QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Strand, London, WC2A 2LL, |
||
B e f o r e :
(SITTING AS A DEPUTY JUDGE OF THE HIGH COURT)
____________________
LISNAVE ESTALEIROS NAVAIS SA |
Claimant |
|
- and - |
||
CHEMIKALIEN SEETRANSPORT GmbH |
Defendant |
____________________
Christopher Smith (instructed by Fleet Hamburg LLP) for the Defendant
Hearing date: 19th February 2013
____________________
Crown Copyright ©
Mr C Edelman QC:
The application
The Issue
The facts
The terms of the Fleet Agreement and the Arbitration Agreement
"This agreement is made on 11th September 2007
Between:
Lisnave...
And
Chemikalien Seetransport GMBH
(hereinafter referred to as the "Owners")
B. Pricing
Dry-docking and repairs to the Owner's fleet of vessels will be carried out under the terms of this Agreement, and the Prices, Terms, and Conditions quoted for individual vessels as may be requested by the Owners.
C. Additional Work
Prices for additional work will be processed within 24 hours after receipt of request from Owners Representative.
D. Delivery
The Yard will quote the delivery time based on two shift working (Monday-Friday) and week-end working as required to meet vessel's commitments.
E. Penalty/Bonus
The Yard will accept a Penalty Clause for late delivery for work not completed by the agreed delivery time. The daily rate of Penalty shall be agreed on a vessel by vessel basis.
F. Payment terms
Total agreed invoice amount to be paid as follows:
- Forty (40) pct upon completion of repairs.
- Thirty (30) pct within 30 days after completion of repairs.
- Balance within 60 days after completion of repairs.
G. Organisation & Planning
The Yard will appoint an exclusive Project Management Team for the Management of the repair contract on each and all of the Owners' vessels.
... The Owners will provide the yard with a schedule of the vessels due for repairs during the period of this Agreement...
H. Service Engineers and Subcontractors
...Owners' subcontractors will be permitted to work on board vessel subject to mutual agreement on a case by case basis.
I. Vessel Discount
A discount will be applied to the Final Agreed Invoice Value for each vessel as follows:
Final Agreed invoice value | Discount |
Below €500,000 | Nil |
€500,000 to €1,000,000 | Three (3) percent |
Over €1,000,000 | Five (5) percent |
J. Fleet Rebate
In addition to the Vessel Discount, the Yard will grant proportionately to each vessel on the accumulated net invoice value on a year by year basis as follows:
Accumulated final net invoice value | Rebate |
0- Euro 1,000,000 | Nil |
Euro 1,000,000-Euro 3,000,000 | Four (4) percent |
Euro 3,000,000-Euro 5,000,000 | Six (6) percent |
Over Euro 5,000,000 | Ten (10) percent |
K. First Refusal
Based on the vessel repair schedule supplied by the Owners (Clause G) the Yardwill offer the Owner first refusal of drydock available and manpower capacity.
The Owner will grant first refusal to the Yard of any vessel trading in Yard's catchment area. "
"Article 15
ARBITRATION AND LEGAL PROCEEDINGS
15.1 The Agreement shall be governed by and construed in accordance with the laws of England and Wales.
15.2 All disputes arising in connection with the Agreement shall be referred to arbitration in London and be conducted in the English language in accordance with the Arbitration Act 1996. ...
15.5 Lisnave may, notwithstanding any of the aforesaid provisions of this Article institute legal proceedings in any court of competent jurisdiction where the Vessel or any sister vessel is to be found or where the customer may have other assets or legal representation, in order to enforce its rights under the Agreement and in particular any claims for payment under Article 8.
