BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
COMMERCIAL COURT (QBD)
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
APACHE NORTH SEA LIMITED |
Claimant |
|
- and |
||
INEOS FPS LIMITED |
Defendant |
____________________
Sonia Tolaney QC and James Willan (instructed by Addleshaw Goddard LLP) for the Defendant
Hearing dates: 15 and 16 July 2020
Further Submissions: 20 July 2020
circulated to the parties: 27 July 2020
____________________
Crown Copyright ©
Mr Justice Foxton :
INTRODUCTION
"On the basis of:
a. the agreed facts set out in Appendix 1; and
b. the assumption that the facts alleged by the Defendant which are set out in Appendix 2 are proven at trial,
is INEOS acting unreasonably and/or non-contractually by withholding consent under clause 5.05(a) of the Apache Forties TPA to an amendment to Attachment F unless Apache agrees to increase the base tariff payable?"
"Are (a) the terms (including as to price) on which INEOS FPS acquired the FPS from BPEOC, and/or (b) INEOS' knowledge at the time it agreed to purchase the FPS from BPEOC, relevant to the assessment of whether INEOS FPS has unreasonably refused consent under clause 5.05(a)?"
i) The background, including the facts which are either agreed or to be assumed for the purposes of this hearing.
ii) The parties' arguments.
iii) The applicable legal principles.
iv) The relevant provisions of the TPA.
v) The First Preliminary Issue.
vi) The Second Preliminary Issue.
THE BACKGROUND
i) Apache contends that it agreed to an increased base tariff under the 2012 Amendment in circumstances in which it was unclear whether there was Uncommitted Capacity, and Apache was seeking to transport significant additional quantities of liquids beyond those originally contemplated by the TPAs.
ii) INEOS contends that the parties agreed to an increased base tariff under the 2012 Amendment because Apache was seeking to transport significant additional quantities of liquids beyond those originally contemplated by the Apache Forties TPAs.
"For periods after 1 January 2021, Apache shall be entitled to request (a) extensions to Attachment F, (b) FMQs and (c) Additional Quantities and Spot Quantities pursuant to Clauses 5.05 and 5.06 of the TPA".
i) that Apache's proposed amendment to Attachment F will have the effect of significantly increasing (by c. 120 million barrels) the quantity of liquids which are to be transported beyond those contemplated when the TPAs were executed, and of significantly extending (by 20 years, to 2040) the period over which Apache is entitled to transport hydrocarbons through the FPS beyond the 18 year period to the end of 2020 contemplated when the TPAs were executed.
ii) INEOS expects to invest around £500 million between 2019 and 2023 for the purpose of extending the life of the FPS, to maintain high levels of reliability of the system through to 2040, and to modernise environmental plants and improve safety systems in line with evolving legislation.
iii) The original base tariff of 60p per barrel was calculated so as to enable BPEOC to recover its initial investment in the FPS on the assumption that production would continue until around the end of 2020, and did not price in the investment and costs required to extend the life of, and upgrade, the FPS so as to enable it to continue operating for the period from 2020 to 2041.
iv) The standard published base tariff which INEOS charges for use of the FPS is currently £1 per barrel, subject to escalation, and all new agreements entered into by INEOS with customers since 2015 in respect of the provision of services in the FPS have used that base tariff.
v) It is common ground that there is and was at the material time Uncommitted Capacity in the Forties System within the meaning of clause 5.05(a) of the TPAs for the period 2021 to 2040.
vi) INEOS does not contend that, but for Apache's request to amend Attachment F, there would be no contractual commitment to any other party to operate the Forties System between 2021 and 2040 or that its investment cannot or will not proceed if INEOS is obliged to provide Apache with services between 2021 and 2040 on the base tariff agreed at clause 7 of the TPA.
THE PARTIES' ARGUMENTS IN SUMMARY
i) It is an established principle when construing contractual provisions which provide that one party's consent is required before a particular step can be taken, such consent not to be unreasonably withheld (hereafter a "consent provision"), that consent cannot be withheld in order to secure a re-writing of fundamental terms of the parties' contract.
ii) Under the TPA, Apache is obliged (with very limited exceptions) to ship all of the production from the Shipper's Fields through the FPS until such time as the TPA is terminated, but the price for transporting and processing that production is fixed by clause 7.01 of the TPA, a provision which provides for the calculation of a contractual tariff by taking an agreed base point, and escalating it by reference to a series of indices over time.
iii) When the TPA was concluded in 2003, Apache's then expected production profile ran only to the end of 2020, and that was reflected in the terms of Attachment F. However, the TPA contemplated that production might continue beyond the end of 2020, in which case Apache's obligation to transport that production through the FPS would continue, as would the right (and obligation) to pay for such transportation at the contractual tariff.
iv) In those circumstances, INEOS' demand for a revised tariff as a condition of agreeing to the amendment of Attachment F is contractually impermissible, because it seeks as the price of consent to require Apache to give up its contractual entitlement to transport hydrocarbons at the agreed tariff.
v) If, contrary to Apache's case, INEOS might be entitled in some cases to condition consent to the amendment of Attachment F on the re-visiting of the tariff, then it is relevant (or potentially relevant) to the issue of whether it is entitled to adopt that course in this case to consider the terms on which INEOS acquired the FPS from BPEOC, and its knowledge at the time of that acquisition.
i) The Court should not seek to limit the operation of clause 5.05(c) as a matter of construction. The issue of whether INEOS is entitled to require a change to the contractual tariff as a condition of amending Attachment F is a question of fact, to be judged in the light of all of the available evidence and by reference to the test of whether INEOS has acted rationally, or at least in way in which a reasonable person might act in the circumstances.
ii) Apache has no contractual right to transport its hydrocarbons through the TPA after the end of 2020, still less to do so at the contractual tariff. In those circumstances, the amendment to Attachment F which Apache asks INEOS to consent to would involve a very substantial increase in Apache's contractual rights.
iii) The only contractual limitation on INEOS' right to refuse or condition its consent is that the reasons for refusing or conditioning consent are relevant to INEOS' contractual relationship with Apache and to the change for which INEOS' consent is sought.
iv) In circumstances in which the use of the TPA to transport Apache's hydrocarbons in the period after 2020 is only possible because of the very substantial investment which INEOS intends to make in the FPS, the condition which INEOS seeks to impose is clearly referable to INEOS' contractual relationship with Apache and to Apache's request to amend Attachment F so that its estimated production profile will now run to 2040.
v) Any other issues which Apache seeks to raise concerning the basis on which INEOS is willing to grant consent are issues of fact, and the reasonableness (in the relevant sense) of INEOS' decision cannot be determined at this preliminary issues hearing.
vi) However, the Court can and should decide now that the terms on which INEOS acquired the FPS from BPEOC, and its knowledge at the time of that acquisition, are clearly irrelevant to that factual enquiry, because the terms on which INEOS acquired the FPS simply require it to stand in BPEOC's shoes.
