BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
COMMERCIAL COURT (QBD)
Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
Sitting as a Deputy Judge of the High Court
____________________
(1) HERITAGE TRAVEL AND TOURISM LIMITED (2) MLDO PRIVATE FOUNDATION |
Claimants |
|
- and - |
||
(1) LARS WINDHORST (2) TENNOR HOLDING B.V. (3) LA PERLA FASHION FINANCE B.V. (4) CIVITAS PROPERTIES FINANCE B.V. |
Defendants |
____________________
(instructed by Withers LLP)
appeared for the Claimants
Mr Robert Anderson QC and Ms Gayatri Sarathy
(instructed by Baker McKenzie LLP)
appeared for the Defendants
Hearing date: 20 July 2021
____________________
Crown Copyright ©
Covid-19 Protocol: This judgment was handed down remotely by circulation to the parties' representatives by email and release to BAILII. The date and time for hand-down is deemed to be 10:30am on 27 August 2021.
MR SALTER QC:
Introduction
Background
The terms of the [February Settlement] included a provision whereby [the Fourth Defendant was] to deliver 10,000,000 shares in [Civitas Property Group SA] to [the Second Claimant]. This did not occur. Also, certain payments have not been made in accordance with the February 2020 Agreement. On this basis, [the First Claimant and the Second Claimant] issued [the present action].
10.1. A "First Amount" of EUR 55,002,559.70 (including EUR 600,000 in respect of the Claimants' legal costs), payable by 30 June 2020 (clause 3.1(a)); and
10.2. A "Second Amount" of EUR 69,197,440.30, plus a daily lump sum payment of EUR 139,134 (the "Daily Lump Sum") accruing pro rata on the unpaid part of the Second Amount from 27 May 2020, payable by 15 February 2021 (clause 3.1(b)).
The Second Amount would be discounted to EUR 50,000,000 if payment in that amount was made in full by 31 December 2020 (clause 3.1(c)).
11.1. Serve notice, declaring that the discounting provision in clause 3.1(c) no longer applied and that the unpaid balances of the First and Second Amounts were immediately due and payable, including the Daily Lump Sum calculated up to 15 February 2021; and
11.2. Enter judgment against the Defendants for the unpaid amounts (clause 7.1).
The terms of the June Settlement further required the Defendants to pay all legal costs reasonably incurred by the Claimants in enforcing the terms of the June Settlement (clause 8.2).
The correct approach to this application
23. The present application is an application to give effect to a settlement agreement scheduled to a Tomlin order, by entering judgment in consequence of breaches of that agreement. There is no dispute that the sums due in respect of the third to sixth instalments were not paid. The claimants therefore have (subject to the question of limitation) a prima facie entitlement to the judgment which they seek; i e to a judgment which would give effect to the court's order.
24. However, the first defendant contends that the court should decline to give effect to that prima facie entitlement because of the oral agreement relied upon by Mr Pieper. A threshold question arises as to the standard which the court should apply in considering the argument as to the alleged oral agreement. Should it determine the matter on the balance of probabilities, based on the documentary and other evidence submitted? Should it adjourn the matter so that there can be oral evidence and cross-examination of witnesses? Should it take an approach, analogous with CPR Pt 24, of asking whether the first defendant's argument has "no real prospect of succeeding"?
25. It seems to me that there is much to be said for the view that this is an application to enforce an order of the court, and that the court should simply form a view on the existing evidence as a whole as to whether it is appropriate to enforce its existing order; or, conversely, whether it should decline to do so because of the issues raised by the first defendant. In circumstances where the claimants can show a prima facie entitlement to the judgment sought, the evidential burden if not the legal burden would be on the defendants to provide the court with satisfactory evidence that would persuade the court to take a different view; i e to decide either not to enforce, or to decide that the matter is not capable of being fairly resolved on the documents or existing evidence alone and requires cross-examination of witnesses. In practical terms, however, I consider that in the context of the present case, the test to be applied is whether or not a further evidential hearing is required because the first defendant has a real prospect both of proving the oral agreement on which it relies, and also of showing that this would be an answer to the claimants' claim.
The terms of the schedule [to a Tomlin Order] are not an order made by the court. The court obviously has the ability to interpret that agreement on well known principles of interpretation .. and would have to do so when it was asked to take any enforcement action under the standard liberty to apply for that purpose in the Tomlin order. Likewise the court has the ability to deal with the terms of that agreement in the same way as any other contract. That would include, for instance, a claim for rectification or a claim that the agreement was unenforceable for some reason. If the court decided that the agreement should be rectified or that it was unenforceable then the court may well take the view that they would vary or revoke the terms of the order part of the Tomlin order, to take account of that determination ..
The grounds of defence put forward
17.1. First, the Defendants say that the June Settlement cannot be enforced against them because it was entered into as a result of economic duress, and has not been ratified and/or affirmed;
17.2. Alternatively, they assert that the June Settlement is not presently enforceable, because an implied condition precedent to the enforceability of the Defendants' obligations under the June Settlement has not been fulfilled;
17.3. In the further alternative, they say that the June Settlement should be rectified so as expressly to provide for that condition precedent;
17.4. Finally, they argue that clause 7.1(b) of the June Settlement is unenforceable as a penalty.
Economic duress
The Defendants' case, in outline
The Evergreen Transaction
.. In around April 2020, an opportunity arose with a third party investor, H2O Asset Management ("H2O"), to raise additional finance so that Tennor [the Second Defendant] would be in a position to buy back the relevant shares in respect of each of the [Prior Transactions] (as varied by the February 2020 Settlement Agreement).
