QUEEN'S BENCH DIVISION
COMMERCIAL COURT
7 Rolls Building, Fetter Lane London, EC4A 1NL |
||
B e f o r e :
____________________
A L CHALLIS LIMITED |
Claimant |
|
- and - |
||
BRITISH GAS TRADING LIMITED |
Defendant |
____________________
Orlando Gledhill (instructed by Bond Dickinson LLP) for the Defendant
Hearing dates: 19-21 January 2016
____________________
Crown Copyright ©
The Hon. Mr Justice Popplewell:
Introduction
The Law
The CERT Scheme and other background to the Agreements
"(3) To estimate the reduction for a market transformation action, [except a market transformation action which is the provision of a real-time display or a home energy advice package,] the Authority must
(a) apply to that action the appropriate carbon co-efficient values set out in Schedule 3; and
(b) increase the reduction in carbon emissions expected to be achieved by that action by 50%."
(1) The 10% cap on market transformation activity which was permitted to qualify for MTU had been increased from 6% with effect from 21 July 2009 and might foreseeably have been adjusted up or down again during the currency of the agreements between the parties. British Gas might have promoted market transformation actions across all schemes, including heating, lighting and insulation, which exceeded in total the 10% cap (or any modified cap). This was what in fact happened, and was foreseeable by both parties at the time of the agreements as a natural incident of the CERT scheme. The widgets fell within the "heating" category of savings under the scheme, which was a smaller proportion of the savings than lighting and insulation, all of which would potentially contribute towards the 10% cap on claimable market transformation activity. In those circumstances, there would be a decision to be made by British Gas in January 2013, after the end of the scheme period, as to which qualifying actions it chose to notify as making up the 10% for which it claimed MTU. That was entirely within British Gas' discretion. Challis' pleaded case in this action originally included a claim that British Gas was obliged to claim MTU for all widgets supplied by Challis, but that claim was abandoned shortly before the hearing. Mr Challis gave evidence to the effect that the water widget was such an attractive product, and so cost effective as an energy saving device, that it was the common assumption of the parties at the outset that MTU would be claimed on all of them, although he did not go so far as to suggest that anything was said expressly to that effect. I am unable to accept that there was any such common assumption. Mr Challis' evidence was premised on cost effectiveness being judged by the very low cost of manufacture by Challis; but this was not the cost which was relevant to an analysis by British Gas of the relative cost effectiveness of all its different schemes which qualified as market transformation activity; that depended upon the cost to British Gas of paying the suppliers of goods or services. The evidence showed that the water widget scheme was far from the most cost effective to British Gas across its whole programme, and I have little doubt that British Gas made no a priori assumption that all widgets would be used to claim MTU. Nor was Challis justified in thinking that British Gas was proceeding on that basis. Accordingly the agreements fall to be interpreted on the footing that the parties contemplated that it would not be until January 2013 that it would be possible to determine which, if any, of Challis' supply of water widgets contributed to British Gas' MTU uplift.
(2) Leaving aside MTU, there was in any event no certainty about what carbon savings would be attributed by Ofgem to Challis' supply of water widgets until final notification to British Gas of its carbon credits in April 2013, again after the end of the scheme period. Article 15 required Ofgem to provide in advance an estimate of the relevant carbon savings for actions which it approved as qualifying actions, but it was not bound by that estimate when making its final determination under article 19, as was made clear in the official guidance issued by Ofgem in January 2008 at paragraph 6.13. The epithet "banking" as applied to the interim notification process is therefore misleading: it did not mean that credit for carbon savings in those amounts were bound to be awarded by Ofgem. The parties' agreements (at clause 6.4) expressly recognised the possibility of Ofgem recalculating the carbon savings attributable to the widgets during the period of the agreements.
The Agreements
"WHEREAS
(A) The Company is a licensed supplier of gas and electricity in the United Kingdom to a range of domestic and commercial customers;
(B) The Supplier specialises in the design, manufacture and distribution across the UK and Europe of a range of water saving products aimed at reducing water & energy consumption and bills;
(C) The Company holds gas and electricity supplier licences and is subject to a Carbon Emissions Reduction Target ("CERT Target"), pursuant to which it is obliged to provide, install or subsidise energy efficiency measures in homes across Great Britain;
(D) As part of meeting the CERT Target, the Company is willing to pay the Payment (as defined below) to the Supplier on the terms set out in this Agreement.
