QUEEN'S BENCH DIVISION
COMMERCIAL COURT
7 Rolls Building, Fetter Lane London, EC4A 1NL |
||
B e f o r e :
____________________
MONDE PETROLEUM SA | ||
Claimant in 2013 Folio 308 & 2014 Folio 1060, | ||
Defendant in 2014 Folio 975 | ||
And | ||
WESTERNZAGROS LIMITED |
Defendant in 2013 Folio 308 | |
& 2014 Folio 1060, | ||
Claimant in 2014 Folio 975 |
____________________
Stuart Isaacs QC & Ruth M D Byrne (instructed by King & Spalding International LLP) for WesternZagros Ltd
Hearing date: 14 January 2015
____________________
Crown Copyright ©
The Hon. Mr Justice Popplewell :
Introduction
The Agreements
"13.1 If any dispute, controversy or claim arises between the Parties in relation to, or in connection with this Agreement, or in connection with the interpretation, performance or non-performance hereof, including any questions regarding the payment of fees, (the "Dispute"), the Parties shall promptly meet to discuss the Dispute in an attempt to resolve such dispute amicably through negotiation.
13.2 If the dispute has not been resolved within sixty (60) days..., then either Party may, by notice in writing to the other, refer the dispute to arbitration to be fully settled."
Clause 13 went on to provide that the arbitration was to be held in London under the ICC Rules.
"Notwithstanding the termination of the [CSA], the provisions of Section 5 thereof (Confidentiality) shall continue to apply."
"This Agreement shall be governed by and construed in accordance with the laws of England and Wales. The parties herein irrevocably attorn to the exclusive jurisdiction of the courts of England and Wales."
"This Agreement constitutes the entire agreement between the parties with respect to the subject matter hereof and shall supersede any and all prior negotiations and understandings."
The procedural background
"6. WZL accordingly seeks:
6.1 a declaration that the arbitration agreement in clause 13 of the CSA is severable and survives termination of that agreement;
6.2 a declaration that it validly terminated the CSA on written notice on 16 March 2007;
6.3 further or alternatively, a declaration that it could have terminated the CSA for cause in March or April 2007;
6.4 accordingly, a declaration that Monde has no further entitlement under the CSA, including with respect to the Alleged Lost Compensation;
6.5 further or alternatively, a declaration that Monde waived or is estopped from seeking to enforce any such rights;
6.6 further or in any event, a declaration that Monde, having withdrawn its claims in this arbitration, is time-barred from reviving any claim under the CSA, including with respect to the Alleged Lost Compensation;
6.7 in any event, a declaration that the Option did not and has never vested, is subject to third party approvals and further agreement and is unenforceable and/or of no value;"
The Issues
"67 Challenging the award: substantive jurisdiction.
(1) A party to arbitral proceedings may (upon notice to the other parties and to the tribunal) apply to the court—
(a) challenging any award of the arbitral tribunal as to its substantive jurisdiction;
…
(3) On an application under this section challenging an award of the arbitral tribunal as to its substantive jurisdiction, the court may by order—
(a) confirm the award,
(b) vary the award, or
(c) set aside the award in whole or in part."
(1) The Tribunal noted that, as matters stand, the Termination Agreement is binding on the parties: Monde accepts that the Court has not yet determined its claims for misrepresentation/duress, and it is WZL's case that the Termination Agreement is valid and binding. The issue therefore falls to be addressed on the basis that the Termination Agreement remains in force and binding on the parties (paragraphs 84 - 87).
(2) The language of clause 3.2 of the Termination Agreement is not sufficiently clear to bring about the complete termination of the distinct arbitration agreement in clause 13 of the CSA (paragraph 93).
(3) Nevertheless the scope of the arbitration agreement was very significantly reduced by the Termination Agreement, in particular because given the width of clause 2.1 and 2.2 of the Termination Agreement, there is no possibility of any dispute falling within the scope of the arbitration clause in the CSA (subject to a possible exception in respect of disputes relating to alleged breaches of confidentiality under clause 5 of the CSA, which by clause 3.2 were excluded from the scope of the termination provisions in clauses 2.1 and 2.2). The net effect is that the arbitration agreement is "inoperative". In this respect the case is analogous to Shanghai Foreign Trade Corporation v Sigma Metallurgical Co Pty Limited (1996) 133 F.L.R (NSW). 417, a decision of the Supreme Court of New South Wales (paragraphs 88-95, especially at 88, 91).
