QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
____________________
(1) THE SERIOUS FRAUD OFFICE (2) MR JOHN MILSON and MR DAVID STANDISH (as joint Enforcement Receivers in respect of the realisable property of Gerald Martin Smith) |
Applicants |
|
- and - |
||
(1) LITIGATION CAPITAL LIMITED & 45 others |
Respondents |
____________________
Kennedy Talbot QC for the Serious Fraud Office
Simon Browne QC (instructed by St Paul's Solicitors Limited) for Nicholas Thomas and Roger Taylor
James Pickering QC and Samuel Hodge (instructed by Spring Law Limited) for Hotel Portfolio II UK Limited (in liquidation)
David Lord QC and Sebastian Kokelaar (instructed by Richard Slade & Co) for Phoenix Group Foundation and Minardi Investments Limited
Hearing dates: 30 September and 1 October 2021
____________________
Crown Copyright ©
"Covid-19 Protocol: This judgment was handed down by the judge remotely by circulation to the parties' representatives by email and release to Bailii. The date and time for hand-down is deemed to be 21 October 2021 at 10:00 am"
Mr Justice Foxton:
A INTRODUCTION
i) The unusual nature of the proceedings: one in which the SFO sought to recover Dr Smith's realisable property in order to satisfy the confiscation order made against Dr Smith, and third parties sought to make good their claims to proprietary interests in various assets which had statutory priority over the SFO's entitlement.
ii) The obscure and complex transaction history of the various assets which were the subject of the Directed Trial.
iii) The fact that interests of the various parties in the action were aligned on some points but not others, and certain issues arose only between some of the parties to the trial, without engaging others.
iv) The September 2019 Settlement Agreement between the Settlement Parties, which led parties who had previously pursued claims which were adverse to each other to adopt a common front in the proceedings.
v) The fact that the Settlement Parties reached a settlement during the trial with two other groups of parties (the so-called LCL Parties and Mr Sodzawiczny).
B THE FRAMEWORK ISSUES
Should the Settlement Parties be treated as a single unit for costs purposes, or should the position of each Settlement Party be considered on an individual basis?
Harbour | 16% |
Stewarts | 30-40% |
The Viscount | 15% |
The SFO | 25% |
The ERs | 30% |
which amounts to about 25% of the total costs of those parties over that period. They invite me to make a similar assumption for the JLs. The evidence from Mr Campbell for the JLs was to the effect that some 20% of the JL's pre-Settlement agreement costs (excluding the costs of the Settlement Agreement itself) were incurred exclusively in dealing with the claims of the other Settlement Parties. In addition, focussing on the other Settlement Parties and not the JLs, they estimate that some 9% of their costs over that period were incurred in the negotiation of the Settlement Agreement.
i) In the responsive statements of case (in which the parties engaged with the cases of the other parties), the Settlement Parties devoted between 40% and 60% of their documents to engaging with each other's cases.
ii) Some 50% of documents were disclosed by the Settlement Parties.
The position of the JLs
i) Claims advanced by the JLs to assets referred to by the JLs in the BVI sanctions proceedings as "the Proprietary Assets" and claims by Unicorn (one of the companies under the JLs' management) to the Connected Companies. The JLs faced competing claims from the other Settlement Parties and the Non-Settlement Parties to those assets. The competing claims as between the JLs and the other Settlement Parties were settled by the Settlement Agreement.
ii) Claims in respect of payments which Dr Cochrane caused or permitted to be made from those companies in breach of fiduciary duty ("the Wrongful Payment claims"), which were (to a substantial extent) not adverse to those of any of the parties now active in the litigation but would inure to the benefit of those found to be ultimately entitled to the assets of those companies. However, the Settlement Parties claiming interests in the Arena Companies did advance the argument that these amounts should be treated as informal dividends, such that they did not represent the traceable proceeds of the relevant company's assets, but property which was subject to the Harbour Trust. I rejected that argument.