15.6 In particular, but without limitation to the generality of the provisions of Article 15.5 above, Lisnave may, in its absolute discretion, institute proceedings in the Maritime Tribunal of the Judicial District of Lisbon, Portugal, in order to enforce its rights under the Agreement and in particular any claim for payment under Article 8. "
The course of the arbitration and the Award
The law
(a) Implied Terms
"The only other ground on which it would seem possible to import these conditions is that based on a course of dealing. If two parties have made a series of similar contracts each containing certain conditions, and then they make another without expressly referring to those conditions it may be that those conditions ought to be implied. If the officious bystander had asked them whether they had intended to leave out the conditions this time, both must, as honest men, have said "of course not. ""
" Would the parties have agreed that a particular term formed part of the contract if they were reasonable men looking at the matter objectively in the knowledge that no adverse consequences could flow from the answer... The term will only be contractual if the parties' answer would have been a definite "Yes". "Possibly" will not do. "
"Does it matter that previously the buyers either dealt with a different Tradax company or in a different commodity and not on CIF terms? The Board of Appeal thought not and I can see no reason to disagree. It is noteworthy that the broker's telex never identified the Tradax company concerned. This was left to the sellers ' agents. I have no doubt that it was immaterial to the buyers. They were dealing with the Tradax organisation and which member of the clan was the seller really did not matter. "
"[T]he court does not make a contract for the parties. The court will not even improve the contract which the parties have made for themselves, however desirable the improvement might be. The court's function is to interpret and apply the contract which the parties have made for themselves. If the express terms are perfectly clear and free from ambiguity, there is no choice to be made between different possible meanings: the clear terms must be applied even if the court thinks some other terms would have been more suitable. An unexpressed term can be implied if and only if the court finds that the parties must have intended that term to form part of their contract: it is not enough for the court to find that such a term would have been adopted by the parties as reasonable men if it had been suggested to them: it must have been a term that went without saying, a term necessary to give business efficacy to the contract, a term which, though tacit, formed part of the contract which the parties made for themselves"
"The question of implication arises when the instrument does not expressly provide for what is to happen when some event occurs. The most usual inference in such a case is that nothing is to happen. If the parties had intended something to happen, the instrument would have said so. "
In some cases, however, the reasonable addressee would understand the instrument to mean something else. He would consider that the only meaning consistent with the other provisions of the instrument, read against the relevant background, is that something is to happen. The event in question is to affect the rights of the parties. The instrument may not have expressly said so, but this is what it must mean. In such a case, it is said that the court implies a term as to what will happen if the event in question occurs. But the implication of the term is not an addition to the instrument. It only spells out what the instrument means.
(b) Arbitration agreements
"In my opinion the construction of an arbitration clause should start from the assumption that the parties, as rational businessmen, are likely to have intended any dispute arising out the relationship into which they have entered or purported to enter to be decided by the same tribunal. The clause should be construed in accordance with this presumption unless the language makes it clear that certain questions were intended to be excluded from the arbitrators' jurisdiction. "
"56. Similar considerations apply by analogy here. Given the close connection between the COA and the guarantee, and between the parties involved, one would expect them as rational businessmen to agree a common method of dispute resolution. It is correct that since there are separate arbitration agreements there would, absent agreement, be separate arbitrations but one would expect, in the interests of efficiency, expediency and costs, for there to be common tribunals, as indeed there are. It would be surprising to find that the parties actively agreed that the COA was to be subject to English law and arbitration but that they wished to have any dispute under the linked guarantee determined by some unspecified court in some unspecified jurisdiction according to some unspecified governing law. "
Lisnave's case
(1) The Fleet Agreement is, on its face, a complete contract. It is self-contained and detailed. It appears to have been carefully drafted and properly executed. It is not comparable with the informal forms of contract considered in the course of dealing cases: for example, the contract concluded by telephone in the SIAT case.
(2) The Fleet Agreement is a different type of contract to the individual ship repair contracts. It does not form part of a series of individual ship repair contracts. It does not require any ship repair work to be carried out. The Fleet Agreement regulates a different commercial relationship, that between Lisnave and CST as the fleet manager. It is far from obvious why any of the provisions of the General Conditions which apply to individual ship repair contracts should be incorporated into the Fleet Agreement.
(3) The course of conduct on which CST relies did not involve contracts to which CST was itself a party. As fleet manager and agent of the individual shipowning companies, CST was not a party to any of the prior contracts and did not incur any liability under those contracts. Although in SIAT v Tradax the Court held that a course of dealing applied even though the dealings had been with different companies within a group, the facts of that case were very different from this case. In SIAT v Tradax. SIAT had traded with a number of individual Tradax trading companies in the Tradax group in 81 prior transactions. In each case, the relevant contract included the Tradax documents clause. It was held not to matter which Tradax trading company had concluded the 82nd contract. Here, CST was the fleet manager and agent of the shipowning companies and was not another individual shipowning company, incorporated in Liberia or some other convenient location. It is a German company that was responsible for managing the fleet. There was no relevant course of dealing by reference to which CST as fleet manager, and Lisnave, agreed to submit their disputes to arbitration.