(E) The Parties wish to enter into this Agreement to record the terms governing the relationship between each of them and in respect of the promotion of certain energy efficient products in order to partially fulfil the Company's obligations under CERT and to operate a scheme acceptable to Ofgem in order to allow the Company to claim credits from Ofgem which count towards the CERT Target.
1. DEFINITIONS AND INTERPRETATION
1.1 In this Agreement unless the context otherwise requires the following words shall have the following meanings:
"CERT" means the Carbon Emissions Reduction Target under the Electricity and Gas (Carbon Emissions Reduction) Order 2008, as amended from time to time, or any replacement scheme;
"Credits" means carbon emissions credits that arise from the carbon savings derived from the Products, and which the Company use to count towards its CERT obligation;
"Payment" means the amounts to be paid by the Company to the Supplier under this Agreement as set out in Schedule 4;
"Products" means those products listed in Schedule 1;
"Scheme" means the scheme relating to the Products operated by the Company and approved by Ofgem for the receipt of Credits as modified, amended or replaced from time to time;
2. TERM
2.1 This Agreement shall commence on the Commencement Date and shall continue for the entire period that the Product continues to be an eligible product (for the purposes of the Company's CERT target) under CERT, unless terminated earlier in accordance with its terms.
6. CALCULATION OF PAYMENT
6.1 The Company shall pay the Payment to the Supplier.
6.2 The Payment is calculated as set out in Schedule 4 and is a fixed amount based on the carbon savings for the Products as agreed between Ofgem and the Company under the Scheme provided that the Supplier shall only be entitled to claim or receive payment:
6.2.1 in respect of one Product per Consumer household as per Ofgem guidance from time to time (unless the regulations of the Scheme and applicable under CERT from time to time enable the Company to claim Credits in respect of more than one Product per Consumer household) but ignoring for these purposes any Products distributed by or at the direction of the Company otherwise than under this Agreement; and
6.2.2 for so long as the Supplier and the Products are compliant with the regulations of the Scheme and applicable under CERT from time to time, provided that this Clause 6.2.2 shall only entitle the Company to recover any Payments already made to the Supplier where the provisions of Clause 17.3 apply.
6.3 The Parties agree that the maximum aggregate amount of Payments by the Company under this Agreement and any amounts payable by the Company under Clauses 12.6 or 12.7 shall not exceed £4,000,000 (excluding VAT).
6.4 The Parties acknowledge that the carbon savings may be recalculated by Ofgem during the Term. If Ofgem do recalculate the carbon savings, the Parties shall use reasonable endeavours (without financial obligation) to agree and implement a mutually acceptable method of mitigating the effect of the recalculation on the terms of this Agreement provided that if the parties (each acting reasonably and in good faith) shall not be able to reach agreement on such mitigation within 20 working days of notification of the recalculation by Ofgem, such obligation to agree and implement a method of mitigation shall cease. Notwithstanding any steps that the parties may agree to take to mitigate the effect of a recalculation by Ofgem of carbon savings, (and without prejudice to the foregoing) the Parties acknowledge that the Payment may change as a result of a recalculation by Ofgem of the carbon savings. Any change to the Payment shall be directly proportionate and in relation to the recalculation by Ofgem of the carbon savings. The Supplier agrees to act bona fide and in good faith in giving all reasonable consideration to accepting the new Payment provided that the Supplier receives 4 weeks' prior written notice of the change or, if Ofgem implement a change to the savings which will take effect before the expiry of such 4 week period, that the Company promptly notifies the Supplier upon the Company becoming aware. If the Supplier is unwilling to agree the new Payment either Party shall be entitled to terminate the Agreement under clause l2.4.
7. PAYMENT
7.1. During the first 4 months of the Term, the Supplier shall submit an invoice with the Weekly Report setting out the Payment claimed in respect of that week and thereafter the Supplier shall submit invoices on a monthly basis setting out the Payment claims in respect of that month in each case pursuant to this Agreement.
