annum) along with the principal sum outstanding shall be paid on or before 30th September 2019."
"As property Villa W43, Emirates Hills, Dubai was a security towards to the loan in the 1st Facility Agreement dated. 31st Aug, 2017 so the following remedy has been discussed and agreed
4.1 The Borrower Chequeand the Guarantor Chequeshall be encashed if the Borrower failsto repay the Unpaid Amount to the Lender by the Deadline date. Transfer the property W43, Emirates Hills, Dubai up to 30th Sept, 2019 (as discussed and agreed DIB outstanding loan of 18.574,228.00 will be paid by the Lender to cover the balance amount of UK loan USD.1,950,000.00 + remaining interest of USD.206,686.00 and will transfer the property W43 under the name of Lender).
4.2 In case Borrower receive any other loan on property W43, Emirates Hills from other bank before 30th Sept, 2019 the amount will be paid by the Borrower to the Lender directly to UK account to settle the balance amount of UK loan + Interest.
4.3 In case Borrower will able to Sell the property W43, Emirates Hills, Dubai before 30th Sept, 2019 after paying the outstanding DIB loan Lender will clear the outstanding UK loan and remaining interest.
4.4 In case Borrower fails to settle the loan by 30th Sept, 2019, he will transfer the property W43 to the Lender and as discussed and agreed by the Lender outstanding loan amount of DIB will be settled by the Lender.
4.5 In case Borrower didn't transfer the property W43 or if there is any block from the bank or Borrower, Lender has the right to use the Security Cheque 401622 of Bank of Baroda for AED.7,900,000.00 by 30th Sept, 2019 which has already been issued by the Borrower to the Lender."
"3) As discussed, security cheque for AED.7.90 Mn has been given in case there is any issue in the transfer of property then you may bank the security cheque.
4) In worst case scenario as a goodwill gesture and my good intention I have already explained you my background of the losses by a very loan SMS. I couldn't sign the legal document because of bank loan and any legal issue may arise with bank. However your team has given a new version of agreement that in case I don't pay the outstanding UK loan and remaining interest by 30th Sept, 2019 you will encash the security cheque. If you please look into worst case scenario, how can I get funding and in case I block the transfer of Villa then you can use the cheque. I am under lots of pressure for sorting out my 3rd Sept loan payment & 10th Sept interest payment so I can focus to sell the property & settle the UK loan matter."
The criminal proceedings in Dubai
The civil proceedings in Dubai
(1) the unsigned Side Agreement had no legal effect, although the Grounds of Appeal stated "an initial loan agreement was signed on August 6, 2019, stating that [SLL] will grant the Appellant a loan of four million US dollars, to be repaid at agreed periods between the two parties in accordance with paragraph E of the agreement." [emphasis added];
(2) NSIL had no basis for retaining the Cheque;
(3) the Cheque was security provided in respect of a loan under the Side Agreement that was never agreed and which remained "in the negotiating stage";
(4) the burden of proof lay on NSIL to show that the fulfilment of the condition to cash the Cheque, namely the non-payment of the Loan and the failure to transfer the Villa, which it had not done;
(5) there should be an adjournment of NSIL's claim until the conclusion of Mr Sethi's criminal complaint against it and these proceedings, which by then were on foot.
"2. The Appellant received the loan amount. It is not true what the Appellant claimed that the Loan Agreement was still in the negotiation stage." and at p. 3 "Whereas the Appellant acknowledged in paragraph 2 of the facts mentioned in his statement of objection that a preliminary loan agreement was signed 6 August 2019, and in the reasons for the objection, he denies signing any loan agreements."
The English proceedings
(1) an allegation of illegality as a matter of UAE law, advanced on the basis that the Loan Agreement provides for interest;
(2) an allegation that the rate of interest is liable to be extinguished or reduced under Sections 140A and 140B of the Consumer Credit Act 1974;
(3) an allegation that SLL is not entitled to charge default interest because it has not satisfied a condition precedent; and, even if it has, the rate amounts to a penalty.
There was also a non-admission that SLL's calculations were correct.
"Alleged Overlap
Your clients are aware that our client is not a party to any proceedings in the United Arab Emirates: the proceedings to which we understand you to refer involve neither the Claimant nor the Defendants to the English action nor do they involve the contract of loan the subject of the English action. Thus, the suggestion that there is some overlap between the present proceedings and proceedings abroad is wrong."
"16. If the Loan is apparently being settled in Dubai, by way of payment to a company that is not the Claimant, this raises a question as to who in fact are the true parties to the Loan, and connectedly what is the proper law governing it. While on the face of it, the parties to the Loan Agreement are the Claimant and the First Defendant, the arrangements in Dubai suggest that the Loan may in reality have been made directly between Mr Nirmal Sethia and the First Defendant, two individuals domiciled in the UAE …
…
21. If the UAE Cassation Court finds for NS Investments Ltd, this means that NS Investments Ltd has the right in the UAE to sue on the Security Cheque. If in parallel, this Court were to find that the Claimant had the right to sue on the Loan Agreement and the Guarantee, Mr Sethia (who for all intents and purposes is the ultimate beneficial owner and directing mind of both companies), would in effect have obtained double recovery: a remedy under the Loan as if it had not been compromised AND a remedy under the Settlement Agreement which was intended to compromise the Loan.