(4) The General Conditions by their own terms are limited in intended scope. The General Conditions are inapposite to apply to anything other than contracts for dry-docking and ship repair. They are not general conditions of trading, capable of general application. The General Conditions are entitled "General Conditions of Contract for Drydocking, Conversion, Maintenance and/or Repair of Vessels and Off-Shore Units". By their own terms, they are to apply to "all contracts for dry-docking, conversion, maintenance, repair and/or other work" carried out by Lisnave (Article 1.1). The Fleet Agreement is not such an agreement but is an agreement primarily concerned with the commercial terms on which repair services will be offered in the future and the provision of a fleet discount. It is far from obvious why the parties to the Fleet Agreement would have wished to incorporate any of the provisions from the General Conditions.
(5) Almost all of the terms of the General Conditions have no relevance to the Fleet Agreement and would make no sense if incorporated into the Fleet Agreement. Those provisions which regulate the repair work to be carried out by Lisnave, and the relative responsibilities of Lisnave and the vessel owner, have no applicability to the Fleet Agreement. Article 8 of the General Conditions, governing payment to Lisnave, has no applicability to the Fleet Agreement under which no payments to Lisnave are contemplated. Article 14.3 would make no sense if incorporated into the Fleet Agreement.
(6) The Fleet Agreement does not even include an agreement that the General Conditions should apply to future repair contracts for CST managed Vessels. Under Article B of the Fleet Agreement, Lisnave and the individual shipowning companies are free to agree any "Prices, Terms and Conditions" for future repair contracts. The fact that there is no commitment to apply the General Conditions to future repair contracts is inconsistent with the notion that the Fleet Agreement in some way incorporates all or even some of the General Conditions.
(7) Article 15 of the General Conditions is itself inapposite for incorporation into the Fleet Agreement:
a. Article 15.2 refers to the arbitration of all disputes arising "in connection with the Agreement". "The Agreement" is a defined term in the General Conditions: see Article 1.2. It means "the invitation to tender, Lisnave's tender and any amendments thereto, these General Conditions and any Special Conditions duly confirmed and agreed in accordance with the provisions of Article 2". It would make no sense to incorporate into the Fleet Agreement a provision which references invitations to tender, the tenders, amendments thereto and any Special Conditions.
b. Article 15.5 permits Lisnave to institute Court proceedings "in order to enforce its rights under the Agreement" and Article 15.6 permits Lisnave to commence proceedings in Portugal, notwithstanding the provision for arbitration in Article 15.2.
c. Insofar as CST contends that it is only part of Article 15 (ie Article 15.2) that is incorporated, without the definition of "the Agreement", it is far from obvious, that Lisnave and CST must have intended the Fleet Agreement to include part (but not all) of the dispute resolution provisions in the General Conditions.
(8) The Fleet Agreement is perfectly workable without any arbitration clause, still less the arbitration clause in the General Conditions which applies to individual ship repair contracts. Many perfectly workable commercial contracts are concluded every day without an arbitration clause. Furthermore, the fact that disputes between Lisnave and individual shipowning companies concerning an individual ship repair contract should be arbitrated does not compel the conclusion that disputes between Lisnave and CST concerning the subject matter of the Fleet Agreement must also be subject to the same method of dispute resolution, i.e. by arbitration.
(9) Ms Bandara's Witness Statement exhibits some further documents to support the proposition that "there is a close, and actually inextricable, relationship between the Fleet Agreement and the individual ship repair contracts" (paragraph 10 of the Witness Statement). Whether there is a "close" or even "inextricable" relationship between the ship repair contracts and the Fleet Agreement is beside the point; the closeness or otherwise of the relationship is not the test. In any event, the relative weakness of the link is illustrated by the fact that the Fleet Agreement did not even require the application of the General Conditions to specific individual ship repair contracts. The question in law is whether Article 15 is incorporated into the Fleet Agreement because that was what the parties must necessarily have intended.