This deal .. required Tennor to establish a special purpose vehicle, Evergreen Funding SÀRL .. which was to purchase a number of securities from H2O, then issue bonds to investors in order to raise the necessary finance .. I anticipated that the amounts raised from this transaction would be up to EUR 1.25 billion, which would readily allow Tennor to repay the amounts outstanding to the Claimants, as I told Ms Levis and Mr Lefebvre at that time ..
As I have recorded in paragraph 2 above, Ms Levis, is the Chief Investment Officer of the First Claimant. As for Mr Lefebvre, he was a named party to some of the Prior Transactions, and to the February Settlement and the June Settlement. According to Mr Windhorst, Mr Lefebvre is the ultimate beneficial owner of the Heritage Group, of which the Claimants are part.
German financier Lars Windhorst has struck a deal to buy back illiquid stocks and bonds from H2O Asset Management, nearly a year after concerns around these hard-to-sell assets sparked a stampede of investor withdrawals from the London-based investment firm.
H2O .. signed an agreement at the end of April with a new investment vehicle set up by Lars Windhorst, which will buy back stocks and bonds linked to the German financier at a discount .. A spokesman for Mr Windhorst's investment company Tennor .. said: "We are aware that a company linked to our founder Lars Windhorst, with backing from a group of German investors, has signed an agreement to purchase securities linked to Tennor Group from H2O Asset Management LLP."
[46] .. It was absolutely clear to all parties that the consummation of the Evergreen Transaction was essential to the performance of the obligations under the June 2020 Settlement Agreement. The principal obligations under the June 2020 Settlement Agreement were the payment terms ... and it was agreed that the first payment could not be met within the short time frames envisaged under the agreement without the Evergreen Transaction taking place. In particular, the date of 30 June 2020 was chosen because it was the date by which I fully expected Evergreen to have issued the relevant bonds to investors, so it would have sufficient funds to meet the first payment obligation contained in the agreement. ...
[48] ... the whole purpose of the negotiations leading up to the June 2020 Settlement Agreement was to put in place a mechanism by which the Defendants could repay the amounts owed to the Claimants, and the Evergreen Transaction was that mechanism. ...
[50] The bond was duly issued by Evergreen on 9 June 2020. Unfortunately, shortly after the [June Settlement] was signed, it became apparent that the Evergreen Transaction would not proceed as had been anticipated. The Financial Conduct Authority ("FCA") confirmed that it was investigating various transactions concerning H2O, in response to a parliamentary question lodged by Lord Paul Myners, the former City Minister. This was naturally the subject of much press attention. As a result of the FCA's confirmation that it was looking into H2O's activities, and as a result of the publicity this received, Evergreen was unable to secure sufficient investors in connection with the bond issuance comprising the Evergreen Transaction.
[51] Nevertheless, I continued to make every effort to secure sufficient subscribers for the bonds in order to raise the necessary finance .. [W]hen it became clear that the 30 June 2020 deadline for the First Amount would not be met .. I discussed this with Ms Levis and we agreed to extend the deadline for payment of the First Amount by an additional 30 days .. However, even with this additional time and despite my efforts, by 30 July 2020 the bonds were not fully subscribed and there was no real prospect of securing sufficient investors to enable the Evergreen Transaction to proceed. It was also clear from my conversations with Ms Levis at this time that Mr Lefebvre was unwilling to consider any further extension for payment of the First Amount. In light of this, it was clear to all parties to the June 2020 Settlement Agreement that there was no prospect of payment in accordance with its terms.
[52] It was in this context, and as a gesture of goodwill in order to keep the ongoing negotiations alive, I personally made a series of payments to Heritage in order to appease Mr Lefebvre as follows:
(a) A payment of EUR 600,000 on 28 July 2020;
(b) A payment on account of EUR 5,000,000 on 5 August 2020;
(c) A payment of EUR 5,000,000 on 17 August 2020, and on receipt of which Heritage delivered to Tennor the corresponding value (i.e. 2 million) of the shares it held in LP Holding; and
(d) A payment of EUR 5,000,000 on 2 September 2020, and on receipt of which Heritage delivered to Tennor the corresponding value (i.e. 2 million) of the shares it held in LP Holding.
[53] Notwithstanding these payments, which I made personally as a gesture of goodwill and for the purposes of maintaining our ongoing commercial relationship, communications between the parties broke down which seems to have led to Heritage issuing the Application
Confidentiality
[12.1] The terms of this Settlement Agreement and the substance of all negotiations in connection with it are strictly confidential to the Parties and their advisors, who shall not disclose them to, or otherwise communicate them to, any third party without the written consent of each of the other Parties.
[12.2] No Party shall make any public comment or comment to the press or other media concerning this Settlement Agreement.