…
24. Put another way, there is a direct conflict between the claim brought in the English Courts on the basis of the sum outstanding on the Loan, and NS Investment Ltd's proceedings in the UAE, which are premised upon the Loan having been settled on the terms of the Settlement Agreement."
"The Claimant's solicitors shall by 4pm on Friday 21of August 2020 state in a letter to the Defendants' solicitors whether it contends that any sums recovered by NSIL pursuant to orders of the courts of Dubai and/or the United Arab Emirates in respect of [the Cheque] should not be applied against the sums claimed by the claimant in this action; and if it so contends, file and serve a witness statement setting out the evidence on which it relies in that regard."
"We hereby confirm on behalf of the Claimant that it accepts that any sums recovered by NS Investments Limited ('NSIL') pursuant to Orders of the Courts of Dubai and/or the United Arab Emirates in respect of the Cheque are to be applied against the sums claimed by the Claimant in this action. We make clear that this is on the basis that merely obtaining judgment on the Cheque would not amount to making recovery: it is only sums actually realised that fall to be applied. We also make clear that it is net recoveries (i.e. less the costs and expenses of any enforcement action) that fall to be applied."
"1. In this undertaking:
(i) the 'Cheque' means cheque No 401622 drawn by the First Defendant on the Bank of Baroda in the sum of AED 7.9 million;
(ii) the 'Judgment' means the judgment entered in favour of the Claimant against the Defendants in this action;
(iii) 'NSIL' means NS Investments Limited, a company registered in Jebel Ali Free Zone Authority under commercial registration no. 177447, having its registered address at 2001, Vision Tower, Business Bay, Dubai, United Arab Emirates;
(iv) 'Outstanding Amount' means the amount of the Judgment (plus interest pursuant to the Judgments Act 1838) less any Recoveries made from time to time;
(v)'Recoveries' means any recoveries (less the costs and expenses of any enforcement action) made pursuant to Orders of the Courts of Dubai and/or the United Arab Emirates in respect of the Cheque.
2. The Claimant undertakes that:
(i) it will credit any and all Recoveries against the Judgment;
(ii) it will not seek to enforce the Judgment in England or in any other jurisdiction in an amount in excess of the Outstanding Amount."
(1) SLL is contractually estopped from bringing a claim upon the Loan Agreement pursuant to an implied agreement entered on or around 2 July 2019, by which the Claimant agreed not to bring a claim upon the loan while NSIL retained possession of the Cheque. As NSIL has obtained judgment from the Dubai Commercial Court against Mr Sethi on 2 March 2020 in respect of the Cheque, SLL cannot now bring a claim upon the Loan (the "Contractual Defence"); alternatively
(2) SLL cannot obtain double recovery or impose double recovery on the Defendants by obtaining judgment for a debt due pursuant to the Loan in circumstances where NSIL has judgment for the debt due pursuant to the Cheque (the "Double Recovery Defence").
(3) the Dubai Proceedings preclude this claim either by virtue of Section 34 of the Civil Jurisdiction and Judgments Act 1982 or by virtue of Henderson v Henderson abuse (the "Res Judicata Defence").
The law in relation to summary judgment
"The court may give summary judgment against the defendant ... on the whole of the claim or on a particular issue if-
(a) it considers that:
(ii) that the defendant has no real prospect of succeeding on the claim or issue ... and
(b) there is no other compelling reason why the case or issue should be disposed of at a trial."