7.2 The Company shall, unless the parties otherwise agree, pay the amount of any invoice submitted by the Supplier within 28 days of the date on which the Company receives the invoice or is deemed to have received the invoice pursuant to the provisions of Clause 20 (whichever is the earlier).
.
9. CONTRACT EXTENSIONS
9.1 The Forecast Delivery Plan sets out the Supplier's reasonable expectation for manufacture and supply of Products in the domestic market in Great Britain over the period 12 months from the Commencement Date. The Parties acknowledge that the Forecast Delivery Plan may envisage the manufacture and supply by the Supplier of more Products than those for which the Company is obliged to pay the Supplier pursuant to this Agreement as at the Commencement Date. During the Term the Parties shall keep under review the performance of the Supplier as compared with the Forecast Delivery Plan and the Supplier shall keep the Company reasonably informed on a regular basis (not less than monthly) as to such performance and as to status of the Supplier's negotiations with any third parties for the distribution or supply of Products by such third parties.
9.2 In the event that:
9.2.1 the Company has made Payments to the Supplier pursuant to clause 7 in an amount in excess of £3,000,000; or
9.2.2 the Supplier is negotiating an agreement with a distributor or Customer (the terms of which reasonably anticipate supplies of Products which would, but for Clause 6.3, cause the Company to be obliged to make Payments to the Supplier in excess of £4,000,000 in aggregate under this Agreement) and such negotiations are considered by the Supplier (acting reasonably and in good faith) to be likely to culminate in the successful conclusion of a legally binding agreement with that third party and the Supplier can demonstrate to the reasonable satisfaction of the Company that such negotiations are well progressed (including, without limitation, by providing to the Company of copy of the signed heads of agreement between the Supplier and the relevant third party in good faith),
the Supplier may by written notice to the Company request that the terms of this Agreement are varied only by replacing the figure of "£4,000,000" in Clause 6.3 with "£10,000,000" ("First Extension Notice").
9.3 In the event that:
9.3.1 the Company does not notify the Supplier within 2 weeks of the date of receipt (or deemed receipt) by the Company of the First Extension Notice that the Company wishes to proceed with the variation set out in the First ExtensionNotice; or
9.3.2 the Company notifies the Supplier at any time following receipt (or deemed receipt) by the Company of the First Extension Notice that the Company does not wish to proceed with the variation set out in the Extension Notice.
the provisions of Clause 25.3 shall cease to apply in respect to the Supplier with effect from 9am on the first Business Day following the date on which the period of 2 weeks specified in Clause 9.3.1 expires or (if earlier) the Company notifies the Supplier pursuant to clause 9.3.2. The Supplier shall continue to work in good faith towards delivery of Products for the Company up to the maximum aggregate value of £4,000,000 unless in the Supplier's reasonable discretion continuing to do so would adversely affect the business interests of the Supplier.
9.4 In the event that:
9.4.1 the Company has elected to proceed with the variation pursuant to clause 9.3 and the Company has made Payments to the Supplier pursuant to clause 7 in an amount in excess of £7,500,000 under this Agreement; or
9.4.2 the Supplier is negotiating an agreement with a distributor or Customer (the terms of which reasonably anticipate supplies of Products which would, but for Clause 6.3, cause the Company to be obliged to make Payments to the Supplier in excess of £10,000,000 in aggregate under this Agreement) and such negotiations are considered by the Supplier (acting reasonably and in good faith) to be likely to culminate in the successful conclusion of a legally binding agreement with that third party and the Supplier can demonstrate to the reasonable satisfaction of the Company that such negotiations are well progressed (including, without limitation, by providing to the Company of copy of the signed heads of agreement between the Supplier and the relevant third party in good faith),
the Supplier may by written notice to the Company request that the terms of this Agreement are varied only by replacing the figure of "£10,000,000" in Clause 6.3 with "£37,500,000" (Final Extension Notice").