.. Upon and at any time after the occurrence of an Event of Default, any Claimant may by notice to Tennor (a) declare that any and all amounts accrued or outstanding owed by the Obligors under this Settlement Agreement be immediately due and payable, at which time they shall become immediately due and payable and/or (b) declare that the Parties shall no longer be bound by any of the obligations set out in Clause 12 (Confidentiality), from which time the parties shall no longer be so bound ..[9]
Pressure
[35] .. [B]y December 2019 .. the relationship between Tennor and Heritage was extremely fragile. I was trying to work with them to reach a resolution over the amounts owing under the agreements, but in parallel Mr Lefebvre and Ms Levis were continually threatening to speak to potential investors in Tennor Group (and its indirect subsidiaries) to try to dissuade them from investing, in breach of the confidentiality obligations referred to above. It was clear to me that they intended to do this by disclosing the confidential terms of the various transaction agreements (and the alleged breaches by Tennor) to potential investors. If this did have the effect of putting off those investors, it would have a significant impact on Tennor's profits and its ability to raise further funds, which would have led to disastrous financial consequences for both Tennor and me personally ..
[37] Ms Levis and Mr Lefebvre were well aware that if this information leaked out into the market, this would prevent us from closing transactions that had been put in place to raise the necessary funds to enable the Defendants to meet their performance obligations. Despite this, however, they deliberately took advantage of the concerns I had raised about this and threatened to do exactly that by seeking to exercise their rights as shareholders to obtain information, including details of potential buyers ..
[38]. I knew (as did Mr Lefebvre and Ms Levis) that, if investors thought that Tennor was in serious financial difficulty, they would pull out of the ongoing asset sales and liquidity events that were necessary to ensure the continuing profitability of Tennor. If these transactions were jeopardised by Heritage leaking confidential information to those investors, as I discussed with Ms Levis, the financial consequences for Tennor would be significant, as it would lose substantial cash investment ..
[39] For these reasons, I had no alternative but to enter into [the February Settlement] ..
[45] In the light of [the potential Evergreen Transaction] Mr Lefebvre was prepared to enter into negotiations with me to terminate the February 2020 Settlement Agreement and enter into a new settlement agreement on revised terms .. In parallel to these negotiations, however, the Claimants issued an Acceleration Notice on 11 May 2020 in which they asserted that they were no longer bound by the confidentiality obligations in the February 2020 Settlement Agreement. This was consistent with their previous practice of, on the one hand seeking to negotiate a deal with me, but on the other purporting to enforce rights or threatening to disclose confidential information. Now that Mr Lefebvre and Ms Levis were aware of the H2O deal and Evergreen Transaction, it was helpful in terms of giving them comfort that an agreement could be reached with Tennor; but they also threatened to jeopardise that transaction if required by disclosing the confidential terms of the various transactions and the February 2020 Settlement Agreement to potential investors in the Evergreen bond, which would have caused the entire deal to collapse ..
[49] I knew that if I did not agree to these terms, Ms Levis and Mr Lefebvre would seek to jeopardise the H2O transaction / Evergreen Transaction by disclosing to potential investors the confidential terms of our agreements which, as outlined above, could ultimately lead to Tennor losing an investment of up to EUR 1.25 billion. This was clear to me from the discussions that had taken place between us. I therefore had no option but to agree to the terms that they dictated, even though I thought that they included punitive payment terms, including the additional Daily Penalty Sum. Now that Mr Lefebvre had issued proceedings against Tennor, I considered there to be a serious risk that he would carry out his other threats and seek to put off potential investors in this way. The June 2020 Settlement Agreement was therefore signed on 8 June 2020.
[17] .. Upon default by the Obligors and the service of the Acceleration Notice, Heritage was no longer bound by any duty of confidentiality It is correct, therefore, to say that Heritage was considering warning potential investors in Tennor of its claim, and indeed it was approached by other creditors of Tennor in this respect ..
The negotiation and drafting of both the February 2020 Agreement and the Settlement Agreement were undertaken against the background of intensive without prejudice discussions primarily involving Mr Windhorst and me, together with significant input from our respective legal representatives.
However, according to Mr Windhorst:
[A]lthough both parties were legally represented, usually the key terms with discussed between me or Mr Eoin Speight (the Chief Operating Officer of Tennor) and [Ms Levis] ..or Mr Lefebvre himself (on behalf of Heritage) directly. Frequently, Ms Levis would insist upon the main conditions, describing them as 'non negotiable' and insist that the documentation should be prepared to that effect either that same day or shortly afterwards. The role of our legal teams was principally to document (or "paper") the provisions that she directed with limited subsequent negotiation over the precise wording.
The law concerning economic duress
34.1. There are two essential elements that a claimant needs to establish in order to succeed in a claim for rescission of the contract on the ground of duress. The first is a threat (or pressure exerted) by the defendant that is illegitimate. The second is that that illegitimate threat (or pressure) caused the claimant to enter into the contract[10].
34.2. Economic pressure can amount to duress, provided it may be characterised as illegitimate[11]. However, in the context of economic (though not of other forms of) duress, there is a third element. This is that the claimant must have had no reasonable alternative to giving in to the threat or pressure[12].