THE APPLICABLE LEGAL PRINCIPLES
The principles applicable to the construction of contracts generally
i) A contractual provision must be read in the context of the contract as a whole: see Wood v Capita [2017] AC 1173 (SC) at [10] per Lord Hodge JSC and Arnold v Britton [2015] AC 1619 (SC) per Lord Neuberger PSC at [15].
ii) As Leggatt J explained in Zhoushan Jinhaiwan Shipyard Co Ltd v Golden Exquisite Inc [2015] 1 Lloyd's Rep 283 (Comm) at [25]:
"Identifying the meaning of the words used, however, and the shared purposes and values which the parties may be taken to have had are not two separate inquiries. The meaning of all language depends on its context. To paraphrase a philosopher of language, a sentence is never not in a context. Contracting parties are never not in a situation. A contract is never not read in the light of some purpose. Interpretive assumptions are always in force. A sentence that seems to need no interpretation is already the product of one. At the same time the main source from which the shared purposes and values of the parties can be ascertained is the contract they have made. It is for these reasons that it is a fundamental principle of the interpretation of contracts that the contractual document must be read as a whole."
"It is, of course, a principle of construction that words capable of a very wide meaning may have to be given a narrower construction to reconcile them with other parts of the document. This rule is particularly apposite if the effect of general words would otherwise be to nullify what the parties appear to have contemplated as an important element in the transaction".
"Any relational contract of this character is likely to be of massive length, containing many infelicities and oddities. Both parties should adopt a reasonable approach in accordance with what is obviously the long-term purpose of the contract. They should not be latching onto the infelicities and oddities, in order to disrupt the project and maximise their own gain".
The construction of consent provisions in contracts
"[3] When a difference is to be resolved between landlord and tenant following the imposition of a condition (an event which need not be separately considered) or a withholding of consent, effect must be given to three overriding principles. The first, as expressed by Balcombe LJ in International Drilling Fluids Ltd v Louisville Investments (Uxbridge) Ltd [1986] Ch 513, 520 is that
'a landlord is not entitled to refuse his consent to an assignment on grounds which have nothing whatever to do with the relationship of landlord and tenant in regard to the subject matter of the lease ;
The same principle was earlier expressed by Sargant LJ in Houlder Bros & Co Ltd v Gibbs [1925] Ch 575, 587:
'in a case of this kind the reason must be something affecting the subject matter of the contract which forms the relationship between the landlord and the tenant, and it must not be something wholly extraneous and completely dissociated from the subject matter of the contract.'
While difficult borderline questions are bound to arise, the principle to be applied is clear.
[4] Secondly, in any case where the requirements of the first principle are met, the question whether the landlord's conduct was reasonable or unreasonable will be one of fact to be decided by the tribunal of fact. There are many reported cases. In some the landlord's withholding of consent has been held to be reasonable , in others unreasonable These cases are of illustrative value. But in each the decision rested on the facts of the particular case and care must be taken not to elevate a decision made on the facts of a particular case into a principle of law. The correct approach was very clearly laid down by Lord Denning MR in Bickel v Duke of Westminster [1977] QB 517, 524.
[5] Thirdly, the landlord's obligation is to show that his conduct was reasonable, not that it was right or justifiable. As Danckwerts LJ held in Pimms Ltd v Tallow Chandlers Company [1964] 2 QB 547, 564: 'it is not necessary for the landlords to prove that the conclusions which led them to refuse consent were justified, if they were conclusions which might be reached by a reasonable man in the circumstances ' Subject always to the first principle outlined above, I would respectfully endorse the observation of Viscount Dunedin in Viscount Tredegar v Harwood [1929] AC 72, 78 that one 'should read reasonableness in the general sense'. There are few expressions more routinely used by British lawyers than 'reasonable', and the expression should be given a broad, common sense meaning in this context as in others."
"The words of the contract are perfectly clear English words: 'such licence shall not be unreasonably withheld'. When those words come to be applied in any particular case, I do not think the court can, or should, determine by strict rules the grounds on which a landlord may, or may not, reasonably refuse his consent. He is not limited by the contract to any particular grounds. Nor should the courts limit him. Not even under the guise of construing the words ."
(emphasis added).
"(1) The purpose of a covenant against assignment without the consent of the landlord, such consent not to be unreasonably withheld, is to protect the lessor from having his premises used or occupied in an undesirable way, or by an undesirable tenant or assignee
(2) As a corollary to the first proposition, a landlord is not entitled to refuse his consent to an assignment on grounds which have nothing whatever to do with the relationship of landlord and tenant in regard to the subject matter of the lease A recent example of a case where the landlord's consent was unreasonably withheld because the refusal was designed to achieve a collateral purpose unconnected with the terms of the lease is Bromley Park Garden Estates Ltd v Moss [1982] 1 WLR 1019.
