QUEEN'S BENCH DIVISION
COMMERCIAL COURT
IN THE MATTER OF AN ARBITRATION CLAIM
Strand, London, WC2A 2LL |
||
B e f o r e :
Sitting as a Judge of the High Court
____________________
Erdenet Mining Corporation LLC |
Claimant |
|
- and - |
||
ICBC Standard Bank PLC Standard Bank of South Africa Limited London Forfaiting Company Limited |
Defendants |
____________________
David Joseph QC, Edward Brown and Stephen Donnelly (instructed by Clifford Chance LLP) for the Defendants
Hearing dates: 27th April 2017
____________________
Crown Copyright ©
Sir Jeremy Cooke:
Introduction
(1) Claim CL-2016-000629 is a claim arising out of an LCIA arbitration between the first three named defendants which claimed against EMC and Just Group LLC ("Just") as respondents. The arbitration agreement in dispute was contained in a written Surety and Undertaking Agreement dated 9th July 2009 ("the SUA") purportedly signed by Mr Ganzorig, the General Director of EMC. Under the SUA, EMC guaranteed and agreed to indemnify the Funding Costs and Relevant Obligations of Just in an underlying trade finance facility of the same date ("the 2009 Facility") as subsequently amended. Mr Thomas H. Webster was appointed as presiding arbitrator of the tribunal. Mr Christopher Lau SC and Mr Dominic Underhill were the co-arbitrators.(2) Claim CL-2016-0000630 is a claim arising out of an LCIA arbitration between the first, second and fourth named defendants which claimed against EMC and Just as respondents. The relevant arbitration agreement in dispute was contained in a written facility agreement dated 5th August 2010 ("the Original 2010 Facility") pursuant to which EMC guaranteed and agreed to indemnify the obligations of just in an underlying trade finance facility. In that arbitration, Mr Thomas H. Webster was the sole arbitrator.
(1) They declared that EMC was bound by the SUA and the Original 2010 Facility and by the arbitration clauses therein.(2) In the arbitration under the SUA they found EMC liable in the sum of USD $36 million plus interest thereon, the amount of which was to be determined.
(3) The tribunal in the Original 2010 Facility arbitration found EMC liable in the sum of USD $14,988,425.60 plus interest thereon with the amount of such interest to be determined.
(4) The tribunals reserved jurisdiction in respect of Standard's claims in tort against EMC (which came in by late amendment) and the issues of interest and costs.
"The court may order that any money payable under the award shall be brought into court or otherwise secured pending the determination of the application … and may direct that the application … be dismissed if the order is not complied with."
The Criteria to be applied under section 70(7) of the Act
"This is a tool of great value, since it helps to avoid the risk that while the appeal is pending, the ability of the losing party to honour the award may (by design or otherwise) be diminished."
(1) In most cases there will be a threshold requirement that the party making the section 70(7) application demonstrates that the challenge to the jurisdiction is flimsy or otherwise lacks substance.(2) As a general principle the court should not order security unless the applicant can demonstrate that the challenge to the award will prejudice its ability to enforce the award. Often this will entail the applicant demonstrating some risk of dissipation of assets, although there may be other ways in which enforcement could be prejudiced.
(1) Standard's applications for security were premised upon the Tribunal's findings being presumed, by the court, to be valid but that this approach was wrong in law on a challenge under section 67, where the court must come to the matter afresh and without assuming that the arbitral award is right or wrong. In this submission as to the approach of the Court, EMC is undoubtedly correct.(2) As was obvious from the lengthy nature of the arbitration proceedings involving three or four weeks of lengthy days' hearings with extensive written submissions, the underlying dispute is large and complex, raising a plethora of issues of fact, law and construction, a number of which turned on oral evidence. It was said that the court was not in a position, in advance of trial and full argument to conclude that the challenge lacked substance. It was said that this was particularly the case where there was a possibility of further evidence being made available to the court which was not available to the arbitrators.
(3) Additional evidence and the difference in the court's approach to such evidence, as compared with the arbitrators, could make all the difference between the decision of the court and the decision of the arbitrators. Additional evidence could be forthcoming in respect of production of documents from MNIA, or its successor investigator which could substantially affect the issues.