"... the court must be careful before giving summary judgment on a claim. The correct approach on applications by defendants is, in my judgment, as follows:
i) The court must consider whether the claimant has a "realistic" as opposed to a "fanciful" prospect of success: Swain v Hillman [2001] 1 All ER 91;
ii) A "realistic" claim is one that carries some degree of conviction. This means a claim that is more than merely arguable: ED & F Man Liquid Products v Patel [2003] EWCA Civ 472 at [8];
iii) In reaching its conclusion the court must not conduct a "mini-trial": Swain v Hillman;
iv) This does not mean that the court must take at face value and without analysis everything that a claimant says in his statements before the court. In some cases it may be clear that there is no real substance in factual assertions made, particularly if contradicted by contemporaneous documents: ED & F Man Liquid Products v Patel at [10];
(v) However, in reaching its conclusion the court must take into account not only the evidence actually placed before it on the application for summary judgment, but also the evidence that can reasonably be expected to be available at trial: Royal Brompton Hospital NHS Trust v Hammond (No 5) [2001] EWCA Civ 550;
(vi) Although a case may turn out at trial not to be really complicated, it does not follow that it should be decided without the fuller investigation into the facts at trial than is possible or permissible on summary judgment. Thus the court should hesitate about making a final decision without a trial, even where there is no obvious conflict of fact at the time of the application, where reasonable grounds exist for believing that a fuller investigation into the facts of the case would add to or alter the evidence available to a trial judge and so affect the outcome of the case: Doncaster Pharmaceuticals Group Ltd v Bolton Pharmaceutical Co 100 Ltd [2007] FSR 63;
(vii) On the other hand, it is not uncommon for an application under Part 24 to give rise to a short point of law or construction and, if the court is satisfied that it has before it all the evidence necessary for the proper determination of the question and that the parties have had an adequate opportunity to address it in argument, it should grasp the nettle and decide it. The reason is quite simple: if the respondent's case is bad in law, he will in truth have no real prospect of succeeding on his claim or successfully defending the claim against him, as the case may be. Similarly, if the applicant's case is bad in law, the sooner that is determined, the better. If it is possible to show by evidence that although material in the form of documents or oral evidence that would put the documents in another light is not currently before the court, such material is likely to exist and can be expected to be available at trial, it would be wrong to give summary judgment because there would be a real, as opposed to a fanciful, prospect of success. However, it is not enough simply to argue that the case should be allowed to go to trial because something may turn up which would have a bearing on the question of construction: ICI Chemicals & Polymers Ltd v TTE Training Ltd [2007] EWCA Civ 725."
(1) the criterion "real" is not one of probability, it is the absence of reality: see Lord Hobhouse in Three Rivers District Council v Bank of England (Number 3) [2003] 2 AC 1 [158];
(2) an application for summary judgment is not appropriate to resolve a complex question of law and fact, the determination of which necessitates a trial of the issues having regard to all the evidence: see Apovdedo NV v Collins [2008] EWHC 775 (Ch);
(3) in relation to the burden of proof, the overall burden of proof rests on the applicant to establish that there are grounds to believe the respondent has no real prospect of success and there is no other compelling reason for trial. The standard of proof required of the respondent is not high; it suffices merely to rebut the applicant's statement of belief.
"The general rule is that it is not normally appropriate in a summary procedure (such as an application to strike out or for summary judgment) to decide a controversial question of law in a developing area, particularly because it is desirable that the facts should be found so that any further development of the law should be on the basis of actual and not hypothetical facts."
The applicable principles when considering whether to grant permission to amend a statement of case
(1) Neither the evidence filed by the Defendants nor the skeleton arguments served on their behalf sought to engage with any of the points made by SLL in relation to the existing defences to which I have referred to in paragraph 35 above. At paragraph 33 of SLL's skeleton, Mr Edwards stated that it was unclear whether the Defendants accepted that the existing defences were unarguable. Mr Macpherson's position to this was somewhat unusual. He stated expressly that they were not being relied upon for the purposes of defending the summary judgment application, but they were not being wholly abandoned. Should the additional defences in the draft amended Defences be permitted to proceed to trial, he reserved the right to raise the original defences in due course, but for present purposes they could be ignored.
(2) Having seen the submissions made by NSIL in the Dubai Court of Cassation, the Defendants accept that there are not inconsistent positions being advanced by SLL in these proceedings and NSIL in the Dubai Proceedings in that it is not being asserted by NSIL that either the Side Agreement or the Third Amendment were validly executed.
The Contractual and Double Recovery Defences – Mr Sethi's submissions
"Payment by negotiable instrument
Apart from express agreement, a creditor is not bound to accept payment in any way except cash, i.e. legal tender. If, however, the creditor accepts a negotiable instrument, such as a bill of exchange, promissory note or cheque, it is a question of fact depending on the intention of the parties, whether it is taken in absolute satisfaction of the debt, or only in conditional satisfaction. In either event, the acceptance of the instrument gives the debtor a good defence to an action for the debt, at least until the instrument matures.
Conditional payment
Normally where a creditor accepts a negotiable instrument for its debt it is presumed to be taken by it as a qualified or conditional payment, and, accordingly, although the original debt is still due during the currency of the instrument, the creditor's remedy is suspended until it is due. If it is then paid, this amounts to payment of the debt; if it is dishonoured when it is presented for payment in the ordinary way, the right to sue upon the original debt revives as if no negotiable instrument had been taken. Hence, if interest was due on the debt, it continues to accrue after the date of acceptance of a cheque which is subsequently dishonoured. It has been held that a claimant who accepts a cheque for part of the debt cannot sign judgment in default of appearance for the full amount claimed unless the cheque is dishonoured. Similarly, acceptance of an irrevocable documentary credit does not constitute absolute payment to the seller so as to release the buyer; if the credit is not honoured, the seller sue the buyer."
"The same result follows:(ii) where the bill or note is, at the creditor's request, payable to a third person: Price v Price (1847) 16 M. & W. 232, 241; National Savings Bank Association Ltd v Tranah (1867) L.R. 2 C.P. 556."
