QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Rolls Building, Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
Sitting as a Judge of the High Court
____________________
LOPESAN TOURISTIK S.A |
Claimant |
|
- and – |
||
(1) APOLLO EUROPEAN PRINCIPAL FINANCE FUND III (DOLLAR A) L.P (2) APOLLO EUROPEAN PRINCIPAL FINANCE FUND III (MASTER DOLLAR B) L.P. (3) APOLLO EUROPEAN PRINCIPAL FINANCE FUND III (MASTER EURO B) L.P (4) APOLLO EPF III CAPITAL MANAGEMENT LLC |
Defendants |
____________________
Laurence Rabinowitz QC, Richard Mott and Michael Watkins (instructed by Latham & Watkins) for the Defendants
Hearing dates: 19 and 20 April 2021
____________________
Crown Copyright ©
Christopher Hancock QC (sitting as a Judge of the High Court)
Introduction and background.
The parties
The SPA
(1) Clause 2.2(b) provides that title to the Shares would transfer on the "Completion Date, once the Condition Precedent has been fulfilled and the Completion Actions are completed".
(2) The "Completion Date" is defined as being a date agreed between the parties within ten Business Days following satisfaction of the Condition Precedent, failing which the Completion Date was to be the first Business Day ten Business Days from the date on which the Condition Precedent was fulfilled: clause 6.2.
(3) The "Condition Precedent" involved obtaining merger control clearance from the European Commission: clause 3.1(a). It is common ground that this condition precedent has been satisfied, but the date on which it was satisfied is not common ground. As I note below, the parties proceeded before me on the basis that it should be taken to have been satisfied by 30th April 2020, at the latest.
(4) The "Completion Actions" are set out in clause 6.3 and involve (amongst other things) payment of the purchase price, transfer of title to the Shares, and ratification or update of various representations and warranties by each party according to clause 7. Each of those actions is to be carried out "in a single act" and are "essential obligations".
(5) The representations and warranties are set out in clause 7 and schedule 1. It is Oldavia's case in Spain, and the Defendants' case in these proceedings, that these representations and warranties were required to be true both as at the date of signing, and as at the Completion Date: see clause 7.1(c).
(6) Lopesan gave a series of further undertakings relating to the management of the Company in the period between the Signing Date and the Completion Date (the "Interim Period"), including that it would be managed in such a manner as to ensure that the representations and warranties remained true on the Completion Date: clause 5.1(b).
(7) Clause 8 of the SPA contains a liability regime for compensating Oldavia for Damages (as defined in the SPA) suffered as a result of a breach of contract or misrepresentation by Lopesan. Amongst other things, the parties agreed that any Damages awarded to Oldavia would operate so as to reduce the price payable to Lopesan under the SPA. However, Lopesan's liability for Damages is stated to be limited to 20% of the Completion Payment.
The ECL
The dispute between Lopesan and Oldavia
The Spanish proceedings
(1) Whether the SPA was validly terminated by agreement between the parties thereto on 13 and/or 19 April 2020;
(2) Whether the SPA was validly terminated by Oldavia on 24 April 2020, 29 April 2020 or 21 May 2020 by reason of Lopesan's alleged breach thereof;
(3) Whether the SPA was terminated by operation of law by virtue of the subject matter thereof being lost or destroyed (i.e. the principle of Desaparicion de la base de negocio);
(4) Whether the SPA was terminated pursuant to the principle of Rebus Sic Standibus;
(5) Whether the alleged Completion Date was ever validly fixed under the terms of the SPA;
(6) Whether Lopesan's alleged breaches of the SPA have resulted in Oldavia's obligation to make the Completion Payment being suspended and/or terminated pursuant to the doctrine of exceptio non adimpleti contractus.
The English proceedings
The applicable legal principles.
(1) The "primary source for understanding what the parties meant is their language interpreted in accordance with conventional usage": Bank of Commerce and Credit International SA v. Munawar Ali (No 1) [2002] 1 AC 251, §39 per Lord Hoffmann; and Arnold v. Britton [2015] 2 WLR 1593, §17 per Lord Neuberger.
(2) It is necessary to consider the contract as a whole checking the rival interpretations against the other clauses in the contract and investigating their commercial consequences: Wood v. Capita Insurance Services Ltd [2017] AC 1173, §12 per Lord Hodge.
(3) In an appropriate case, it may also be necessary to consider the admissible factual matrix: Wood v. Capita, §10 per Lord Hodge.
(4) The weight to be given to these considerations varies from case to case: Wood v. Capita, §§10 and 13 per Lord Hodge.
(5) Finally, although the commercial consequences of a given interpretation may be relevant, "a court should be very slow to reject the natural meaning of a provision as correct simply because it appears to be a very imprudent term for one of the parties to have agreed, even ignoring the benefit of wisdom of hindsight. The purpose of interpretation is to identify what the parties have agreed, not what the court thinks that they should have agreed": Arnold v. Britton at §20 per Lord Neuberger.
(1) First, it relied on the fact that the commercial purpose of the ECL was to provide funding for the Transaction, in circumstances where Oldavia otherwise had no means of funding the Transaction. Hence, the object was to ensure that Oldavia was in funds so as to be able to complete on the Transaction.
(2) Second, it relied on the fact that Oldavia was the Defendants' SPV for the purposes of the Transaction, and that the Defendants had control over it. It was argued that it would therefore be wrong to construe the ECL on the basis that the Defendants and Oldavia were at arm's length from one another.
(3) Third, it relied on the close connection between the SPA and the ECL. The commercial purpose of the ECL was to provide funding for the completion of the SPA. The SPA expressly required the ECL to be issued. The ECL expressly adopted defined terms used in the SPA, and is itself expressly subject to the terms of the SPA. The two contracts were therefore intended to work in harmony with one another, and the ECL should be construed on that basis.
The relevant contractual clauses.
(1) "Completion" means "the act in which on Completion Date (as a sole act or en unidada de acto) where a complementary public deed will be granted before the Notary, the Shares will be sold and transferred to the Buyer, the Completion Payment will be paid, and the remaining actions set out in clause 6 will be carried out."
(2) The "Completion Date" is determined by clause 6.2 of the SPA, as follows:
"The Completion Date shall take place on the date set out by the Parties within ten (10) Business Days from the date on which the fulfillment (sic) of the Condition Precedent is proved. In the case of discrepancy on the Completion Date, Completion Date will be set on the first Business Day following the termination of the above mentioned ten (10) Business Days term."
(3) Pursuant to clause 3.1 of the SPA, the "Condition Precedent" was obtaining merger clearance from the European Commission. As to this:
a) There is a dispute between the parties as to when this Condition Precedent was satisfied, although both parties accept that it was satisfied.
b) Lopesan contends that it was satisfied on 15 April 2020 such that the Completion Date would be 30 April 2020.
c) The Defendants contend the Condition Precedent was satisfied on 8 April 2020 and that the Completion Date would have been 21 April 2020, alternatively that if the Condition Precedent was satisfied on 15 April 2020 then the Completion Date would have been 28 April 2020.
d) This gives rise to questions of Spanish law as to when the Condition Precedent was satisfied under the SPA and how the relevant time period is to be computed.
e) For present purposes, however, it is sufficient to note that the Completion Date would have been 21 or 28 or 30 April 2020.
f) Both parties were content to adopt the latest of these dates for the purposes of argument, and I therefore follow suit in this judgment.
(4) Clause 4 dealt with the payment of the Completion Payment, which was to be a sum calculated by reference to a formula involving the payment of the purchase price of €93m plus or minus estimated net financial debt and plus or minus estimated working capital. There was then provision for adjustment to be made post completion.