34.3. In determining (in relation to the first element) whether pressure is illegitimate, it is relevant to consider both the nature of the pressure and also the nature of the demand which the pressure is applied to support[13]:
34.3.1. A threat of unlawful action such as the commission of a tort or similar wrong or of an offence will usually be treated as illegitimate, whatever the nature of the demand. Many, if not most, threats to break a contract will also similarly be regarded as illegitimate[14].
34.3.2. Where, however, the action threatened is a lawful one, the question of whether it is illegitimate focuses on the nature and justification of the demand rather than the nature of the threat. The court will have regard to, among other things, the behaviour of the threatening party including the nature of the pressure which it applies, and the circumstances of the threatened party[15].
34.3.3. In the commercial context, it is only in extremely limited circumstances that the law will regard a threat to act lawfully as illegitimate or unconscionable. It is not ordinarily duress to threaten to do that which one has a right to do, for instance to refuse to enter into a contract or to terminate a contract lawfully. The pursuit of commercial self-interest is justified in commercial bargaining. The pressure applied by a negotiating party (unless it involves a threat to act unlawfully) will very rarely come up to the standard of illegitimate pressure or unconscionable conduct. It will therefore be a rare circumstance in which a court will find lawful act duress in the context of commercial negotiation[16].
34.4. A contract entered into under duress is not void, but voidable. A person who has entered into a contract under duress may therefore either affirm or avoid the contract after the duress has ceased. If he has voluntarily acted under it with a full knowledge of all the circumstances he may be held bound on the ground of ratification, or if, after escaping from the duress, he takes no steps to set aside the transaction, he may be found to have affirmed it[17].
The submissions of the parties
35.1. The purpose of the Prior Transactions was clearly to obtain short term finance to enable Tennor Group to complete other transactions. The evidence also establishes that it was known to both parties that it was critical to Tennor's profitability that the terms and conditions of the various agreements, as well as the information relating to the parties, remained confidential.
35.2. That need for confidentiality was protected by the contractual confidentiality provisions of the February Settlement set out in paragraph 28 above.
35.3. The Claimants were also subject to an equitable duty of confidence, which (at least arguably) would have continued even after service of the Acceleration Notice brought the contractual obligations of confidence to an end: see CF Partners (UK) LLP v Barclays Bank plc[18]. It would be wrong for me to determine against the Defendants on this application the issue of whether that equitable duty did so continue, since that issue requires the sort of detailed examination of all the facts and surrounding circumstances that is only possible at trial.
35.4. Mr Windhorst's evidence to the effect that he was pressured into agreeing the June Settlement by threats to break those obligations is credible and must be assumed to be true for the purposes of this application.
35.5. Insofar as those threats took place prior to service of the Acceleration Notice on 11 May 2020, they were (inter alia) threats to commit a breach of contract and so amounted to the sort of economic pressure that the law regards as illegitimate.
35.6. Insofar as those threats took place after service of the Acceleration Notice:
35.6.1. They were threats to breach the Claimants' continuing equitable duty of confidentiality and so also amounted to the sort of economic pressure that the law regards as illegitimate; alternatively
35.6.2. To the extent that (contrary to Mr Anderson's primary submission) those threats amounted to 'lawful act duress', the Claimants' conduct:
35.6.2.1. was a reprehensible and unconscionable means of applying pressure, not merely the Claimants exploiting their bargaining power in hard-nosed commercial negotiation; and/or alternatively
35.6.2.2. caused the Defendants to enter into the kind of unconscionable bargain which the law will not uphold.
35.6.2.2.1. As Lord Burrows noted in Times Travel[19], the law of unconscionable bargains:
.. is concerned with the exploitation by A of a weakness of B by entering into a contract that is clearly disadvantageous to B who has not obtained independent advice. In almost all past English cases on unconscionable bargains, B has been an individual with a mental weakness such as inexperience, confusion because of old age or emotional strain .. But it is not inconceivable that the relevant weakness could be the very weak bargaining position of a company ..
35.6.2.2.2. Here, the Defendants were in a very weak bargaining position because they were unable to pay the sums due under the various agreements if potential investors formed the view that Tennor was in serious financial difficulty.
35.6.2.2.3. The Claimants were aware of the Defendants' financial position and acted unconscionably by threatening to disclose confidential information if the Defendants refused enter into the February and June Settlements on the Claimants' terms (largely on a "take it or leave it" basis).
35.6.2.2.4. The terms of those agreements were highly disadvantageous to the Defendants: The June Settlement also contained punitive terms, including the Daily Lump Sum.
35.6.2.2.5. On Mr Windhorst's evidence, the involvement of lawyers in the commercial negotiations was minimal.
35.6.3. In the present, developing state of the law concerning economic duress, it would be wrong for me to determine any of these issues against the Defendants on this application, since they require the sort of detailed examination of all the facts and surrounding circumstances that is only possible at trial.
36.1. Mr Windhorst's evidence of threats in relation to the June Settlement is vague, unspecific and incredible, and should not be accepted even for the purposes of this application:
36.1.1. Most of Mr Windhorst's evidence is concerned with events leading up to the February Settlement, and is therefore not directly relevant to the issues on this application, which is concerned only with the enforceability of the June Settlement.