(3) The onus of proving that consent has been unreasonably withheld is on the tenant
(4) It is not necessary for the landlord to prove that the conclusions which led him to refuse consent were justified, if they were conclusions which might be reached by a reasonable man in the circumstances
(5) It may be reasonable for the landlord to refuse his consent to an assignment on the ground of the purpose for which the proposed assignee intends to use the premises, even though that purpose is not forbidden by the lease
(6) There is a divergence of authority on the question, in considering whether the landlord's refusal of consent is reasonable, whether it is permissible to have regard to the consequences to the tenant if consent to the proposed assignment is withheld . . But in my judgment a proper reconciliation of those two streams of authority can be achieved by saying that while a landlord need usually only consider his own relevant interests, there may be cases where there is such a disproportion between the benefit to the landlord and the detriment to the tenant if the landlord withholds his consent to an assignment that it is unreasonable for the landlord to refuse consent.
(7) Subject to the propositions set out above, it is in each case a question of fact, depending upon all the circumstances, whether the landlord's consent to an assignment is being unreasonably withheld".
"Looking at the question as a matter of substance, it cannot be said that the Lease, read as a whole, conferred an unqualified right on the tenant to use the whole, or any particular part, of No 51 for residential purposes. Clause 3(11) must be read with clause 3(19), which required the tenant to perform and observe all the provisions and requirements of the planning legislation. Read together, the effect of those two clauses was to permit the tenant to use for residential purposes only such parts of No 51 as were from time to time permitted by the planning regime to be used for residential purposes".
"to address the question whether the landlord's consent was unreasonably withheld by reference to an over-refined attempt to identify a limited original purpose behind clause 3(19), contrary to Lord Denning MR's dictum in the Bickel case, approved in the Ashworth Frazer case, that it is wrong in principle to address the question 'under the guise of construing the words'".
"in any rigid or doctrinaire way, still less solely by reference to the original purposes of the [relevant covenant] which may have been within the contemplation of the parties when the lease was granted. It will in every case be a question of fact and degree measured as at the date upon which the relevant consent is sought ".
"The most relevant circumstances to take into account are the other provisions of the lease, including the lessee's unrestricted right to use the whole of the premises if he wishes to do so for residential purposes. I do not agree that this sub-clause must be read subject to the lessee first obtaining the lessor's consent to a planning application for a change of use (where that is required) or that, as Lord Briggs JSC has concluded, the right to use the premises for residential purposes was limited to those parts for which planning consent had already been obtained. That would involve writing words into the user clause as opposed to treating the lessor's power reasonably to refuse its consent in clause 3(19) as impliedly limited to other aspects of a planning application".
At [47], she observed:
"On my interpretation of the lease, the power to refuse consent to a planning application was not granted to enable the landlord to cut down the user clause".
"Like the courts below, I cannot accept that an express grant of permission for residential use can reasonably be overridden by the freeholders deployment of an entirely unfocussed provision in relation to applications for planning permission".
"When considering the reasonableness of conditions, it seems to me that if the landlord would have been entitled to refuse consent on some particular ground, a condition neutralising the landlord's concern will ordinarily be reasonable. The most common example would be a case in which the landlord would be entitled to refuse consent to an assignment to a financially weak assignee, but in fact grants consent on condition that the assignee's obligations are guaranteed or that the assignee puts up a rent."
THE TPA
Was the TPA a "life of field" agreement?
i) Clause 3 of the TPA, which was concerned with the duration of the TPA, had a start date ("the Commencement Date"), but no fixed termination date. Instead clause 3.03(a) provided that the TPA would "continue in full force and effect until termination upon the earlier of the following occurrences ". Ex facie, the provisions which would continue "in full force and effect" would include the contractual tariff in clause 7.01.
ii) There followed six termination events:
a) Reasonable notice of the cessation of production from the Shipper's Fields.
b) The expiry of 150 days after a notice served by INEOS following Apache's breach of contract in failing to make payments when due (i.e. termination for breach).
c) The service by Apache of a notice of termination after INEOS had given notice of the exercise of its option (which I address further below) to move from the contractual tariff payable under clause 7.01 to a "costs share" scheme of charging under clause 7.05(a).
d) Notice of termination by INEOS under clause 18.01 or Apache under clause 18.03 (both of which depend on INEOS giving notice of its intention to abandon or remove all or part of the FPS necessary for INEOS to fulfil its obligations under the TPA).
e) By either party on 90 days' notice if, following an INEOS Force Majeure event, it is reasonably anticipated by INEOS that it will be unable to transport and process Shipper's Pipeline Liquids for a continuous period of more than twenty four months.
f) By either party on 90 days' notice if, following an Apache Force Majeure event, Apache reasonably anticipates that it will be unable to tender Shipper's Pipeline Liquids for a period of more than twenty-four months.
iii) Reflecting its indeterminate nature, a number of key definitions in the TPA are open-ended, or are "living definitions" which are intended to reflect the position from time-to-time, without express limitation as to time. For example the definition of Contract Year is indeterminate ("a period beginning at 06.00 hours on 1 October in any Year and ending at 06.00 hours on 1 October in the next succeeding Year") (emphasis added), and the definitions of "Forties System" and "Shipper's System" are to facilities "existing from time to time".
iv) Clause 4.02 of the TPA imposes a maintenance obligation on INEOS "throughout the continuation of this Agreement". However, reflecting the fact that there may come a time when the age of the FPS is such that the maintenance costs become disproportionate, clause 4.02 qualifies INEOS' obligation to "provide, repair and operate" the FPS, by providing that "if at any time and for any reason" INEOS is unable to fulfil its obligations under the TPA, and in order to resume doing so it would have to "rebuild, repair, reconfigure, rectify or reinstate" some part of the FPS, it is not obliged to do so if it "would, in the reasonable opinion of [INEOS] be uneconomic to [INEOS]".