(5) Clause 6 set out the requirements for completion under the SPA:
"6.1 Once the fulfillment of the Condition Precedent of the Agreement has been evidenced, the Parties shall be obliged to comply on the Completion Date with all of the Completion Actions describe[d] in clause 6.
6.2 The Completion Date shall take place on the date set out by the Parties within ten (10) Business Days from the date on which the fulfilment of the Condition Precedent is proved. In the case of discrepancy on the Completion Date, Completion Date will be set on the first Business Day following the termination of the above mentioned ten (10) Business Days term.
6.3 Acts and Procedures to be carried out by the Parties on Completion Date. [This clause set out a series of actions which were to be carried out before the Notary Public on the Completion Date]
6.4 All acts and procedures described in clause 6.3 above will be carried out on the Completion Date, in a single act. The parties acknowledge and agree that the performance of each and every one of the actions provided for in this clause are essential obligations of this Agreement, and that none of them shall be deemed to have been performed until such time as each and every one of them has been duly executed in accordance with the terms of this Agreement."
(1) Pursuant to clause 1.1 of the ECL, "Completion" and "Completion Date" are given the meaning ascribed to them in the SPA.
(2) Clause 2.1 of the ECL provides:
"The [Defendants] hereby agree, on the terms and subject to the conditions set forth herein and in the [SPA], to contribute or cause to be contributed to [Oldavia], through one or more entities wholly owned by the [Defendants], in cash in immediately available funds an amount equal to €93,000,000 required by [Oldavia] to complete the acquisition of the Shares at Completion in accordance with the terms of the [SPA] (such amount being in aggregate, the "Commitment") immediately prior to the Completion Date."
(3) Clause 2.3 stated that:
"The funding of the Commitment is, solely for the purposes of funding, and to the extent necessary to fund, that portion of the Completion Payment (net of any reductions contemplated in the [SPA]) to be paid by [Oldavia] pursuant to and in accordance with the [SPA] on the Completion Date. The [Defendants] shall not, under any circumstances, be obligated to contribute, or cause to be contributed, to [Oldavia] or to any other person or entity, an amount exceeding the Commitment. For the avoidance of doubt and notwithstanding anything that may be expressed or implied in this Letter or any document or instrument delivered contemporaneously with this letter (including, without limitation, the [SPA]), in no event shall the [Defendants] have any obligation to make (or cause one or more of their Affiliates to make) any payment or contribution under this Letter other than to fund the Completion Payment in connection with the Completion and the sale of the Shares to the Purchaser."
(4) Clause 3 set out various conditions, as follows:
"3. Conditions
3.1 The [Defendants'] obligation to fund the Commitment described in Clause 2 (Commitment) is subject to the satisfaction, or waiver, of all of the conditions precedent to the obligations of [Oldavia] to consummate the transactions contemplated by the [SPA] which are to occur on the Completion Date (other than those conditions that by their nature are to be or can only be satisfied at Completion or are not satisfied as a result of a breach by [Oldavia]).
3.2 In the event that [Oldavia] terminates the [SPA] in accordance with the terms of the [SPA] due to a failure of the [Claimant] to close the transactions contemplated therein, all copies of this Letter shall be immediately returned to the [Defendants]."
(5) Clause 5 dealt with termination:
"5.1 The [Defendants'] obligation to fund (or cause one or more of their Affiliates to fund) the Commitment is subject to the terms of this Letter and to (a) the execution and delivery of the [SPA] and (b) [Oldavia] becoming obligated unconditionally under the [SPA] to effect the Completion. The obligation of the [Defendants] to fund (or cause one or more of their Affiliates to fund) the Commitment will terminate automatically and immediately (at which time the Investors' obligations under this Letter shall be discharged) upon the earlier to occur of (i) the consummation of Completion, (ii) the valid termination of the [SPA] in accordance with its terms, (iii) 1 January 2021, or (iv) the assertion by the [Claimant] or any of its Affiliates of any claim against any [Defendant] or any Party Affiliate (as defined below) thereof in connection with the [SPA] or any transaction contemplated hereby or thereby, except for (x) claims by the [Claimant] against the [Defendant] under the [SPA] and (y) claims by the [Claimant] against the [Defendants] to enforce [Oldavia's] rights under this Letter. Clauses 4 (Confidentiality) and 10 (Limitation on Liability of Party Affiliates) of this Letter shall survive any such termination.
5.2 The only claims to be made by the Seller under this Letter shall be claims brought by it pursuant to the exercise of the Seller's rights pursuant to Clause 6 (Third Party Beneficiaries) and Clause 12 (Governing Law and Enforcement) solely to give effect to Completion or otherwise pursuant to Clause 4 (Confidentiality), Clause 8 (Assignment) or Clause 9 (Amendments and Entire Agreement) and for no other reason."
(6) Clause 6 then dealt with Third Party Beneficiaries, as follows:
"6.1 Except as expressly set forth in this Clause 6 (Third Party Beneficiaries), nothing in this Letter, express or implied, is intended to confer upon any person or entity, other than the Purchaser, any right, benefit, or remedy under or by reason of this Letter pursuant to the Contracts (Rights of Third Parties) Act 1999 or otherwise.
6.2 Notwithstanding Clause 6.1 (Third Party Beneficiaries), each of the Investors, the Purchaser and the Seller acknowledge and agree that the Seller has relied on this Letter and accordingly, subject to the Contracts (Rights of Third Parties) Act 1999 the Seller is an express third-party beneficiary hereof and the Seller is entitled and shall have the right to specifically enforce the obligations of the Investors for the purposes of Completion but for no other purposes:
6.2.1 directly against the Investors (provided that, however, this paragraph shall not be understood in the sense that the Seller shall have the right to require payment of the Commitment to the Seller but only to the Purchaser); and/or
6.2.2 by requiring the Purchaser to enforce any of its rights under this Letter, in each case, to the full extent hereof (including by obtaining specific performance as contemplated in Clause 12 … except that such rights of the Seller shall be exercisable subject to the satisfaction of the conditions to funding set forth in Clause 3 (Conditions); and
6.2.3 save as set out in this Clause 6 (Third Party Beneficiaries) Clause 8 (Assignment), Clause 9 (Amendments and Entire Agreement) and Clause 12 (Governing Law and Enforcement) neither the Seller nor any of its Party Affiliates or representatives shall have any other rights or remedies hereunder."
Issue 1: When does Apollo's obligation to fund the Commitment arise?
The Defendants' contentions.
(1) There is some overlap between clause 3.1 and clause 5.1(b), in that both clauses are concerned to ensure that the Defendants' obligation to fund the Commitment is conditional upon Oldavia being obliged to consummate the transactions pursuant to the SPA. However, clause 3.1 is concerned only with satisfaction of the "conditions precedent" to Oldavia's obligation to consummate the transaction under the SPA, whereas clause 5.1(b) is concerned with the broader question whether, in any event, Oldavia is unconditionally obligated to complete under the SPA. It is however clear that both conditions must be satisfied before the obligation to fund can arise.
(2) Here, Oldavia, for a number of different reasons, contends that as at 23:59 on 29 April 2020 (when the Claimant alleges that the funding obligation arose) it was not unconditionally obliged to complete the acquisition. These include the following:
a) The parties terminated the SPA by agreement prior to 29 April 2020.
b) To the extent that there was any doubt about that, Oldavia terminated the SPA on 24 April 2020 by reason of Lopesan's breaches of contract.
c) Further, to the extent that there was no termination in accordance with (a) or (b) above:
i. Oldavia was in any event not obliged to complete in circumstances where Lopesan was itself in breach of contract; and/or
ii. the SPA had terminated by operation of law.