36.1.2. With regard to the June Settlement, Mr Windhorst gives no evidence about what was allegedly said, when or by whom. Nor does he refer to any contemporaneous documents to support the Defendants' case. Indeed, the only contemporaneous document to which he refers in support of his allegations of illegitimate pressure is the Acceleration Notice.
36.1.3. Mr Windhorst's complaints in paragraph 45 of his witness statement conflate "purporting to enforce rights or threatening to disclose confidential information" and wrongly treat the service of the Acceleration Notice (a plainly lawful act) as part of the pressure which he complains was illegitimate.
36.1.4. Mr Windhorst's assertion that the Claimants were threatening to jeopardise the Evergreen Transaction cannot be reconciled with his repeated refrain that it was understood by all parties that the Evergreen Transaction was the only way for the Claimants to get paid. Such conduct would make no commercial sense.
36.2. Mr Windhorst's evidence (even taken at its highest) only describes pressure said to have been felt by him personally. That is significant because Mr Windhorst did not sign the June Settlement on behalf of any of the Second to Fourth Defendants. It was instead signed by Mr Kindler and Mr Khan. Unlike Mr Kindler and Mr Khan, Mr Windhorst was not a member of the management board of any of the Second to Fourth Defendants when the June Settlement was concluded. There is therefore no evidence at all of any duress against the Second to Fourth Defendants, and no reason why the Claimants should not be able to enforce against those Defendants.
36.3. In any event, the June Settlement was entered into on 8 June 2020, almost a month after the service of the Acceleration Notice on 11 May 2020 caused the contractual obligations of confidence relied on by the Defendants to come to an end.
36.4. The Defendants' suggestion that there could be a continuing equitable obligation of confidentiality is misconceived and unsupported by the authority relied on. That case says in terms that "where the parties have specified the information to be treated as confidential and/or the extent and duration of the obligations in respect of it, the court will not ordinarily superimpose additional or more extensive equitable obligations"[20]. There is nothing in the evidence to suggest that this is a case involving "circumstances that are not ordinary" justifying the imposition of any wider equitable duties of confidence.
36.5. Furthermore, even if the June Settlement had been voidable on the grounds of economic duress or as an unconscionable bargain, it is clear on Mr Windhorst's own evidence that he was free of any such duress and had full knowledge of the relevant circumstances by very shortly after the June Settlement was concluded. Not merely have the Defendants thereafter omitted to take any steps to avoid the June Settlement (which would itself preclude any defence based upon economic duress) but they have positively affirmed the June Settlement by making the payments identified in paragraph [52] of Mr Windhorst's witness statement (set out in paragraph 27 above).
Analysis and conclusions on this issue
38.1. That both parties believed at the relevant time that the Evergreen Transaction stood reasonable prospects of being successful and would, if successful, produce the funds required for the Defendants to meet their obligations to the Claimants;
38.2. That both parties believed at the relevant time that, unless the Evergreen Transaction were successful, it was highly unlikely that the Defendants would be able to perform their obligations under the February Settlement or the June Settlement.
38.3. That, both before and after service of the Acceleration Notice, the Claimants communicated to the Defendants that, unless the Defendants agreed to the terms eventually incorporated into the June Settlement, the Claimants were prepared to disclose to potential investors matters which, prior to service of the Acceleration Notice, would have been subject to the obligations of confidentiality in the February Settlement; and that
38.4. The Defendants, in the belief that such disclosure would be likely to jeopardise the Evergreen Transaction, considered that they therefore had no realistic alternative but to accede to the Claimants' demands.
Condition precedent
.. this Settlement Agreement constitutes the entire agreement between the Parties and supersedes and extinguishes all previous agreements, promises, assurances, warranties, representations and understandings between them, whether written or oral, relating to the subject matter of this Settlement Agreement ..
59.1. In an email dated 6 April 2020, Ms Levis acknowledged that the payment of the First Amount would occur only upon receipt of funds following the Evergreen Transaction:
In the call you told me you think it is possible to use part of the money you collect, to buy back the shares from us, so we look forward to receiving a firm commitment and a precise date.
59.2. Ms Levis acknowledges in paragraph 21 of her witness statement that
Mr Windhorst gave [her] various assurances that the Evergreen Transaction would happen and complete, and that [she] took considerable comfort from this when entering into the Settlement Agreement.
59.3. Ms Timms states in paragraphs 16 and 17 of her witness statement that the Defendants told the Claimants that
Evergreen was in June 2020 in the process of raising funds backed by third party investors to fund these acquisitions and Mr Windhorst and Tennor stated that sufficient funds could be raised at the same time in order for the Defendants to purchase the La Perla Shares and the Avatera Shares to which the First Amount related ..
.. In the light of the difficulties encountered by Evergreen in raising funds, it was apparent to the Claimants as early as late June that the Defendants would breach the Settlement Agreement and fail to pay the First Amount.
She also acknowledges in paragraph 13 that
Funding with which to pay the Settlement Sums was intended to come from the issue of a bond to Evergreen
59.4. Schedule 3 to the June Settlement clearly shows the intention of the parties that the First Amount payable under the June Settlement should be paid by Evergreen.
59.5. In paragraph 28 of her Witness Statement, Ms Levis states that the Daily Lump Sum provided for in clause 3.1(b) of the June Settlement was calculated on the basis that the Evergreen Transaction would take place, and that this was the justification for the inclusion of such a provision.