The role of FMQs and Attachment F
i) First, an absolute numerical limit of 75,000 barrels per Day (referred to as the "Peak Entitlement").
ii) Second, the "Firm Maximum Quantity" or FMQ.
i) Apache's obligations and entitlements in relation to the daily FMQ comes to an end at the end of 2020, unless a revised Attachment F is agreed.
ii) Even if no revised FMQ is agreed in respect of the period after 2020, Apache remains entitled to tender Additional and Spot Quantities to the FPS on the existing terms of the FPS.
iii) However, INEOS is not obliged to reserve capacity for such tenders, with the result that Apache is under no "send or pay" obligation in relation to them, and if INEOS legitimately declines to carry these quantities, it does not come under the compensatory "free barrel" obligation which applies to a failure to transport the FMQ.
i) FMQ is defined as "the Shipper's specification of the maximum quantity of Shipper's Pipeline Liquids which it wishes to deliver to the Transfer Point on any given Day during the relevant period (Contract Year)". The FMQ is, therefore, a figure unilaterally specified by the shipper, rather than one which is agreed. It is a term whose principal function appears to create a daily limit on the quantities of hydrocarbons which Apache can tender, rather than a term limit. Further, it is defined in terms which are not limited to any particular period, through the use of the chronologically open-ended phrase Contract Year, with clause 5.01 providing that the FMQ applies "during the Contract Year in question". All of these matters tell against the suggestion that the FMQ is intended to create the important and highly nuanced time limit on Apache's obligations and entitlements for which INEOS argued in its supplemental submissions.
ii) INEOS points to the fact that clause 5.01 provides that at the start of the TPA's operation "on the Completion Date" Apache is to notify INEOS "of its estimated maximum quantity for each Quarter for all subsequent Contract Years", and that the clause also provides that "the expected Production Profile for the Shipper's Pipeline Liquids is set out in Attachment F". It is common ground that the estimate which was originally notified for the purposes of this provision was that set out in Attachment F, which in its original form only included Contract Years out to 2020. However the suggestion that this notification defined the duration of key rights and obligations is difficult to reconcile with (a) the unilateral nature of the communication (which would involve Apache's unilateral estimate defining the duration of the key obligations under the TPA); (b) the fact that it is an estimate of something inherently uncertain which is said to have this effect; and (c) the fact that clause 5.01 appears to contemplate that this original estimate will be superseded by later estimates during the life of the TPA.
iii) This last aspect is particularly noteworthy. Just as at the very start of the TPA's operation, Apache is to notify FMQs for each quarter of the first Contract Year, and its estimate "for each Quarter of all subsequent Contract Years", so at the end of each Contract Year thereafter Apache is to notify its FMQ for each Quarter of the next Contract Year, and an "estimated maximum quantity for each Quarter of all subsequent Contract Years during the anticipated duration of this Agreement" (emphasis added). This provision suggests not only that a new estimate for "all subsequent Contract Years" will be provided at the start of each new Contract Year, but that the duration of Apache's rights and obligations is not fixed by the very first estimate it gives (which is what INEOS' argument assumes). The transient status of Attachment F is reinforced by the reference in clause 5.01(b)(i) to "Attachment F in force at that time".
i) That might be thought a rather oblique method of imposing a very significant time limit on important rights and obligations.
ii) The argument assumes in INEOS' favour that the effect of Attachment F not extending to the Contract Year in question is to create an FMQ of zero, rather than meaning that there is no "maximum specified in respect of that Quarter in Attachment F in force at that time" which might be thought to be the more natural consequence of failing to agree a figure intended to act as a maximum.
iii) INEOS' argument appears to prove too much. Attachment F, as originally notified, provided for FMQs only for 2003 and the first three quarters of 2004, and EMQs (Estimated Maximum Quantities) thereafter. EMQ is defined as "the Shipper's Estimated Maximum Quantity of Shipper's Pipeline Liquids which it wishes to deliver to the Transfer Point on any given Day". The fact that only EMQs were originally given from the end of 2004 to 2020 appears more consistent with the parties' recognising the difficulty of giving estimates of the end-of-life of the Shipper's Fields longer than that into the future, rather than an attempt to impose a time-limit on Apache's rights and obligations under the TPA. But in any event, if INEOS is right that the absence of an FMQ in Attachment F from time-to-time means that the FMQ is zero, that would have been the position from October 2004 (absent further agreement between the parties to amend Attachment F, which would have required INEOS' consent under clause 5.05(a) on whatever conditions it might rationally have decided to impose).
"Subject to the terms and conditions herein contained, the Shipper undertakes to tender for delivery at the Transfer Point its total production of Shipper's Pipeline Liquids".
(emphasis added). The definition of Shipper's Pipeline Liquids includes a requirement that they are liquids which "subject to the terms of this Agreement, the Shipper is entitled to have transported and processed under the terms of this Agreement".
"If the daily quantity of such Shipper's Pipeline Liquids for such an accumulation together with the existing Shipper's Pipeline Liquids for any Quarter would exceed the Production Profile for that Quarter given in Attachment F, then the following arrangements shall apply:
(i) Shipper shall seek a change to the Production Profile in Attachment F for such increased quantities in accordance with clause 5.05(a).
(ii) And if there is insufficient Uncommitted Capacity in the Forties System for the whole of such Shipper's Pipeline Liquids from that accumulation and/or the specification by reference to Attachment C for such Shipper's Pipeline Liquids for that accumulation is not accepted by [INEOS];
(iii) the Shipper shall be entitled to make alternative transportation arrangements for the Shipper's Pipeline Liquids for that accumulation or part thereof".
i) First, it creates a special regime for "a previously undeveloped hydrocarbon accumulation".
ii) Second, clause 5.05(d) assumes that Apache is required to tender production of such hydrocarbons under the TPA, and, where the total production would exceed the FMQs in Attachment F, to seek a change to the estimated Production Profile.
iii) Third, it provides that INEOS can only refuse to agree to uplift Attachment F to account for such production if either (a) there is insufficient Uncommitted Capacity; or (b) the specification of product from the previously undeveloped hydrocarbon accumulation is such that it cannot be mixed with the other hydrocarbons being transported through the FPS. If INEOS' right to refuse to increase the Production Profile in Attachment F is thus constrained in respect of newly developed hydrocarbons, it is not clear why there should be a much wider right of refusal for hydrocarbons within accumulations which were already developed when the TPA was concluded.