(4) It is not necessary to decide the "interesting question" of what the position would be if and when the Termination Agreement were rescinded in the Commercial Court proceedings. If that occurred, the Tribunal could "see some force" in the argument that the restriction in the scope of the arbitration agreement brought about by the Termination Agreement no longer applies and that Monde's claim for damages for the alleged wrongful termination of the CSA was then covered by the arbitration agreement. However in such circumstances there would be no possibility of Monde now falling back on its claims in the arbitration, because they had been withdrawn, and any new claims in arbitration would be time-barred (paragraphs 96-101).
(5) The Tribunal rejected WZL's argument that Monde was precluded from contesting the Tribunal's jurisdiction by sections 31(1) and 73 of the Arbitration Act and/or an estoppel. There is no challenge to this aspect of the decision.
Analysis and conclusion
'But the decision in Fiona Trust has limited application to the questions which arise where parties are bound by several contracts which contain jurisdiction agreements for different countries. There is no presumption that a jurisdiction (or arbitration) agreement in contract A, even if expressed in wide language, was intended to capture disputes under contract B; the question is entirely one of construction ... The same approach to the construction of potentially-overlapping agreements on jurisdiction (but there will, in this respect, be no difference between the construction of agreements on jurisdiction, arbitration agreements and service of suit clauses) was taken in [UBS]…
In the final analysis, the question simply requires the careful and commercially-minded construction of the various agreements providing for the resolution of disputes, the point of departure being that agreements which appear to have been deliberately and professionally drafted are to be given effect so far as it is possible and commercially rational to do so, even where this may result in a degree of fragmentation in the resolution of disputes. It may be necessary to enquire under which of a number of inter-related contractual agreements a dispute actually arises; this may be answered by seeking to locate its centre of gravity.
The same approach, namely to focus on the commercially-rational construction, governs the interpretation of agreements on jurisdiction as exclusive or nonexclusive, and of agreements which specifically provide that the parties will not take objection to the bringing of proceedings if proceedings are brought in more courts than one.'
[50] I therefore turn to the construction of the agreements in issue focusing on finding the commercially rational construction and giving effect to clear agreements, even if this may result in a degree of fragmentation in the resolution of disputes between parties to the series of agreements."
[15]. … I cannot see that the arbitrator's jurisdiction would be in any way affected by the termination of the Distributorship Agreement. It was argued by Mr Berragan, who appeared for Holdings, that the 4 November 1999 Airport Agreement brought the Distributorship Agreement to an end and terminated all rights to compensation under schedule 3 with the result that there was nothing left to arbitrate about and no possibility of triggering an arbitration by a failure to agree on such compensation. The right to a compensatory payment and the right to arbitrate in default of agreement about such a figure both came to an end.
16. I am unable to accept that submission. The terms of section 7 of the Arbitration Act 1996 provide that "unless otherwise agreed by the parties, an arbitration agreement which forms … part of another agreement…shall not be regarded as invalid, non-existent or ineffective because that other agreement is invalid, or did not come into existence or has become ineffective, and it shall for that purpose be treated as a distinct agreement". This is a statutory codification of the well recognised position which existed prior to the Act – see Harbour Assurance Co (UK) Ltd v Kansa General international insurance Co Ltd [1993] 1 Lloyd's Rep 455. If the Distributorship Agreement had been brought to an end by accepted repudiation or frustration, the Arbitration Agreement would continue in being in order to deal with issues of compensation, should such arise. It is nothing to the point that the assignment of assets by Holdings occurred after the termination of the Distributorship Agreement, since the allegation is made that compensation is due under the agreement. Whilst the effect of the Airport Agreement, if binding and effective, would be to negate any claim, it would not of itself bring the Arbitration Agreement to an end once a claim for compensation, which could not be agreed, was made. In my judgment there was no agreement to bring the Arbitration Agreement to an end within the meaning of section 7, when the Distributorship Agreement was allegedly brought to an end and Holdings could point to no wording which suggested that this was the case."
"[t]he doctrine of separability requires direct impeachment of the arbitration agreement before it can be set aside. This is an exacting test. The argument must be based on facts which are specific to the arbitration agreement. Allegations that are parasitical to a challenge to the validity to the main agreement will not do".
Security for costs
(1) £20,000 in relation to preliminary tasks which are those relating to the issues in the Commercial Court proceedings which do not overlap with those which have already been the subject matter of WZL's claims for declaratory relief in the arbitration;
(2) £50,000 in relation to statements of case;
(3) £30,000 in relation to pre-trial applications. Those exclude any costs in relation to jurisdiction challenges, on which WZL has failed, or any of the costs for the security for costs application which will be dealt with by way of separate order;
(4) £70,000 in relation to disclosure;
(5) £50,000 in relation to preparation of factual witness evidence.