"Where the bill has been negotiated and is outstanding in the hands of a third party, the creditor's remedy is still suspended: Davis v Reilly [1898] 1 QB 1; Re A Debtor [1908] 1 KB 344 (except where the third party is a trustee for the claimant: National Savings Bank Association Ltd v Tranah (1867) L.R. 2 C.P. 556; or agent for the claimant: Hadwen v Mendisabal (1825) 10 Moo C.P. 477."
"It seems to be clearly settled at common law that an action will not lie for the price of goods, for which a bill of exchange has been given, while the bill is outstanding in the hands of a third party."
"The defendant, however, relies on the fact that the note is outstanding in the hands of Williamson and Wieland. It was, however, placed in their hands by consent of both parties, and not in satisfaction but only on account of the claim made in this action, and it is still held by them as trustees for the plaintiffs. It seems to me, therefore, that the replication is good both in law and equity, and differs very little from one averring that the note is overdue and unpaid and in the hands of the plaintiffs themselves."
"I think the authorities which have been cited to us shew that what was done operated as an agreement not to sue, and an agreement not to sue not merely during the currency of the bill, but afterwards, notwithstanding dishonour, so long as the bill was outstanding in the hands of a third party. The authorities which have been called to our attention seem to me to establish that proposition beyond question."
"A parallel case where a bill is taken in payment of a debt, say for instance in payment for goods sold, exactly illustrates what is the effect of taking a bill. It is perfectly true that it is only a conditional payment. It is a payment if the bill is paid, and if it is in your hands when it becomes due and is dishonoured the debt revives. But if you have availed yourself of the character of the bill as a negotiable instrument, and have passed it out of your possession so that the right to proceed on that bill is vested in some one else and not in you at the date of the dishonour, the suspension of the debt continues just as much as if the bill was not overdue. A moment's consideration will shew that the Courts would not be administering justice if they did not hold this to be the case, because otherwise you could sue for the price of the goods, while another man, through possession by your act of the negotiable instrument which had been given for the price, could make the debtor pay the amount over again."
SLL's submissions on the Contractual and Double Recovery Defences
(1) By mid-2019, there had been two formal extensions to the term of the loan. The second extended the repayment date to 31 June 2019. Non-payment by that date amounted to the clearest possible Event of Default.
(2) On the occurrence of that Event of Default, the Villa stood charged in equity to SLL. Thus, by the time of the conversation in early July 2019 on which the Defendants now rely, the Villa was charged in equity to SLL.
(3) The Cheque was handed over on 2 July 2019. At paragraph 10 of Sethi 1, Mr Sethi says that the AED 7.9 million was "the approximate amount outstanding under the Loan" at that time. It was obviously foreseeable that if it came to be presented, the amount due would have increased or that the US$/AED exchange rate would have moved, because under Clause 9.2 of the Loan Agreement, the currency of account was US$.
(4) There is nothing to show that the intention was that, if by the time the Cheque was presented, the amount due in US$ was, for whatever reason, more than AED 7.9 million, SLL was foregoing any right to the balance. Indeed, the draft Side Agreement provides by Clause 3.3(b) that NSIL shall "date and encash the Supplementary Cheque towards the settlement of the outstanding Loan Amount". [emphasis added]
(5) It was plainly foreseeable that if the Cheque were presented it might be dishonoured.
(6) What Mr Sethi now seeks to do is avoid paying what he undoubtedly owes under the Loan Agreement. The Cheque was dishonoured when presented and throughout the Dubai Proceedings Mr Sethi denied his liability to pay in those proceedings. Simultaneously, he seeks to defend this action on the basis that the Cheque was presented by NSIL. The inconsistency is obvious: Mr Sethi says to this Court that the Cheque amounted to payment and to the UAE court that he is not liable on it.
(7) There is no risk of double recovery. That is because SLL accepts that any recoveries made by virtue of the action on the Cheque must be credited against the debt due under the Loan Agreement and has offered an undertaking to the Court in the event that judgment is entered in its favour, as set out in the 21 August Letter.
"Normally where a creditor accepts a negotiable instrument for its debt it is presumed to be taken by it as a qualified or conditional payment, and, accordingly, although the original debt is still due during the currency of the instrument, the creditor's remedy is suspended until it is due. If it is then paid, this amounts to payment of the debt; if it is dishonoured when it is presented for payment in the ordinary way, the right to sue upon the original debt revives as if no negotiable instrument had been taken." (Chitty on Contracts, para 21-075)
"I have always understood the principle of transit in rem judicatam to relate only to the particular cause of action in which the judgment is recovered operating as a change of remedy from its being of a higher nature than before. But a judgment recovered in any form of action is still but a security for the original cause of action, until it be made productive in satisfaction to the party; and therefore till then it cannot operate to change any other collateral concurrent remedy [259] which the party may have. If indeed one who is indebted upon simple contract give a bond or have judgment against him upon it, the simple contract is merged in the higher security. So one may agree to accept of a different security in satisfaction of his debt; but it is not stated here that the note and bill were accepted in satisfaction, and in themselves they cannot operate as such until the party has received the fruits of them: and then, although they were not originally given in satisfaction of the higher demand, yet, ultimately producing satisfaction, it would be a bar to so much of the present demand. But here they are neither averred to have been accepted as satisfaction, nor to have produced it in themselves; and therefore the matter pleaded is no bar to the action."
