QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Corporate Oil and Gas Limited |
Claimant |
|
- and - |
||
Marshall Aviation Services Limited |
Defendant |
____________________
Mr Steven Thompson QC and Mr Harry Sharpe (instructed by Clyde & Co LLP) for the Defendant
Hearing dates: 6, 7, 8, 12, 13, 14 and 19 October 2015
____________________
Crown Copyright ©
Mr Justice Knowles:
Introduction
Common Ground
a. On 23 April 2009, the Defendant made a written proposal to the Claimant for work to the Aircraft including replacement of corroded wing bolts, routine maintenance and repainting. The Claimant accepted the proposal.
b. Shortly after the delivery in May 2009, work on the Aircraft was suspended because of proceedings brought by a third party. These proceedings (the "ownership proceedings") put the ownership of the Aircraft into question.
c. Within the ownership proceedings, a consent order was signed on 15 July 2009 ("the Consent Order") under which the Defendant was to provide (and be paid for) hangarage, full systems checks, engine runs and weekly visual inspections. The Defendant did not keep the Aircraft in a hangar at all times but for some periods kept it outside.
d. In June 2010 the ownership proceedings were settled and the Claimant was confirmed as the owner of the Aircraft.
e. On 13 July 2010, the Defendant made a further written proposal to the Claimant for the completion of the work that had been suspended, various inspections and maintenance. The proposal provided that certain works were to be proposed under a Contract Change Order (CCO) process. The proposal set out terms and conditions for the conduct of the work.
f. On 13 July 2010, the 2010 proposal was signed by Mr Sam Iwuajoku (the Claimant's CEO) for the Claimant and Mr Paul Williams for the Defendant. From July 2010, the Defendant worked on the Aircraft under the 2010 proposal.
g. The Defendant told the Claimant that the work was substantially complete in February 2012, and then conducted test flights. During the course of the work to that point, the Defendant issued around 77 CCOs, all but 10 of which were signed by the Claimant.
17 February 2012
Charges made for work done and materials supplied
Hangarage, systems checks and engine runs
"It has had two years of flying in all sorts of conditions, different heat applied to the aeroplane going from very high temperatures in Africa to altitude and, you know, you have got different coefficients of expansion to the steel bolts to the wing skin alloys, you're going to get movement, particularly in an old aeroplane, and water will get in. If it's present, it will get in, as will moisture …"
Assessment, planning and estimating
Lien, conversion and final matters