iv) Fourth, the limited right to transport the production of previously undeveloped hydrocarbons using alternative arrangements, which only arises if INEOS has refused a request to increase the Production Profile for one of two reasons, strongly tells against Apache having any right to transport hydrocarbons from known accumulations by another system where INEOS is willing to allow them to be transported on the FPS (but, on INEOS' case, only at a higher tariff). That omission is particularly noteworthy because the TPA specifically addresses quantities from known hydrocarbon accumulations which exceed the FMQ for any Day - in the form of Additional and Spot Quantities addressed in clause 5.06 but makes no provision entitling Apache to use other transportation arrangements if INEOS refuses to carry them.
v) Finally, the clause is drafted on the basis that hydrocarbons from previously undeveloped accumulations, even to the extent that they lead to total daily production exceeding the FMQs in Attachment F, are nonetheless Shipper's Pipeline Liquids. That tells against INEOS' contention that the definition of Shipper's Pipeline Liquids (particularly when used in clause 2.01(a) of the TPA), is limited to quantities falling within the FMQ as set out in Attachment F from time to time.
i) Clause 3.03(b)(ii) allows Apache to terminate the TPA if, after a force majeure event affecting Apache, it is reasonably anticipated that Apache will be unable to tender Shipper's Pipeline Liquids for a continuous period of more than twenty four months.
ii) However, in the event of such a termination, clause 3.03(b)(ii) provides that if Apache "at any time thereafter" wishes to export Shipper's Pipeline Liquids from the Shipper's Fields, it "shall resume doing so pursuant to the terms of this Agreement subject to any technical amendments to this Agreement".
iii) Apache is also required to seek to novate the TPA, including this term, to any third party to whom it assigns or transfers any interest in the Shipper's Fields in those circumstances.
iv) There is nothing which limits these obligation to the period addressed by Attachment F (on the contrary, it is expressed to apply "at any time"). The parties must have contemplated that clause 3.303(b)(ii) might "revive" the Shipper's obligation at a point in time which was not covered by Attachment F in force at the date of termination.
i) In relation to the period up to the end of 2020, the flaw in this argument is that clause 5.01 does not provide that Apache cannot tender its production, it merely regulates the period of time over which Apache's "total production" will be tendered because of the limit on the volume of product which INEOS is obliged to accept any particular Day. Absent the time-limit which INEOS' argument must prove rather than simply assume, the effect of the daily limit created by the FMQs and the Peak Entitlement is simply to increase the period of time over which the same volume of production will have to be transported.
ii) In relation to the period after the end of 2020, INEOS' argument assumes that it has the unfettered right to allocate FPS capacity after the end of 2020 in such a way as to leave no capacity at all for Apache. Once again, however, that is to assume in INEOS' favour that which it seeks to prove. To the extent that INEOS has a contractual commitment to carry Shipper's Pipeline Liquids under the TPA after December 2020, that will not be capacity which INEOS is permitted to sell elsewhere. As INEOS only raised this argument after the hearing, I heard no submissions on the question of whether it is open to INEOS to sell all of the FPS capacity after 2020 to other users and leave nothing for Apache. I have real doubts that it is. Clause 5.01 refers to Apache having a "Peak Entitlement", which is defined as "the maximum quantity of Shipper's Pipeline Liquids which the Shipper will be entitled to specify for the FMQ" (emphasis added). The language of entitlement, and the fact that the FMQ within that limit is a matter to be "specified" unilaterally by Apache rather than agreed by INEOS, would suggest that INEOS is not entitled to enter into contractual commitments with third parties which have the effect that that Apache was unable to nominate up to the Peak Entitlement. It is not necessary to determine for the purposes of this hearing whether that is effect of the TPA, or whether there is some narrower implicit limit on Apache's obligation to tender Shipper's Pipeline Liquids if all of the capacity of the TPA has been committed elsewhere. This issue is certainly not a reason to imply the wider limit to Apache's clause 2.01(a) obligation for which INEOS is forced to argue.
What were the parties' obligations and entitlements if Apache continued producing from the Shipper's Fields after the end of 2020?
i) Clause 5.05(a) addressed what happens when "the Shipper requires to amend Attachment F" (in contrast, for example, to the language of clause 5.06(a) which states "if at any time the Shipper wishes").
ii) Clause 5.01 imposed an obligation on Apache for each Contract Year (which phrase, as I have noted, is not limited to any particular period) to notify its FMQ for each Quarter of that year, and an EMQ for all subsequent Contract Years during the anticipated duration of the TPA.
iii) Each FMQ and EMQ notified by Apache must be Apache's "bona fide estimate of maximum daily production during the relevant Quarter".
i) some linguistic infelicity, because Additional and Spot Quantities are defined as figures "in excess of the FMQ determined pursuant to clause 5.01 for the period in question", which pre-supposes that there has been such a determination, rather than the scenario which INEOS' submission is addressing when there is no FMQ;
ii) the curiosity that INEOS would continue to owe Apache an obligation under clause 4.2(a) of the TPA to maintain the FPS, even though Apache had no committed capacity on the FPS and (on INEOS' case) no obligation to use it; and
iii) some commercial infelicity, because the tariff payable for Additional and Spot Quantities after 2020 would continue at the existing rate, if Attachment F was not amended, but increase if it was amended, although Apache's rights in relation to the transportation of such Quantities would not change, and its rights were not (even on INEOS' case) being enlarged in this respect.
On this last issue, I should note that INEOS' opening submissions asserted an entitlement to charge at a rate higher than the contractual tariff for Spot Quantities for the period after 2020, referring to a figure of £1.20 as "the price which INEOS proposes to charge in the absence of any agreement to Attachment F, i.e. if it was accepting liquids on a spot basis". However, in its post-hearing submissions INEOS appeared to accept that, in such an eventuality, if INEOS agreed to carry Spot Quantities, it was obliged to do so at the contractual tariff by reason of the words "subject to all the relevant terms and conditions of this Agreement" in clause 5.06.
The contractual status of the tariff in clause 7.01
i) Apache's "Send-or-pay" obligation under clause 7.04(a) involves a payment "calculated by multiplying the tariff specified in Clause 7.01" by the Tariff Shortfall Quantity
ii) Clause 7.05 provides that "with effect from 1st October 2015", INEOS is entitled on 12 months' notice to require Apache to pay a charge calculated on the basis of Apache's share of INEOS' costs, with a 10% uplift, "in lieu of the tariff and fee referred to in clause 7.01 that would otherwise have applied". In that eventuality, Apache is entitled to terminate the TPA.
iii) Clause 8.01 provides for INEOS to invoice Apache "in respect of the tariff payable pursuant to Clause 7.01".