59.6. The Claimants agreed a one-month extension for the payment of the First Amount to 31 July 2020. This was the anticipated date for consummation of the Evergreen Transaction. When agreeing this extension on 24 July 2020, Ms Levis asked Mr Windhorst by email to provide
.. the agreement terms and waiver with H2O ..
and
.. evidence that the bond is now fully subscribed and the money is in the account ..
[41] .. a term may be implied on the basis of business necessity or obviousness. These are alternatives, in that only one needs to be established, although .. in practice it would be a rare case where only one of those two requirements would be satisfied. In relation to business necessity, this involves a value judgment; it is not a test of absolute necessity; it is rather a question of whether without the term, the contract would lack commercial or practical coherence .. In relation to obviousness, one way of testing this is by reference to Mackinnon LJ's officious bystander .. but if this is done, it is necessary to formulate the question to be posed by him with great care ..
[42]. It is necessary, for a term to be implied, that it should be clear what that term is, and that it is capable of clear expression .. it is not enough to show that had the parties foreseen the eventuality which in fact occurred they would have wished to make provision for it, unless it can also be shown either that there was only one contractual solution or that one of several possible solutions would without doubt have been preferred. In this regard, the fact that an implied term may take several different formulations is a classic sign that it is neither necessary nor obvious ..
Rectification
.. [B]efore a written contract may be rectified on the basis of a common mistake, it is necessary to show either (1) that the document fails to give effect to a prior concluded contract or (2) that, when they executed the document, the parties had a common intention in respect of a particular matter which, by mistake, the document did not accurately record. In the latter case it is necessary to show not only that each party to the contract had the same actual intention with regard to the relevant matter, but also that there was an "outward expression of accord"—meaning that, as a result of communication between them, the parties understood each other to share that intention ..[32]
Penalty
The issue
In consideration for the full and final satisfaction of the Proceedings and settlement of the Disputes, the Obligors shall pay unconditionally and irrevocably to the Claimants to the Settlement Account (and, in relation to such payment, Tennor shall on the date of such payment notify the recipient of the payment in writing) the following:
..
b) subject to paragraph c) below, for value by no later than 15 February 2021, an amount equal to EUR 69,197,440.30 plus a daily lump sum payment of EUR 139,134 (if the full EUR 69,197,440.30 remains outstanding otherwise reduced pro rata) which shall accrue pro rata on the unpaid amount from 27 May 2020 until payment has been made in full (the "Second Amount"). The daily lump sum payment has been negotiated and agreed between the parties as being a fair reflection of the value to the Claimants of ensuring compliance by the Obligors with the terms of this Settlement Agreement:
or, alternatively to sub-paragraph b) above;
c) subject to clause 7 (Failure to make payment), if the Obligors pay to the Settlement Account for value by no later than 31 December 2020 an amount equal to EUR 50,000,000 in respect of the Second Amount (the "Discounted Second Amount") such that the aggregate amount received for value in the Settlement Account on or prior to 31 December 2020 is not less than the sum of (i) any costs payable under clause 8.2 and (ii) EUR 105,002,559.70 (being an amount equal to the aggregate of the First Amount and the Discounted Second Amount) the Obligors shall have fully satisfied their payment obligations under this Clause 3.1.
The Defendants' case is that that provision is a penalty, in that it is a sum payable upon breach which extends far beyond any reasonable compensation for that breach, and which is not designed to protect any legitimate interest of the Claimants.
7.1. If the First Amount is not paid in full and on time in accordance with Clause 3.1(a) above, any Claimant may by notice to Tennor:
a) declare that clause 3.1(c) concerning the Discounted Second Amount shall cease to have effect, following which that clause shall immediately cease to have effect; and
b) declare that the unpaid balance of the First Amount and the Second Amount be immediately due and payable by the Obligors jointly and severally, at which time any Claimant can immediately enter judgment upon default against any Obligor individually or two or more Obligors jointly and severally for the unpaid balance of the First Amount and/or the Second Amount (which shall include the daily lump sum payment with respect to any unpaid amount calculated up to 15 February 2021) and/or the legal costs referred to in Clause 8.2 below; or c) declare that the First Amount be immediately due and payable by the Obligors jointly and severally, but permit the Obligors further time to make payment of the Second Amount but only on the basis that during this period the daily lump sum payment payable under clause 3.1(b) shall continue to accrue with respect to any unpaid amount until payment of the Second Amount.
The law
.. whether the impugned provision is a secondary obligation which imposes a detriment on the contract-breaker out of all proportion to any legitimate interest of the innocent party in the enforcement of the primary obligation ..
[14] This means that in some cases the application of the penalty rule may depend on how the relevant obligation is framed in the instrument, ie whether as a conditional primary obligation or a secondary obligation providing a contractual alternative to damages at law. Thus, where a contract contains an obligation on one party to perform an act, and also provides that, if he does not perform it, he will pay the other party a specified sum of money, the obligation to pay the specified sum is a secondary obligation which is capable of being a penalty; but if the contract does not impose (expressly or impliedly) an obligation to perform the act, but simply provides that, if one party does not perform, he will pay the other party a specified sum, the obligation to pay the specified sum is a conditional primary obligation and cannot be a penalty.