(4) Further, expert evidence on Mongolian law would be available in the shape of oral testimony with cross-examination whereas before the arbitrators it was in the form of reports only.
(5) Since the arbitrators adopted the IBA rules of evidence and the court would adopt the more stringent requirements of the English rules of procedure requiring any witness to be cross-examined whose witness statement was challenged and for a party's case to be fully put to witnesses, particularly where there were serious allegations of fraud or otherwise, no conclusions could be drawn from the findings of the arbitrators.
(6) This was a complex case requiring extensive investigation of the facts as could be seen from the length of time taken in arbitration and the number of witnesses who gave evidence before the Tribunal. A range of factual issues arose relating to the prior relationship between the parties, allegedly stretching back to 2000, and, in particular, the structure, purpose and execution of a prior loan facility, extended by Standard in 2007 to Just, with a guarantee from EMC. The negotiation of the relevant facilities took place through the intermediary of Just, including the execution of the relevant documents. There was very little dealing direct between Standard and EMC. The structure and purpose of the facilities was an issue with a particular focus on whether or not EMC was a beneficiary of the overall arrangements and whether there was, as described by the arbitrators, a "symbiotic relationship".
(7) It was clear that Just had misappropriated the loan facilities and these had not in fact devolved to the benefit of EMC in any way. The motivation of Mr Ganzorig, Mr Munkhjargal and Mr Amarbat required exploration in relation to their part in the execution and operation of the agreements upon which Standard relied.
(8) There were difficult questions of construction which arose as to the nature of EMC's obligations, namely whether they were primary or secondary, and whether any liability fell on EMC in relation to amendments and increases which it had not specifically signed or to which it had not specifically consented.
(9) There were a large number of issues under English and Mongolian law including the definition and effect in law of a forgery, questions of corporate capacity, actual and ostensible authority of EMC's officers, agreements by conduct and the effect of section 4 of the Statute of Frauds Act, estoppel by convention, ratification of a forgery and the rule in Holme v Brunskill.
(10) In circumstances where there was handwriting evidence that over 100 questioned signatures were not genuine, questions arose as to why such forgeries existed if EMC had agreed to the Facilities. It was said that this had not been properly explained by Standard and in EMC's written Reply Submissions, it contended that there were 13 unanswered questions. (Many of those questions related to amendments to the facilities which were not held to be binding on EMC, so do not in fact fall to be taken into account).
(11) No inferences should be drawn, it was said, from the absence of disclosure of much internal correspondence of EMC relating to the facilities or the failure to produce the Original SUA. The evidence was that MNIA had seized many documents and had prevented access to EMC's server which meant that historic documents could not be produced.
Is the challenge flimsy or lacking in substance?
(1) The SUA Claim Form"4. By the Award, the Tribunal concluded that it had jurisdiction over the Claimant on the basis that: (1) Mr Ganzorig and Mr Munkhjargal signed the Original SUA on or about 7 July 2009, which included the arbitration agreement at Clause 27.2 (Award, paragraphs 212, 236, 276, 307); (2) the Claimant had legal capacity and Mr Ganzorig had legal authority (actual and ostensible) to enter into the Original SUA, and arbitration agreement at Clause 27.2 (Award, paragraphs 332, 264, 371, 412).5. Those conclusions were wrong for the reasons set out by the Claimant in the arbitration. In particular, but without prejudice to the generality of the foregoing and the full scope of the issues arising which will (as set out below) require pleading:(1) The Claimant did not execute the Original SUA and the signatures of Mr Ganzorig and Mr Munkhjargal appearing in the Original SUA had been forged or fraudulently obtained (and therefore non est factum and/or mistake applies);(2) The Claimant did not intend to be and is not bound by the Original SUA or the arbitration agreement contained in Clause 27.2;(3) The Claimant did not have legal capacity to enter into the Original SUA including the arbitration agreement (which raises issues of Mongolian law, being foreign law and therefore raising issues of fact);(4) Mr Ganzorig had no actual or ostensible legal authority to enter into the Original SUA on behalf of the Claimant including the arbitration agreement (which raises, to the extent applicable, Mongolian law, being foreign law and therefore raising issues of fact)."(5) The 2010 Facility Agreement Claim Form
