BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
COMMERCIAL COURT (QBD)
Strand, London, WC2A 2LL |
||
B e f o r e :
(SITTING AS A JUDGE OF THE HIGH COURT)
____________________
PREMIER CRUISES LIMITED |
Claimant/ Respondent |
|
- and - |
||
(1) DLA PIPER RUS LIMITED (2) DLA PIPER UK LLP |
Defendants/ Applicants |
____________________
George Spalton and Joshua Folkard (instructed by Bryan Cave Leighton Paisner LLP) for the Defendants/Applicants
Hearing dates: 24-25 November 2020
____________________
Crown Copyright ©
Covid-19 Protocol: This judgment will be handed down by the judge remotely by circulation to the parties' representatives by email and release to Bailii. The date and time for hand-down will be deemed to be 10:30 AM on 01 February 2021.
David Edwards QC:
Introduction
"1. By the engagement letter signed by the Claimant and dated 26 May 2015, the Claimant and the First Defendant agreed that in the event that any dispute could not be settled through negotiation, the matter shall be resolved under arbitration, under the rules of the International Commercial Arbitration Court at the Chamber of Commerce and Industry of the Russian Federation ('the Arbitration Agreement'). The Arbitration Agreement is set out in full in the attached evidence. It encompasses all matters which are the subject of these proceedings, including on the basis that the Second Defendant was agent of, or sub-contractor to, the First Defendant in respect of the matters which are the subject of the claim".
Factual Background
(i) The Shipbuilding Contract
(ii) Early communications with DLA Russia
(iii) December 2014 – May 2015
i) On 16 December 2014 Vladimir Esakov sent an email to Mr Lamzin indicating that he would send Mr Lamzin copies of letters exchanged between PCL and the Shipyard. Mr Lamzin responded saying that he would revert with any comments or questions;
ii) On 23 December 2014 Mr Lamzin sent an email to Vladimir Esakov in which Mr Lamzin explained that:
"I have studied carefully the [Shipbuilding Contract] and forwarded correspondence. I enclose my comments below."
The email went on to make a number of remarks about the Shipyard's claims, the parties' respective rights under clause XII(2) of the Shipbuilding Contract, and the information and documents that Mr Lamzin needed to assess PCL's position;
iii) On 24 December 2014 Mr Lamzin sent an email to Vladimir Esakov attaching a draft letter to be sent by PCL to the Shipyard rejecting its claim for permissible delay. A further draft letter, in response to subsequent correspondence from the Shipyard, was sent by Mr Lamzin to Vladimir Esakov on 16 January 2015;
iv) On 25 March 2015 Mr Lamzin sent an email to Vladimir and Dmitry Esakov attaching a further draft letter and setting out his thoughts on the termination provisions in the Shipbuilding Contract. The email referred to two provisions, clauses XI.A(b) and XII, which Mr Lamzin suggested were somewhat contradictory. It concluded:
"Accordingly,
a) the Yard can dispute the point at which the Buyer's right to cancel the contract arose (and expired) if it proves that the Buyer knew about this at an earlier point. To be on the safe side, we need to double-check whether the Yard expressly communicated a time frame for the delay. If not, we will treat their reply to our attached letter as such a notice.
b) I would recommend seeking further advice from our English colleagues as concerns how to interpret the conflict between the two clauses of the contract. If we are to take the more cautious position, it would be advisable to send them formal notice of cancellation on the earlier date (when we formally learned of the delay in delivery). Do let me know if, at this stage, it is worth bringing in London to ask them for comment."
v) On 19 April 2015 Mr Lamzin sent an email to Vladimir Esakov attaching a draft letter to be sent by PCL in response to a notification from the Shipyard that it intended to deliver the Vessel on 4 August 2015. The draft was headed "Warning Letter". It said that:
a) The Shipyard was in breach in failing to deliver the Vessel by 30 March 2015 (taking account of 15 days admitted permissible delay);
b) PCL was willing to accept a new Delivery Date of 4 August 2015, but only on certain conditions, including an acceptance that neither party had any claim against the other in connection with the delay;
c) If those conditions were not accepted by the Shipyard, then PCL would have no choice other than to initiate termination of the Shipbuilding Contract and to demand the refund of the purchase price plus damages for breach of contract.
A letter in these terms was duly sent by PCL to the Shipyard on 20 April 2015;
vi) On 28 April 2015, following a response from the Shipyard, Mr Lamzin sent an email to Vladimir Esakov attaching a draft letter. The draft, headed "Notice of Rescission", purported to rescind the Shipbuilding Contract with immediate effect under clause XII.4 and demanded the repayment of that part of the purchase price that had already been paid.
i) PCL did not have a contractual right to terminate the Shipbuilding Contract; and
ii) PCL had failed to pay the fifth instalment of the purchase price which had now fallen due.
The Shipyard said that it was rescinding the Shipbuilding Contract pursuant to clause XV.3, alternatively that it was treating PCL's Notice of Rescission as a repudiatory breach, which it accepted, bringing the Shipbuilding Contract to an end.