iii) Claims in relation to the IUAs as the traceable proceeds of the Wrongful Payments. Those claims conflicted with the tracing claims of HPII and/or Mr Pelz to the same assets, some of which were resolved (in a manner adverse to HPII as a result of the failure of the bona fide purchaser defence and/or Mr Pelz) at the Directed Trial, and some of which remain to be determined.
iv) Claims arising from the Hayes Settlement, which were settled as against the other Settlement Parties in the Settlement Agreement and abandoned against the Non-Settlement Parties in closing.
i) 40% of the JLs' costs before the Settlement Agreement are to be allocated to issues arising between the Settlement Parties inter se which were settled by the Settlement Agreement.
ii) Having taken account of the claims between the Settlement Parties inter se at i) above, a further 50% of the JLs' costs before the Settlement Agreement are to be allocated to the claims to the Wrongful Payments and the disputed tracing claims to the IUAs. This represents my assessment of what proportion of the JLs' total costs are referable to these issues (together with associated overhead), and no determination by the costs judge as to whether particular costs were incurred on particular issues is required. I intend to reserve 40% of these costs (that is to say 40% of the JLs' total costs pre-Settlement Agreement) for the following reasons:
a) In relation to a number of the IUAs, there remain outstanding issues as between HPII, Mr Pelz and the JLs which have yet to be resolved.
b) In addition, to the extent that the JLs can be said to have incurred costs in establishing that the Wrongful Payments were made by the Arena Companies and represent traceable assets of those companies, I can see scope for argument (which I have not heard) as to how those costs should be treated, in the context of disputes between the Settlement and Non-Settlement Parties as to who is beneficially entitled to the assets of those companies.
The other 10% of that 50% are referrable to those IUA claims in which the JLs were opposed by HPII but succeeded.
iii) 10% to the issue of the Hayes' Settlement, for which the JLs are not entitled to any costs order.
iv) So far as the position after the Settlement Agreement is concerned, the position is as follows:
a) 83% of the JL's costs are to be allocated to the Wrongful Payment and disputed tracing (that is 83% of the JLs' total costs post the Settlement Agreement) of which 66% are reserved and 17% payable by HPII;
b) 17% of the JL's are referable to the Hayes Settlement, for which the JLs are not entitled to any costs order.
The position of the Non-Settlement Parties
i) There are other parties with whom the Settlement Parties subsequently settled: the LCL Settlement Parties and Mr Sodzawiczny.
ii) There are those who actively participated in the Directed Trial itself: HPII, P&M, Messrs Thomas and Taylor and Mr Pelz.
iii) Finally, Mr Barton participated in the early management hearings of the litigation, without participating in the Directed Trial.
i) the period of time over which the relevant party was actively engaged in the litigation;
ii) the financial and evidential significance of the issues the relevant party was engaged with; and
iii) whether that party took a leading or supporting role on such issues (although adopting a point run by someone else is not generally a costs-neutral activity: risk and reward are usually litigation bedfellows).
The LCL Settlement Parties | 20% |
LCL and various parties associated with Dr Smith raised a number of issues – including in relation to the so-called LCL Funding Agreement and the SFO's nominee case, and the IUAs. Dr Smith served 11 witness statements and gave substantial disclosure which would have to have been analysed and responded to. There were also documents served by the other LCL Settlement Parties setting out their own cases, and witness evidence. I accept that their active involvement grew over time (but so did the overall costs charge as case preparation became more intensive in and from 2020). However, based on my review of earlier transcripts, and my experience of the hearings I conducted, the LCL Parties were a significant presence at the various case management hearings. In addition, costs were incurred by the Settlement Parties in negotiating the LCL Settlement Agreement. | |
Mr Pelz, Mr Barton and Mr Sodzawiczny | 5% |
Mr Barton played no role beyond the very early directions stages. Mr Sodzawiczny had all but dropped out of the case by the time the trial began, and Mr Pelz's role in the Directed Trial was very limited. However, there was significant disclosure from Mr Sodzawiczny, some from Mr Pelz, and written filings by them both (most particularly by Mr Pelz). As I have stated, the costs relating to Mr Barton and Mr Pelz are reserved. | |
HPII | 25% (plus 10% of the JLs' pre-Settlement Agreement costs and 17% of the JLs' post-Settlement Agreement costs) |