Grose J at p. 596: "The note or bill, not having been accepted as satisfaction for the debt, could only operate as a collateral security; and though judgment has been recovered on the bill, yet not having produced satisfaction in fact, the plaintiff may still resort to his original remedy on the covenant." [emphasis added]
Lawrence J at p. 597: "Nothing has happened to alter the situation of the parties in respect of the plaintiff's original remedy on the covenant. It is clear that the bill and note when first given were no satisfaction: and the judgment recovered on the bill is in itself no satisfaction until payment be obtained upon it." [emphasis added]
Le Blanc J at p. 597: "The giving of another security, which in itself would not operate as an extinguishment of the original one, cannot operate as such by being pursued to judgment, unless it produce the fruit of a judgment." [emphasis added]
"The cheque was dishonoured and Thomas did not pay it. Thereupon the plaintiff sued him upon the cheque. The cause of action in that action was the dishonour of the cheque, and upon that the plaintiff recovered judgment. If that judgment had been satisfied, and the plaintiff had obtained the fruits of it by execution, that would have been equivalent to payment of the debt on the guarantee; but it has not been satisfied … It is contended, nevertheless, that the rule of law on the subject is that by reason of this transaction with regard to the cheque which took place between the plaintiff and Thomas, and which did not prejudicially affect the defendant in any way, the plaintiff cannot now sue the defendant on the guarantee. To my mind, if the rule were as alleged, it would be a technicality of the most stringent kind, and one which would make the law on the subject contrary to the justice and truth of the matter. I for one object to such a technicality and will not act upon it, unless I am obliged to do so by authority."
"Anything plainer than these expressions there cannot be. In this case no judgment had been recovered against Thomas in respect of the particular cause of action on which the defendant is sued, viz., the breach of the guarantee."
"It was suggested that the defendant has a ground of complaint in that he could not have Thomas joined as a co-defendant. It seems to me that it was his own fault that that was not done, and that he had the means of compelling such joinder if he had wished it. For these reasons, I come to the conclusion that the judgment is right and should be affirmed."
"The only remaining point is this. When it is established that the mere judgment in the action on the cheque was no satisfaction of the joint contract of the guarantors, the question arises how it came about that Thomas was not sued jointly with the defendant. It was involved in the decision in Kendall v. Hamilton that it remains the substantial right of one joint contractor not to be sued without the other. But it is at his option whether he will raise any such defence or not. In the case of a plaintiff's suing only one of two joint contractors, the defendant could originally have pleaded in abatement, and since the Judicature Act he can take other means to enforce the joinder of the other joint contractor. Here no such step was taken. If the defendant had taken the proper steps I think the plaintiff could not have obtained judgment against the defendant without joining Thomas. He chose not to take such steps, and, consequently, judgment was rightly given against him alone."
(1) First, the Cheque was handed over merely as security and therefore was not suspensory of SLL's rights under the Loan Agreement. Mr Sethi's argument that the Cheque was payment on account of the debt due under the Loan Agreement is inconsistent with the plea in paragraph 34(iii) of the draft Amended Defence that "it was an implied term that the Cheque would be returned if the parties failed to agree the terms of the Written Agreement within a reasonable time.";
(2) NSIL was acting merely as an agent for SLL. Indeed, the Defendants positively allege this at paragraphs 40 and 42 of the draft Amended Defence[1]. It is what the document the Defendants identify says and there is no suggestion that NSIL itself gave value for the Cheque. Moreover, the acceptance by SLL that recoveries must be credited against the Loan Agreement debt, puts the point beyond doubt. Accordingly, that NSIL hold the Cheque, and has sued upon it, makes no difference;
(3) Even if NSIL were not acting as agent/trustee for SLL, it gave no value for the Cheque. NSIL was not a holder in due course for value. Accordingly, any defence which was available against SLL would be available against NSIL and therefore SLL's rights are not suspended;
(4) There is no basis for saying that on 2 July 2020, the sum of AED 7.9 million would be sufficient to meet the US$ sum due under the terms of the Loan Agreement, if and when presented, nor that SLL gave up any of its contractual rights under the Loan Agreement, such that it gave up its right to recover the balance of the Loan or the difference in value between what the Cheque realised in US$ and the actual US$ sum due under the loan agreement.
"It was a further term of the Final Extension Agreement, implied to ensure business efficacy further or alternatively because it was obvious alternatively by law, that: ('the Implied Term')….
'The Claimant would not enforce its rights under the Loan Agreement if NSIL sought and/or obtained judgment on the Cheque against the First Defendant as (A) the presentation of the Cheque was intended to settle the Loan; and (B) to avoid the prospect of double recovery by separate claims by the Claimant and NSIL.' Mr Edwards submitted that the premise of that sub-paragraph was the presentation of the Cheque was to be treated as an absolute, rather than a conditional payment, because it was payable to NSIL rather than SLL."