9.5 In the event that:
9.5.1 the Company does not notify the Supplier within 2 weeks of the date of receipt (or deemed receipt) by the Company of the Final Extension Notice that the Company wishes to proceed with the variation set out in the Final Extension Notice; or
9.5.2 the Company notifies the Supplier at any time following receipt (or deemed receipt) by the Company of the Final Extension Notice that the Company does not wish to proceed with the variation set out in the Final Extension Notice,
the provisions of Clause 25.3 shall cease to apply in respect to the Supplier with effect from 9am on the first Business Day following the date on which the period of 2 weeks specified in Clause 9.5.1 expires or (if earlier) the Company notifies the Supplier pursuant to clause 9.5.2. The Supplier shall continue to work in good faith towards delivery of Products for the Company up to the maximum aggregate value of £10,000,000 unless in the Supplier's reasonable discretion continuing to do so would adversely affect the business interests of the Supplier.
.
12.3 Either Party may at its convenience terminate the Agreement or any part thereof at any time by l2 months' written notice to the other Party.
12.4 The Company may terminate the Agreement by not less than 28 days' notice if the Company (acting reasonably and in good faith) is reasonably able to demonstrate to the Supplier considers that the Company is suffering or may suffer damage to its goodwill, reputation and/or its relationship with Ofgem, DECC or any other government or regulatory body as a result of continuing to pay the Supplier under this Agreement in respect of carbon savings or anticipated carbon savings associated with the Products where Ofgem, DECC or another relevant government or regulatory body indicates that such payments, whilst compliant with the specific regulations of the CERT Scheme, are inconsistent with the spirit and intent of or do not deliver the purpose of the CERT Scheme.
.
12.7 The Company may terminate this Agreement with immediate effect if the Scheme is altered for whatever reason, other than through the fault of the Company, so that the Company is unable to obtain Credits under the Scheme (whether specifically under this Agreement or generally under the Scheme). The Supplier may terminate this Agreement with immediate effect if the Scheme is altered so that the Supplier and the Products are no longer compliant with the regulations of the Scheme and applicable under CERT from time to time and as a result does not or will not receive Payment pursuant to the operation of Clause 6.2.2.
17. LIABILITY AND INDEMNITY
17.3 The Supplier will not be entitled to retain Payments in circumstances where Ofgem refuses to grant the Credits relating to such Payments due entirely to the negligent act or negligent omission of the Supplier or of any subcontractor of the Supplier.
SCHEDULE 4 PAYMENT CALCULATION
The Company shall pay the Supplier the Payment as calculated below:
1. For each tonne of CO2 deemed to have been claimed by the Company (as set out in the Supplier's invoice):
1.1 £6.70 per tonne of CO2 attributable to Consumers other than Priority Group Consumers
1.2 £8.70 per tonne of CO2 attributable to Priority Group Consumers.
2. The Parties agree that the supply of 1 Product by the Supplier (or retailer or other third party supplied by the Supplier) to a Consumer household shall equate to 1.018 tonne of CO2 savings.
3. Without prejudice to the provisions of Clause 6.3 (as the same may be varied pursuant to Clauses 9.2 and 9.3) the Payment shall remain as set out in paragraph 1 for up to the first 5 million Products and thereafter the price will be agreed from time to time between the Parties but in the absence of such agreement the payments shall continue at the levels set out at paragraph 1.
4. For the avoidance of doubt VAT shall be added to the above in order to calculate the full amount due to the Supplier under each and any invoice raised pursuant to this Agreement."
"SCHEDULE 4 - PAYMENT CALCULATION
Definitions for the purpose of this Schedule 4:
"Total Products" shall mean the total number Products distributed pursuant to the Marketing Activity in excess of 176,000 units of Product and the Sainsbury's Marketing Activity.
Subject to the provisions of this Agreement, including the maximum amount payable pursuant to clause 6.3, the Company shall pay the Supplier the Payments as calculated below in accordance with the bandings set out in paragraph 1.1-1.3 (inclusive) and 2.2.1-2.2.3 (inclusive) (each a "Banding"):
1. In respect of Sainsbury's Marketing Activity
1.1 if the number of Total Products distributed is between 1 and 999,999 (inclusive) then the Payment shall be £3.70 per tonne of CO2 attributable to the Products distributed to Consumers pursuant to the Sainsbury's Marketing Activity;
1.2 if the number of Total Products distributed is between 1,000,000 and 1,999,999 (inclusive) then the Payment shall be £4.70 per tonne of CO2 attributable to the Products distributed to Consumers pursuant to the Sainsbury's Marketing Activity; and
1.3 if the number of Total Products distributed is above 2,000,000 then the Payment shall be £5.70 per tonne of CO2 attributable to the Products distributed to Consumers pursuant to the Sainsburys Marketing Activity..