The bona fide purchaser for value issue raised by HPII, and its claim to the IUAs, took significant time. HPII played a key role in challenging the Settlement Parties on various other issues – the effect of the IOM Settlement (which occupied a significant amount of time in cross-examination and on which HPII succeeded - I address the consequences of that below) and Jersey law. It also advanced an unsuccessful claim to the Non-Arena Companies, although that did not consume much time (I address the argument that this success was not of any economic value at [36] below), and up until the PTR, an attack on the Geneva Settlement under s.423 of the Insolvency Act 1986 which was abandoned at that point. Claims by two other companies making up the acronym OMH had previously been abandoned. Time was also spent in relation to matters arising from HPII's use of privileged material at trial. I do not accept HPII's argument that it was "very much a bit player". While I accept HPII came into the action later than some, it joined at a very early stage of proceedings, and I do not accept that its date of joining of itself provides a chronological cut-off for liability for such of the Settlement Parties' costs as are properly characterised as costs of and incidental to the Directed Trial. It is clear that HPII was itself heavily engaged in the issues which featured in the Directed Trial before April 2017, writing a 10-page letter to the SFO in December 2016, and a 163-page letter in April 2017. Had HPII succeeded, it would surely have been claiming the costs of at least parts of those exercises as its costs of the Directed Trial. Thereafter HPII was a significant presence at the various interlocutory hearings. | |
P&M | 22.5% |
P&M ran arguments relating to the equitable assignment (which carried with it a series of alternative or subsidiary issues, as well as requiring the Court to consider the background and context of the Geneva Settlement) and as to the effect of the CJA 1988. They took the lead in opposing Stewarts' claim to the £2m as well as being the party principally concerned with the associated application to discharge the injunction. Together with HPII, they played a key role in challenging the IOM Settlement including through cross-examination (on which they largely succeeded – an issue which I consider below); challenging Stewarts' lien case (a case which failed as against P&M, albeit P&M's own failure on the equitable assignment point made that failure moot); and in responding to the various alternatives to Harbour and Stewarts' primary cases (Berkeley Applegate relief) on which they succeeded. P&M advanced a (late-emerging) claim to the Non-Arena Companies as part of a wider subrogation argument and adopted (without significant engagement) HPII's case on Jersey law. They also ran a series of contractual and some factual arguments intended to challenge the scope of the Harbour Trust and the SFO's nominee case. Costs were also incurred in addressing the Geneva Nominee issue - which arose, among others, between the Settlement Parties and P&M - until it was removed from the scope of the Directed Trial in the first week of the trial. That issue was reasonably raised, and could have proved significant depending on how other issues were resolved. There was some skirmishing initiated by P&M around the effect of the Settlement Agreement which made it necessary to look carefully at the BVI proceedings. My conclusion that, looking at the litigation overall, P&M were a significant player, rather than the "bit player" depicted in Mr Lord QC's submissions, derives some support from the £7.5m they spent on their own legal fees – a sum which exceeds Harbour's and Stewarts' fees combined. Finally, I reject the suggestion that Phoenix and Minardi should be treated separately for costs purposes. They are both (on their account) vehicles beneficially owned by Mr Stevens, who ran a common case through a single legal team throughout. | |
Messrs Thomas and Taylor | 12.5% |
Messrs Thomas and Taylor raised pre and post-Settlement Agreement issues against the SFO (and succeeded on a key issue, which I address below) and pre- and post- Settlement Agreements against the Settlement Parties on Orb's entitlements under the Harbour Trust, Stewarts' fee and lien claims, the Jersey law issue, the SFO's nominee case and (in a very limited way) the £2m. In my view, a 12.5% figure fairly captures their level of participation across the Directed Trial process as a whole. | |
Reserved tracing / IUA costs | 15% |
This reflects the costs of the Settlement Parties other than the JLs in relation to the Wrongful Payments tracing exercise and the associated costs of the IUA issues to the extent that those have survived to Phase 2, together with the applicable overhead. |
The framework position in summary
i) The relevant costs of the Settlement Parties comprise:
a) in respect of the period prior to the Settlement Agreement, 60% of the costs of the SFO, ERs, Harbour, Stewarts (less the pre-6 March 2017 Stewarts' Costs) and the Viscount;
b) in respect of the period after the Settlement Agreement, 100% of the costs of the SFO, ERs, Harbour Stewarts and the Viscount; and
c) for HPII only, 10% of the pre-Settlement Agreement costs of the JLs and 17% of the post-Settlement Agreement costs of the JLs.
