QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
ESSENTIALLY DIFFERENT LTD |
Claimant |
|
- and - |
||
BANK OF SCOTLAND PLC |
Defendant |
____________________
Mr Giles Wheeler (instructed by Eversheds) for the Defendant
Hearing dates: 21, 22, 23, 24 and 25 February 2011
____________________
Crown Copyright ©
Mr Justice Burton :
"6.01. The Borrower represents and warrants that:
(e) the information given by the Borrower in the Application was and remains true, complete and accurate in all respects and the Borrower is not aware of any such facts or circumstances that have not been disclosed to the Lender which might if disclosed adversely affect the decision of the person considering whether or not to provide finance to the Borrower.
10(01). If any of the following events occur, the Lender shall be under no obligation to advance monies hereunder and may by notice to the Borrower require repayment of all sums outstanding hereunder together with accrued interest thereon and/or cancel any portion of the Facility then undrawn, that is to say, if:
(b) any statement or representation or warranty made by the Borrower in or in connection with the Application of this agreement or any certificate, statement or document delivered or made by the Borrower pursuant hereto proves to have been incorrect or inaccurate when made or would be incorrect or inaccurate if made at any time during the continuation of this agreement."
i) Whether a condition precedent was agreed between the parties as alleged by the Defendant, in either form relied upon, justifying the non-payment of the second tranche: if so, whether the Facility Letter should be rectified so as to incorporate it.
ii) Whether there were material misstatements or misrepresentations (or non-disclosures) entitling the Defendant not to make payment of the second tranche and to recover payment of the first tranche.
iii) If neither of these arises, then, the Claimant's claim for damages for breach of contract thus being established, whether the Claimant can show that it suffered any material loss. The agreed format of the issue is whether as a result of the refusal by the Bank to release the second tranche of the loan the company was not able to exploit its own intellectual property and the patent and intellectual property rights licensed to it.
A case pleaded by the Claimant, based on implied terms, was not pursued.
The Condition Precedent
"(a) On 19 November 2003, Mr Mark Laming of the Credit Sanctioning department of the Bank informed Mr Cheetham that a loan to the Company of £245,000 had been approved, subject to the condition that the loan be in two tranches, the first being of £100,000 and the second to be drawn on the provision of evidence of contracts sufficient to service the full £245,000 debt after the costs of the business had been met.
(b) Mr Cheetham informed Ms Connelly of the Company that the loan had been approved subject to the said condition ("the Condition") on or about 20 November 2003.
(c) On behalf of the Company, Ms Connelly then informed Mr Cheetham that the company would agree to accept the loan subject to the Condition."
"Having been briefed by Jo Connelly it has come to my attention that [the Defendant] has imposed conditions restricting the drawdown of the second tranche on the basis that we are unable to supply documents that were not requested or mentioned in the contracted agreement.
I would like to express my surprise and concern that a condition to the drawdown has apparently been stipulated at the last minute without my prior knowledge and without any form of prior agreement We have now reached the appointed drawdown date without any member of [the Bank's] staff contacting us.
I have searched at great length through out records of the transaction and can find no mention of any requirement for as yet unsupplied documentation."
"I write to advise that the 2nd Tranche of the Small Firms Loan Guarantee Scheme was disbursed to your current account on the 22nd June prematurely. We have today corrected this error.
In order for us to release the 2nd Tranche, it is a requirement of the facility letter that the undernoted conditions are satisfied:
1. The Bank requires sight and satisfaction that the company can comfortable [sic] service the full £245,000 lending. Can you arrange to forward confirmation of contracts to support the cash flows.
2. An ongoing requirement is the receipt of Quarterly Management Accounts. To date, we have not received these. Please make arrangements for the latest quarterly Managements Accounts to be sent to this office.
3. There was a condition subsequent in the facility letter, which stipulates an assignation [sic] of life policy on the lives of Jo Connelly and Matthew Bate to the sum of £245,000 over the life of the loan (i.e. 60 months). This issue remains outstanding.
The points raised above are conditions, which must be satisfied prior to the release of the 2nd Tranche of your Small Firms Loan."
"Following discussions with both yourself and the Bank's legal advisers, I write to confirm the requirements to allow release of the second tranche of the loan. These conditions are
- the business to satisfy [the] Bank that sufficient contracts have been achieved to service the full loan after all costs of the business have been met."
"Our clients have passed us a copy of the attached email dated 20 November from Andrew Cheetham to Jo Connelly. You will note that it is stated in that email that "the remainder to be drawn on evidence of contracts sufficient to service £245k debt after all costs of the business are met". Your clients were therefore advised in writing of the condition at the time of agreement of the facility."
