QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Fetter Lane, London EC4A 1NL |
||
B e f o r e :
____________________
DGM COMMODITIES CORP |
Claimant |
|
- and - |
||
SEA METROPOLITAN S.A. |
Defendant |
____________________
Sara Cockerill QC (instructed by Holman Fenwick & Willan) for the Claimant
Hearing dates: 12 July 2012
____________________
Crown Copyright ©
The Hon. Mr Justice Popplewell
"Was the Charter-party frustrated?
136… the Charterers argued that on a date (see below) following the April order temporarily preventing the discharge of the cargo, the Charter-party was frustrated by the continuing (in)actions of the Veterinary Service and the delays engendered by them. The Charterers argued not that the April order was a frustrating event when it was made but that it proved not to be temporary; it remained in place until October 2008."
……………….
"139. The Charterers submitted that although the Veterinary Service's April order was supposed to be temporary, in the event it was not – it went "…on and on…" Counsel for the Owners described it as "shocking" and the Russian law experts in their joint memorandum said the Veterinary Service acted "…unreasonably and, unexpectedly…" and in breach of the law. The essence of the Charterers' case as expressed by counsel for the Charterers in her skeleton argument was that "…The continuation of the April Order, and the absence of any decision countermanding it, resulted in delays which made performance of the Charterparty in accordance with its terms impossible (or at least radically different from that contemplated)…"
140. The essence of the Owners' case was that this was not a situation in which the Charterers were prevented by some outside event from unloading the cargo. On the contrary, the Receivers chose to interrupt the discharge; the underlying reason for their continued failure to discharge the cargo was the continuation of their efforts to achieve an immediate cash settlement of their cargo claim and not to be left with a P and I Club LOU. As Mr Weiss-Lev said: "…it was all about money…" and "… we wanted either to get our cargo or to get our money…"
141. In the course of her closing submission, counsel for the Charterers invited us to consider a number of possible dates on which it could be said that the Charter-party was frustrated. The dates with the Charterers' comments were as follows.
(a) 29 April 2008…
(b) Early May 2008…
(c) Early May or early June 2008…
(d) Early July 2008…
(e) Late July 2008…
142. In the end what broke the impasse so as to enable the Vessel to sail away (albeit with the cargo still aboard) was in fact the cash settlement of the Receivers' cargo claim. As mentioned above, the option of re-exporting the cargo was not a new idea. …
143. From the contemporaneous correspondence, the role played by the Veterinary Service in achieving the breakthrough appears to us to have been necessary (in a bureaucratic way) but not sufficient and it was passive, not active. It responded (or failed to respond) to the parties' requests, rather than initiated anything. It appears to us that after the Owners and Receivers had reached their settlement agreement, on being requested to do so, the Veterinary Service merely granted the official permission. The correspondence reveals a simple request for permission to re-export the cargo and the granting of that request on 13th November 2008. Apart from the agreement of the Charterers to take the cargo back, there is no evidence that the Veterinary Service imposed any conditions or made any requests or otherwise exerted any directing influence.
144. Given the Veterinary Service's role in bringing about the resolution – essentially bureaucratic rather than instrumental, as we have found and described it above – we have concluded that we cannot agree with the Charterers' submission that it was "…The continuation of the April Order, and the absence of any decision countermanding it…[that] …resulted in delays which made performance of the Charter-party in accordance with its terms impossible (or at least radically different from that contemplated)…". On the evidence we have seen, there is no reason to suppose that, had the Owners and Receivers reached an accommodation earlier than they in fact did, the Veterinary Service would have been any less willing to grant the required permission than it was on 13th November 2008.
145. We agree with the Owners' submission that the real reason for the continued failure to discharge the cargo was the Receivers' desire to have a cash settlement of the cargo claim and the continuation of their efforts to achieve one, to the exclusion of other possibly more normal forms of settlement. That desire and efforts do not constitute a frustrating event. We do not consider that there was any obligation on the Owners to enter into any or any particular settlement with the Receivers and so it cannot be said that the Owners ought to have acceded to the Receivers' demands earlier. Had the Receivers been prepared to deal with what was prima facie a legitimate cargo claim by accepting proper security as was offered in the form of a P & I Club LOU (subject to establishing liability and quantum in the usual way), then apart from the delay in discharge that we have decided above would have occurred in any event [footnote: by reason of the Owners' breach] the subsequent delay would not have occurred.
146. In those circumstances we consider that the ingredients necessary for a finding of frustration are not present and accordingly we find and hold that the Charter-party was not frustrated either on any of the dates suggested by the Charterers or on any other date."
"Where a voyage charterparty is delayed without the fault of either party, in circumstances that would otherwise amount to frustration, but where those delays are in part caused and/or contributed to by the action or inaction of the cargo receivers (not being parties to the charterparty), is the charterparty frustrated? Or does that action or inaction mean that what would otherwise be frustration is "self induced" by charterers, such that charterers cannot contend that the charterparty is frustrated".
