QUEEN'S BENCH DIVISION
COMMERCIAL COURT
B e f o r e :
(Sitting as a Deputy High Court Judge)
____________________
SC DG PETROL SRL | Claimant | |
VITOL BROKING LIMITED | ||
VITOL SA | ||
BOGDAN PAICU | Defendants |
____________________
MR. CHRIS SMITH (instructed by Clyde & Co LLP) for the First and Second Defendants
MS. SOPHIE HOLCOMBE (instructed by Reed Smith LLP) for the Third Defendant
____________________
Crown Copyright ©
Introduction
The procedural course
The realisation of assets
(1) The Claimant is in an insolvency procedure but a business continues.(2) The Claimant's preference was to sell land in Bucharest to provide security. It found a purchaser, at a price of around Euro 500,000. The sale price (not the concept of sale) led to an objection from a minority creditor that was pursued before the Romanian Court. That challenge was resolved in favour of the Claimant but not until 17 September 2013. The creditor is now pursuing an appeal and the estimated time for hearing the appeal is late January or early February 2014. Legal opinion expects the appeal court (whose decision is final) to uphold the decision under appeal and allow the sale. In a parallel development on 5 December 2013 another, slightly higher, offer was received from a different prospective purchaser.
(3) An alternative source of security identified by the Claimant has been the sale of five filling stations. Indeed this source was identified as the source of a larger "fighting fund" for the current proceedings recognising that the security ordered to date is only to the stage of exchange of disclosure lists, and the Claimant has its own legal costs to meet. However the sale of these stations forms, according to the Claimant, part of a Reorganisation Plan and that Plan unexpectedly failed to gain the required approval of the relevant judge in Romania, the Syndic Judge. An appeal is being pursued before the appeal court. The Claimant refers to the possibility of selling the stations notwithstanding the appeal, but acknowledges that any opposition will delay that process. It is in order to allow for these avenues to conclude that Mr Scorey seeks an extension of time to as late a date as May 2014.
(4) The Claimant has other assets (terminals and inland depots are mentioned) and says it would be willing to sell these although adding that "the same problems will be encountered in any event" (paragraph 28 of the fifth witness statement of Mr Dan Igniska made on Thursday 5 December 2013, the day before the hearing last Friday). There are no details of any current effort to sell these other assets.
(5) Mr Igniska, a shareholder in the Claimant, originally offered a charge over property he owns in Romania as security. This was declined by the Defendants, and Mr Igniska then also found himself unable to use the property to obtain a bank guarantee which could stand as security for costs. He has more recently offered to sell property and other assets, but has not done so. He adds "… given the current financial climate, I could not predict how long any such sale would take" (paragraph 29 of his fifth witness statement, referred to above).
(6) Save insofar as Mr Igniska himself is a creditor as well as a shareholder, the Court has been provided with no evidence of the ability of the creditors of the Claimant to resource the required security from their own assets.
Application for relief from sanctions
"On an application for relief from any sanction imposed for a failure to comply with any rule, practice direction or court order, the court will consider all the circumstances of the case, so as to enable it to deal justly with the application, including the need –
(a) for litigation to be conducted efficiently and at proportionate cost; and
(b) to enforce compliance with rules, practice directions and orders."
(1) "It will usually be appropriate to start by considering the nature of the non-compliance with the relevant rule, practice direction or court order": see [40]. "If the non-compliance cannot be characterised as trivial, then the burden is on the defaulting party to persuade the court to grant relief. The court will want to consider why the default occurred. If there is a good reason for it, the court will be likely to decide that relief should be granted.": see [41].(2) "Later developments in the course of the litigation process are likely to be a good reason if they show that the period for compliance originally imposed was unreasonable, although the period seemed to be reasonable at the time and could not realistically have been the subject of an appeal.": see [41]. "… [G]ood reasons are likely to arise from circumstances outside the control of the party in default": see [43].
(3) On an application for relief from a sanction a submission that the sanction should not have been imposed in the first place would be "misguided": see [44]. "On an application for relief from a sanction … the starting point should be that the sanction has been properly imposed and complies with the overriding objective": see [45]. "An application for relief from a sanction presupposes that the sanction has in principle been properly imposed. If a party wishes to contend that it was not appropriate to make the order, that should be by way of appeal or, exceptionally, by asking the court which imposed the order to vary or revoke it under CPR 3.1(7)": see [44].