"Grounds4. By the Award, the Tribunal concluded that it had jurisdiction over the Claimant on the basis that: (1) the Claimant concluded the Original 2010 Facility Agreement (and ancillary agreements) by conduct (Award paragraphs 349-50); (2) the Claimant had legal capacity and Mr Ganzorig had legal authority (actual and ostensible) to bind the Claimant by conduct to the Original 2010 Facility Agreement and the arbitration agreement at clause 39.2 (Award paragraphs 305, 331, 441, 474-477, 492, 506-507).5. Those conclusions were wrong for the reasons set out by the Claimant in the arbitration. In particular, but without prejudice to the generality of the foregoing and the full scope of the issues arising which will (as set out below) require pleading:(1) The Claimant did not by conduct bind itself to the Original 2010 Facility Agreement including the arbitration agreement in Clause 39.2;(2) Mr Ganzorig had no actual or ostensible legal authority to approve the conduct that was determined to have bound the Claimant to the Original 2010 Facility Agreement including the arbitration agreement at Clause 39.2 (which raises, to the extent applicable, Mongolian law, being foreign law and therefore raising issues of fact);(3) The Claimant did not have legal capacity to enter into the Original 2010 Facility Agreement including the arbitration agreement (which raises issues of Mongolian law, being foreign law and therefore raising issues of fact)."
"EMC has launched a dispute in court regarding this issue and the relevant preparations are being made. In reality, EMC is in the situation of losing [the case]. As of today a final decision to pay USD $51 million was issued. Loan interest, forfeiture, late fees and fees to the law firm may be payable in addition thereto."
Grounds 1 and 2
The SUA
(1) No original copy of the Short Form SUA has been produced by EMC despite the evidence of its witnesses that a copy was retained.(2) A photocopy of the Short Form SUA was produced by EMC consisting of 27 pages, followed by the signature page which is numbered 40, that being the number of the signature page on the Original SUA. That number appears immediately below Mr Munkhjargal's signature but he states that he did not notice it.
(3) The Short Form SUA included clause 18 which had the heading "Non-Financial Guarantee". It provided that "EMC shall not be obliged to guarantee against any losses for agent or arising from or in connection with any failure by Just under this agreement. EMC does not take any financial responsibilities under this Agreement." The effect of this would of course be to negate a fundamental obligation which Standard required EMC to undertake in replacement of the like obligation that it had undertaken for the previous facilities for Just which were being replaced. Furthermore it remained entitled "Suretyship and Undertaking Agreement", a wholly inappropriate title in the light of its contents.
(4) Mr Ganzorig's evidence that the Short Form SUA was in itself a sham is significant and the contemporary documents render his version of events surrounding its production so improbable as to defy acceptance.
(5) The photocopy of the Short Form SUA was first mentioned by EMC four years after the date of its apparent signature and after the arbitration proceedings began, in July 2014. In the meantime the replacement facility for the 2007 Facility had been operated.
(6) The Short Form SUA contains a multiplicity of changes from the original SUA of a kind which could only have been drafted by someone with extensive understanding of English and of loan facility documentation. On his own evidence, Mr Munkhjargal does not qualify for this description and nor does Mr Batkhuu.
(7) Additionally, supporting security documentation in the form of a Short Form Security Assignment and the Short Form EMC TRAC was also drafted with detailed changes from the original security assignment. This too would have required detailed understanding of English legal documents of this kind. None of the alleged participants in the redrafting had any real working knowledge of the English language, let alone detailed knowledge of financial documents. The work required for these amendments would have been considerable even for such a qualified person.
(8) Funds were advanced on 9th July 2009 following transmission by Just on 7th July to Standard's lawyers of both the cover and signature pages of the Original SUA bearing Mr Ganzorig's and Mr Munkhjargal's signatures. The Original SUA had not been stamped or sealed at that point. These were then sent by Standard's lawyers to Standard on the same day. The sums advanced to Just were advanced as a replacement facility for the 2007 Facility previously in place.
(9) As reflected in an email of 29th July 2009, Mr Mahoney of Standard's lawyers spoke to Mr Munkhjargal about obtaining a stamped version of the documents and Mr Munkhjargal said that this would only be possible after his return from holiday in August. There was no suggestion that the email was not authentic. A cover page of the Original SUA was dated 8th July 2009 and the stamp on it was dated 20th August 2009.