(3) It is plain that if any of these contentions (relating to the position under the SPA) is upheld, then the obligation to fund will not even have arisen. It is for this reason that, the Defendants argued, none of the preliminary issues are capable of finally resolving this claim in Lopesan's favour.
(4) On the other hand, if the SPA had not already been terminated for one or more of the reasons identified above, then the Defendants do not dispute that if, as at 23:59 on the day before the Completion Date, the Condition Precedent had been satisfied and Oldavia's obligation to complete under the SPA was subject only to conditions that would be satisfied at Completion itself, or which were not satisfied by reason of a breach of contract by Oldavia, it would in those circumstances follow that, by reason of clause 3.1 of the ECL, the obligation to fund the Commitment would nonetheless have arisen.
(5) However, what does not follow, is that anything that happens on the Completion Date, or thereafter, would be irrelevant especially if and insofar as these are or were matters capable of falling within the circumstances described by clause 5.1 of the ECL. In particular, and for the reasons explained in more detail in relation to Issue 2, the obligation to fund the Commitment, even if it may have arisen prior to this, would subsequently have lapsed if Oldavia was, for whatever reason, not obliged to complete on the Completion Date itself, or if, again for whatever reason, the SPA terminated on that date, or thereafter. That is because it makes no sense for the Defendants to remain subject to an obligation to provide funding for the purposes of a transaction that will no longer occur or conclude.
(6) The second precondition for any funding obligation even to have arisen is that the ECL must not have terminated pursuant to clauses 5.1(i) to (iv) prior to the date on which the obligation to fund otherwise falls due.
(1) the conditions referred to in clauses 3.1 and 5.1(b) have been satisfied; and
(2) the ECL has not, prior to that time, otherwise terminated under clause 5.1(i) to (iv).
Lopesan's contentions.
(1) In context, there is only one function which these words could be fulfilling – namely, specifying the point in time by which the Defendants were required to put Oldavia in funds by paying the Commitment.
(2) The clause provides (a) for the parties to agree a Completion Date within ten Business Days of the date on which the satisfaction of the relevant condition precedent (i.e. obtaining merger control clearance) was "proved"; and (b) in the event that the parties cannot agree such a date, for a long-stop Completion Date 10 Business Days after the merger control clearance had been obtained.
(3) Whilst, on the pleadings, there is a dispute between the parties as to how to apply clause 6.2 to the particular facts of this case, (as I have already noted), that dispute does not arise for determination at this stage. What matters for present purposes is that clause 6.2 clearly operates to set a particular calendar day as "the Completion Date".
(4) It follows that, when clause 2.1 of the ECL stipulates that the Defendants shall pay the Commitment "immediately prior to the Completion Date", it is requiring that the Defendants make the payment immediately prior to the relevant calendar day – i.e. by no later than 11:59pm on the preceding day.
(5) As well as being the only realistically available construction of the words used in the ECL, this construction also makes commercial sense. In order for Oldavia to proceed with Completion of the Transaction on the Completion Date, it needed to be in funds. It did not have (and the parties never expected it to have) any funds of its own, or any means to raise funds other than via the ECL. One would therefore expect that payment under the ECL would have to be made in advance of the Completion Date in order for the Transaction to proceed in accordance with the terms of the SPA.
(6) Whilst clause 6.3 of the SPA requires the parties to carry out a series of actions on the Completion Date to effect Completion, which are itemized at sub-clauses (a) to (j), and which the SPA defines as "the Completion Actions", there are two key points to note about this clause:
a) First, certain of the actions specified therein would only be capable of being fulfilled after the Defendants had paid the Commitment to Oldavia. These include the actions at sub-clause (d) (Oldavia making the Completion Payment – see also clause 4.2 of the SPA), and those at sub-clause (f) (the parties granting a supplementary deed which was to include inter alia evidence of the Completion Payment having been made by Oldavia).
b) Second, the clause creates no temporal (or other) hierarchy as between the various actions identified in sub-clauses (a)-(j), or any order of priority as between the parties. As clauses 4.2 and 6.3 of the SPA make clear, all of these Completion Actions are to be made on the Completion Date.
(7) Further, both the definition of "Completion" and clause 6.4 of the SPA (set out above) point away from the idea that Completion under the SPA was to proceed as a series of sequential steps. Clause 6.4 is particularly clear on this point.
(8) Accordingly, it is not realistic to speak of a particular moment in time at which, as a result of Lopesan undertaking a series of acts, Oldavia became "unconditionally obliged to effect completion". Instead, if and when the Completion Date was set in accordance with the SPA, both Lopesan and Oldavia were unconditionally obliged to attend before the Notary on that date and, "in a single act", undertake the actions identified in clause 6.3 of the SPA. None of those actions would be deemed to be completed until they were all completed. Once that had happened, Completion under the SPA would have occurred. That is precisely what clause 6.1 of the SPA provides.
(9) Oldavia obviously needed to be in funds in order for the Completion Actions to be undertaken in accordance with clauses 4.2 and 6.3 of the SPA.
a) This leads to the question – what is the proper construction of the words: "[Oldavia] becoming obligated unconditionally under the [SPA] to effect the Completion" in clause 5.1 of the ECL? Lopesan submits that the only sensible construction of these words, given the terms of clauses 4.2 and 6 of the SPA and the points raised above is: "Oldavia becoming obliged unconditionally to attend upon the Notary and, together with Lopesan, carry out the Completion Actions identified in clause 6.3 of the SPA".
b) As well as being the only construction which makes sense, given the terms of the SPA, this construction also has the following virtues:
i. It is entirely consistent with clause 2.1 of the ECL – which requires the Defendants to pay the Commitment "immediately prior to the Completion Date".
ii. It corresponds precisely with clause 6.1 of the SPA, set out above.
Discussion and conclusions.
Issue 2: If Apollo's obligation to fund the Commitment has arisen, will that obligation be discharged upon the occurrence of any of the following events?
a) if Oldavia is not obliged unconditionally to effect Completion pursuant to the SPA;
b) the valid termination of the SPA (for whatever reason); and/or
c) on 1 January 2021 if Completion has not occurred by that date?
The Defendants' contentions.
(1) Clause 5.1(b) provides that the Defendants' "obligation to fund (or cause one or more of their Affiliates to fund) the Commitment is subject to the terms of this Letter and … (b) [Oldavia] becoming obligated unconditionally under the [SPA] to effect the Completion." (emphasis added);
(2) The natural and ordinary meaning of these words is that the Defendants' obligation to fund the Commitment is contingent upon Oldavia being unconditionally obliged to effect Completion under the SPA, with the result that the Defendants' obligation to fund the Commitment does not arise if, prior to the time at which it might otherwise have arisen, Oldavia is no longer unconditionally obliged to effect Completion. Similarly, even if the obligation to fund has arisen, but then, for whatever reason, Oldavia ceases to be under an obligation to effect Completion, the obligation to fund will lapse and be discharged.
(3) Not only is this what the words of the ECL actually provide, any other interpretation makes no commercial sense. In particular, it makes no sense to say that, once the obligation to fund has arisen, nothing thereafter can cause it to lapse or be discharged. In this regard, the Defendants put forward various scenarios in which it was suggested that the result that it contended for would obviously follow:
a) At midnight on 29 April 2020, Oldavia was unconditionally obliged to complete the transaction, such that the funding obligation arose, but the very next day – before Completion could be effected – the Spanish Government enacted measures which made it unlawful to close.
b) The funding obligation arose immediately prior to the Completion Date, but Lopesan, because of a pandemic event, was unable to perform one of its essential obligations on the Completion Date itself[1]. In those circumstances, Oldavia would not be obliged to perform its obligations on the Completion Date and would be entitled to terminate the SPA.