ii) The costs at i)a) and i)b) are to be treated as:
a) 25% referable to HPII (together with 10% of the pre-Settlement Agreement costs of the JLs and 17% of the post-Settlement Agreement costs of the JLs);
b) 22.5% referable to P&M; and
c) 12.5% referable to Messrs Thomas and Taylor.
iii) 40% of the costs of the pre-Settlement Agreement costs of the JLs, 66% of the post-Settlement Agreement costs of the JLs, 15% of the costs of the other Settlement Parties as referred to at i) and b) above, 15% of HPII's costs (as to both of which see [57] below) and any costs relating to Mr Pelz and Mr Barton are reserved.
C THE GENERAL PRINCIPLES
i) There is no automatic rule that the costs of a successful party will be reduced because it lost on some issues, and it has been noted that in complex litigation, it is a rare party who succeeds on every point it argues (see e.g., Travellers' Casualty and Surety Co of Canada v Sun Life Assurance [2006] EWHC 2885 (Comm), [12] and F&C Alternative Investments (Holdings) Ltd v Barthelemy [2011] EWHC 2807 (Ch), [2012] Bus LR 891, [16]-[21],).
ii) There are various factors which are likely to weigh in the balance when determining whether to make such an order, although these are inevitably matters of weight rather than independently determinative considerations. The more significant and self-contained the issue on which the successful party has lost, the more likely it is that some downwards costs adjustment for that failure is appropriate. Failure on an argument which was simply an alternative route to the same substantive relief as that obtained may provide a less compelling case for a downwards adjustment than (for example) a party who seeks to recover some further relief and fails. The unreasonableness of taking the unsuccessful point is also a relevant consideration, but that does not mean that an adjustment to the costs order to reflect the successful party's failure is only appropriate if it has acted unreasonably in relation to the points on which it lost. Similarly, the character of the point - for example an unsuccessful claim in fraud – may also weigh in favour of a reduced costs award to the successful party.
iii) Where an issue-based (or, perhaps more accurately in the present context, issue-influenced) costs order is appropriate, a judge should hesitate before making an order by reference to the costs of the specific issue, as opposed to a proportionate reduction in the successful party's costs: see [23].
iv) In those cases in which it is appropriate to depart from the general rule, a further issue arises as to whether the court should stop at depriving the successful party of part of its costs or go further and make the successful party pay part of the costs of the other party (R (Viridor Waste Management Ltd and ors) v Revenue and Customs Commissioners [2016] EWHC 2502 (Admin), [2016] 5 Costs LR 965, [7]). This will only be appropriate in a suitably exceptional case and is to be regarded as far from routine (ibid, [19] and Summit Property Ltd v Pitmans [2001] EWCA Civ 2020, [17]).
v) While I was referred to no authority on this issue, it is frequently the case that a party raises an alternative case which the Court does not need to decide (and does not decide) because of the way in which other issues are determined. In those circumstances, unless the decision to pursue the alternative argument was unreasonable, the fact that there has been no decision on the merits of the point will not preclude the successful party from recovering those costs.
i) HPII's claim to the Arena Companies was abandoned during the Directed Trial and its claim to the IOM Settlement Cash failed on the bona fide purchaser for value issue (with knock-on impacts on its claim to certain IUAs). Its claim to the Jersey Properties failed as a matter of Jersey law. Its claim to the Non-Arena Companies (albeit the subject of limited argument) also failed. It abandoned its attack on the Geneva Settlement under s.423 of the Insolvency Act 1986 after the PTR. Its claim to the IUAs failed in a number of significant respects, but in other respects survived to the Phase 2 trial.