(iv) Mr Lamzin's approach to DLA UK
"We've got a potential request for assistance from a company called Premier Cruises Limited. The company operates one luxury river cruiser in Russia and has a contract for construction of a new ship in Croatia with Brodosplit (see copy attached).
The vessel was due to be delivered on 30 March 2015, but the builder delayed delivery (claiming delays in provision of drawings by the buyer) for a few months.
After series of negotiations and formal correspondence the buyer decided to terminate the contract and claimed refund of the PDPs in total amount of $5m + interest. The deadline for payment is 29 May 2015 at which point Premier Cruises Limited is considering to enforce the contract through arbitration.
We are asked to provide a fee proposal for assisting the client with enforcing the contract and our estimation of associated costs/timing.
The contact [sic] provides for mediation and then arbitration. It does not look like mediation is going to succeed so the client would appreciate our views on whether we do need to follow it or can skip this step in practice."
"It is therefore critical to analyse the claim on the merits in the first instance and provided the merits are in clients favour parties will usually proceed with arbitration having the above in mind."
(v) The Engagement Letter
"I inform you below about the current status of work.
We analyse and systematize with colleagues all available documentation and correspondence for a more detailed analysis out [sic] position in the Arbitrage. I think it will take a few more days.
Colleagues assured me that there is no rush with our reply to the Yard. Every next should be taken after we have completed our analysis.
As discussed on the last week, please find attached our standard engagement letter. We will also need to go through KYC procedures."
"Please find set out in this engagement letter (the 'Engagement'), the terms and conditions under which DLA Piper Rus Ltd. (the 'Company') will be pleased to provide PREMIER CRUISES LIMITED (the 'Client') with legal advisory services.
Scope of Services
We will respond to your requests for advice regarding various legal issues and other ancillary services that the Client may encounter. The scope of the services to be provided (the 'Services') will be defined upon a case-by-case basis by mutual agreement between the Company and the Client. The Company's Services may be rendered orally or in writing (including by facsimile or unencrypted electronic mail). The Company shall be entitled to accept instructions, oral or written, from any person representing the Client, unless notified in writing in advance of any restrictions in this respect.
…
Fees and Billing Procedures
Compensation for our Services will consist of professional fees and reimbursement of expenses. Professional fees will be based on the hours worked by the various levels of personnel, at the rates applicable to each. Reimbursement of expenses will include travel time; any out of pocket expenses such as airfare, lodging and meals; per diems; telecommunication expenses such as cost of business calls by the personnel's mobile phones; any other expenses directly related to the Services.
Current Billing Rates for Moscow office (exclusive of VAT)*
[Table of US dollar hourly rates for staff of various levels of seniority]
…
Payment of our invoices shall be made within 14 (fourteen) days from the date the invoice is issued. Each invoice shall be accompanied by an act of acceptance wherein the Client shall confirm its acceptance of the rendered Service and return to the Company signed act of acceptance within 14 (fourteen) days from receipt of the same. If the Company does not receive the signed act of acceptance or a substantiated refusal to sign such act within the above period, the parties acknowledge that the act of acceptance shall be deemed signed, and the Services shall be deemed rendered by the Company and accepted by the Client within the scope and conditions as stated in such act of acceptance. Invoices shall be denominated in United States Dollars, depending on the applicable schedule for charge out rates as agreed with the client. Payments shall be made in United States Dollars or Russian Roubles to the bank account indicated in the invoice, quoting the invoice number.
…
Liability and Confidentiality
…
It may be necessary from time to time to enlist any person or entity to assist in providing Services to you without obtaining your prior approval. When we use the Services of such person or entity in connection with this Engagement we take liability for their activities as if they were in all respects our own activities. Considering the above, no person or entity, including either our affiliate or member firm of DLA Piper Group, assumes any responsibility to the Client in connection with this Engagement.
…
Dispute Resolution
This Engagement shall be governed by the Russian law. All disputes and disagreements, which may arise from the terms of this Engagement, as outlined above, or in connection therewith, shall be settled by the parties through negotiations. In the event that the parties fail to reach an agreement, the matter shall be forwarded to the International Commercial Arbitration Court at the Chamber of Commerce and Industry of the Russian Federation to be settled under the court's statutory rules.
Term and Termination
This Engagement becomes effective from the date it is accepted and signed by the Client and shall continue to be in full force and effect until it is terminated by either the Client or the Company by giving at least ten (10) working days prior written notice. The Client will be responsible for payment of all fees and expenses incurred by the Company prior to the date of termination.
Other Matters
…
Please sign one copy of this letter acknowledging your acceptance of the offer of terms set forth herein, and return it to DLA Piper Rus Ltd. Please retain one copy of this signed letter for your files. If you have any questions concerning our Engagement, please contact me."
(vi) The Arbitration
i) PLC's 29 April 2015 Notice of Rescission was premature, ineffective and constituted a renunciation of the Shipbuilding Contract entitling the Shipyard to bring it to an end, as it had done;
ii) PCL was obliged to pay the Shipyard the fifth instalment of the purchase price, which had fallen due for payment prior to the termination of the Shipbuilding Contract;
iii) The Shipyard was additionally entitled to compensation for its proven losses in accordance with a formula set out in the Shipbuilding Contract in an amount to be quantified, and also to its costs of the arbitration.