(4) In either of the scenarios posited above, it makes no sense for the Defendants' accrued obligation to remain enforceable, such that either Oldavia, or Lopesan, could sue the Defendants requiring them nonetheless to pay over the funds in relation to a transaction that was no longer to conclude.
(5) Moreover, such a result would be directly contrary to the terms of ECL (in particular, clauses 2.3, 5.2 and 6.2) which make it clear that the funds can only be used for the purposes of Completion, and that (in the case of clause 2.3) "in no event shall the Defendants have any obligation to make" a payment other than for that purpose. Completion plainly will not happen if Oldavia's obligation under the SPA to complete does not arise, or is discharged, and it can make no difference whether the events that lead to this outcome occur before midnight on the day before the Completion Date, or a few minutes later, on the Completion Date itself.
(1) It is well established that money which falls due under a contract can generally be recovered if it is paid subject to a condition which subsequently fails.
(2) It is clear that, in the scenarios described above, the Defendants would be entitled to recover the funds if the Defendants had paid the funds to Oldavia on 29 April 2020, but Oldavia's obligation to complete was subsequently discharged, such that Completion never occurred. Indeed, this would appear to be common ground. If the funds had been paid prior to discharge of Oldavia's obligation, then it is common ground that those funds would be liable to be returned. It must follow that if the obligation to fund the Commitment had technically arisen, but the funds had not been paid prior to discharge of Oldavia's obligation, then the obligation to fund the Commitment would fall away.
(3) However, it is also the case that an obligation to pay money that has fallen due but has not yet been performed is discharged if the condition fails before the money is in fact paid. That is because it makes no sense to order one party to pay money and then immediately to order the recipient to repay it: Rover International Ltd v. Cannon Film Sales Ltd [1989] 1 WLR 912 (the "Proper Appeal"), Kerr LJ at 928E-932-H; Dillon LJ at 935H-937H; and Nicholls LJ at 938A; summarised in Burrows, The Law of Restitution (3rd Ed; OUP), p. 355.
(4) It follows that if the Defendants' funding obligation had arisen, but the funds had not already been paid on 29 April 2020, and Oldavia's obligation to complete was subsequently discharged, such that Completion never occurred, then the obligation in clause 2.1 would also be discharged. It makes no sense for Oldavia, or Lopesan, to be able to sue the Defendants for the purposes of forcing the Defendants to pay funds to Oldavia in circumstances where those funds would immediately be recoverable.
(5) In short, clause 5.1(b) does no more than spell out what would otherwise be the position at common law.
"11. I formed the impression that the Lapse Argument is weak for the following reasons.
12. First, Apollo's obligation under the ECL arises not when Completion actually takes place (indeed that would be too late), but is an obligation to provide the funds required "to complete the acquisition", and to do so "immediately prior to the Completion date" (clause 2.1 of the ECL). Similarly clause 5.1 refers to Apollo's obligation "to fund the Commitment", and is said to be subject to the conclusion of the SPA and "the Purchaser becoming obligated unconditionally under the Sale and Purchase Agreement to effect the Completion". That might suggest that it is Oldavia's obligation unconditionally to effect completion which triggers the performance of Apollo's obligation to fund.
13. Apollo's argument appears to be that the words "required by the Purchaser to complete the acquisition" in clause 2.1 have the effect that if Oldavia decides not to complete, Apollo's obligation to fund does not arise. Mr Davies, in his witness statement, explained:
"On a true construction of the ECL, the obligation to fund the Commitment only arose if Oldavia required the funds to complete under the SPA, and the funds were not required for that purpose because completion did not occur …
The Defendants also observe that on the Claimant's own case, there is no prospect of that state of affairs changing at any point prior to 1 January 2021 when the ECL will terminate in accordance with its own terms. Oldavia has refused to complete, and it is the Claimant's own case that there is no prospect of the Madrid Court ordering Oldavia to do so before that date".
14. While the ultimate merits of that argument are a matter for another day, it might be thought a commercially surprising outcome if, by a simple decision not to perform its contractual obligations under the SPA, Apollo (through its SPV) could prevent its funding obligation arising, and it might be thought that the words "required by the Purchaser to complete the acquisition" mean required by Oldavia to perform its contractual obligations, whether it wants to or not. Apollo's argument might be thought to become even more surprising when:
i) clause 3.1 expressly provides that Apollo's funding obligation arises when all condition precedents have been satisfied other than those "not satisfied as a result of a breach by the Purchaser" (something scarcely consistent with Apollo's funding obligation not arising if Oldavia wrongfully refused to complete); and
ii) consistently with that, clause 3.2 provides for the position when the SPA is terminated "due to a failure of the Seller to close the transactions contemplated therein" but says nothing about such a failure by Oldavia.
15. I also had some difficulty in understanding how far the argument based on the words "required by the Purchaser" went. Mr Rabinowitz QC (who, to be fair to him, had not come to court to argue this point, and was merely providing an initial reaction in response to impromptu questioning from the court) explained Apollo's position as follows:
i) If Oldavia disputed that its obligation to complete had arisen, Apollo's funding obligation did not arise because there would be no completion.
ii) If the Spanish court ordered Oldavia to complete, Apollo's funding obligation would then arise, but only if the ECL had not lapsed.
iii) If the Spanish court ordered Oldavia to complete, but Oldavia refused to complete that would give rise "to a very interesting question".
iv) If the Spanish court (on the unproven hypothesis that it is able to do so) refused to order specific performance but only the payment of damages, Apollo's funding obligation would not arise even if Oldavia had come under an obligation to complete.
16. The distinction drawn between the position where Oldavia owes a primary obligation to complete, and one where that primary obligation has been supplemented by a tertiary obligation arising from a court order, might be thought to appeal only to the most devoted rights theorist. In so far as the touchstone of Apollo's obligation is when completion would take place in fact, it would seem to follow that a contemptuous refusal by Oldavia to complete in defiance of a court order would help "run down the clock" so far as Apollo is concerned.
17. If Apollo's obligation to fund had accrued before 1 January 2021, then conventional principles of construction would suggest that clear words would be required for that obligation to lapse on 1 January 2021 – whether by applying the principle in Modern Engineering (Bristol) Ltd v Gilbert Nash (Northern) Ltd [1974] AC 689 , an argument based on the fact that Apollo was the proferens of the ECL (if that survives as an independent rule of construction) or the possible application, given Oldavia's status as an SPV through which Apollo effected its investment, of the presumption when interpreting a contract that a party cannot take the benefit of its wrong.
18. Approached from that perspective, it might well be thought that the provision for the ECL to terminate automatically on 1 January 2021 was intended to address the position when Oldavia's obligation to complete had not arisen by that date, because conditions precedent to completion had not been satisfied. In this regard, the SPA itself contains no long stop date for completion, save such as would follow from the deadline for addressing the clause 3.1 condition of European Commission approval for the acquisition, which was to be satisfied by 28 February 2020 "unless the Parties agree to an extension of the said term". In this regard, it might prove to be of some relevance that in another contract entered into between the same economic interests as part of the same overall transaction, relating to the acquisition of another Spanish hotel (the Hotel Faro), the date of 1 January 2021 was the date by which certain conditions precedent had to be satisfied, and was also the termination date in the ECL for that transaction (in which context, the date would appear to be addressing the date by when the obligation to fund must first arise, rather than when it would terminate in all circumstances and for all purposes).