Other applications
(1) The circumstances in which the court might appropriately exercise its discretion to vary or revoke the order are "normally only (i) where there had been a material change of circumstances since the order was made; (ii) where the facts on which the original decision was made had been misstated; or (iii) where there had been a manifest mistake on the part of the judge in formulating the order. Moreover … the application must be made promptly." This approach is required because "considerations of finality, the undesirability of allowing litigants to have two bites of the cherry and the need to avoid undermining the concept of appeal all require[] a principled curtailment of an otherwise apparently open discretion.": see [44], following Tibbles v SIG plc (trading as Asphaltic Roofing Supplies) [2012] EWCA Civ 518; [2012] 1 WLR 2591.(2) "If the application for relief is combined with an application to vary or revoke under CPR 3.1(7) then that should be considered first and the Tibbles criteria applied": see [45].
Disposition
(1) The non-compliance cannot be characterised as trivial. The Claimant realistically accepts as much through Mr Scorey. The burden is therefore on the Claimant to persuade me to grant relief.(2) Eder J's order required security to be provided and provided in good time. He had already allowed an extension of time, and even that had been materially exceeded.
(3) It has been the Claimant's choice to confine its efforts in the last 6 months to provide security to attempts to realise certain assets, rather than to respond to circumstances by extending its efforts to seeking other sources for the security. Whilst the Claimant offers explanations of why it has been frustrated in its attempts to realise assets of its choice, there is no good reason for the default.
(4) The creditors of the Claimant stand to gain if the Claimant is successful in the proceedings. The absence of any evidence from the Claimant of the ability (or rather, any inability) of the creditors of the Claimant to resource the security from their own assets, leaves me further unpersuaded.
(5) Although "good reasons are likely to arise from circumstances outside the control of the party in default", and some things have happened that are outside the Claimant's control, the Court has not been provided with anything like an adequate account of matters within its control.
(6) Individual developments in the form of challenge to the realisation of the land and the view of the Syndic Judge have not rendered the period for compliance originally imposed unreasonable. The Court was setting a period for the provision of security for costs. The fact that it considered evidence and argument directed to the realisation of particular assets does not mean that its order was confined to the realisation of those assets. 28 days was first allowed at the first Case Management Conference. The Claimant then effectively enjoyed a further period of twice that length between the expiry of the 28 days and the hearing of the second Case Management Conference. Eder J then allowed a further six weeks. That period remains in my view reasonable.
(7) It is most unlikely that the Claimant and its creditors, with the benefit of their experienced legal advisers, would not have given thought to how to resource the litigation, including potential security for costs or ultimate adverse costs orders, before the litigation commenced. By the date of the first Case Management Conference the application for security had been pending for a month and the litigation had been on foot for six months. This too was all time available to the Claimant.
(8) To grant an extension of time and relief from the sanction would be to leave compliance with an order for security for costs unenforced in a case in which the provision of security was justified. The litigation would have to remain idle for a further extended period; there is little that could appropriately be done in the meantime to manage it towards trial. Already Eder J's case management directions marshalling the case towards the point of consideration of the appropriateness of a Mediation Order or a split trial have been disabled, yet such consideration is a material part of the active case management that the Court is required to give to further the overriding objective (see CPR 1.4(1) and (2)(d) and (e)).
(9) I have referred to the submission of the Claimant that it could issue fresh proceedings if the present claim remains struck out. If it was clear that it could, then considerations of efficiency and proportionate cost might argue in favour of relief from the sanction of a strike out in some cases. But it is not accepted by the Defendants that the Claimant could issue fresh proceedings without being met successfully by, for example, an argument of abuse of process. This point being at issue, and taking into account also the possibility that what underlies the breaches of order that have occurred is the fact that the Claimant is not serious about its claim and so might choose not to start again, I am not persuaded that considerations of efficiency and proportionate cost argue in favour of relief from the sanction of a strike out in the present case.
(10) The application for an extension of time was not made promptly. The day it was issued was the day the claim stood struck out. The Claimant knew that that was the inevitable position when it decided to leave it until 17 October to issue the Application in circumstances where only an order and not the mere issue of an application seeking an order would prevent the sanction taking effect automatically in accordance with the order of Eder J.
Further Observations