The Proceedings
i) The claim against DLA Russia (see paragraphs 6 to 25) is for negligence on the part of Mr Lamzin in the advice that he gave in the period from December 2014 to April 2015 in relation to the termination provisions of the Shipbuilding Contract and in his drafting of the Notice of Rescission;
ii) The claim against DLA UK (see paragraphs 26 to 42) is for negligence on the part of Mr Choo in the period from May 2015 onwards in failing to advise PCL of the risks inherent in defending the Shipyard's claims and in pursuing its own counterclaims in the arbitration, and in advising PCL to commence and pursue proceedings to obtain security for its claim against the Shipyard in Croatia.[1]
"10. For the avoidance of doubt, although PCL and DLA Russia did sign a written engagement letter on 26 May 2015 ('the Engagement Letter'), which was said to set out the terms on which DLA Russia was to provide PCL with 'legal advisory services' going forward and to invoice PCL in respect of those services, the Engagement Letter did not have retrospective effect and is therefore of no relevance to the obligations owed by DLA Russia to PCL in respect of work done prior to the date of its signature."
The Section 9 Application
(i) Principles
"9 Stay of legal proceedings
(1) A party to an arbitration agreement against whom legal proceedings are brought (whether by way of claim or counterclaim) in respect of a matter which under the agreement is to be referred to arbitration may (upon notice to the other parties to the proceedings) apply to the court in which the proceedings have been brought to stay the proceedings so far as they concern that matter."
"… any issue which is capable of constituting a dispute or difference which may fall within the scope of an arbitration agreement":
see Sodawiczny v Ruhan [2018] EWHC 1908 (Comm), [2018] 2 Lloyd's Rep 280 per Popplewell J at [43(1)]. The search is not confined to the main or the most substantial issues in the proceedings, but the relevant issue must be reasonably substantial: Republic of Mozambique v Credit Suisse International [2020] EWHC 2012 (Comm) per Waksman J at [90].
"… in respect of a matter which under that agreement is to be referred to arbitration".
i) The Arbitration Agreement provides that it applies to:
"All disputes and disagreements, which may arise from the terms of this Engagement, as outlined above, or in connection therewith, …";
ii) Do those words extend to the claim made by PCL against DLA Russia in this action in respect of advice allegedly given and the work allegedly carried out by DLA Russia prior to 26 May 2015 when the Engagement Letter came into force, i.e., does the arbitration agreement have retroactive effect in that sense?[2]
"The Engagement Letter post-dates the matters giving rise to PCL's claim against DLA Russia, and is forward-looking in its terms. It is PCL's case that the Arbitration Agreement, on its proper construction, cannot apply retroactively to a previous legal relationship between DLA Russia and PCL, and in particular where the matters giving rise to PCL's cause of action had already taken place."
"(a) First, properly construed, the Arbitration Agreement encompasses all work done by DLA Russia before and/or after the date of the agreement."
(ii) The proper approach
i) The court can decide on the basis of the written evidence that there is a valid and enforceable arbitration agreement and that the dispute falls within its scope, in which case a stay will be granted;
ii) The court can grant a stay under the court's inherent jurisdiction in order to leave the issue as to the existence, validity or scope of the arbitration agreement to be determined by the arbitral tribunal;
iii) The court can order an issue to be tried as to the existence, validity or scope of the arbitration agreement; or
iv) The court can decide on the basis of the written evidence that there is no arbitration agreement, or that the claim falls outside the scope of the arbitration agreement, in which case the application for a stay will be dismissed.
"I of course accept that there may be situations where despite [an agreement between the parties that the matter could be resolved on affidavit evidence] the Court may simply feel that it cannot resolve the issue without hearing witnesses. But it also seems to me that the Court should be looking for the most economical way of deciding what is after all, a dispute about where the real disputes should be resolved. On an application under s. 9 a Court is bound to have to consider the affidavit evidence, and to spend time in so doing. There is bound to be argument about the strength or otherwise of the case as to whether the arbitration clause covers the subject matter of the action in considering what course to take. It thus also seems to me that in the interests of good litigation management and the saving of costs, the Court should see whether it can resolve that point on the affidavit evidence. Certainly, it should try and do so if both parties are agreed that they would like the matter resolved on the affidavits. I would add that in addition, if the parties do not come agreed, as in the instant case, depending on how important any factual disputes appear to be to the ultimate resolution of the disputes about jurisdiction, it may be worth exploring whether they would agree, or even in some circumstances where the disputes on fact seem immaterial, using the powers under CPR 32.1."
"[14] I turn now to the first issue. The first question raised is what (if anything) Naza Motors needs to establish as conditions precedent to invoking the jurisdiction conferred by s 9(1) to grant a stay of court proceedings. In my judgment the language of s 9(1) plainly establishes two threshold requirements. The first is that there has been concluded an arbitration agreement and the second is that the issue in the proceedings is a matter which under the arbitration agreement is to be referred to arbitration. The first condition is as to the conclusion and the second is as to the scope of the arbitration agreement. Accordingly, unless and until the court is satisfied that both these conditions are satisfied the court cannot grant a stay under s 9.