19. Finally, clause 5 carves out from those circumstances in which the ECL will automatically terminate if Lopesan commences proceedings against either Apollo or Oldavia, proceedings to enforce the SPA or the ECL. It does, therefore, appear to have been within the parties' contemplation that legal proceedings might have to be brought under either or both contracts. In those circumstances, it might be thought that any provision by which the ECL would terminate during the course of such proceedings if they had not reached fruition by 1 January 2021 would have been clearly stated.
20. By contrast, if Apollo's argument that nothing other than completion under the SPA can trigger its obligation under the ECL is correct, then it is not clear how Lopesan will be any better off by obtaining a determination before 1 January 2021 that Oldavia is obliged to complete under the SPA. Whatever else the English court might do, it cannot order Oldavia (who is not before it) to complete under the SPA (a dispute over which the Spanish court has exclusive jurisdiction). It seems clear from Mr Davies' witness statement that it is indeed Apollo's position that determination of Lopesan's claim before 1 January 2021 will not take the Lapse Argument off the table if specific performance has not been ordered in the Spanish proceedings by that date."
(1) Such obligations are often implied into contracts which contain conditional obligations. As the editors of Lewison, The Interpretation of Contracts (7th ed) observe:
"16.40 There is imposed on parties to a contract a general duty to cooperate in the performance of the contract. This duty includes a duty not to prevent the fulfilment of conditions. …
16.42 Where the condition to be fulfilled is one which is dependent on the discretion of one party to the contract, or even of a third party, it will be an implied term that that person must act in good faith, and in some cases reasonably".[2]
(2) The question of whether such a term is to be implied, and its scope, is to be assessed on the basis of the particular contract in question and its express terms: see The Law Debenture Trust Corpn Ltd v Ukraine [2018] EWCA Civ 2026, [2019] QB 1121, paragraph 207.
(3) This implied term would meet the concern identified in Foxton J's judgment without having to do violence to the natural and ordinary meaning of the words used by the parties in the ECL. Here, no such term is pleaded and no allegation of bad faith is made.
(1) First, they referred to the contrast between clause 3.1 and clause 3.2, noting that the latter confirmed that the ECL would terminate if the Claimant wrongly refused to close, whilst clause 3.1 did not contain a similar provision relating to a breach by Oldavia. They submitted that this should not make a difference to the proper meaning and effect of clause 5.1(iii). In particular, neither clause says anything about the circumstances in which the funding obligation might be discharged under clause 5.1, nor does either clause suggest a need to give clause 5.1 anything other than its ordinary meaning.
(2) Second, the Defendants made reference to the suggestion, at paragraph 17 of the judgment, that if the funding obligation had arisen, then "conventional principles of construction would suggest that clear words would be required for that obligation to lapse on 1 January 2021." It was their case that, in relation to the three separate principles of construction relied on by Foxton J, namely the principle in Modern Engineering (Bristol) Ltd v. Gilbert Nash (Northern) Ltd [1974] AC 689; the contra proferentem principle, and "the possible application, given Oldavia's status as an SPV through which Apollo effected its investment, of the presumption when interpreting a contract that a party cannot take the benefit of its wrong", the short answer to these points is that the words of clause 5.1(iii) are clear: the obligation is discharged automatically and immediately upon the occurrence of the relevant event. In other words, clause 5.1 is plainly concerned with circumstances in which Lopesan and Oldavia would give up otherwise valuable rights as against the Defendants. They argued that the learned Judge did not address the question whether, or in what way, the words were unclear, which they are not. In these circumstances, the canons of construction referred to do not provide any basis for departing from the clear words of the contract. In any event, the Defendants contended, such principles are rarely decisive as to the meaning of provisions in a commercial contract, especially where the language of the contract is clear: K/S Victoria Street v. House of Fraser (Stores Management) Ltd [2012] Ch 497, at §68 per Lord Neuberger MR (giving the judgment of the Court). Finally, the Judge's reliance on the principle against construction of a document so as to excuse one party from its own wrong is also incorrect because the Judge focussed on Oldavia's alleged breach of contract under the SPA and the principle does not apply where the relevant wrong is a breach of a separate contract by a third party: Lewison, §7.117. Whilst Lopesan seeks to argue that the relevant "wrong" is the Defendants' failure to pay the money, if the Defendants had paid the money, Completion would still not have taken place because of the dispute between Oldavia and Lopesan, and that dispute would not have been resolved by the January Termination Date. The Defendants are not seeking to rely on their failure to pay the funds as a reason for termination of the ECL under clause 5.1(iii).
(3) At paragraph 19, Foxton J noted that clause 5.1 expressly permits proceedings between the parties under the ECL and the SPA and that it would be surprising if the parties intended that the obligations under the ECL could be discharged before those proceedings had concluded. As to this:
a) Foxton J was referring to sub-paragraphs (x) and (y), which come at the end of clause 5.1(iv). Clause 5.1(iv) provides for the immediate and automatic termination of the ECL if Lopesan asserted any claim against the Defendants. Sub-paragraphs (x) and (y) constitute a carve-out to clause 5.1(iv), excluding the application of this limb of the termination events to claims by Lopesan against Oldavia under the SPA and claims to enforce Oldavia's rights under the ECL. The purpose of that carve-out is to make it clear that the assertion of such claims will not, without more, bring the ECL to an end.
b) The carve-out does not indicate any intention that any such dispute could be freely litigated thereafter without the ECL expiring in the meantime. The mere fact that the assertion of a claim against the Defendants under the ECL did not, in and of itself, cause the automatic termination of the ECL under clause 5.1(iv), says nothing about the circumstances in which the ECL would terminate under the other termination events in clauses 5.1(i) to (iii), especially when clause 5.1 provided that the ECL would terminate on the "earlier to occur" of those dates. Moreover, when the SPA was executed in November 2019, there was more than a year before the January Termination Date. There is no evidence to suggest that when the parties entered into the relevant contracts, this would have been regarded as an unreasonable period of time in which for any such disputes to be resolved.
(1) First, each of the events identified in clauses 5.1(i) to (iv) leads to the automatic and immediate termination of the "obligation of the [Defendants] to fund … the Commitment". For good measure, clause 5.1 also says in terms that the Defendants' obligations under the ECL will be "discharged". There can be no dispute about what is meant by the word "discharged". Nor can there be any dispute about what is being discharged: "the [Defendants'] obligations under [the ECL]." The natural and ordinary meaning of those words is that all of the Defendants' obligations are discharged (save for those obligations identified in the final sentence). There are no words in clause 5.1 to suggest that some obligations would nonetheless survive, or (as Lopesan apparently suggests) that the parties intended there to be any distinction between obligations that had arisen (which would survive) and those that had not arisen (which would come to an end).
(2) Second, the ECL is discharged upon "the earlier to occur" of each of the termination events. The first termination event in the list is "consummation of Completion". That point in time (i.e. consummation of Completion) then determines the application of the other termination events in the list. If the other events occur before the consummation of Completion, then the obligation to fund the Commitment terminates and the obligations arising under the ECL are discharged. Conversely, if consummation of Completion occurs first, then the other termination events become irrelevant. It follows that the proper construction of the January Termination Date is clear: if consummation of Completion has not occurred before 1 January 2021, then the "obligation to fund the Commitment will terminate automatically and immediately (at which time the Investors' obligations under this Letter shall be discharged)." Notably, the application of the clause 5.1 termination events is not qualified in any way by reference to whether or not, for example, any other event may (or may not) have occurred. There is nothing to suggest that the clause will not operate in the way suggested if, for example, the Condition Precedent has been satisfied; nor, if the obligation to provide funding has previously accrued.
(3) Third, and by way of a related point, it is obviously the case that if the Court is satisfied that any one of the events identified operates to discharge an obligation that had previously arisen, then the same must be true of the other events identified. That is because there is no language whatever in clause 5.1 to support an interpretation whereby some of the termination events operate to discharge accrued obligations, but others do not.