The parties acknowledge that the Company will make a separate payment to Sainsbury's in the amount of £1 for each Product which the Supplier distributes to Consumers via the Sainsbury's Marketing Activity in accordance with the terms of an agreement between the Company and Sainsbury's.
Notwithstanding the payment terms set out in clause 7, any payments due to the Supplier which are calculated pursuant to paragraphs 1.1, 1.2, or 1.3 above shall be paid to the Supplier in accordance with this Agreement and the Supplier shall invoice the Company for Payment in respect of the total volumes of Products distributed to Consumers pursuant to the Sainsbury's Marketing Activity as soon as reasonably practicable after conclusion of the Promotion (but in any event before the end of April 2011) to help ensure that the CO2 can be successfully submitted towards the Company's CERT obligations in line with Ofgem guidelines.
2. In respect of all other Marketing Activity
2.1 up to a maximum of 176,000 Products distributed pursuant to the Marketing Activity:
- £6.70 per tonne of CO2 attributable to Products distributed to Non-Priority Consumers; and
- £8.70 per tonne of CO2 attributable to Products distributed to Priority Consumers,
For the avoidance of doubt, the number of Products distributed pursuant to the Sainsbury's Marketing Activity shall not be included in the calculation of the number of Products distributed pursuant to this paragraph 2.1.
2.2 for Products distributed in excess of 176,000:
2.2.1 if the number of Total Products distributed is between 1 and 999,999 (inclusive) then the Payment shall be £4.70 per tonne of CO2 attributable to the Products distributed to Consumers pursuant to the Marketing Activity;
2.2.2 if the number of Total Products distributed is between 1,000,000 and 1,999.999 (inclusive) then the Payment shall be £5.70 per tonne of CO2 attributable to the Products distributed to Consumers pursuant to the Marketing Activity; and
2.2.3 if the number of Total Products distributed is above 2,000,000 then the Payment shall be £6.70 per tome of CO2 attributable to the Products distributed to Consumers pursuant to the Marketing Activity.
Any payments which are payable pursuant to this paragraph 2 shall be payable in accordance with clause 7 of this Agreement.
4. (sic) The number of Total Products distributed pursuant to this Agreement shall be recalculated by the Company throughout the Term and, if following such re-calculation the volume of Total Products distributed results in a change to the applicable payment Banding, any further payment due (subject to such Products still eligible for Credits) in excess of the amount already paid to the Supplier pursuant to this Agreement shall be payable to the Supplier in accordance with the provisions of clause 7.
5. The Parties agree that the supply of 1 Product by the Supplier (or retailer or other third party supplied by the Supplier) to a Consumer household shall equate to 1.018 tonne of CO2 savings.
6. For the avoidance of doubt VAT shall be added to the above in order to calculate the full amount due to the Supplier under each and any invoice raised pursuant to this Agreement."
Analysis
(1) The defined term Credits is not used in the Recitals, and is only used in clauses 6.2.1, 12.7, 15.1, 17.3, 25.3.2 and 25.4.2 of the 2010 Agreement, and the equivalent provisions of the 2011 Agreement. It also appears in paragraph 4 of Schedule 4 of the 2011 Agreement. In those provisions it is there used to refer to credits which British Gas receives from Ofgem.
(2) By contrast the price payable is identified in clause 6.1 and 6.2, which does not use the defined term for that purpose. Clause 6.1 directs the reader to Schedule 4 via the definition of Payment. Paragraphs 1.1 and 1.2 of Schedule 4 express the price be payable at an identified £ figure "per tonne of CO2 attributable to" the relevant consumer groups. This must be a reference to CO2 savings, as is further apparent from paragraph 2 which identifies how such savings are to be calculated per widget: 1.018 tonnes of CO2 savings per widget supplied to each household.