THE FIRST PRELIMINARY ISSUE
i) For the reasons set out at [47]-[65], Apache is entitled and obliged to tender Shipper's Pipeline Liquids for transportation on the FPS at the contractual tariff for the duration of the TPA, which continues until it is terminated on one of the six bases the TPA provides.
ii) For the reasons set out at [50]-[65], the terms of Attachment F do not limit that entitlement and obligation to the period up to 2020.
iii) In those circumstances, it would be inconsistent with the terms and scheme of the TPA if INEOS was entitled to make its consent to the amendment of Attachment F conditional on Apache agreeing to a fundamental revision of the parties' bargain in the form of a new tariff.
i) [60], INEOS' argument is inconsistent with the treatment in the TPA of production from previously undeveloped hydrocarbon accumulations;
ii) [66]-[70] above, INEOS' argument sits uneasily with the contractual rights and obligations which INEOS accepts continue after 2020 even if no amendment to Attachment F is agreed.
iii) [74], INEOS' argument also sits uneasily with the significant importance which the parties clearly attached to a change to the contractual tariff.
iv) [67] and [70], INEOS' argument would give rise to considerable contractual asymmetry in the operation of the FPA. Indeed if I am right in my conclusion that Apache's obligation to tender its "total production of Shipper's Pipeline Liquids" was not limited to the period up to 2020 (absent a revised Attachment F), then it was not clear to me whether INEOS challenges the conclusion that the concomitant of that obligation was an entitlement to pay the existing contractual tariff. Clearly, it would render the TPA a particularly one-sided bargain if Apache had either to accept any rational conditions sought by INEOS as the price of amending Attachment F, or risk being unable to transport its production ashore.
THE SECOND PRELIMINARY ISSUE
"It is anticipated that interrogation of the terms upon which INEOS acquired the FPS and its knowledge at this time will further evidence that INEOS' conduct in conditioning its consent to an increase in tariff is simply to increase profit, thus demonstrating the unreasonableness of its conduct".
CONCLUSION
i) The First Preliminary Issue: On the basis of the agreed facts and the assumption the Court has been asked to make, INEOS is acting non-contractually by withholding consent under clause 5.05(a) of the Apache Forties TPA to an amendment to Attachment F unless Apache agrees to increase the base tariff payable
ii) The Second Preliminary Issue: The terms (including as to price) on which INEOS acquired the FPS from BPEOC, and/or INEOS' knowledge at the time it agreed to purchase the FPS from BPEOC are not relevant to the assessment of whether INEOS has unreasonably refused consent under clause 5.05(a).
IN THE HIGH COURT OF JUSTICE Claim No. CL-2019-000763
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
COMMERCIAL COURT (QBD)
BETWEEN:
APACHE NORTH SEA LIMITED
Claimant
and
INEOS FPS LIMITED
Defendant
___________________________________________
TRANSPORTATION AND PROCESSING AGREEMENT
DATED 11 JANUARY 2003
SELECTED CLAUSES
___________________________________________
Contract Year means a period beginning at 0600 hours on 1 October in any Year and ending at 0600 hours on 1 October in the next succeeding Year.
Estimated Maximum Quantity or EMQ means the Shipper's estimate of the maximum quantity of Shipper's Pipeline Liquids which it wishes to be entitled to deliver to the Transfer Point on any given Day during the relevant period (Contract Year), expressed in Barrels per Day.
Firm Maximum Quantity or FMQ means the Shipper's specification of the maximum quantity of Shipper's Pipeline Liquids which it wishes to be entitled to deliver to the Transfer Point on any given Day during the relevant period Contract Year, expressed in Barrels per Day.
Forties Field means the hydrocarbon accumulation generally known as Forties Field underlying Blocks 21/09, 21/10 and 22/06 of the United Kingdom Continental Shelf.
Forties Pipeline means those parts of the Forties System comprising:
Peak Entitlement means the maximum quantity of Shipper's Pipeline Liquids which the Shipper will be entitled to specify for the FMQ.
Production Profile means that relationship between production and time as expressed in the form of a table showing flow rates per Day and the period over which such rates apply.
Shipper's Field(s) means any hydrocarbon accumulation located within Licence P.057 Block 21/9, Licence P.246 Block 21/10 and Licence P.084 Block 22/6a in which and to the extent that the Shipper has an ownership interest.
A plan showing the Shipper's Field(s) at the date of this Agreement is annexed to this Agreement as Attachment A Part II.
Shipper's Pipeline Liquids means Pipeline Liquids in which the Shipper has a beneficial interest and which:
ii) subject to the terms of this Agreement, the Shipper is entitled to have transported and processed under this Agreement.
Uncommitted Capacity means such capacity (if any) in any part of the Forties System which is not required for the transportation and handling of the total of Pipeline Liquids to be delivered pursuant to contractual commitments entered into by BP (including, without limitation, this Agreement).
Year means a calendar year ending on 31 December.
Clause 2.01
Clauses 3.01, 3.02 and 3.03
3.01 Effective date
This Agreement shall be effective on the Completion Date.
3.02 Commencement Date
Subject to BP receiving the notices required under Clause 5, the date on which BP shall commence the Services and the date of commencement of delivery of Shipper's Pipeline Liquids at the Transfer Point shall be the Completion Date or, such other date as the Parties may agree. Such date or such date as the Parties shall agree shall be the "Commencement Date".