…
[24] I must accordingly turn to the second issue whether it would be right in the present circumstances to exercise the inherent jurisdiction to grant a stay and (in effect) remit the issue whether the JVA was concluded to be decided in the arbitration proceedings. The absence of jurisdiction under s 9(1) to order a stay for this purpose does not preclude the existence and exercise by the court of its inherent jurisdiction to order a stay for this purpose. The court may in exercise of its inherent jurisdiction in its discretion order such a stay both where the issue is as to the conclusion or as to the scope of the arbitration agreement. But the court should only exercise its inherent jurisdiction to order such a stay and decline to decide the issue of the conclusion of the arbitration agreement or of the scope of the arbitration agreement in an exceptional case."
(iii) Russian law
i) DLA's expert was Maxim Kulkov, a member of the Moscow Bar, currently the managing partner at a Russian law firm, Kulkov, Kolotilov and Partners and a member of the ICC's Russia Arbitration Committee;
ii) PCL's expert was Alexander Muranov, a qualified Russian lawyer, the managing partner of Muranov, Chernyakov & Partners Law Firm in Moscow and an Associate Professor on Conflict of Laws, International Litigation and International Commercial Arbitration at the Moscow State Institute of International Relations.
i) He had written articles critical of the Russian International Commercial Arbitration Court ("ICAC") under the auspices of which, if DLA Russia's stay application was successful, any arbitration would be heard; and
ii) He had instigated litigation against ICAC, unsuccessfully challenging ICAC's decision, following the publication of these articles, to remove him from its recommended list of arbitrators (although, as Mr Muranov explained, he continued to sit as an arbitrator in ICAC arbitrations).
i) There are no rules in the Law of the Russian Federation "On International Arbitration", No. 5338-1 dated 7 July 1993 ("the ICA Law"), either in its original form or as amended in 2015, or in any other Russian legislation on arbitration, explicitly governing the retroactive effect of arbitration clauses (paragraph 10.2);[4]
ii) An arbitration clause cannot have a retroactive effect by default. A rule of law can provide to the contrary, or the parties can agree otherwise (paragraph 10.4). So far as party agreement is concerned, Russian law allows (and allowed) parties to conclude both "narrow" and "wide" arbitration clauses (paragraphs10.6 and 10.7);
iii) The principles and rules of Russian law applicable to the construction of contracts generally are also applicable to the construction of arbitration clauses. Russian courts construe arbitration clauses in particular on the basis of Article 431 of the Civil Code of the Russian Federation ("the RF CC"), namely:
"… taking into consideration primarily the principle of literal interpretation of a contract and secondarily other relevant evidence including the correspondence and factual relations of the parties"
(paragraph 10.14).
"Article 431 Interpretation of a Contract
In the interpretation of the terms of a contract a court shall take into account the literal meaning of the words and expressions contained in it. The literal meaning of a term of a contract, in case the term is not clear, shall be established by comparison with the other terms and the sense of the contract as a whole.
If the rules contained in the first part of the present Article do not allow the determination of the content of the contract, the real common will of the parties must be ascertained, taking into account the purpose of the contract. In such a case, all surrounding circumstances shall be taken into account, including negotiations and correspondence preceding the contract, the practice established in the mutual relations of the parties, business customs and the subsequent conduct of the parties."
"Article 425 Effect of a Contract
1. A contract shall enter into and become obligatory for the parties from the time of its conclusion.
2. The parties have the right to establish that the terms of a contract concluded by them shall be applied to their relations that arose before the conclusion of the contract."
i) Paragraph 7.1 of the contract, as amended by addendum no. 5 dated 28 December 2007, which was stated to apply to the legal relations between the parties from 00:00 on 1 January 2008, provided that:
"… all disputes, disagreements and claims arising from this agreement or in connection herewith, including those related to its conclusion, modification, execution, violation, termination, expiry and validity shall be subject to resolution at the Arbitral Court at the non-profit organization – the Fund 'Law and Economics of the Fuel and Energy Complex' (Moscow) in accordance with its rules in force as of the date of filing of the statement of claim";
ii) Paragraph 7 of addendum no. 8 dated 4 March 2010, which was stated to apply to the legal relations between the parties from 00:00 on 1 January 2010, as subsequently amended on 12 May 2010, provided that:
"… all disputes, disagreements and claims arising from this agreement or in connection herewith, including those related to its conclusion, modification, execution, violation, termination, expiry and validity shall be subject to resolution at the Arbitral Court at the Russian Union of Industrialists and Entrepreneurs (Moscow) in accordance with its rules in force as of the date of filing of the statement of claim."
As will be apparent, the terms of the two arbitration agreements were substantially the same, save that they provided for arbitration under the auspices of different bodies.
"On the basis of paragraph 2 of Article 1 of the Federal Law dated 24.07.2002 No. 102-FZ 'On Arbitral Tribunals in the Russian Federation' (hereinafter referred to as the Law on Arbitral Courts), by agreement of the parties to the arbitration proceeding, any dispute arising from civil legal relations may be submitted to the arbitral tribunal, unless otherwise provided by federal law.