(3) Paragraph 1 of Schedule 4 of the 2010 Agreement (but not the 2011 Agreement) refers to this as a tonne of CO2 "deemed to have been claimed by [British Gas] (as set out in [Challis'] invoice)". The invoices are to be weekly or monthly pay as you go invoices pursuant to clause 7. The price is therefore based on a carbon saving per widget irrespective of whether British Gas in fact claims uplift, and at a time when it will be impossible to tell what, if any, MTU will be claimed by British Gas in respect of such widgets.
(4) The explanatory words in clause 6.2 are that the price so calculated is "a fixed amount based on the carbon savings for the Products as agreed between Ofgem and [British Gas] under the Scheme." The "Scheme" is defined as the water widget scheme, not the CERT scheme. The price is said to be fixed by reference to carbon savings, not Credits. This is a reference to the carbon score set by Ofgem at the outset, not, as Mr Shepherd submitted, the final determination process by which Ofgem awarded credits to British Gas in 2013. Mr Shepherd objected that the carbon score had been agreed at the outset by Ofgem with Challis, not British Gas, prior to the Agreements; but it was also agreed as between Ofgem and British Gas in the discussions and presentations in April and May 2010 once the widgets were to be promoted by British Gas under the CERT Scheme.
(5) The price is a "fixed amount" in the sense that it is ascertainable as a price per widget which can be calculated by reference to the carbon savings per widget agreed in paragraph 2 of Schedule 4, i.e. the agreed carbon score of 1.018 tonnes per widget.
(1) They are for pay as you go invoicing, weekly for the first four months and thereafter monthly. That assumes that the price is calculable as soon as the number of widgets supplied is ascertained. There is no provision for any subsequent invoicing in 2013 to take account of MTU if and when it was claimed by British Gas following conclusion of the CERT scheme. This would be a surprising omission from the careful invoicing provisions if MTU were intended to be included within British Gas' payment obligation. The possibility of subsequent invoicing in one specific circumstance is addressed in paragraph 4 of Schedule 4 of the 2011 Agreement and would arise if, for example, a new band of Sainsbury's marketing activity were reached, because the new price applies not just to the widgets supplied in the new band but also all widgets supplied previously in the lower band. But there is no provision for subsequent invoicing for MTU.
(2) Moreover, what is to be invoiced weekly/monthly is the "Payment" claimed, Payment being a defined term and comprising the whole of the price payable under the pricing mechanism in clause 6. If the price included MTU it would not be possible to invoice weekly/monthly for "the Payment", which is what clause 7 requires. This too suggests that MTU was not included in the price. Mr Shepherd sought to meet this difficulty by submitting that the invoices under clause 7 were for Payment "in respect of that week" or "in respect of that month", and so were not for the whole of the price payable under clause 6 as the Payment. A more natural reading of the qualification "in respect of that week/month" is that the Payment is in respect of the widgets supplied during that week/month. If so, it remains the totality of the price payable in respect of the weekly or monthly supply of widgets, and excludes the notion that Payment in clause 6 allows for an additional element of the price which is only later calculable and to be invoiced in 2013.
(1) There is a cap on the total aggregate amount of Payments which Challis can recover in clause 6.3, being £4 million (excluding VAT) in the 2010 Agreement, and £21.2 million (excluding VAT) in the 2011 Agreement. Since the cap is on "Payments", which is the price defined in Schedule 4, Challis' case has to be that the cap applies to the total amount payable by British Gas, including MTU. If that were so, however, there would be no way of the parties knowing during the currency of the scheme whether or when the cap was reached: it might be any time after supply of sufficient widgets to invoice for £2,666,666, depending upon what MTU was later claimed by British Gas in respect of those widgets. If Challis continued to supply until the monthly invoicing reached £4 million, it would be running the risk that it was supplying up to 50% more products than it needed to in order to earn the maximum it could under the agreement. If on the other hand it tailored its supply to take account of the possibility of MTU it would not know how many widgets to supply in order to maximise its income until too late, after the Scheme closed. Such an interpretation is inimical to the commercial certainty which the parties would expect from their agreement.