Mr Edwards submits that the underlying premise is that the Cheque was payable to NSIL and not SLL. He makes three points:
(1) First, to suggest that the Cheque was being treated as absolute, rather than conditional payment, is entirely inconsistent with the general rule outlined above. It is only said to amount to absolute payment because of the involvement of NSIL: but, as with the plea in paragraph 36(i) of the draft amended Defence, the short answer is that NSIL was acting as agent/trustee for SLL and so its involvement means that the position is the same as if the Cheque had been made payable to SLL;
(2) Even if it were being treated as absolute payment, it could only be for the US$ equivalent of the AED 7.9 million at the prevailing exchange rate, not the whole debt due under the Loan Agreement;
(3) There neither was nor is a prospect of double recovery. Because NSIL was acting as agent/trustee for SLL, payment to it is the same as payment to SLL. A payment to NSIL would operate as a (partial) discharge of the debt due under the Loan Agreement.
Discussion and conclusion on the Contractual and Double Recovery Defences
(1) It is common ground that neither the Side Agreement nor the Third Amendment was signed. I have some difficulty in accepting that the Heads of Terms agreed orally between Mr Sethia and Mr Sethi on 2 July 2020, which were always understood to be subject to contract (see: paragraph 34(i) of the draft amended Defence and paragraph 11 of the Defendants' skeleton dated 24 September 2020), could have contained a self-standing binding implied term or were subject to an implied agreement;
(2) There is no suggestion in the draft Side Agreement or the draft Third Amendment, even as further amended by Mr Sethi, that the Cheque was payment on account of the outstanding debt, as opposed to being provided as security. Indeed, the plea at paragraph 34(iii) of the draft amended Defence is inconsistent with a payment on account;
(3) In my judgment, NSIL is to be regarded as receiving the Cheque as agent for SLL. NSIL was not a holder in due course for value. On the authorities referred above [at paragraphs 77-88 above], that it is a distinguishing feature, because the position is the same as if the Cheque has been made payable to the SLL, and any defences available as against SLL could be raised against NSIL in relation to it. It is not for me to go behind the decision of the Dubai Court of Cassation;
(4) When the Cheque was provided on 2 July 2019, it was not on the basis that the sum of AED 7.9 million would be sufficient to meet the US$ sum due (including accrued interest) under the terms of the Loan Agreement, if and when presented, nor was it given on the basis that SLL gave up any of its contractual rights under the Loan Agreement. Indeed Clause 3 of the draft Third Amendment expressly provides that the Loan Agreement remains in full force and effect and made provision for the payment of accrued default interest to be paid on 10 September 2019. In my view the presence of that clause presents considerable difficulties for the Contractual Defence. It cannot simply be ignored when considering whether there was a binding implied agreement as contended by Mr Sethi;
(5) In the Wegg Prosser case, it is significant, in my view, that both Lopes and Rigby LJJ found that joint guarantor, Mr Thomas, who had provided the cheque could have been joined as a co-defendant, notwithstanding the earlier judgment against him in relation to the cheque. While Mr Macpherson rightly highlighted that both Drake and Wegg Prosser are joint debtor cases, it seems to me that the dicta of Lopes and Rigby LLJ must be applicable here, with the effect that a claim still lies against Mr Sethi under the Loan Agreement, notwithstanding the presentation of the Cheque;
(6) Given the terms of the undertaking which has been offered by SLL, there is no element of double recovery. I do not accept the submission of Mr Macpherson that granting judgment on the basis of such an undertaking is unacceptable, applying the approach taken by Hart J in the Westminster City Council case. The undertaking from SLL will have the same force as if it were an Order of the Court. Were judgment to be granted in this case on the outstanding amount due under the Loan Agreement, subject to the credit being given for any net recovery arising from the Dubai Judgment, this achieves a just result, because SLL will be limited to the amount due under the Loan Agreement and nothing more. It eliminates the possibility of double (or excessive) recovery.
(7) I find that there is some force in the argument raised by Mr Edwards that the issues concerning enforcement of a judgment in this action in the UAE will only arise if Mr Sethi fails to pay a debt, which this Court found to be owing, and which should have been repaid at the end of June 2019. It is not for Mr Sethi to complain that his continuing refusal to pay the sums due causes him inconvenience.
(8) As for the alternative submission that given SLL's earlier lack of candour in relation to the overlap between the Cheque and the Loan Agreement requires the undertaking offered by SLL to be fortified by a further undertaking from Mr Sethia, whom I accept controls both SLL and NSIL, that is a matter which I consider further at paragraph 113(3) below, when considering the draft amendment to the defence based on the principle in Henderson v Henderson.