(10) When CST pressed its claim under the Fleet Agreement, CST's lawyers invited Lisnave to agree London arbitration, implicitly acknowledging that this was not something which CST could compel. These invitations are not consistent with CST's current case that the Fleet Agreement obviously incorporated the General Conditions and Article 15.2 in particular.
(11) Even if there had been general words of incorporation in the Fleet Agreement, referring to the General Conditions, it is doubtful that this would have been sufficient to incorporate the arbitration clause, Article 15.2, as a matter of English law.
CST's case
(1) At the time the Fleet Agreement was concluded, the parties had concluded some 8-12 individual ship-repair contracts and these contracts made it clear that Lisnave provided its services subject the General Conditions and/or that any contract with Lisnave was subject to acceptance of the General Conditions.
(2) CST having negotiated the ship-repair contracts, and CST and the ship-owning companies having an identity of interest, the parties to the Fleet Agreement and the ship-repair contracts were, for all practical purposes, one and the same. In any event, the decision in SIAT v Tradax makes it clear that in the context of the incorporation of terms via a prior course of dealing, it is not essential that the parties to the immediate contract must be exactly the same as the parties to the prior course of dealing. It is sufficient if they are part of the same "clan". CST, as manager of the fleet, is part of the same "clan" as the ship-owning companies whose vessels make up that fleet (indeed, CST, given their managerial capacity, could be said to be the head of that clan).
(3) The General Conditions are germane to the Fleet Agreement. The Fleet Agreement contains various General Conditions which clearly are intended to apply as between Lisnave and the ship-owning companies (for instance Article F can only be construed as applying to payments to be made to Lisnave under the ship-building contracts and not payments under the Fleet Agreement as CST undertakes no obligation in the Fleet Agreement to make any payments to Lisnave). The General Conditions likewise stipulate the terms which govern the underlying ship-repair contracts. Furthermore, Article 1.1 of the General Conditions should be construed so as to apply to contracts in relation to drydocking etc, thereby encompassing the Fleet Agreement. Accordingly, save to the extent that they contradict the terms of the Fleet Agreement, the General Conditions must be germane to the Fleet Agreement.
(4) Even if most of the General Conditions are not germane to the Fleet Agreement, this is not a bar to the incorporation of Article 15.2 into the Fleet Agreement. It is entirely justifiable to conclude that the parties intended to incorporate the arbitration agreement contained in Article 15.2 into the Fleet Agreement but none of the other General Conditions. It is a standard feature of the process of incorporating terms from one contract into another of identifying which terms in the former are germane to the latter and only incorporating such terms. As such, the fact that there are terms in the contract being incorporated which have no relevance to the incorporating contract cannot be regarded as a basis for asserting that no terms should be incorporated whatsoever.
(5) The Fleet Agreement was not a standalone agreement and had no independent purpose or vitality without the individual ship-repair contracts. Rather, the Fleet Agreement was premised on further individual ship-repair contracts being concluded and sought to regulate the terms of such agreements. The purpose of the Fleet Agreement must have been to dictate the terms on which Lisnave were to offer to perform repair works to CST's vessels. If Lisnave truly was free subsequently to offer to perform ship-repair works only on terms which were inconsistent with the Fleet Agreement, the Fleet Agreement would be an entirely meaningless transaction. Further, whilst the Fleet Agreement did not expressly provide that the General Conditions were to apply to the subsequent ship repair contracts, the parties were aware that Lisnave insisted on contracting subject to the General Conditions, and that the General Conditions included an English arbitration clause. As such, the Fleet Agreement was inextricably linked to the individual ship-repair agreements and there is no reason to think that the parties, so far as law and jurisdiction was concerned, would want to treat the Fleet Agreement any differently to the individual ship-repair contracts.
(6) This conclusion is consistent with the views expressed by Lord Hoffmann in The Fiona Trust to the effect that rational businessmen are usually to be assumed to intend for any dispute arising out of the relationship into which they have entered to be decided by the same tribunal. The Fleet Agreement and individual ship-repair contracts form part of the same relationship between CST (whether acting in its own right or as agents for the individual ship-owning companies) and Lisnave, and hence it should be assumed that the parties intended any dispute arising out of that relationship to be decided by the same tribunal.