By virtue of paragraph 2 of Article 5 of the Law on Arbitral Tribunals, an arbitration agreement may be concluded by the parties in respect of all or certain disputes that have arisen or may arise between the parties in connection with any particular legal relationship.
In this case, a new arbitration agreement comes down to the submission of all disputes arising from the agreement dated 19.12.2005 No. 144-P and in connection therewith, to another tribunal – the Arbitral Court at the Russian Union of Industrialists and Entrepreneurs.
Consequently, the will of the parties, expressed in the addendum dated 04.03.2010 No. 8, is aimed at submitting all disputes related to the said agreement to the competence of another tribunal from the moment the said addendum is concluded.
As a general rule, the arbitration clause included in the agreement is intended for this agreement and is one of the provisions thereof. In the situation under consideration, the arbitration clause formulated by the parties in the addendum dated 04.03.2010 No. 8 refers to the agreement as a whole and applies to a different period of relations than the addendum in which it is contained."
"Thus, the Supreme Court of the Russian Federation applied an arbitration clause to the relations which appeared prior to its conclusion. The court expressly established the presumption that, unless otherwise indicated, a wide arbitration clause covers all disputes related to the contract, including those based on facts/circumstances that occurred prior to the signing of such arbitration clause."
Thus, he said, "wide" arbitration agreements, e.g., arbitration agreements not limited to disputes arising "under" a contract, were presumed to operate retroactively.
"… all disputes, disagreements or claims arising out of or in connection with this Agreement, including those related to its conclusion, modification, performance, violation, termination, expiry or invalidity shall be resolved at the International Commercial Arbitration Court at the Chamber of Commerce and Industry of the Russian Federation".
"In accordance with Article 425(2) of the RF CC, the parties have the right to establish that the terms of the contract they have concluded apply to their relations that arose before the conclusion of the contract.
Based on this rule, concluding the General Contractor Agreement, the parties agreed that it shall apply to all obligations of the contractor arising from the execution of the preliminary stage of the Complex Contract, and to liability associated with such execution, and the obligations of the parties arising from the Complex Contract and not fulfilled for the date of entry into force of the General Contractor Agreement, shall be executed in accordance with the terms of the Complex Contract, unless otherwise expressly specified in the General Contractor Agreement, at the same time any provisions of the Complex Contract, contrary to the terms of the main contract shall not apply (paragraph 24.1 of the General Contractor Agreement). The parties also determined the total cost of reconstruction of the facility, taking into account advance payments made during the term of the Complex Contract.
The aforementioned terms of the Complex Contract and the main contracts allow us to conclude that the Complex Contract was intended to regulate the relations of the parties in the period until they agreed on the terms of the General Contractor Agreement. At the same time, having concluded the main contract, the parties explicitly and unambiguously expressed their will to extend its effect to the relations of the parties from the Complex Contract, and the parties did not make exceptions to this rule in relation to the dispute settlement procedure for the fulfilment of the contractual obligations established by the Complex Contract.
Consequently, the courts did not have grounds for concluding that, with the entry into force of the General Contractor Agreement, the Complex Contract remained valid with regard to the clause on the consideration of disputes arising from it in the Arbitrazh (Commercial) Court of the city of Moscow. The arbitration clause on referring the dispute to the ICAC at the RF CCI enshrined in the General Contractor Agreement, is also subject to extension to the claims to return the advance payments paid by the plaintiff in accordance with the Complex Contract. The arbitral tribunal, considering the dispute in this part, acted within the scope of the arbitration agreement."
i) Mr Kulkov agreed that the case showed that, when considering the meaning of an arbitration agreement, although the arbitration agreement was a separate and severable contract the court would look at it in the context of the contract of which it formed part;
ii) He did not agree that the case demonstrated that, although parties can agree that an arbitration agreement can apply to relations predating its conclusion, they must do so "explicitly and unambiguously". He said that, although the judgment used those words, that did not mean that some less direct expression of the parties' will would not suffice;
iii) Mr Kulkov did not agree that the need for an explicit and unambiguous expression of the parties intent that the arbitration agreement should apply retroactively reflected the terms of Article 425 of the RF CC and the presumption against retroactivity. Mr Kulkov said that:
"I agree that the parties should somehow express their will, but I disagree that it should be explicit expression. So, it could be any kind of evidence that the parties meant that the arbitration clause could apply to a predating contract – a contract predating relations."
"The effect of the arbitration clause may extend to relations that arose prior to the conclusion of the arbitration agreement, if this is indicated in the contract contained such a clause."
Mr Muranov said that this case simply developed the position established in the case referred to in paragraphs 84 to 92 above to which the decision in this case, one of the few cases directly to address retroactivity, expressly referred.
"Well, first, it is – there is no word 'must', such a strong word. Here it is 'If this is indicated …' And again, so there is no test here, so the court didn't elaborate what kind of indication. But somehow it should be indicated, I agree, according to the rules of contract law interpretation."
