QUEENS BENCH DIVISION
COMMERCIAL COURT
In the matter of the Arbitration Act 1996
B e f o r e :
(sitting as a Judge of the High Court)
____________________
UNION MARINE CLASSIFICATION SERVICES LLC |
Applicant |
|
- and - |
||
(1) THE GOVERNMENT OF THE UNION OF COMOROS (2) BRUCE HARRIS |
Respondent |
____________________
John Robb (instructed by Clyde & Co. LLP, Solicitors) for the First Defendant
The Second Defendant did not appear and was not represented
____________________
Crown Copyright ©
INTRODUCTION
BACKGROUND AND PROCEDURAL HISTORY
"in the result… my conclusion is clearly that the Government was not entitled to terminate the Agreement, and accordingly that it was in fact the Government which was in repudiatory breach itself. (So far as I know, however, Union Marine have not accepted that as such.)"
"… I am unable to find that, on the balance of probabilities, Union Marine did not meet their payment obligations under the Agreement. This does not mean that my conclusion is that they did fulfil those obligations: as the parties' lawyers at least will appreciate, I would have had to be persuaded that it was more likely than not that Union Marine were in breach… And the evidence is not sufficiently weighty to enable me to come to that conclusion. Moreover, I am far from persuaded that there was here any case of bribery."
"Union Marine ceased making the minimum US$11,000 monthly payments under… the contract after August 2011, that this was a breach of that Article and that Union Marine continued to be in breach in this respect until 17 April 2012. I do not, however, consider that this entitled the Government to terminate the contract as it did on that date, but it is entitled to damages for this breach to be assessed."
He went on to further hold that Comoros was entitled to an account and damages as claimed in paragraph 77 of its counterclaim.
"We refer to Clyde & Co.'s email below dated 22 June. In this email Clyde & Co. have asked for the Arbitration reference to proceed further and have asked for the tribunal to make three declarations in their further award. The Claimant by our email of 20 June have also sought two declarations. This being so, there is no question of your jurisdiction being in issue. We would be grateful if you would give appropriate directions for the purpose of proceedings with the declarations sought by both sides. No doubt you will keep in mind that you had heard extensive oral evidence from both sides over the period of two days in respect of the accounting issues.
"These repudiatory breaches of contract by your client have been accepted by the government's unequivocal acts and statements since October 2012 and throughout the arbitration proceedings by which the Government has made clear that it considers the contract to have been terminated."
THE PRESENT ISSUES: INTRODUCTION
"Serious irregularity means an irregularity of one or more of the following kinds which the court considers has caused or will cause substantial injustice to the applicant-
(a) failure by the tribunal to comply with section 33 (general duty of tribunal);
(b) the tribunal exceeding its powers (otherwise than by exceeding its substantive jurisdiction: see section 67…."
(1) as a general point affecting all three bases, the arbitrator had no power to decide the question of termination or not, at all. It was not part of Union Marine's original claim, was not up for decision on the First Award, nor did it flow from the decision of the Court of Appeal. If that point was correct, then there would have been unfairness and/or excess of powers amounting to a serious irregularity within s68 (2) (a) and/or (b); ("Issue 1");(2) as an alternative, there was no basis for the arbitrator to find that there had been non-payment by Union Marine under the Contract and if this point was correct, then the first and third particular bases for his decision were vitiated. This was much more than a mere challenge to an arbitrator's finding of fact because, according to Union Marine, the arbitrator simply ignored plain evidence to the contrary and reversed the burden of proof in a way which was unfair and contrary to s68(2) (a) and/or (b); ("Issue 2");
(3) further, there was no basis for finding that the claim made by Union Marine for damages for the loss of the entire Contract over 25 years could amount to an acceptance and the decision here was a serious irregularity within the meaning of s68 (2) (a) and/or (b); ("Issue 3")
(4) further, Union Marine had suffered "substantial injustice" within the meaning of s68 (2); ("Issue 4");
(5) further, if there had been any power to decide the question of termination at all, that question must now be remitted and in the circumstances, to a new arbitrator in place of Mr Harris, pursuant to section 24 of the Act; ("Issue 5").