(4) Fourth, as already noted above, the tailpiece to clause 5.1 expressly confirms which obligations are to survive termination. Notably, clause 2.1 (which contains the funding obligation) is not one of them. The obvious inference from this is that the obligations in clause 2.1 were intended to be among those obligations which were "discharged".
(1) First, as already noted above, "Completion" under the SPA occurs on the Completion Date itself. It follows, therefore, that, in circumstances where, if the funding obligation arises, it arises immediately prior to the Completion Date, Completion is an event that will inevitably occur after the funding obligation has arisen.
(2) Most obviously, this provision is concerned with a situation in which the funding is advanced prior to the Completion Date, and the transaction completes, and is 'consummated' the following day. In short, the parties wished to make it clear that the purpose of the funding obligation having thereby been achieved, the ECL would terminate and any obligations under it would be discharged.
(3) It is also possible that this provision could apply if Oldavia completed the transaction using other funds, for example, from a different fund or from a bank. In that situation, although unlikely to be how the parties envisaged Completion was most likely to be consummated, it would also make perfect sense for the ECL to terminate, and for the funding obligation to be discharged, because there would be no need for the funding, "consummation of Completion" having taken place.
(4) Either way, however, it is significant to note that the first termination event in the list is "consummation of Completion" itself; it is not the occurrence of the day on which the obligation to fund accrues, nor (which is the same thing) the occurrence of the day immediately before the Completion Date. And, critically, it is that event, viz., consummation of Completion itself, by reference to which the other termination dates operate. This being so, and absent any language that would support any such approach, it would not make sense to qualify the potential application of the various termination events by reference to the occurrence of some other, non-stated event.
(1) As reflected in the language used in clause 5.1(i) to (iv), the January Termination Date with which clause 5.1(iii) is concerned, was intended to operate as a 'drop dead' date in respect of the Defendants' funding obligation. In other words, if there had been no consummation of Completion by this date, then the obligation to fund would cease.
(2) In this way, the January Termination Date provided the Defendants with a measure of certainty as to the latest date on which they could be required to advance the funds to Oldavia. Upon expiry of this date, the Defendants would be free to use those funds for other purposes.
(3) It is not understood to be in dispute (nor could it be) that provisions of this sort are commonly found in funding agreements; that is because it is not reasonable (and can be expensive) to expect a funder to provide an open-ended funding commitment: see for example Travelport Limited v. WEX Inc [2020] EWHC 2670 (Comm), § 3.
(4) Where funding obligations are made the subject of a 'drop dead' date, it does not matter (subject to the point made below) to the funder why Completion has not occurred by the relevant date. Rather, what matters to the funder is simply that, by that date, there has not been any Completion and, therefore, no call on the funding.
(5) This, however, must be made subject to the parties not deliberately and in bad faith obstructing Completion simply with a view to frustrating the obligation to fund.
Lopesan's contentions.
(1) First, it can refer to the obligations created by the ECL from the moment it was issued by the Defendants. In this instance, those obligations included a contingent obligation on the Defendants to fund the Commitment, subject to the terms of the ECL itself. When the word "obligation" is used in this sense, the Defendants can be said to have been under an obligation (albeit a contingent obligation) to pay the Commitment since November 2019.
(2) Second, it can refer to the immediate, non-contingent, obligation on the Defendants to actually pay the Commitment. That obligation (a) represents the crystallisation of the pre-existing contingent obligation referred to above; and (b) accrues (on Lopesan's case) immediately prior to the Completion Date.
(1) Clause 5.1 provides inter alia for the termination of the Defendants' "obligation" to fund the Commitment on 1 January 2021.
(2) On the Defendants' case, the effect of this provision is to relieve it of the liability to pay the Commitment, even if its failure to pay the same by 1 January 2021 was attributable to the Defendants' own breach of an accrued liability to pay under the ECL.
(3) The ECL ought not to be construed so as to permit the Defendants to take the benefit of their own wrongdoing in that way: see Alghussein Establishment v Eton College [1988] 1 WLR 587 at p.594B-F. Moreover, such a construction would involve reading clause 5.1 as an exclusion of any remedy which Lopesan might otherwise have in respect of a breach of contract by the Defendants. Clear and unequivocal wording would be required if the clause were to have that effect: see Gilbert Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd [1974] AC 689 per Lord Diplock at 717H and Filatona v Navigator Equities [2020] EWCA Civ 109 per Simon LJ at [63]-[67]. Clause 5.1 does not contain any such wording.
(4) Further, reading clause 5.1 in the manner for which the Defendants contend would risk creating a situation in which compliance with the ECL was, from the Defendants' perspective, optional. Faced with a liability to pay, they could simply withhold payment and "run out the clock" on Lopesan (and on Oldavia, assuming that Oldavia wished to complete on the Transaction).
(5) Further, clause 5.1 expressly envisages (at (iv)) that the Defendants' obligations will not terminate as a result of claims brought by Lopesan under either the SPA or the ECL. It would be extraordinary if clause 5.1 was read as, on the one hand, leaving the Defendants' liability to pay intact in the face of claims under the SPA and ECL whilst, on the other, extinguishing that very liability because claims happen not to have been resolved by 1 January 2021.
(6) Finally, construing clause 5.1 in a manner which permitted the Defendants to rely on their breach of the ECL and/or Oldavia's breach of the SPA as a means of avoiding payment of the Commitment would be inconsistent with clause 3.1 of the ECL. That clause makes clear that the Defendants would be liable to pay the Commitment even where Completion failed to occur by reason of breach of the SPA by Oldavia.
(1) It makes perfect sense if it is construed as being applicable to the Defendants' contingent obligation to pay the Commitment if and when certain conditions are met; but not applicable to the Defendants' immediate liability to pay the Commitment (if and when that liability arises).
(2) On that reading, the clause would prevent the Defendants' contingent obligation from ever crystallising into an immediate liability to pay if the SPA was validly terminated before then, or if such crystallisation had not occurred by 1 January 2021.
(3) It also avoids a situation in which clause 5.1 can operate to shield the Defendants from the consequences of their own breach of the ECL, or enable the Defendants positively to benefit from such a breach.
Discussion and conclusions.
(1) For the reasons already noted, Oldavia will become obliged to complete on the completion date as defined (whatever that date may be – for present purposes, as I have noted, the parties have been content that I take that date to be 30th April 2020), and the Defendants will be obliged to put them in funds to do so immediately prior to that completion date.
(2) It is common ground that, if the SPA validly terminates prior to that date, the obligation to provide funding will not arise.
(3) However, in my judgment, once the obligation has arisen, then it must be fulfilled. A failure to provide funding will be a breach on the part of the Defendants.
(4) If the obligation to complete is, thereafter, rendered moot (for example because the SPA is, to use an English term, frustrated, or because Lopesan cannot perform, ie the two scenarios put forward by the Defendant to which I have made reference above) then there would be an obligation on the part of Oldavia to repay monies to the Defendants. This does not detract from the fact that the Defendants would have been obliged to pay those monies to Oldavia prior to the completion date.
(5) I agree with Foxton J that the reference to Oldavia becoming unconditionally obliged to complete is a reference to the satisfaction of the condition precedent in the contract. Once that condition was satisfied, the obligations of Oldavia were indeed unconditional, albeit that there were other obligations on the part of Lopesan which fell to be satisfied at the same time as Oldavia performed its obligations.