ii) P&M's claim that, under the LICSA, Phoenix was the equitable assignee of any distributions made by the Arena Companies failed, as did their challenge to the Harbour Trust, their opposition to the SFO's claims to the Non-Arena Companies (advanced both as a matter of statutory construction, by reference to the terms of various settlement agreements and on the facts), their contention that Stewarts were not entitled to the £2m which Phoenix had frozen and their own (very late) claim against the assets of the Non-Arena Companies.
i) Harbour, the Viscount and Stewarts succeeded on the issues arising as between themselves and Messrs Thomas and Taylor. It was always inherent in Harbour and the Viscount's claims (qua Orb) that Messrs Thomas and Taylor would receive such amount, if any, as was available for distribution at the relevant stage of the Harbour waterfall. Messrs Thomas & Taylor's proprietary claim was also always inherent in Stewarts' claim (for a lien over any proprietary claim which Messrs Thomas and Taylor had).
ii) The issues which did arise as between those three parties and Messrs Thomas and Taylor were all issues on which Messrs Thomas and Taylor failed. This included the argument that the share of Orb (represented by the Viscount) should be reduced to reflect misappropriated assets, the argument that the Jersey Properties did not form part of Dr Cochrane's estate; the attack on Stewarts' fees and entitlement to a lien (although, largely as a result of issues raised by the Court, Stewarts reduced the size of their lien claim) and (somewhat surprisingly) on Stewarts' claim to the £2m.
iii) Messrs Thomas and Taylor do not seek any costs order against HPII or P&M (something Mr Browne QC and Mr Crossley confirmed during the hearing).
i) The origin of these proceedings was a restraint order obtained by the SFO on 20 May 2005 and amended on 23 May 2016, intended to prevent the dissipation of assets which the SFO contended represented the Realisable Property of Dr Smith.
ii) When it became apparent that there were rival claimants to the property which the SFO sought to recover, the SFO issued an application on 26 June 2017 which provided the framework within which the rival claims to that property were to be determined. It is clear that Messrs Thomas and Taylor were among those asserting such an interest.
iii) The SFO's initial position was to contend that all the property in issue in the Directed Trial was Dr Smith's Realisable Property (e.g., in their Statement of Claim of 25 October 2017). At one point, Messrs Thomas and Taylor indicated their acceptance of the SFO's claim, and said that the claim ranked "equal but not in priority" to their claim (Messrs Thomas & Taylor's position paper of 31 January 2018).
iv) However, in a short document which I have not seen, but which was filed before June 2018, Messrs Thomas & Taylor made it clear that they were challenging the SFO's entitlement. That appears from the terms of the SFO's reply filed in June 2018, criticising Messrs Thomas & Taylor for only filing a one-and-a-half-page document which it was said did not comply with Popplewell J's order, but stating nonetheless that the SFO understood that Messrs Thomas and Taylor had denied the SFO's case in general terms. The SFO concluded:
"In the foregoing premises, the Applicants rely upon the contents of their Statement of Case, deny any facts asserted by Mr Thomas and Mr Taylor (to the extent that any are asserted) give rise to any proprietary interest held by either of them in the Shares or Jersey Properties, and reserve the right to apply to strike out the Statement of Case of Mr Thomas and Mr Taylor ….".
v) The SFO's position with regard to Messrs Thomas and Taylor at this point can be deduced from its case against Harbour (which was equally dependent on the Harbour IA establishing a trust over the Relevant Property). The SFO advanced various construction points as to why it was said the Harbour IA had not created an effective trust, and otherwise put Harbour to proof.
vi) Messrs Thomas & Taylor served a further pleading on 28 February 2019. Moulder J ordered them to meet any additional costs incurred as a result of the service of this document, which was only necessary because Messrs Thomas and Taylor had not done what they were required to do by Popplewell J. It is apparent from that document that Messrs Thomas and Taylor were at that point not only asserting their claims in opposition to those of the SFO but also (i) resisting claims of LCL, Dr Cochrane and those claiming priority over the Harbour Trust (such as HPII and P&M); (ii) resisting the Viscount's claims to the Jersey Properties; (iii) seeking to reduce Orb's share under the Harbour Trust and (iv) advancing a case which was inconsistent with the SFO's claim to the Non-Arena Companies.