"59. According to the general rule it was previously the case that an arbitration agreement does not have retrospective effect unless the parties specifically provided for that. The parties did not include such terms expressly stating on retrospective effect of such clause.
60. However, the strict approach on absence of retrospective effect of an arbitration clause was reconsidered as a result of the recent arbitration reform in September 2016. The reform was intended to modernize the legal framework in the Russian Federation by bringing it into line with the UNCITRAL Model Law on International Commercial Arbitration of 1985 and address those issues some of the perceived problems associated with using arbitration in the Russian Federation."
i) The Resolution post-dated the Arbitration Agreement. As Mr Kulkov agreed in cross-examination, Russian court decisions generally do not have retrospective effect;
ii) Although Mr Kulkov said that the Resolution also reflected the practice of the Russian courts prior to 10 December 2019, not only did it post-date the 2015 amendments to Russian arbitration law but it was adopted pursuant to those laws as amended. Mr Kulkov, furthermore, accepted that court practice prior to the Resolution was inconsistent; and
iii) As he accepted in cross-examination, paragraph 21 of the Resolution to which Mr Kulkov referred in his report said nothing expressly about whether arbitration agreements were presumed to apply to disputes arising from legal relations predating the arbitration agreement.
"… any dispute, conflict or complaint arising pursuant to or in connection with, or issues of breach, termination or validity of [the contract]"
should be referred to arbitration. The tribunal held that the clause extended to the architect's claim for compensation for the additional work. The court agreed.
"In this regard, the ICAC at the RF CCI has jurisdiction over both disputes arising from contractual relations and disputes arising from other civil relations, including claims arising from unjust enrichment, including claims where one party to an obligation seeks the return of consideration provided under such an obligation from the other party. This conclusion is in line with Russian legal doctrine and ICAC case law.
The arbitration clause agreed upon by the parties provides that 'disputes, differences or claims arising under or in connection with this Contract' shall be referred to international commercial arbitration. As a rule, such a broad scope of arbitration clause, covering not only disputes under the Contract but also disputes 'in connection with the Contract' is characterized in domestic and foreign practice as covering any type of disputes, whether contractual or non-contractual, as long as the basis of such dispute is the relations between the Parties relating to the underlying Contract."
"46. In practice the courts applied the wide approach to interpret arbitration clauses, extending its scope to the disputes related to the legal relationship connected to the contract, if parties themselves had not excluded such disputes from the scope of arbitration (see Section 1.4 below)."
Mr Kulkov continued in paragraph 48 as follows:
"48. The regulation on the date of signing of the Engagement letter, as well as the case law and legal doctrine allowing arbitration clauses with a wide ambit supports a wide interpretation of arbitration clauses. Thus, the Arbitration Agreement covered all disputes, including those arising from relationships pre-dating the Engagement Letter, as I explained in paragraphs 59-69 of MK-1."
Mr Kulkov's opinion was, thus, that Russian courts applied a wide interpretation to arbitration agreements, and that a widely expressed arbitration agreement would be interpreted to embrace all disputes between the parties, including any disputes arising out of a prior relationship.
"By their nature, the Surety Agreements are agreements that formalize the security for the fulfillment of obligations under the Loan Agreement. They are of accessory (secondary) nature in respect of the Loan Agreement. Therefore, all disputes under the Surety Agreements are related to the Loan Agreement and are subject to its arbitration clause."
"… any disputes, discrepancies and claims arising from or in connection with the Agreement or connected with its conclusion, violation, termination or invalidity shall be decided by the International Commercial Arbitration Court …"
The ICAC tribunal concluded that it had jurisdiction on the basis that the lease specifically provided that, in the event of default by the lessee, the lessor could terminate the lease and seeking damages after termination; the claim was, thus, a claim for damages for breach of the lease agreement.
i) The principles of Russian law applicable to the construction of contracts generally are also applicable to the construction of arbitration clauses, including Article 431 of the RF CC;
ii) In accordance with Article 431, it is necessary to adopt a staged approach to the exercise of construction:
a) The starting point in relation to construction is the literal meaning of the particular provision in question;
b) If the literal meaning is unclear, Russian law allows consideration of the contractual context; and
c) If the meaning of the provision remains unclear, it is permissible to consider a broader spread of evidence, including subjective evidence, to establish the actual intent of the parties. The contra proferentem canon of construction may also be relevant;
iii) In accordance with Article 425 of the RF CC, an arbitration agreement will not be construed to have retroactive effect by default. Accordingly, in the absence of any contrary provision, the arbitration agreement will not apply retroactively, and to that extent there is a presumption that it will not;
iv) This presumption is not affected by the fact that the arbitration agreement is expressed in wide terms, e.g., embracing not just disputes arising under but also in connection with a contract, and thus non-contractual claims. The use of wide language does not mean that the arbitration agreement will be interpreted as operating retroactively;
v) The parties can, however, agree that that an arbitration agreement should operate retroactively. Such an agreement, however, requires language either in the arbitration agreement itself, or in the remainder of the contract in which the arbitration agreement is contained; there needs to be clear expression of the parties' will that the arbitration agreement should apply retroactively.