(7) Therefore, at the time the Fleet Agreement was concluded, the parties must have intended for any disputes thereunder to be resolved in the same way and in the same forum as any disputes under the individual ship-repair contracts, i.e. in arbitration by reference to English law as required by Article 15.2.
(8) A dispute under the Fleet Agreement is a dispute arising in connection with "the Agreement" for the purposes of Article 15.2. Article 1 of the General Conditions defines "the Agreement" as meaning "the invitation to tender, Lisnave's tender and any amendments thereto, these General Conditions and any Special Conditions agreed in accordance with the provisions of Article 2". Article 2.2 defines "Special Conditions" as "amendments to these general conditions". Accordingly, in circumstances where the Fleet Agreement clearly did vary the General Conditions (for instance Article 8 thereof relating to the time for payment of Lisnave's invoice), the Fleet Agreement amounted to "Special Conditions" and hence fell within the definition of "the Agreement" for the purposes of Article 15.2.
(9) Even if the Fleet Agreement does not fall within the General Conditions' definition of "the Agreement", this is not a bar to its incorporation into the Fleet Agreement. When incorporating terms from one contract to another it is permissible to apply a degree of verbal manipulation to those terms to bring them into line with the intentions of the parties to the latter contract. For instance, where a bill of lading purports to incorporate an arbitration or jurisdiction clause in a charter, the fact that that clause only refers to disputes under "the charter" being referred to arbitration is not a bar to its incorporation into the bill of lading. In such circumstances, the charter's arbitration clause will, within the context of the bill of lading, be construed or manipulated so as to be taken to refer to disputes under the bill of lading, see Stellar Shipping at paragraph 63(e).
(10) The views of the parties' lawyers, expressed some 4 years after the conclusion of the Fleet Agreement, can be of no assistance in ascertaining the parties' intentions at the time that agreement was concluded. In any event, the suggestion that CST's lawyers somehow acknowledged that Article 15.2 did not form part of the Fleet Agreement is incorrect.
(11) If there had been general words of incorporation, the inextricable links between the Fleet Agreement and the ship-repair contracts would mean that this is not a case where it was appropriate or necessary for the parties to have expressly referred to the arbitration agreement in the Terms and Conditions in order for the Court to be satisfied that they intended to incorporate it into the Fleet Agreement. In any event, an express reference in contract A to the arbitration agreement in contract B is not an immutable requirement for the incorporation of the arbitration agreement into contract A, see IRCP v Lufthansa Systems [2013] 1 Lloyd's Rep. 24 at paragraph 82 et seq.
(1) Article F of the Fleet Agreement defines when payment of any sums due to Lisnave under any subsequent ship-repair contracts must be made.
(2) In circumstances where the subsequent ship-repair contracts were negotiated by CST, and where the terms of the Fleet Agreement would have formed part of the matrix of fact against which those contracts were concluded, the obligations contained in Article F of the Fleet Agreement must have formed part of the subsequent ship-repair contracts.
(3) Accordingly, to the extent that a dispute arose as to when the ship-owning companies were due to make payment to Lisnave Under the subsequent ship- repair contracts, that dispute would be capable of giving rise to an issue about the true construction of article F of the Fleet Agreement under both the Fleet Agreement and the individual ship-repair contracts.
(4) Article I of the Fleet Agreement is another example of a provision which could give rise to disputes under both the Fleet Agreement and any subsequent ship repair contracts as it clearly affects the overall amount that Lisnave would be entitled to charge the ship-owning companies under those contracts.
(1) Any disputes under the Fleet Agreement would in all likelihood be subject to the jurisdiction of the Portuguese courts (by virtue of Lisnave being domiciled in Portugal and/or Portugal being the place of performance of the contractual obligation in question, i.e. the repair work to the vessels).
(2) Further, the Fleet Agreement would, in all likelihood, be subject to Portuguese law pursuant to Article 4 of the Rome Convention 1980. If the parties did not intend for the Fleet Agreement to be subject to the same jurisdictional regime as the individual ship-repair contracts, then there is no reason for concluding that the parties impliedly chose English law as the proper law of the Fleet Agreement or that the laws of England and Wales are the most closely connected with the Fleet Agreement (for the purposes of Articles 3-4 of the Rome Convention).