ISSUE 1: POWER TO DECIDE THE QUESTION OF TERMINATION
Ad hoc agreement
Issue Estoppel
Improper Approach to determination of the non-payment issue
ISSUE 2: NON-PAYMENT BY UNION MARINE
The Law
The Evidential Point
(1) Comoros stated the fact of non-payment in the table set out in paragraph 12 for the period after August 2011;(2) it repeated the fact of non-payment in paragraph 13 (iii) which contained footnote 5;
(3) that footnote referred to the fact that there had been evidence at the First Arbitration hearing of the payment of US$73,597 which Union Marine had said was in fact in compliance with its obligation to pay a guaranteed minimum of US$11,000 per month up to 17 April 2012; that was disputed by Comoros and of course the arbitrator found that there had been non-payment up to that date;
(4) at paragraph 22, Comoros stated as follows:
"… It is submitted that UM's second Notice of Termination served on 10 November 2014 was unquestionably justified. Since the Tribunal does not have the benefit of full evidence and submissions relating to the period after 17 April 2012 it is sufficient for present purposes to note that UM has not made any payments to Comoros under Articles 4-5 of the Contracts in 17 April 2012. This is despite it being under an obligation… to pay…US$11,000 per month. Its unexplained refusal to do so between April 2012 and November 2014… is in itself a sufficiently serious breach to justify Comoros' termination of the Contract on that date".(5) footnote 10 makes it clear that the reference to the period "after 17 April 2012" was in particular concerned with the allegation of bribery itself relied upon in the 10 November Further Notice as well as non-payment. And so, the sense of the second sentence of paragraph 22 was not so much that there was insufficient evidence on the question of non-payment, but rather that there was incomplete evidence on the bribery point, but this did not matter because there was the non-payment. Footnote 11 effectively repeated the earlier footnote 5.
".. Tribunal could not have considered that the contract was lost as a result of the Claimant accepting repudiatory breach on 17 April 2012 because the tribunal had made a clear finding in its award [i.e. in paragraph 94]… Similarly the Tribunal did not anywhere in the award say that the alleged failures (which are strenuously denied by the Claimant) to pay US$11,000 per month was a good reason because of which the Government could terminate the Claimants contract."
"Bare denials in defence and subsequent submissions in response to an allegation will not be acceptable. If an allegation is denied, reasons must be given and if appropriate a positive contrary case put forward."
Union Marine did not do so here.
"19. … The Government contended that Union Marine effectively accepted the Government's repudiatory breach on or shortly after 17 April 2012 by virtue of Union Marine's failure to pay any sums under Article 4 of the contract. That, the Government said, amounted to an unambiguous election by Union Marine to treat itself as discharged from its obligations. This was not an argument that Union Marine endeavoured to meet in their reply submissions and having considered the authority… I am of the view that the Government is right on this point, although it seems to me that a couple of months must be allowed following 17 April 2012 before, looking at the position objectively, it could be said that Union Marine had elected to treat themselves as discharged.…
24. The Government had a further alternative, namely that Clyde & Co.'s notice of termination of 10 November 2014 was plainly justified and brought an end to the contract. That too seems to me correct… And Zaiwalla & Co. for Union Marine could only say in response to this point that it was accepted that I did not have the benefit of full evidence and submissions for the period after 17 April 2012 and could not invite any such further evidence. But it is clear (and it was not denied) that Union Marina had not paid the $11,000 per month since April 2012. That in my view was a sufficiently serious breach to justify the Government terminating in November 2014 if the contract had not, contrary to my view, already come to an end.
(1) any complaint about his reasoning here is far removed from the sort of very rare residual case concerning evidence that might fall within s68 (2) (a), and indeed(2) it is difficult if not impossible to see how the arbitrator could seriously have found otherwise.
Excess of powers or unfairness in respect of the non-payment findings
(1) paragraph 1 (c) of Schedule 2 to the LMAA Terms states that written submissions must be accompanied by paginated supporting documentation relevant to the issues between the parties, other than documents which accompanied previous submissions;(2) in addition the arbitrator had the well-known extensive powers in respect of the admission of evidence in various forms in any event, pursuant to section 34 (1) AA (2) (f) of the Act. In particular it was for him to decide whether to apply the strict rules of evidence (or not) as to the admissibility, relevance or weight of any material sought to be tendered.
ISSUE 3: THE EFFECT OF THE DAMAGES CLAIM MADE BY UNION MARINE
"that does not seem to me to answer the point. The Government did not and never has "reinstated" the contract: on the contrary. Accordingly, even if I am wrong that Union Marine's failure to pay the monthly $11,500 [it should be $11,000] amounted to an acceptance of the Government's repudiation, I conclude that the claim advanced by Union Marine had that effect."
ISSUE 4: SUBSTANTIAL INJUSTICE
(1) Union Marine could not do anything with it. Unlike the successful Plaintiff in the well-known case of White and Carter v McGregor [1962] AC 413, Union Marine could not perform the Contract without the active assistance and co-operation of Comoros which all the evidence shows has not been and will not be forthcoming;(2) as an alternative, Mr Brindle QC suggested that there was value even in the declaration itself since it would help Union Marine's reputation in some way. But I cannot see how, if Union Marine could not go on to perform the Contract alone. Indeed, to publicise that there was a binding contract still in place and then not to be able to deliver under it would surely be much worse from Union Marine's point of view than not mentioning it now at all;
(3) given the history of non-payment now extending over some 6 years, Comoros would be entitled in any event to serve a yet further notice of termination which would be incontrovertibly valid.
ISSUE 5: REMOVAL OF THE ARBITRATOR
CONCLUSION