3.03 Termination
Provided always that if the Shipper so terminates this Agreement for the reasons given in Clause 3.03(b)(ii) there shall be a surviving obligation that if at any time thereafter it wishes to export Shipper's Pipeline Liquids from the Shipper's Field(s), then it shall resume doing so pursuant to the terms of this Agreement subject to any necessary technical amendments to this Agreement including but not limited to any revised Transfer Point. After such a termination of this Agreement there shall also be a surviving obligation that if the Shipper should assign or transfer any beneficial interest owned by the Shipper in the Shipper's Field(s), then it shall novate this Agreement with such obligation to undertake the export of Shipper's Pipeline Liquids pursuant to the terms of this Agreement and BP shall not unreasonably withhold consent to such novation.
Clauses 4.01, 4.02, 4.03 and 4.05
4.01 Services
Subject to the terms of this Agreement, BP undertakes:
(d) to deliver such Raw Gas to the Shipper at the delivery points for Raw Gas which are currently located at the following flow elements ("FEs") as specified by BP at the Kerse of Kinneil: FE304, FE305, FE313, FE318, FE404, FE405, FE413 and FE418.
The services specified in this Clause 4.01 (a) - (e) shall be referred to as "the Services". In the event that the Shipper requires gas processing services in respect of Shipper's Pipeline Liquids, BP and the Shipper shall meet and in good faith negotiate the terms and conditions upon which such gas processing service would be provided. Any terms and conditions offered to the Shipper by BP in respect of such gas processing services shall be no less favourable than those terms and conditions contained within the new field transportation and processing agreement either published at www.fortiespipeline.com or, if not so published, otherwise generally offered as at the time the Shipper makes its request to BP for the provision of the gas processing services.
4.02 Provision of the Forties System
For the purposes of this Agreement, BP shall provide, maintain, repair and operate throughout the continuation of this Agreement those parts of the Forties System necessary to fulfil its obligations hereunder, provided that if at any time and for any reason BP is unable to fulfil its obligations hereunder and in order to resume its performance thereof it would have to rebuild, repair, re-configure, rectify or reinstate any part of the Forties System, it shall be under no obligation to rebuild, repair, reconfigure, rectify or reinstate such part or to resume such performance if to do so would, in the reasonable opinion of BP, be uneconomic to BP.
4.03 Other Pipeline liquids
BP shall retain absolute discretion in respect of the acceptance or otherwise, and the conditions of any such acceptance into the Forties System, of Pipeline Liquids other than Shipper's Pipeline Liquids. Acceptance of Pipeline Liquids other than Shipper's Pipeline Liquids shall be without prejudice to the Shipper's rights under this Agreement.
4.05 Temporary Alternative Arrangements
To the extent BP fails for reasons of Force Majeure to accept Shipper's Pipeline Liquids into the Forties System for any reason not caused by the Shipper then, notwithstanding Clause 2, the Shipper may, after giving written notice to BP, make temporary alternative arrangements for the disposal of those Shipper's Pipeline Liquids. The Shipper shall use reasonable endeavours to ensure that any such temporary arrangements can be terminated promptly without undue cost or liability following receipt of notification from BP that it is able to resume acceptance of Shipper's Pipeline Liquids. As soon as BP is able to reasonably predict the date on which it expects to be able to resume acceptance of Shipper's Pipeline Liquids it will notify the Shipper of that date. On receipt of such notice the Shipper shall immediately take all necessary steps to terminate its alternative temporary arrangements in accordance with the terms and conditions of such alternative arrangements, provided that in no event shall the Shipper be obliged to incur termination costs or liabilities in connection with any such termination. The Shipper shall immediately on termination of such arrangements recommence delivery of Shipper's Pipeline Liquids under this Agreement
Clauses 5.01, 5.02, 5.03, 5.05, 5.06, 5.07
5.01 Firm Maximum Quantity
Subject to the provisions of this Agreement, the maximum quantity of Shipper's Pipeline Liquids that may be tendered for delivery of any Day at the Transfer Point will be the FMQ applicable during the Contract Year in question. Such FMQ shall not exceed a Peak Entitlement of seventy-five thousand (75,000) Barrels per Day. The expected Production Profile for the Shipper's Pipeline Liquids is set out in Attachment F.
On the Completion Date the Shipper shall notify BP of the FMQ for the remainder of the Quarter in which the Commencement Date occurs and each Quarter thereafter in the Contract Year in which the Commencement Date falls and for each Quarter of the following Contract Year (for purposes of the first Contract Year the "Subsequent Contract Year"). At the time of giving such notice the Shipper shall also notify BP of its estimated maximum quantity for each Quarter of all subsequent Contract Years. Thereafter, the FMQ applicable during each Quarter will be determined in accordance with notices given by the Shipper on or before 30th September in each Year. The notices will specify an FMQ for each Quarter of the Contract Year commencing on the 1st October after service of the notice (the "Next Contract Year"), an FMQ for each Quarter of the next following Contract Year (the "Subsequent Contract Year") and an EMQ (estimated maximum quantity) for each Quarter of all subsequent Contract Years during the anticipated duration of this Agreement. Each notice shall comply with the following requirements:
(a) the FMQ for each Quarter of the Next Contract Year must be the same as was nominated for the corresponding Quarter of the Subsequent Contract Year in the immediately preceding notice; and
5.02 Estimated Average Daily Production
5.03 Monthly nominations information
Not later than the twentieth (20th) Day of each Month, the Shipper shall provide to BP the following:
5.06 Additional and Spot Quantities
5.07 Information
The Shipper shall provide all relevant data and information as reasonably required from time to time hereunder in a timely manner upon the request of BP to the extent such data and information is reasonably required to enable BP to provide the Services hereunder.
Clause 7.01, 7.02, 7.04, 7.05
7.01 Transportation Tariff
For the Services the Shipper shall pay to BP a tariff (Tr) at the rate of sixty pence sterling (£0.60) per Barrel of Shipper's Pipeline Liquids delivered in each Month at the Transfer Point in accordance with this Agreement.
7.02 Escalation
The tariff and the fee specified in Clause 7.01 shall be adjusted effective from the commencement of each Quarter for application during each Month of the Quarter in question by application of the following formula:
T = (To) x P2
P1
where:
T is the tariff in pounds sterling applicable for each Month of the Quarter in question per Barrel of Shipper's Pipeline Liquids;
P1 is the "Index numbers of producer prices - Price Index Number of Output: home sales - Output of manufactured products" as contained in Table Number 18.7 of the Central Statistical Office Monthly Digest of Statistics (the "Producer Price Index"), avenged for the Fourth Quarter 2002;
P2 is the Producer Price Index, averaged for the Quarter preceding the Quarter in question.