(6) I am also in agreement with Foxton J's various other points, which are set out above. As regards the Defendants' suggested answers to those points:
a) In my judgment, the distinction between clause 3.1 and clause 3.2 is indeed instructive. It is clear that the funding obligation will cease if the SPA comes to an end by reason of a breach by Lopesan (as to which see clause 3.2) but there is no similar provision in relation to a breach by Oldavia. That is entirely consistent with the conclusion that the funding obligation will remain in being notwithstanding the fact that, by reason of a breach on the part of Oldavia, completion has not been consummated.
b) Secondly, I agree that the wording of clause 5.1 is not sufficiently clear to overcome the normal principle that a party cannot rely on a provision to terminate a contract if that provision has only been triggered by virtue of the wrongful conduct of that party. In this connection, I take the view that the passage from Lewison, para 7.117 which was relied on by the Defendants is not in fact of assistance in the circumstances of this case, where the breach would be by the Defendants' wholly owned subsidiary, incorporated for the purposes of the transaction. I am reinforced in this conclusion by the terms of clause 3.2, to which I have already made reference, which distinguish between the situation where the funding obligation ceases due to a breach by Lopesan, and the lack of a similar provision in relation to a breach by Oldavia. The whole scheme of the transaction is that completion should take place before 1 January 2021, and that each party should play its part in enabling this to happen.
c) As to the third point relied on by Foxton J in paragraph 19 of his judgment, I again agree that it would be very surprising if, in circumstances in which the obligations under the ECL were kept alive where proceedings were brought to enforce the SPA, those obligations would nevertheless fall away by virtue of the simple effluxion of time during the pendency of those proceedings. Contrary to the Defendants' submissions, it is my view that the existence of the carve out in relation to court proceedings does indeed shed light on the meaning of the other termination provisions, including that in clause 5.1(iii).
(1) If the SPA is validly terminated in accordance with its terms, for reasons other than a breach by Oldavia, then the funding obligation will also come to an end. If this occurs before 1st January 2021, then the issue of termination due to effluxion of time will not arise. If the SPA is validly terminated after 1st January 2021 in accordance with its terms, for reasons other than a breach by Oldavia, then the funding obligation will, likewise, either come to an end (if the Completion Date has not arrived as at that stage) or will be reversed (in the sense that Oldavia will be obliged to repay the money to the Defendants). This is the answer to issue 2(b).
(2) If, as at 1st January 2021, the funding obligation has arisen, and not been terminated, then the mere effluxion of time will not bring it to an end. This is the answer to issue 2(c). In my judgment, clause 5.1(iii) is intended to cater for the situation where the funding obligation has not arisen at all, either because the condition precedent has not been satisfied, or because Lopesan is not in a position to complete as at that date. It will not apply so as to bring an end to the obligation where completion should have taken place but has not.
(3) As regards Issue 2(a), then in my judgment, the answer to this question will depend on why Oldavia has ceased to be unconditionally obliged to effect completion. As I have indicated, if, by way of example, the SPA has been frustrated (to use the English term) then Oldavia will no longer have to complete, and thus the Defendants will be entitled to their money back (if they have, or should have, already paid it) or will not have to pay that money. Since this will depend on Spanish law and the decisions of the Spanish Court, I do not propose to answer this question definitively.
Issue 3: are the Defendants obliged to fund the Commitment if the same is not to be used for the purposes of funding Completion pursuant to the SPA?
The Defendants' contentions.
Lopesan's contentions.
(1) That case assumes that these clauses are, in effect, further conditions precedent to the Defendants' liability to pay the Commitment. There is no basis for that assumption – particularly in circumstances where clause 3 of the ECL identifies conditions upon the Defendants' liability to pay. It ignores the fact that the ECL is a tripartite agreement, to which Oldavia is a signatory. If the Defendants paid the full Commitment to Oldavia, and Oldavia did not ultimately require the full sum of €93m for the purposes of the Transaction, then the Defendants would have a claim to recover any balance from Oldavia. It is in the context of such a claim that the clauses quoted above would be most likely to come into play.
(2) Both the wording of the ECL and the commercial context require that the Defendants put Oldavia in funds prior to the Completion Date – and therefore at a point in time when Oldavia might well be uncertain as to whether it would need the full amount of the Commitment. This is consistent with clause 4.3 of the SPA, which expressly provides for adjustments to the total sum payable to Lopesan after Completion.
(3) This position is particularly stark if (as Lopesan submits is the case here) Oldavia wrongfully refused to proceed with Completion of the SPA. In that scenario (in accordance with clauses 2.1 and 3.1 of the ECL - see above) the Defendants would be liable to pay the entire Commitment to Oldavia at a time when: (a) there was inevitable uncertainty as to what Oldavia would be required to do with the Commitment; and (b) the resolution of that uncertainty would necessarily have to await the determination of Spanish proceedings between Lopesan and Oldavia under the SPA.
Discussion and conclusions.
(1) If the SPA came to an end before the Completion Date, so would the Defendants' obligation to provide funding;
(2) If the obligation to complete was, for example, frustrated, or the SPA was validly terminated on account of Lopesan's breach after the Completion Date, then, whilst the obligation to provide funding would have accrued and should have been performed, Oldavia would be obliged to repay the Defendants since Completion would now not complete.
Issue 4: Are the Defendants obliged to fund the Commitment in circumstances where there is a bona fide dispute between the Claimant and Oldavia which has not yet been resolved by the Spanish Courts, whereby Oldavia has indicated that it does not intend to effect Completion under the SPA because it contends that it is not obliged to do so?
The Defendants' contentions.
(1) It is clear from the language of the ECL (quoted above) that the funds could only be provided for the purposes of Completion. It follows that the Defendants' obligation to provide the Commitment under clause 2.1 did not arise unless Oldavia "required" the funds in order to effect Completion under the SPA. Since the funds are not presently required for this purpose, the funding obligation has not yet arisen (and did not arise prior to 1 January 2021).
(2) Moreover, that interpretation is consistent with clauses 2.3, 5.2 and 6.2 of the ECL which (as explained above) tie the obligation in clause 2.1 (and its enforcement) to the act of Completion, not the existence of an obligation on Oldavia's part to complete (which is separately addressed by clauses 3.1 and 5.1 of the ECL).
(3) It is unsurprising that the Defendants' obligation should ultimately depend on Completion taking place. In particular, it is unlikely that the parties reasonably intended that the Defendants should be obliged to pay Oldavia the funds in circumstances where a dispute had arisen between the Claimant and Oldavia, such that Completion was unlikely to occur for a significant period of time. That would give rise to considerable uncertainty as to Oldavia's duties in relation to the funds during that period. For example, it would be unclear whether those funds formed part of Oldavia's assets, available to its other creditors and, if not, what steps Oldavia should take to safeguard those funds and/or earn a return pending determination of the underlying dispute.
(4) Moreover, it would give rise to uncertainty as to the circumstances in which the funds would subsequently be repaid. Lopesan acknowledges that the consequence of its interpretation of the ECL is that the funds may be paid over in circumstances where Completion ultimately never occurs, or occurs on different terms. Lopesan also acknowledges that in certain circumstances, the funds might fall to be repaid.
(5) In his judgment dated 8 October 2020, Foxton J expressed the same concern in relation to this point as he did in relation to the January Termination Date, namely that the Defendants would be able to procure a situation in which Oldavia refused to complete, thereby preventing the Defendants' funding obligation from arising. Any such concern (had it been relevant) is one that might have been addressed by reference to an implied term aimed at a bad faith attempt to frustrate any funding obligation that might otherwise arise, as already noted; but there is no allegation of bad faith.
(6) Lopesan also argues that the interpretation identified above would subject the Defendants' alleged obligations to "an additional layer of complexity" that cannot have been intended. It is difficult to see why this is so: there can be no real doubt as to what is meant by bad faith in this context and, in any event, no allegation of bad faith has been made.