(10) EMC had no pleaded case as to when the Short Form SUA was signed and, as indicated above, produced no original of it. In cross-examination Mr Munkhjargal stated that it was signed on 20th August 2009 but there is no documentary evidence to support that and it is inconsistent with the contemporaneous documentation which shows genuine signatures on 7th July.
(11) The evidence of EMC's witnesses as to stamping and registration of the document with the legal department was also inconsistent with the contemporaneous documents. If Mr Batkhuu's evidence was accurate, every version of the original SUA should have received a stamp on the first page and a stamp on the signature page since Mr Batkhuu stated that it was only after he stamped both of those pages that he presented the Short Form SUA to Standard. The cover page of the Original SUA, however, has neither the stamp on the first page nor the stamp on the signature page and the history shows the stamp being added later.
(12) Standards's witnesses gave evidence of the meeting on 25th August 2010 where the operation of the original SUA and the Original 2010 Facility were the subject of discussion. Mr Munkhjargal and Mr Amarbat maintained that the meeting did not happen in the face of contemporaneous documents showing that it did and later documents relating to a meeting of 24th May 2013 show that Mr Amarbat at this later meeting confirmed the August 2010 meeting.
(13) On 4th September 2010 Mr Munkhjargal confirmed the execution of the amendment agreement to the original SUA and attached the execution version of it which incorporated all of the material terms of the original SUA and did not incorporate clause 14 of the Short Form SUA.
(14) Standard released the security for the 2007 Facility and in July 2009, security was provided to the 788 account in respect of the new facility.
(15) EMC operated the 788 account with transfer instructions from Mr Amarbat, that account being the security account.
(16) Whilst it was EMC's case that it had been deprived of relevant documents by an investigation by the Mongolian National Investigation Agency, which had seized documents and computers and would not allow EMC access to them in the course of the arbitration and that EMC did not have access to its server in order to produce historic documents, the fact remains that a large number of historic documents were disclosed but no operational Short Form SUA. In a witness statement served two days prior to the hearing of this application, a solicitor acting for EMC stated that the investigation had been taken over by the Independent Authority Against Corruption in September 2016 and in consequence, the confiscated material may become available. The IAAC allowed EMC to review documents in the former's possession and to take copies over a period of two days in March of this year. EMC estimated that it was provided with 42 bundles of materials (approximately 10,500 pages) for review but permission was not being given by the authority for disclosure of any documents to EMC's solicitors. There is however no suggestion that the original Short Form agreement was seen or is available.
The Original 2010 Facility Agreement
(1) How EMC paid off the $27 million in EMC Promissory Notes that were returned to EMC in August 2010.(2) Why the original 2010 Facility Agreement was performed for over 2 years by Mr Amarbat with tens of millions of dollars being paid into the security account numbered 148.
(3) Why no objection was raised to the Facility Agreement at any time prior to May 2013.
"344. Without repeating the discussion under Issue 1(A):
(1) EMC and in particular Mr Ganzorig assumed primary liability to pay $27 million to the holder of the EMC Promissory Notes to assist Just financially. To ensure that Just had the benefit of the EMC Promissory Notes, it was essential that Just obtain financing for them.
(2) EMC represented by Mr Ganzorig and Mr Amarbat signed the 2010 Term Sheet with the revised delivery schedule to MH to induce Standard to prepare and conclude the Original 2010 Facility Agreement.
(3) EMC assigned the proceeds of the Milliford Contract to Standard as security for the Original 2010 Facility Agreement to be paid to the 148 Account and Milliford actually paid $136 million to the 148 Account.
(4) EMC received the EMC Promissory notes from Savings and Golomt Bank after those banks had received the $27 million proceeds of the Original 2010 Facility Agreement. Therefore EMC received a direct benefit of the proceeds of the Original 2010 Facility Agreement.
(5) On 25 August 2010, Messrs Amarbat and Munkhjargal confirmed that EMC had entered into the Original 2010 Facility Agreement.