Submissions
(1)The Tribunal found that the charterparty had been frustrated by reason of the April order of the Veterinary Service, but that the plea of frustration failed because the Tribunal treated such frustration as self-induced or caused by the Charterers' fault.(2)The Tribunal thereby treated the Charterers as vicariously liable for the acts of the receivers in insisting upon a cash settlement.
(3)This involved an error of law: charterers are not liable for acts or omissions of receivers, save insofar as they constitute receivers' failure to discharge the cargo. Charterers are generally liable for a failure to discharge the cargo because that is within the ambit of what has been delegated by charterers to receivers. But this is a case in which the relevant conduct fell outside the ambit of something delegated by the Charterers to the receivers. The relevant conduct is properly characterised in either of two ways: it was receivers' conduct in pursuing their own commercial interests; or it was receivers' conduct preventing re-export of the cargo (as opposed to its discharge). In either analysis, as Ms Cockerill QC put it in argument, it is the "otherness from discharge" which is the key. Where delay is caused by receivers' acts or omissions other than in carrying out discharge, they are not to be attributed to the charterers so as to make what would otherwise be a frustrating event "self induced".
(4)The case is analogous to Adelfamar S.A. v Silos Mangimi Martini SPA, ("The Adelfa") [1988] 2 Lloyds Rep 466, which supports the above analysis and should have been applied so as to hold that the frustrating effect of the Veterinary Service's order was unaffected by the conduct or fault of the receivers.
(1)The frustration argument had been rejected in paragraphs 144 and 145 of the award on the basis that the frustrating event contended for was not causative of any delay.(2)The Tribunal had found in paragraph 146 of the award that the ingredients (his emphasis) necessary for a finding of frustration had not been established.
(3)Both these findings were findings of fact, each of which was fatal to the Charterers' frustration argument. Such findings of fact are not open to review on an appeal on a point of law under s.69 (see The Baleares [1993] 1 Lloyds Rep 215, 228 and the requirements of section 69 that an appeal must be on an issue of law and "on the basis of the findings of fact in the Award").
(4)The dichotomy argued for by the Charterers between receivers' acts in discharging the cargo, or failing to do so, (for which charterers are liable) and other acts of receivers (for which charterers are not liable) was not a distinction identified in the argument before the Tribunal, the arbitration claim form, or the formulation of the issue of law set out above. In any event, on the Tribunal's findings, the relevant causative activity was the failure of the receivers to discharge the cargo, which would fall within Ms Cockerill QC's formulation of that for which charterers bear responsibility.
(5)The Adelfa is distinguishable.
Analysis and conclusions
(1) The relevant conduct described in paragraphs 19 to 53 of the award is conduct by which the receivers were failing to discharge the cargo for so long as they were maintaining an attempt (which the Tribunal found was unjustified) to be paid US$ 2 million or more in respect of the alleged damage to the cargo.
(2)Paragraph 140 of the award records the Owners' submission that it was not some outside event which precluded unloading the cargo but the receivers' choice to interrupt discharge. In paragraph 145 of the award the Tribunal expressly accepted that submission.
(3)Paragraph 145 of the award also contains a finding that the receivers' conduct was the reason "for the continued failure to discharge the cargo". This is a finding that what the receivers were doing was failing to discharge the cargo for the stated reason.
"Clause 5 of the Charterparty provided for the cargo to be discharged by the Charterers or their agents and clause 18 provided that the Vessel was to be discharged by the receivers' stevedores. It was common ground that, however the Charterers might choose to fulfil their obligation under clause 5, they were under a non-delegable duty to discharge the cargo. Therefore even if, as between the Charterers and Receivers, it was the Receivers' obligation to discharge the cargo, the position under the Charterparty remained that for the purpose of performing the Charterers' obligation to discharge the cargo, the Receivers were the agents or delegates of the Charterers and the Charterers remained responsible."
"(ii) Receivers' Acts
The second submission is that the charterers are vicariously liable for the delay caused by the receivers and their various actions described above. This argument in my judgment is misconceived. The charterers having undertaken, subject to exceptions, that the cargo will be discharged within the agreed period, they will clearly be liable if this is not done, notwithstanding that the discharging operation has become the responsibility of the receiver or of some other party and the charterer plays no part in it himself. Even if this can properly be described as delegating the charterers' contractual duty, it does not follow that the charterer becomes responsible, vicariously or otherwise, for the receivers and all that they do, or fail to do. The charterer can only be liable when there has been a failure to achieve what the charterers undertook to the shipowner would be done. There was, of course, a failure to discharge within the laytime, for which the charterers are liable in damages or demurrage. The vessel was detained by her arrest and the subsequent judgment. There is no undertaking in the charterparty, express or implied, that cargo receivers will not arrest the vessel, or seek to do so, at the discharging ports."