i) They criticise the SFO for advancing a case on the Safekeeping Agreement in its original statement of case, which it dropped after judgment in the Directed Trial. However, the Safekeeping Agreement never formed part of the Directed Trial, and the claim was only dropped once the Settlement Parties' success at the Directed Trial had rendered the point academic.
ii) They criticise the SFO for not calling evidence at the Directed Trial in support of the nominee case. There is nothing in that criticism, for the reasons I gave at [48] of the Directed Trial Judgment. Nor can the SFO, in the period after the Settlement Agreement, be criticised for advancing an alternative nominee case which was (as alternative cases very often are) inconsistent with the Settlement Parties' primary case. In respect of the period before the Settlement Agreement, there was considerable uncertainty as to the position (given the propensity of the primary actors to be less than transparent in many aspects of their business dealings) and against that background the SFO's decision to maintain its wider case cannot be said to be unreasonable.
iii) They say that the SFO made insufficient attempts to settle with them (prompting the response that Messrs Thomas and Taylor have ended up in a worse position than if they had accepted the settlement offer the Settlement Parties made to them). However, it is impossible to evaluate those competing submissions, and there was no attempt to take me through the underlying material. I have concluded that there was no sufficiently clear conduct by either party in relation to settlement to impact on the appropriate costs order.
D THE POSITION AS BETWEEN THE SETTLEMENT PARTIES AND EACH SURVIVING DEFENDANT
The Settlement Parties and P&M
i) no costs should be recovered until the point when the relevant Settlement Party first pleaded reliance on the Geneva Settlement; and
ii) the issues which arose as to the status and immediate effect of the IOM Settlement were so significant and the costs of them so substantial, that the Court should exceptionally make no costs order against P&M (the IOM Settlement failure being sufficient to outweigh any success).
i) the IOM Settlement did not consume as much time and costs as P&M contend;
ii) it represented an alternative route to the same outcome which the Settlement Parties achieved in any event;
iii) much of the ground raised by the IOM Settlement would have had to have been traversed in any event;
iv) they acted reasonably in, in effect, requiring the other parties to make good their contention that the IOM Settlement involved a fraudulent breach of trust by Messrs Cooper and McNally in which Dr Smith was complicit, given the seriousness of these allegations; and
v) given their overall success against P&M, no reduction in any costs order in their favour would be appropriate.
i) The Pre-6 March 2017 Stewarts' Costs, which have already been the subject of a costs order to the extent of 25% of the costs of Stewarts' application of 9 January 2017.
ii) Stewarts also contend that a proportion of their recovery in the action as a whole against P&M after this date should be allocated to this issue. They have estimated 25%, but P&M suggest that the appropriate figure is significantly less. These issues generated appreciable time in opening, during Mr Upson's cross-examination and in closing, and must carry their share of the accompanying overhead. I am satisfied that a figure of 15% of Stewarts' costs from 6 March 2017 onwards are fairly attributable to the £2m.
i) The total costs recovery made in favour of the Settlement Parties other than the JLs should be allocated across the SFO, ERs, Harbour, Stewarts and the Viscount's costs on a pro rata basis.
ii) 15% of Stewarts' costs should be carved out of the costs order in the Directed Trial and included in the costs order relating to Phoenix's freezing order application.
iii) The costs order in the freezing order application should also reflect the order I have made in relation to 90% of the Pre-6 March 2017 Stewarts' Costs, after carving out those costs which have already been the subject of Popplewell J's order of 6 March 2017.
i) The Pre-6 March 2017 Stewarts' Costs are to be deducted (and are dealt with separately at iii).
ii) Having done that, the SFO, ERs, Harbour, Viscount and Stewarts are entitled against P&M to 70% of 22.5% (i.e. 15.75%) of:
a) 60% of their pre-Settlement Agreement costs; and
b) their post-Settlement Agreement costs.
iii) Stewarts are entitled against P&M to 90% of the Pre-6 March 2017 Stewarts' Costs (25% of the costs awarded to Stewarts by Popplewell J's order of 6 March 2017 to be deducted before the 10% reduction is applied).
iv) The costs in iii) and 15% of Stewarts' share of the costs in ii) are payable by P&M pursuant to the costs order made in the freezing order proceedings.
v) The remaining 85% of Stewarts costs in ii) are payable pursuant to the costs order in the Directed Trial.