The res judicata defence – Mr Sethi's submissions on the application of Section 34 of the Civil Judgments and Jurisdiction Act (the "CJJA")
"On the other hand, if a man is entitled to one of two inconsistent rights, it is fitting that, when, with full knowledge, he has done an unequivocal act showing that he has chosen the one, he cannot afterwards pursue the other, which, after the first choice, is by reason of the inconsistency, no longer his to choose. Instances are the right of a principal dealing with an agent for an undisclosed principal to choose the liability of the agent or the principal, the right of a landlord whose forfeiture of a lease has been committed to exact the forfeiture or to treat the former tenant as still tenant, and the like…"
"Third, there is the doctrine of merger, which treats a cause of action as extinguished once judgment has been given upon it, and the claimant's sole right as being a right upon the judgment. Although this produces the same effect as the second principle, it is in reality a substantive rule about the legal effect of an English judgment, which is regarded as "of a higher nature" and therefore as superseding the underlying cause of action: see King v Hoare (1844) 2 Dow & L 382, 1 New Pract Cas 72, (1844) 13 M & W 494, 504 (Parke B). At common law, it did not apply to foreign judgments, although every other principle of res judicata does. However, a corresponding rule has applied by statute to foreign judgments since 1982: see Civil Jurisdiction and Judgments Act 1982, s 34."
"No proceedings may be brought by a person in England and Wales or Northern Ireland on a cause of action in respect of which a judgment has been given in his favour in proceedings between the same parties, or their privies, in a court in another part of the United Kingdom or in a court of an overseas country, unless that judgment is not enforceable or entitled to recognition in England and Wales or, as the case may be, in Northern Ireland."
"I do not say that one must be the alter ego of the other: but it does seem to me that, having due regard to the subject matter of dispute, there must be a sufficient degree of identification between the two to make it just to hold that the decision to which one was a party should be binding in proceedings to which the other is party. It is in that sense that I would regard the phrase "privity of interest"."
(1) A creditor who brought a claim on a debt and in parallel on a cheque offered on account of that debt would be obliged to elect on judgment between judgment on the debt and judgment on the cheque. He could not obtain judgment on both because it would provide the creditor with double recovery, unless the cheque was for less than the debt. In support of this proposition Mr Macpherson relied upon the late eighteenth century case of Seddon v Tutop (1796) 6 Term Rep 607, where a creditor brought proceedings on a promissory note for £5 and the underlying debt of £25/7. At trial, he only had evidence for the promissory note so took judgment for £7/10 (including interest). Later he brought new proceedings for the underlying debt of £25/7 and the defendant objected that he could have recovered this sum in the former action. The Court gave judgment on the grounds that the causes of action were different. He contended, however, that the report omits the key issue, namely the amount in which the court gave judgment.
(2) In this case, SLL has, by its agent NSIL, obtained judgment against Mr Sethi on the Cheque. Had either SLL or NSIL brought proceedings on the Cheque in this jurisdiction, the cause of action created by the Loan would have merged in the judgment on the Cheque. The Defendants would have been entitled to rely on the defence of "former recovery";
(3) Because NSIL obtained judgment on the Cheque in Dubai, the doctrine of merger in judgment does not apply. The scope of Section 34 of the CJJA applies equally, however, to prevent SLL from bringing a claim on the cause of action created by the Loan so long as the other factors referred to in the section are satisfied;
(4) The other factors referred to in Section 34 of the CJJA are satisfied because:
(a) SLL is a privy of NSIL because it has an interest in the Dubai Judgment, NSIL having obtained the Dubai Judgment as its agent; and
(b) the Dubai Judgment, being a final and conclusive judgment, is enforceable and entitled to recognition in England and Wales.
SLL's submissions on the application of Section 34 of the CJJA
Discussion and conclusion on Section 34 of the CJJA
Mr Sethi's submissions on the breach of the principle in Henderson v Henderson
"The principles to be derived from the authorities, of which by far the most important is Johnson v Gore Wood & Co [2002] 2AC 1, can be summarised as follows:
i) Where A has brought an action against B, a later action against B or C may be struck out where the second action is an abuse of process.
ii) A later action against B is much more likely to be held to be an abuse of process than a later action against C.
iii) The burden of establishing abuse of process is on B or C or as the case may be
iv) It is wrong to hold that because a matter could have been raised in earlier proceedings it should have been, so as to render the raising of it in later proceedings necessarily abusive.
v) The question in every case is whether, applying a broad merits based approach, A's conduct is in all the circumstances an abuse of process.
vi) The court will rarely find that the later action is an abuse of process unless the later action involves unjust harassment or oppression of B or C."
(1) Mr and Mrs Sethi say that they have no assets in the jurisdiction. This is not denied by SLL;
(2) SLL has not stated any benefit to obtaining judgment in England on the Loan;
(3) Mr and Mrs Sethi should not be put to the expense of conducting a defence to the English proceedings as well as dealing with the enforcement of the Dubai Judgment. Had SLL brought the claim on the Cheque in England, it would have had to follow the requirement to notify the court of its intention to bring related proceedings on the Loan, see: Aldi Stores v WSP Group plc [2008] 1 WLR 748 at [29]-[31].)