(7) For these reasons, the answer to issue 4 is "no": the Defendants are not obliged to provide the funds in circumstances where there is a bona fide dispute between the Claimant and Oldavia that has yet to be resolved by the Spanish Court.
Lopesan's contentions.
(1) Oldavia either was obliged to proceed with Completion under the SPA in April 2020, or it was not. If it was so obliged at that time, it has been in breach of the SPA since April 2020.
(2) The existence of Oldavia's obligations under the SPA, and any breach thereof, are matters of objective fact. They do not owe their existence to any ruling by the Spanish Court (or this Court). The effect of such a ruling would be to provide an authoritative statement of what the true position had been all along.
(3) On Lopesan's case, the Defendants' liability to pay the Commitment is triggered by reference to the setting of the Completion Date in accordance with the SPA. On the Defendants' case, the relevant trigger is Oldavia becoming "unconditionally obliged to effect completion pursuant to the SPA". Those conditions share a key feature – they both depend upon what Oldavia's obligations under the SPA actually were at the relevant point in time. Neither case can justify the suspension or discharge of the Defendants' liability to pay the Commitment by reference to Oldavia raising a dispute under the SPA which is said to be bona fide, but is in fact misguided.
(4) In fact, this part of the Defendants' case is a variant of its argument that, when clause 2.1 of the ECL refers to the Commitment being "required" by Oldavia, it means that Oldavia itself must actually be pressing for payment of the Commitment. That construction of the word "required" is wrong. The correct construction is that "required" means "needed in order for Oldavia to comply with its obligations under the SPA".
(5) Accordingly, all that matters for the purposes of determining the accrual (and/or the subsistence) of the Defendants' liability to pay the Commitment is the actual state of Oldavia's rights and obligations under the SPA.
Discussion and conclusions.
(1) The Defendants' obligation to fund arises when Oldavia becomes unconditionally obligated under the SPA.
(2) In my judgment, that moment came when the condition precedent to Oldavia's obligations was satisfied. I agree with Foxton J in this regard.
(3) The time at which that obligation was to be satisfied – ie the moment at which it accrued due – was immediately before the Completion Date. This was the subject of Issue 1, which I have dealt with above.
(4) The Defendants are not able to justify a failure to comply with their obligation by reference to the fact that Oldavia has raised a dispute as to its obligation to complete on the Completion Date. Instead, the Defendants must put Oldavia in funds to enable it to complete prior to that date; and if, in fact, Oldavia can establish that it is not obliged to complete, then Oldavia will have to return the funds to the Defendants, since the funds in question were not to be used for any purpose other than completion: see issue 3 above.
Issue 5: Does the Claimant have the right to require the Defendants to fund the Commitment for the purposes of enabling Oldavia to meet any claim for damages made against Oldavia in the Spanish Proceedings?
The Defendants' contentions.
Lopesan's contentions.
Discussion and conclusions.
Issue 6: Is the Defendants' obligation to fund the Commitment limited to a sum equal to the net amount required to be paid by Oldavia in connection with Completion? In particular (without prejudice to the generality of the above):
a. Does the amount payable by the Defendants fall to be reduced if and to the extent that Oldavia is entitled to damages as against the Claimant and if and to the extent that such damages are to be set-off against any amounts payable by Oldavia under the SPA?
b. Does the amount payable by the Defendants fall to be reduced if and to the extent that the terms of the SPA fall to be amended under Spanish law so as to reduce the amount payable by Oldavia under the SPA?
The Defendants' contentions.
(1) Oldavia has a counterclaim in damages that falls to be set-off against the purchase price; and
(2) under Spanish law, the terms of the contract can be amended by the Court, including so as to reduce the price that is payable thereunder.
Lopesan's contentions.
Discussion and conclusions.
Issue 7: Pursuant to the terms of the Commitment Letter:
a. Does the Claimant have the right to require the Defendants to pay the Commitment to anyone other than Oldavia?
b. Does the Claimant have the right to sue the Defendants for damages for breach of the obligation to fund the Commitment or is the Claimant limited to a claim for specific performance (if available under the general law)?
Issue 7(a)
The Defendants' contentions.
Lopesan's contentions.
Discussion and conclusions.
Issue 7(b)
The Defendants' contentions.
(1) First, it is said that clear words would be required in order to exclude any claim for damages for breach of clause 2.1. However:
a) Lopesan ignores clause 6 altogether which says (at clause 6.2) that Lopesan is entitled to "specifically enforce the obligations of the [Defendants] for the purposes of Completion but for no other purpose" and (at clause 6.1) that save as set out in Clause 6 "nothing in this Letter, express or implied, is intended to confer upon any person or entity, other than [Oldavia] any right, benefit or remedy under or by reason of this Letter pursuant to the Contracts (Rights of Third Parties) Act 1999."
b) These words plainly exclude any "right, benefit or remedy" other than the right to claim specific performance under clause 6.2.
c) This point is reinforced by clause 6.2.3 which provides (so far as relevant) that save as set out in clause 6, neither Lopesan, nor its Party Affiliates, "shall have any other rights or remedies hereunder."
(2) Second, Lopesan says that a failure to pay under the ECL would be a repudiatory breach of contract that Lopesan could accept so as to bring an end to the contract and that, upon termination of the ECL, clause 5.2 would be discharged by reason of the final sentence of clause 5.1. A number of points can be made about this submission:
a) Lopesan does not have the right to terminate the ECL in any circumstances: see clause 6.1 and 6.2.
b) In any event, termination for repudiatory breach by the Defendants is not one of the termination events governed by clause 5.1.
c) If (contrary to the above) clause 5.1 were to govern such a claim, then it would follow that on Lopesan's own case, clause 5.1 operates to discharge obligations in the ECL after the alleged obligation to pay the Commitment has arisen. That is scarcely consistent with Lopesan's case as to the proper construction of clause 5.1.
Lopesan's contentions.
(1) Clause 5.2 does not purport to exclude a common law claim for damages sufficiently clearly or unequivocally. It purports to regulate claims brought "under this letter". A common law claim for damages does not fit that description. It is a claim that is brought "under" the general law, and which happens to arise as a result of the terms of the ECL.
(2) In any event, a failure by the Defendants to pay the Commitment would inevitably be a repudiatory breach of contract, entitling Lopesan to terminate the ECL. Clause 5.2 would not survive such termination (particularly given the final sentence of clause 5.1 – which does not identify clause 5.2 as one of those which would survive termination). It would be odd to construe clause 5.2 as excluding a claim which Lopesan could easily bring in any event by simply terminating the ECL for breach.
Discussion and conclusions.
(1) The language of clause 6 is, in my view, only consonant with an obligation on the part of the Defendants to provide funding, with a right given to Lopesan to require specific performance of that obligation.
(2) The imposition of this obligation is quite sufficient to ensure that Lopesan are given the protection that, as a matter of the commercial construction of the contract viewed in its context, would be expected. Thus, Lopesan's primary contract is with Oldavia, and their interest in ensuring that the Defendants' obligations towards Oldavia are fulfilled so as to ensure that Oldavia is in funds to meet its obligations to Lopesan is perfectly adequately addressed by means of a right to specifically enforce those obligations owed to Oldavia.
Final comments.
Note 1 This is indeed a contention that is put forward by Oldavia in the Spanish proceedings. [Back] Note 2 See, to similar effect, Chitty on Contracts (33rd ed) at paragraphs 14-023 and 14-024. [Back] Note 3 I have set out the relevant passages of Foxton J’s judgment above. [Back]