The Settlement Parties and HPII
i) The attempt to re-open the Privilege Application has already been the subject of a prior order, with no reservation as to costs.
ii) In my view, there was nothing improper in HPII's case as to Stewarts' involvement in the IOM Settlement, although, for the reasons I gave in the Directed Trial judgment, I did not uphold HPII's complaints.
iii) The issues which arose in relation to the use of material provided by Mr Campbell at trial involved a misjudgement in the pressure of the moment. However, this was a very small incident in a very long and complex piece of litigation.
i) the SFO, ERs, Harbour, Viscount and Stewarts are entitled against HPII to 80% of 25% (so 20%) of:
a) 60% of their pre-Settlement Agreement costs (the Pre-6 March 2017 Stewarts' Costs to be deducted from this figure before the 40% reduction is applied); and
b) their post-Settlement Agreement costs; and
ii) the JLs are entitled to 10% of their pre-Settlement Agreement costs and 17% of their post-Settlement Agreement costs against HPII.
The Settlement Parties and Messrs Thomas and Taylor
i) There is no order as to the costs of the Settlement Parties as against Messrs Thomas and Taylor in respect of the period prior to the Settlement Agreement.
ii) The SFO, ERs, Harbour, the Viscount and Stewarts are entitled to recover 10% of their post-Settlement Agreement costs from Messrs Thomas and Taylor. No reduction from the 10% to reflect failure on particular issues is required.
Previously reserved costs
E PAYMENTS ON ACCOUNT
i) P&M must make a payment on account of costs to the Settlement Parties of £1,037,000.
This takes the pre-Settlement Costs of £9.8m (which reflects a deduction of 15% of Stewarts' costs of the freezing injunction which are dealt with separately). 60% of that figure is £5.88m. 15.75% of that figure is £926,000. The post-Settlement Agreement costs are £6.1m. 15.75% of £6.1m is £960,000. These total £1,886,000. The POA is 55% of that figure.
ii) P&M must make a further payment on account to Stewarts in the freezing order proceedings of £240,000.
This takes the Pre-6 March 2017 Stewarts' Costs of £577,000 and deducts 25% of the £370,000 which was the subject of the order of Popplewell J on 6 March 2017 to arrive at £484,500. 90% of this figure is £436,000. The POA is 55% of that figure.
iii) HPII must make a payment on account to the Settlement Parties of £1,557,000.
This takes the pre-Setlement Costs of £9.8m. 60% of that figure is £.5.88m. 20% of that figure is £1,176,000. The post Settlement Agreement costs are £6.1m. 20% of that is £1.22m. These total £2.396m. 10% of the JLs' pre-Settlement Agreement costs are £205,000. 17% of the JLs' post-Settlement Agreement costs are £231,000 which produces a total of £2.832m. The POA is 55% of that figure.
iv) Messrs Thomas and Taylor must make a payment on account to the Settlement Parties of £335,000.
This takes the post-Settlement Agreement costs of £6.1m. 10% of that figure is £610,000. The POA is 55% of that figure.
i) They have asked for 18 months, to allow time for any distribution to them under the Harbour Trust to be take place.
ii) They have also stated that they are unable to meet the costs order without the benefit of any such distributions, and would be made bankrupt. Both are subject to continuing IVAs: Mr Taylor's ending in June 2022 and Mr Thomas' ending in October 2022.
iii) The Settlement Parties challenge the assertion that Messrs Thomas and Taylor stand to receive any substantial benefit from the Harbour Trust, and also suggest that Messrs Thomas and Taylor have not given a full and frank account of their financial position.