(6) EMC by Mr Amarbat performed the Original 2010 Facility Agreement by giving instructions to repay principal and interest under the agreement from September 2010 to November 2012. On 23 June 2011 for example Mr Amarbat sent a letter to Standard stating in relevant part:
Ref. Funds Transfer from EMC's account no. 100099788 to EMC's account no. 1001135148
We refer to the Facility Agreement of US$27,000,000 dated 05 August 2010.
Please be requested to process the following instructions:
[…]
ii. Debit US$ 1,420,036.96 from account no 1001135148 to settle the principal and interest due on 6 July, 2011 on the above facility.
(7) Until May 2013, EMC not only performed the Original 2010 Facility Agreement but also never objected to its terms. Mr Amarbat would not have operated a facility without Mr Ganzorig's approval. The only conclusion of an honest sensible businessman would be that there was a contract in the terms of the Original 2010 Facility Agreement.
(8) Unlike in the Baird case, there is no sensible explanation for these actions other than that the parties wished to enter into contractual relations on the terms of the Original 2010 Facility Agreement. Moreover, it is obvious that the parties would not have acted as they did if they did not understand that they were bound by the Original 2010 Facility Agreement."
Conclusion on Grounds 1 and 2
Grounds 3 and 4
"Unless otherwise agreed by the parties, an arbitration agreement which forms or was intended to form part of another agreement (whether or not in writing) shall not be regarded as invalid, non-existent or ineffective because that other agreement is invalid, or did not come into existence or has become ineffective, and it shall for that purpose be treated as a distinct agreement."
"Where the arbitration agreement is set out in the same document as the main contract, the issue whether there was an agreement at all may indeed affect all parts of it. Issues as to whether the entire agreement was procured by impersonation or by forgery, for example, are unlikely to be servable from the arbitration clause."
Prejudice in the enforcement of the Award
(1) There is no realistic prospect of enforcing the Awards in Mongolia until the challenges in this Court have been resolved.(2) EMC has no assets in the UK or in any jurisdiction subject to the Regulation.
(3) The audit reports for EMC's accounts between 2009 and 2013 were qualified in every year on a number of different issues including the provision of insufficient information relating to the value of assets.
(4) The audit firm changed twice between 2009 and 2013.
(5) The carrying amount of certain assets had been revalued upwards in 2009, 2010, 2011 and 2013 in circumstances where there had been a material decline in net assets between 2011 and 2013 and net current liabilities in 2013 of $150 million.
(6) EMC has filed no accounts since 31st December 2013 contrary to Mongolian law and has failed to answer requests for financial information in relation to that period.
(7) It is unlikely that a Mongolian court would order any party to provide any security pending the disposal of the challenge in this Court.
(8) In mid-2016 a 49% shareholding in EMC previously owned by Rosneft/the Government of the Russian Federation was sold to Mongolian Copper Corporation (MCC) for a reported total purchase price of $400 million.
(9) There are at least two official investigations into the legality and/or propriety of EMC's activities, namely a joint investigation by the Ministry of Finance and the State Property Agency under the direction of the Mongolian Parliament's Economic and Legal Standing Committees – commonly referred to as the Joint Standing Committees Investigation; and a further joint investigation by the Bank of Mongolia, the Ministry of Finance and the State Property Agency under the leadership of the National Audit Office.
(1) It had been concluded that the sale of the 49% of EMC to a third party by the previous Government in June 2016 was in violation of the law.(2) The purchase price of US$400 million approximately was financed by loans obtained by MCC from the Trade and Development Bank to companies formed by the director of that Bank and individuals related to him. MCC used that money to purchase the 49% shareholding.
(3) In so doing, the Trade and Development Bank violated the law in its use of monies deposited with it.
(4) The working group concluded that it was appropriate for the Government to take back the 49% shareholding which had been purchased with these funds and to take EMC entirely into State ownership.
(5) Between 27th June 2016 and 21st November 2016 EMC paid dividends to MCC. These dividends comprised US$47 million for the year 2012 and US$8.6 million in respect of 2013. MCC had no connection whatever with EMC in those years as it was not a shareholder then and has dissipated the money.
(6) Approximately MNT 2 billion has been transferred by EMC to companies associated with its previous management and political connections.
(7) The impact of all of this has been to diminish the tax take of the Mongolian State.
Conclusion