(2) Clause 9 also assumes that the parties know when the cap has been reached as they go along. It provides for the possibility of two sequential contract extensions to increase the cap. The first involves a potential increase in the cap from £4 million to £10 million where Payments have reached £3 million and Challis anticipates aggregate Payments exceeding £4 million. The second involves a potential increase in the cap from £10 million to £37.5 million where Payments have reached £7.5 million and Challis anticipates aggregate Payments exceeding £10 million. Again, these provisions are framed by reference to the defined term "Payments" reaching or being anticipated to reach the specified amounts. This only works if Payments do not include MTU on the widgets, which cannot be known during the currency of the Scheme.
(3) The background to the 2011 Agreement was discussion and recognition from at least December 2010 that the £4 million cap under the 2010 Agreement had been exceeded. Those discussions between the parties proceeded on the expressed understanding that it was the invoiced amounts which had reached and breached the cap; in other words that the cap in the 2010 Agreement applied net of any uplift for MTU. Whilst that is not admissible as an aid to construction of the 2010 Agreement, it is relevant factual matrix to the 2011 Agreement and suggests that the cap in those agreements was also understood to be net of any uplift for MTU. Moreover the discussion between the parties in an exchange of emails on 11 February 2011 indicates that they were calculating what became the £21.2 million cap in the 2011 Agreement by estimates of amounts payable to Challis on predicted supplies of widgets which would not include any MTU. In other words the cap in the 2011 Agreement was calculated by the parties as one which was intended to exclude any MTU.
(1) There was a risk that Challis would be found not to have complied with the Ofgem requirements for the practical implementation of the supply of widgets under the scheme, the performance of which fell to Challis under the terms of the Agreements. The carbon score granted by Ofgem on 26 January 2010 was subject to certain conditions, including, for example, that the device should only be fitted to properties suited to it; only supplied to householders who specifically requested it; sold with a test bag or similar to enable customers to test its suitability and a facility for returning the product if not; and that there should be extensive customer satisfaction monitoring to ensure that it was being used. The approvals of the scheme as a qualifying action by Ofgem of 16 June 2010 and 5 November 2010 were subject to Challis complying with the procedures discussed with Ofgem and Challis/British Gas in April and May 2010. For example there was a limitation on the supply of free widgets, which had to have been requested in writing after August 2010. This execution risk, as it was described in argument, of Ofgem denying or reducing the credits for failure to ensure compliance with these conditions, fell on British Gas, who nevertheless had to pay weekly/monthly when the widgets were distributed by Challis, whose known financial circumstances might make any later clawback for breach impractical.
(2) There was a risk that the carbon score might be revised as a result of further scientific data or changes affecting what was referred to as its "additionality". The carbon saving awarded by Ofgem had to be a genuine saving over and above the energy consumption of other comparable goods or services. Accordingly as a class of products became more efficient over time, it might become harder to demonstrate the extent of the energy savings which were additional to the existing norm: there was a potentially moving baseline against which the carbon saving fell to be measured. The scientific data underlying the carbon score might also be subject to reconsideration or review. Indeed in November 2010 Ofgem raised a query that the carbon score for the Challis widgets might be too high, by reference to water pressures in showers and the longevity of the product. In the event Challis was able to allay Ofgem's concerns, but this episode illustrates one of the risks undertaken by British Gas. Clause 6.4 provided protection to British Gas against such risks only for subsequent sales; downward revision of the carbon score would affect British Gas' ability to claim credits for previous supplies without it being entitled to revisit the payments already made to Challis under clause 7 for previous supplies.
(3) There was a risk of Ofgem changing the scheme rules or guidance. This sometimes occurred. For example, at the beginning of the CERT scheme, energy saving lightbulbs qualified, and it was a popular carbon saving measure amongst energy suppliers to give them away. However there came a point at which Ofgem questioned the extent to which consumers were actually using such free light bulbs and therefore whether such supply actually resulted in energy savings. Restrictions were introduced in January 2010 requiring purchase from a retail outlet. Another example was a change to what could qualify as "innovative" with effect from 1 April 2011. A further example was the introduction in 2011 of a specific cap of 11 million on the total number of shower regulators which could qualify.
Conclusion
Note 1 Subject to adjustment for demonstration actions, which can be ignored for the purposes of the current dispute. [Back]