7.04 Send-or-pay
For avoidance of doubt in the last Contract Year, the Tariff Minimum Quantity shall be 65% of the sum of the daily FMQs applicable during such Contract Year pursuant to Clause 5.01 as may be adjusted from time to time pursuant to the terms of this Agreement.
7.05 BP's operating cost option
7.06 Free barrels
(a) A Free Barrel accrues to the Shipper in respect of any Barrel which:
(i) has been nominated under Clause 5.03, up to a maximum of the FMQ for the relevant Month; and
(ii) the Shipper was ready willing and able to deliver, in accordance with this Agreement; and
(iii) was not accepted by BP as a consequence of its failure to act as a Reasonable and Prudent Operator; and
(iv) has not previously been deducted under this Clause 7.06.
Clause 8.01
8.01 Invoicing and payment of tariffs
Clause 9.04
Clause 11.01
11.01 Reduction of throughput entitlement
Where in Barrels of Pipeline Liquids per Day:
A is the available capacity in the Forties System during a throughput restriction.
B is the capacity required in the Forties System to provide Shell and Esso their combined entitlement to Forties Blend allocated in respect of Pipeline Liquids from the Forties Field in the period concerned.
C is the Shipper's entitlement to deliver Shipper's Pipeline Liquids under Clause 5.01.
D is the Total User Nomination in the Forties System during the period concerned after making reductions referred to in Clauses 11.01(a)(i) and 11.01(a)(ii).
18.01 Notice by BP
BP shall, upon giving at least twenty four (24) Months' prior written notice to Shipper, have the right on or after 1 January 2020 to abandon or remove all or part of the Forties System necessary for BP to fulfil its obligations under this Agreement, and to terminate this Agreement accordingly.
18.02 Good faith discussions
If BP gives notice pursuant to Clause 18.01 the Parties shall meet to discuss in good faith alternative means of enabling the Shipper to safeguard its interests, including the possibility of the Shipper, either alone or with others, assuming ownership and/or operatorship of all or part of the Forties System on reasonable terms and conditions.
18.03 Shipper's right to terminate
If BP gives notice pursuant to Clause 18.01 then the Shipper may, by giving BP not less than twelve (12) Months' prior notice in writing, terminate this Agreement.
ATTACHMENT F
PRODUCTION PROFILE OF SHIPPERS PIPELINE LIQUIDS
[Data as supplied by the Shippers (DATE)]
Year |
Quarter |
Volume (MSm3) |
Volume (mbd) [1] |
Booking |
2003 |
1Q |
|
|
FMQ |
2Q |
|
|
FMQ | |
3Q |
|
|
FMQ | |
4Q |
|
|
FMQ | |
2004 |
1Q |
|
|
FMQ |
2Q |
|
|
FMQ | |
3Q |
|
|
FMQ | |
4Q |
|
|
FMQ | |
2005 |
1Q |
|
|
EMQ |
2Q |
|
|
EMQ | |
3Q |
|
|
EMQ | |
4Q |
|
|
EMQ | |
2006 |
1Q |
|
|
EMQ |
2Q |
|
|
EMQ | |
3Q |
|
|
EMQ | |
4Q |
|
|
EMQ | |
2007 |
1Q |
|
|
EMQ |
2Q |
|
|
EMQ | |
3Q |
|
|
EMQ | |
4Q |
|
|
EMQ | |
2008 |
1Q |
|
|
EMQ |
2Q |
|
|
EMQ | |
3Q |
|
|
EMQ | |
4Q |
|
|
EMQ | |
2009 |
1Q |
|
|
EMQ |
2Q |
|
|
EMQ | |
3Q |
|
|
EMQ | |
4Q |
|
|
EMQ | |
2010 |
1Q |
|
|
EMQ |
2Q |
|
|
EMQ | |
3Q |
|
|
EMQ | |
4Q |
|
|
EMQ | |
2011 |
1Q |
|
|
EMQ |
2Q |
|
|
EMQ | |
3Q |
|
|
EMQ | |
4Q |
|
|
EMQ | |
2012 |
1Q |
|
|
EMQ |
2Q |
|
|
EMQ | |
3Q |
|
|
EMQ | |
4Q |
|
|
EMQ | |
2013 |
1Q |
|
|
EMQ |
2Q |
|
|
EMQ | |
3Q |
|
|
EMQ | |
4Q |
|
|
EMQ | |
2014 |
1Q |
|
|
EMQ |
2Q |
|
|
EMQ | |
3Q |
|
|
EMQ | |
4Q |
|
|
EMQ | |
2015 |
1Q |
|
|
EMQ |
2Q |
|
|
EMQ | |
3Q |
|
|
EMQ | |
4Q |
|
|
EMQ | |
2016 |
1Q |
|
|
EMQ |
2Q |
|
|
EMQ | |
3Q |
|
|
EMQ | |
4Q |
|
|
EMQ | |
2017 |
1Q |
|
|
EMQ |
2Q |
|
|
EMQ | |
3Q |
|
|
EMQ | |
4Q |
|
|
EMQ | |
2018 |
1Q |
|
|
EMQ |
2Q |
|
|
EMQ | |
3Q |
|
|
EMQ | |
4Q |
|
|
EMQ | |
2019 |
1Q |
|
|
EMQ |
2Q |
|
|
EMQ | |
3Q |
|
|
EMQ | |
4Q |
|
|
EMQ | |
2020 |
1Q |
|
|
EMQ |
2Q |
|
|
EMQ | |
3Q |
|
|
EMQ | |
4Q |
|
|
EMQ |
[1] : Estimated Average Daily Flows of Shippers Pipeline Liquids averaged over the Quarter in question
Note 1 : Estimated Average Daily Flows of Shippers Pipeline Liquids averaged over the Quarter in question [Back]