(3) Accordingly, if a dispute arose as to the true meaning and effect of the provisions of the Fleet Agreement then:
(i) In the event of that dispute arising under the Fleet Agreement, it would in all likelihood be decided by the Portuguese courts as a matter of Portuguese law.
(ii) In the event of that dispute arising under the individual ship-repair contracts, it would be decided by English arbitration as a matter of English law.
(iii) In such a scenario, there would be the risk of inconsistent judgments and the risk of the provisions of the Fleet Agreement bearing one meaning in the context of the Fleet Agreement itself and another meaning in the context of the individual ship-repair contracts.
(4) This cannot be what the parties intended, see the Fiona Trust and IRCP v Lufthansa [2013] 1 Lloyd's Rep. 24 at paragraphs 73 and 76, a decision of the High Court of Singapore.
Discussion
(1) Article 1.1 of the General Conditions provides for the General Conditions to apply to all contracts "for" dry docking etc. and the Fleet Agreement is not a contract "for" such work, with the result that the General Conditions are inapposite for application to the Fleet Agreement. Mr Smith sought to get round this point by equating the word "for" with "in relation to" so as to encompass the Fleet Agreement. Such a watering down of the effect of the word "for" is not tenable in the context in which the word is used. In its context, "for" is plainly intended to mean and only to mean "for".
(2) I agree with Mr Lockey's submission and reject Mr Smith's contrary submission that the words "arising in connection with the Agreement" in Article 15.2 are not wide enough as they stand to apply to the Fleet Agreement. Mr Smith sought to rely on the inclusion in the General Conditions within the definition of "Agreement" of "Special Conditions" and the definition of "Special Conditions" as meaning "any conditions by way of amendment to or in addition to those General Conditions" as being sufficient to encompass the Fleet Agreement as a whole. That does not seem to me to be the appropriate construction. What the definition of "Special Conditions" does is to ensure that any terms adopted as part of the ship-repair contract by way of amendment to or in addition to the General Conditions will be within the ambit of the "Agreement" for the purposes of the General Conditions and therefore for the purposes of Article 15.2. Those words are not sufficient to apply to the Fleet Agreement which is merely the source of the supply of amendments or additions to the General Conditions for the purposes of a particular Ship-Repair Contract. That would not of itself prevent the incorporation of Article 15.2 into the Fleet Agreement because, as Mr Smith rightly pointed out, if it was obvious that the parties intended Article 15.2 to apply, it could be read into the Fleet Agreement with appropriate manipulation but the fact that CST's case requires Article 15.2 of the General Conditions not only to be plucked out of the General Conditions for incorporation into the Fleet Agreement but also to be manipulated so as to fit into the Fleet Agreement makes it all the less obvious that the parties intended the clause to apply.
(3) The plucking out of Article 15.2 of the General Conditions is all the more difficult when it appears as part of a set of dispute resolution provisions which include Articles 15.5 and 15.6. Mr Smith sought to treat Articles 15.5 and 15.6 as mere surplusage, reflecting what in any event would be Lisnave's rights in rem as a ship repairer. However, as Mr Lockey rightly pointed out, those provisions are wider than the rights in rem. Article 15.5 confers on Lisnave the right to institute proceedings in any Court of competent jurisdiction where "the Customer may have other assets or legal representation" and Article 15.6 confers "absolute discretion" on Lisnave to institute proceedings in the Maritime Tribunal of the Judicial District of Lisbon. These provisions would seem to me to form an integral part of the overall scheme of Article 15 and there is no particular reason why the parties should be regarded as having intended to select Article 15.2 alone for the purposes of the Fleet Agreement. Mr Lockey gave the example of Lisnave having overpaid a rebate and wishing to recover its overpayment. If it were to seek to do so under the Fleet Agreement, it is not obvious that it would have been intended by Lisnave and CST that such recovery should only be through the route of an arbitration under the incorporated version of Article 15.2.
(4) Whilst there was in existence at the time of the making of the Fleet Agreement a course of dealings between Lisnave and ship owners for whom CST acted whereby the General Conditions would be applicable to ship-repair contracts, that course of dealing was not directly relevant to the Fleet Agreement and in any event CST does not seek to contend for the general application of the General Conditions (and could not so contend because they are inapposite to the Fleet Agreement) but seeks only to draw out Article 15.2 of the General Conditions.
Conclusion