"According to the general rule it was previously the case that an arbitration agreement does not have retrospective effect unless the parties specifically provided for that."
(emphasis added)
I was not persuaded by the remainder of Mr Kulkov's written evidence or his oral evidence that the position had changed in any relevant respect.
(iv) Submissions
"28. We had not discussed anything about the Engagement Letter covering events before it was entered into. This was, as far as I was concerned, because everything before the Engagement Letter was not formal advice and we had decided by the Engagement Letter to formalise the relationship."
So, Mr Spalton submitted, the relationship was there before; the purpose of the Engagement Letter was simply to formalise it, and thereby to capture the entirety of the relationship.
"24. Following the sending of the Notice, and again in accordance with Mr Lamzin's advice, PCL made no further payments under the Shipbuilding Contract."
i) The date of the Engagement Letter;
ii) The Scope of Services, the Fees and Billing Procedures, and Dispute Resolution provisions; and
iii) The Term and Termination provision, explaining that the engagement only became effective from the date on which it was accepted and signed.
She submitted that there was nothing to rebut the presumption of retroactivity.
i) Mr Lamzin and DLA Russia had been advising from December 2014 through the first months of 2015, leading to the draft Notice of Termination sent on 29 April 2015, sent on by PCL to the Shipyard;
ii) Thereafter, nothing occurred for a period of around three weeks, and then on 19 May 2015, according to Vladimir Esakov's evidence, Mr Lamzin suggested that PCL should think about arbitration to recover its funds;
iii) Mr Lamzin then wrote to Mr Choo in London referring to a "potential request for assistance" who produced a fee estimate for conducting a putative arbitration, and then on 26 May 2015 Mr Lamzin sent the Engagement Letter.
"… everything before the Engagement Letter was not formal advice and we had decided by the Engagement Letter to formalise the relationship."
(v) Decision
"… may arise from the terms of this Engagement, as outlined above, or in connection therewith"
to be resolved by arbitration. The term "Engagement" is defined earlier as:
"… this engagement letter (the 'Engagement') … under which DLA Piper Rus Ltd. (the 'Company') will be pleased to provide PREMIER CRUISES LIMITED (the 'Client') with legal advisory services"
i) The Engagement is stated to become effective from the date on which the Engagement Letter is accepted and signed by PCL, which was 26 May 2015. On its face, it does not embrace matters that have occurred before that date;
ii) The opening paragraph of the Engagement Letter (see paragraph 23 above), which contains the definition of the term "Engagement", refers to the letter setting out the terms of which DLA Russia "will" be pleased to provide services to PCL;
iii) The Scope of Services provision states that DLA Russia will
"… respond to your requests for advice regarding various legal issues and other ancillary services that the Client may encounter. The scope of the services to be provided (the 'Services') will be defined upon a case-by-case basis by mutual agreement between the Company and the Client."
This anticipates future requests for assistance and a scope of services that "will be defined". The words are inapt to embrace services that have been provided in the past.
DLA UK's application for a case management stay
"If claims against DLA (Russia) are stayed, also [to] stay the claim(s) brought against DLA UK pursuant to CPR 3.1(2)((f)".
I had read that as an indication that the application for a case management stay in relation to the proceedings against DLA UK was pursued only if I were minded to grant a section 9 stay of the proceedings against DLA Russia. So too had Ms Hopkins, QC, as paragraph 61 of her own skeleton argument made clear.
i) PCL was obliged to bring any claim against DLA Russia out of post-26 May 2015 events by way of Russian arbitration pursuant to the Arbitration Agreement;
ii) Although PCL had not in fact made any claim against DLA Russia in relation to post-26 May 2015 events, it was arguable as a matter of Russian law that DLA UK had been acting as a sub-contractor or agent of DLA Russia. In reality, therefore, the claim against DLA UK was really a claim against DLA Russia under the Engagement Letter;
iii) That being so, the English proceedings against DLA UK ought to be stayed pending the commencement and conclusion of an arbitration in Russia in relation to post-26 May 2015 events. Mr Spalton said that DLA Russia could commence such an arbitration itself; a claim against DLA UK might not be necessary if DLA Russia was liable for any failings on its part, but Mr Spalton said that an undertaking could be given that DLA UK would submit to the jurisdiction of the Russian tribunal so that any claim against it could also be brought in that forum.
i) In circumstances where no such claim has been made or intimated against DLA Russia in respect of such events such an arbitration would seem somewhat artificial;
ii) In any event, DLA Russia has had ample opportunity to commence such an arbitration if it wished to do so, but has not done so.