[15] However, the capricious consequences of this state of affairs are mitigated by the fact that, as the equitable jurisdiction shows, the classification of terms for the purpose of the penalty rule depends on the substance of the term and not on its form or on the label which the parties have chosen to attach to it ..[35]
.. the penal character of a clause depends on its purpose, which is ordinarily an inference from its effect. As we have already explained, this is a question of construction, to which evidence of the commercial background is of course relevant in the ordinary way ..
.. The innocent party can have no proper interest in simply punishing the defaulter. His interest is in performance or in some appropriate alternative to performance. In the case of a straightforward damages clause, that interest will rarely extend beyond compensation for the breach .. But compensation is not necessarily the only legitimate interest that the innocent party may have in the performance of the defaulter's primary obligations .. [36]
Primary or secondary obligation?
Disproportionate detriment
Disposition
Note 1 Times Travel (UK) Ltd v Pakistan International Airlines Corpn [2021] UKSC 40. [Back] Note 2 [2019] EWCA Civ 828, [2020] Ch 98. [Back] Note 3 Mr Windhorst’s evidence was that these transactions were “effectively a loan”. That evidence was disputed by Ms Levis in her responsive witness statement, who asserted that the transactions were instead in substance “the purchase of shares with an option for Heritage to sell them back at a profit”. However, Ms Levis did not dispute that the economic effect was to make cash available to the Defendants. [Back] Note 4 [2019] EWHC 547 (Comm), [2019] 4 WLR 44 at [23] – [25]. [Back] Note 5 [2010] EWHC 959 (QB), [2012] 1 WLR 338 at [28]. See also CFL Finance Limited v Laser Trust, Moises Gertner [2021] EWCA Civ 228 at [26], per Newey LJ. [Back] Note 6 [2007] EWHC 1044 (Ch), [2007] PNLR 28 at [4]. [Back] Note 7 [2009] EWHC 339 (Ch) at [15]; approved by the Court of Appeal in AC Ward & Son v Catlin (Five) Ltd [2009] EWCA Civ 1098, [2010] Lloyd's Rep IR 301 at [24], per Etherton LJ, and in Global Asset Capital Inc and another v Aabar Block SARL [2017] EWCA Civ 37, [2017] 4 WLR 163 at [27], per Hamblen LJ. See also TFL Management Services Ltd v. Lloyds TSB Bank plc [2013] EWCA Civ 1415, [2014] 1 WLR 2006 at [26]-[27] per Floyd LJ. [Back] Note 8 [2018] EWHC 519 (Comm) at [27], [30] and [31]. [Back] Note 10 Times Travel (UK) Ltd v Pakistan International Airlines Corpn (fn 1 above), per Lord Burrows JSC, and at [1], per Lord Hodge DPSC (with whom Lord Reed PSC, Lord Lloyd-Jones and Lord Kitchin JJSC agreed). [Back] Note 11 Universe Tankships Inc of Monrovia v International Transport Workers Federation [1983] 1 AC 366; Dimskal Shipping Co SA v International Transport Workers Federation [1992] 2 AC 152; Times Travel (UK) Ltd v Pakistan International Airlines Corpn (fn 1 above) [78], per Lord Burrows JSC, and at [1], per Lord Hodge DPSC (with whom Lord Reed PSC, Lord Lloyd-Jones and Lord Kitchin JJSC agreed). [Back] Note 12 Times Travel (UK) Ltd v Pakistan International Airlines Corpn (fn 1 above) at [79], per Lord Burrows JSC, and at [1], per Lord Hodge DPSC (with whom Lord Reed PSC, Lord Lloyd-Jones and Lord Kitchin JJSC agreed). [Back] Note 13 The Universe Sentinel [1983] 1 AC 366 at [401], per Lord Scarman; R v Attorney-General for England and Wales [2003] UKPC 22, [2003] EMLR 24 at [16], per Lord Hoffmann. [Back] Note 14 Times Travel (UK) Ltd v Pakistan International Airlines Corpn [2019] EWCA Civ 828, [2020] Ch 98 at [51], per David Richards LJ (not discussed on appeal). See also Kolmar Group AG v Traxpo Enterprises Pvt Ltd [2010] EWHC 113 (Comm) | [2011] 1 All ER (Comm) 46 at [92], per Christopher Clarke J. [Back] Note 15 Times Travel (UK) Ltd v Pakistan International Airlines Corpn (fn 1 above) at [88] and [96], per Lord Burrows JSC, and at [1], per Lord Hodge DPSC (with whom Lord Reed PSC, Lord Lloyd-Jones and Lord Kitchin JJSC agreed). [Back] Note 16 Times Travel (UK) Ltd v Pakistan International Airlines Corpn (fn 1 above) at [28] – [30], per Lord Hodge DPSC (with whom Lord Reed PSC, Lord Lloyd-Jones and Lord Kitchin JJSC agreed), citing J Beatson, A Burrows and J Cartwright (eds), Anson’s Law of Contract (31st edn, OUP 2020) ch 10.2(d). [Back] Note 17 Beale and others, Chitty on Contracts (33rd edn, Sweet & Maxwell 2018) at [8-054]; North Ocean Shipping Co Ltd v Hyundai Construction Co Ltd [1979] QB 705 at 719-720, per Mocatta J. [Back] Note 18 [2014] EWHC 3049 (Ch) at [132]-[134] and [894]-[895], per Hildyard J.