(4) If SLL seeks to enforce the English judgment in the UAE, it will be enforced in parallel with the enforcement of the Dubai Judgment;
(5) The grant of a judgment in these proceedings raises a real risk that SLL could seek to enforce it in Dubai in a manner that would constitute harassment or oppression of the Defendants;
(6) The lack of candour by SLL in these proceedings increases the risk that SLL would seek to use the English judgment to harass Mr Sethi. In particular, lack of candour of SLL by initially: (i) stating by their solicitors' letter of 24 July 2020 that there was no overlap between the Dubai Proceedings and these proceedings; and (ii) initially denying in oral submissions on 27 July 2020 that sums recovered under the Dubai Judgment should be set off against any judgment in these proceedings is said to raise a real risk of abuse;
(7) Mr and Mrs Sethi should not have to face the risk that SLL would use the English judgment oppressively in Dubai and to suffer the expense of applying for the English judgment and the Dubai Judgment to be enforced together.
SLL's Submissions on the principle in Henderson v Henderson
(1) The claim on the Cheque was properly brought in the UAE and there is no suggestion that it was governed by English law or that the English court would have had jurisdiction. By contrast, the Loan Agreement is subject to English law and jurisdiction.
(2) The asserted absence of English assets on the part of the Defendants is irrelevant. The Loan Agreement is subject to English jurisdiction and SLL is entitled to a judgment of this Court on it. That judgment will be for the full amount now due, including accrued interest, and not merely the dollar equivalent of AED 7.9 million and SLL will be entitled to enforce that judgment (subject to giving credit for recoveries resulting from the Dubai Judgment). There are further advantages to an English judgment, not least its enforceability in Europe and the Commonwealth.
(3) Mr Sethi's enforcement point is a bad one. If SLL were compelled to enforce the judgment in this action in Dubai that would be because Mr Sethi had failed to pay a debt this Court had found to be owing. It is not for Mr Sethia to complain that his own obstructive behaviour causes him inconvenience.
(4) There is no reason to believe that SLL will not abide by the undertaking it proposes to give to the Court.
Discussion and conclusion on the principle in Henderson v Henderson
(1) In my judgment the claim on the Cheque was properly brought in Dubai. This claim, in contrast, is governed by English law and in my view SLL was entitled to bring it here;
(2) The amounts recoverable as I have earlier found are not by any means identical. Clause 24 of the Loan Agreement expressly envisaged the possibility of claims in different jurisdictions and Clause 3 of the draft Third Amendment expressly provided that despite the proposed new arrangements, save as otherwise provided, the Loan Agreement remained in full force and effect.
(3) For the reasons given earlier at paragraph 94(6) above, I am not persuaded that the Court should refuse to accept the undertaking offered by SLL, which will have the same force as if it were an Order of this Court. I am, however, willing to hear further argument, upon the handing down of this judgment, as to whether Mr Sethi should give a personal undertaking so as to fortify that given by SLL.
Conclusion on the draft amendments
Is SLL entitled to default interest?
(1) Clauses 7.1 and 7.6 impose an absolute and unconditional obligation to pay default interest. Clause 7.2 provides merely for calculation, and in particular permits (but does not require) it to elect to calculate by reference shorter than 7 days. Absent an election to calculate by reference to shorter rests, default interest is calculated by reference to 7 day rests. It should be noted that SLL has in fact calculated the default by using 1 month rests. But like any compounding exercise, longer rests work to the advantage of the paying rather than the receiving party.
(2) In the absence of any binding written agreement between the parties after the Second Amendment, there was no forbearance to sue until 30 September 2019 by the provision of the Cheque on 2 July 2019. The letters of 5 September 2019 were valid.
Conclusion on default interest
Is there some other compelling reason why the matter should go to trial?
"Pre-CPR, the following circumstances were held to afford "some other reason for trial": where the claimant's case appears to be "devious and crafty" and not "plain and straightforward" (Miles v Bull (No. 1) [1969] 1 Q.B. 258; [1968] 3 All E.R. 632); where the defendant is an executor or administrator who can raise facts by reference to the existence or absence of letters, accounts or such like of the deceased which make it reasonable to require full investigation (Harrison v Bottenheim [1878] 26 W.R. 362) where the claimant's case tended to show that he had acted harshly and unconscionably and it is thought desirable that if he were to get judgment at all it should be in the full light of publicity (per Cairns LJ in Bank fur Gemeinwirtschaft Aktiengesellschaft v City of London Garages [1971] 1 W.L.R. 149 at 158; [1971] 1 All E.R. 541 at 548). However, in 2015, a somewhat different view was expressed by the Court of Appeal. In Berntsen v Tait [2015] EWCA Civ 1001 the lower court's decision to summarily dismiss a claim was upheld; the lower court had been right to conclude that the claimants had no real prospects of success; thus there was no point in letting this case proceed to trial even though the underlying facts raised matters of considerable concern as to the lending practice of banks."
Conclusion and disposal
Note 1 Although I note that this is not the Defendants’ primary case. [Back]