i) DLA UK is an English domiciled LLP, and pursuant to Article 4 of Regulation 1215/2012 ("the Recast Regulation") the English court has mandatory jurisdiction over DLA UK;
ii) In Owusu v Jackson (Case C-281/02), [2005] QB 801 at [46], the ECJ held in the context of Article 2 of the Brussels Convention that it was not open to an English court to stay a claim against an English-domiciled defendant in favour of a court of a non-contracting state on forum non conveniens grounds;
iii) Subsequent authority, see Equitas Ltd v Allstate Insurance Company [2008] EWHC 1671 (Comm), [2009] 1 All ER (Comm) 1137 per Beatson J at [64], has confirmed that it is not open to an English court to stay proceedings against an English-domiciled defendant on discretionary case management grounds where it would undermine mandatory provisions of Regulation 44/2001. The same applies to the Recast Regulation: see Gulf International Bank BSC v Aldwood [2019] EWHC 1666 (QB) per John Kimbell, QC at [104] and [136];
iv) A stay might be permissible consistent with Owusu if it was temporary in effect: see Equitas at [64]; Jeffries International Ltd v Landsbanki Islands LF [2009] EWHC 894 (Comm) per Cooke J at [27]-[29]. PCL submitted, however, that the stay sought by DLA UK was to all intents and purposes permanent.
"… where a plaintiff has founded jurisdiction in this country as of right, there is a real burden on a defendant who seeks a stay to satisfy the court that the ends of justice would be better served by granting a stay"
See Equitas at [54]. In Reichhold Norway ASA v Goldman Sachs International [2000] 1 All ER 679 at 690H Lord Bingham of Cornhill CJ said that such stays should only be granted "in rare and compelling circumstances". PCL submitted that there were no such circumstances here.
i) The Owusu line of authority could be distinguished or did not apply in the present situation because the present claim was an arbitration claim and would not undermine the Recast Regulation;
ii) The stay sought was only a temporary stay, and the authorities recognised that temporary, case management stays could be granted consistently with Owusu; and
iii) The present case was a case where the circumstances were rare and compelling in the Reichhold sense.
"This Regulation should not apply to arbitration. Nothing in this Regulation should prevent the courts of a Member State, when seised of an action in a matter in respect of which the parties have entered into an arbitration agreement, from referring the parties to arbitration, from staying or dismissing the proceedings, or from examining whether the arbitration agreement is null and void, inoperative or incapable of being performed in accordance with national law."
Article 1(2)(d) of the Recast Regulation itself states:
"2. This Regulation shall not apply to:
…
(d) arbitration".
i) No Russian arbitration has yet been commenced by DLA Russia; there is no evidence before me as to when it might be started or how long it might take;
ii) There is no reason to suppose that any Russian arbitration that might be commenced by DLA Russia will canvass any of the matters that are the subject of the claim against DLA UK. Ms Hopkins, QC confirmed that PCL does not intend to advance a claim against DLA Russia arising out of post-Engagement Letter events;
iii) There is no obvious advantage in having any Russian arbitration proceedings go ahead first, in advance of the English court proceedings against DLA Russia which it is to be assumed, given my decision on the section 9 application, will proceed.
Conclusion
Note 1 Whilst the claim against DLA UK principally concerns the period in and after May 2015 and the pursuit of the arbitration, paragraph 39 of the Particulars of Claim contains thiscaveat: “If and insofar as [DLA UK] had any involvement in the advice given by Mr Lamzin in March-April 2015 and/or the drafting of the Notice, it was negligent or in breach of the duties owed to PCL for the reasons identified in paragraph 9 above, which are repeated.” There is no positive allegation, however, that DLA UK did have any such involvement. [Back] Note 2 Following the course taken by counsel, when I refer in this judgment to an arbitration agreement being “retroactive” what I mean is whether it covers disputes between the parties arising out of legal relations between them that predate the conclusion of the arbitration agreement. [Back] Note 3 The reports also addressed the relationship between DLA Russia and DLA UK. The day before the hearing I was informed by counsel that an agreement had been reached between them as follows:
“The parties agree the following, for the purposes of this application only, with reference to section 1.3 of Mr Kulkov’s first report, sections IV and V of Mr Muranov’s report, section 3 of Mr Kulkov’s second report and Block 3 of the Joint Memorandum:
The English court is not invited by either side at this hearing to make any findings based on that evidence (or otherwise) as to the nature of the relationships between (i) DLA Russia and DLA UK and (ii) PCL and DLA UK;
PCL accepts that, if Russian law applies to determine the nature of those relationships (which PCL disputes), it is arguable as a matter of Russian law that DLA UK was a sub-contractor of DLA Russia.”
[Back] Note 4 The only change made to Article 7(1) of the ICA Law, which contained a definition of an arbitration clause, was the addition of language that made clear that an arbitration clause could be limited to a specific part of the parties’ legal relationship, although Mr Kulkov made clear in his reply report that such a possibility had existed before the 2015 reforms. [Back] Note 5 Ms Hopkins, QC suggested that English law takes a not dissimilar approach to the question of retroactivity of arbitration agreements and referred me to two cases in that context, the decision of Jacobs J in Etihad Airways PJSC v Flöther [2019] EWHC 33107 (Comm), [2020] QB 793 at [104] and the decision of Bryan J in Terre Neuve Sarl v Yewdale Ltd [2020] EWHC 772 (Comm) at [26]-[35]. In circumstances where there Arbitration Agreement is governed by Russian law, I do not think it is helpful to consider how the agreement might have been construed if governed by English law. [Back]