[Back] Note 19 Times Travel (UK) Ltd v Pakistan International Airlines Corpn (fn 1 above) at [77]. [Back] Note 20 CF Partners (UK) LLP v Barclays Bank plc (fn 18 above) at [131]. [Back] Note 21 CF Partners (UK) LLP v Barclays Bank plc (fn 18 above) at [895]. [Back] Note 22 CF Partners (UK) LLP v Barclays Bank plc (fn 18 above) at [132].
[Back] Note 23 Times Travel (UK) Ltd v Pakistan International Airlines Corpn (fn 1 above) at [98], per Lord Burrows JSC, and at [1], per Lord Hodge DPSC (with whom Lord Reed PSC, Lord Lloyd-Jones and Lord Kitchin JJSC agreed). [Back] Note 24 See Lungowe and others v Vedanta Resources plc [2020] AC 1045 at [45], per Lord Briggs JSC (with whom Baroness Hale of Richmond PSC, Lord Wilson, Lord Hodge and Lady Black JJSC agreed). In reaching this conclusion, I have not forgotten that something did in fact turn up for Mr Micawber, who by the end of David Copperfield had emigrated to Australia, where he became a successful Magistrate. [Back] Note 25 Arnold v Britton [2015] UKSC 36, [2015] AC 1619 at [21], per Lord Neuberger of Abbotsbury PSC, [Back] Note 26 [2017] UKSC 24, [2017] AC 1173. [Back] Note 27 Trillium (Prime) Property GP Limited v Elmfield Road Limited [2018] EWCA Civ 1556 at [9], per Lewison LJ. [Back] Note 28 [2015] UKSC 72, [2016] AC 742. [Back] Note 29 [2021] EWHC 1157 (Comm) [Back] Note 30 Chartbrook Ltd v Persimmon Homes Ltd [2009] AC 1101 at [14], per Lord Hoffmann; Arnold v Britton (fn 28 above) at [15], per Lord Neuberger of Abbotsbury PSC. [Back] Note 31 See e.g. Lloyds TSB Bank Ltd v Crowborough Properties Ltd [2013] EWCA Civ 107 at [55]-[70]. [Back] Note 32 FSHC Group Holdings Ltd v GLAS Trust Corpn Ltd [2019] EWCA Civ 1361, [2020] Ch 365 at [176].per Leggatt LJ (giving the judgment of the court). [Back] Note 33 Swainland Builders Ltd v Freehold Properties Ltd [2002] EWCA Civ 560, [2002] 2 EGLR 71 at [34(2)], per Peter Gibson LJ. [Back] Note 34 [2015] UKSC 67, [2016] AC 1172 at [32], per Lord Neuberger of Abbotsbury PSC. [Back] Note 35 Cavendish Square Holding BV v Makdessi (fn 34 above) at [14]-[15], per Lord Neuberger of Abbotsbury PSC. [Back] Note 36 Cavendish Square Holding BV v Makdessi (fn 34 above) at [28] and [32], per Lord Neuberger of Abbotsbury PSC. [Back] Note 37 Robophone Facilities Ltd v Blank [1966] 1 WLR 1428, CA, at 1447, per Diplock LJ. [Back] Note 38 Philips Hong Kong Ltd v Attorney General of Hong Kong (1993) 61 BLR 41, PC, at 59, per Lord Woolf. [Back] Note 39 Se eg Lordsvale Finance v Bank of Zambia [1996] QB 752 (1% uplift); ZCCM Investments Holdings plc v Konkola Copper Mines plc (rate increasing in stages from 2.5% to 10% over LIBOR); Cargill International Trading Ltd v Uttam Galva Steels Ltd [2019] EWHC 476 (Comm) (LIBOR + 12%); Taiwan Scott Co Ltd v the Masters Golf Company Ltd [2009] Civ 685 (15%); Davenham Trust Plc v Homegold [2009] WLUK 368 (36%) (but see White v Davenham Trust Limited [2011] Bus LR 615); Holyoake v Candy [2017] EWHC 3397 (Ch) (50%); Cargill International Trading Pte Ltd v Uttam Galva Steels Ltd [2019] EWHC 476 (Comm) (LIBOR + 12%); ICICI Bank UK plc v Assam Oil Co Ltd [2019] EWHC 750 (Comm) (4% uplift); Lombard North Central plc v European Skyjets Ltd [2020] EWHC 679 (QB) (5% uplift); Biosol Renewables UK Ltd v Lovering [2021] EWHC 71 (Comm) (1.5% per month); Bedford Investments Ltd v Sellman [2021] EWHC 799 (Comm) (standard rate 3% per month, concessionary rate 1.25%). [Back] Note 41 [1963] 2 QB 104. See, more recently, Lombard North Central plc v Butterworth [1987] QB 527 dealing with a lease which, like the June Settlement, contained a provision making time of the essence, and which held that in such a case the proper comparison at stage 2 was with loss of bargain damages, and not simply with the instalments accrued to the date of termination. [Back]