"Our clients' position is that it was understood and agreed before the facility letter was issued that the terms and conditions now in dispute would form part of the terms and conditions of loan if necessary, our clients will raise an action for rectification of the facility letter "
"To avoid [the Bank] unnecessarily issuing rectification proceedings, please provide us by return with full evidence clearly demonstrating that the parties agreed for the alleged conditions 1-3 to be included within the Facility Letter In the absence of such evidence, we strongly consider that any attempt by [the Bank] to rectify the Facility Letter will be unsuccessful."
"The conditions mentioned in [Mr Somerville's] letter of 25 June were the same conditions that had been discussed with you at meetings with Andrew Cheetham. There is no doubt in Andrew's mind that these conditions were discussed. The conditions which are disputed were imposed by the Bank's Credit Sanctioning Committee in response to your representations that you did not feel you would be able to meet the conditions imposed in its initial approval of 29 October 2003. The condition on the ability to service the debt is included in Andrew's email to Jo Connelly dated 20 November 2003. Andrew has a clear recollection of the condition being discussed with Jo Connelly. Indeed he recalls that Jo Connelly was delighted with the condition because she considered it easily achievable."
"Andrew Cheetham contacted Jo Connelly to advise that the facility had been granted subject to conditions. He explained the conditions to Jo Connelly. Andrew Cheetham has a clear recollection that Jo Connelly was delighted with them, since she thought they were easily achievable. The following day Andrew Cheetham emailed Jo Connelly saying:
"His actual wording remainder to be drawn in evidence of contracts sufficient to service £245k after all costs of business are met "
The phrase "his actual wording" is consistent with an earlier discussion with Jo Connelly about the fact that the Credit Sanctioning Committee had agreed to make the facility available subject to the condition about turnover, albeit that there was uncertainty about what the level should be."
"11. I think it is very likely that Mark Laming and I would have discussed the wording of a revised condition which was acceptable to Mark Laming and which I though EDL would accept. Therefore on 19 November 2003 Mark Laming wrote to me stating the wording of the second condition This wording was that the second tranche of the loan was to be drawn down only upon the prior provision of evidence of contracts won by EDL which were sufficient to service the complete debt of £245,000 after all costs of business are met.
12. On a date after EDL's rejection of the first condition, but before 29 November 2003, I verbally conveyed the details of the second condition to Jo Connelly of EDL
13. it is my recollection that the condition was discussed specifically with Jo Connelly of EDL as being a condition that had to be satisfied before the second tranche of the advance was released."
"I understand that, notwithstanding EDL's allegation that I did not discuss the second condition with EDL and that EDL did not receive my email of 20 November 2003, which I wholly refute, EDL claim that the condition was "unworkable" as "no figure had been mentioned" (at paragraph 67 of the witness statement of Jo Connelly). Again, my recollection is very different to that of Jo Connelly, I did discuss a figure with both Jo Connelly and Matthew Bate. I recall discussing a figure on the telephone before I sent my email on 20 November 2003, and I certainly discussed the figure at the meeting on 25 November 2003. The value of the contracts which would be required to demonstrate to the Bank that EDL had won sufficient business, in the three months from the first tranche of the loan being drawn down, such that it could be confident of being able to service its debt, as discussed and agreed with Jo Connelly and Matthew Bate as being achievable, was £120,000."
"The said approval was subject to the condition ("the Condition") that the second tranche of the loan would be available for drawdown only on the Company providing evidence that it had entered into contracts:
(i) with a value to the Company of £125,000 or more:
(ii) alternatively of sufficient value to service the full £245,000 debt after the costs of the business had been met."
"The Condition was further discussed between Mr Cheetham and Ms Connelly and Mr Bate of the Company at a meeting between them on 25 November 2003. At the meeting, Ms Connelly and Mr Bate reiterated the agreement of the Company (alternatively agreed on behalf of the Company) to the drawdown of the Second Tranche of the loan being subject to the Condition."
"33. The party seeking rectification must show that:
(1) the parties had a common continuing intention, whether or not amounting to an agreement, in respect of a particular matter in the instrument to be rectified;
(2) there was an outward expression of accord;
(3) the intention continued at the time of the execution of the instrument sought to be rectified;
(4) by mistake the instrument did not reflect that common intention.
34. I would add the following points derived from the authorities:
(1) The standard of proof required if the court is to order rectification is the ordinary standard of the balance of probabilities.
"But as the alleged common intention ex hypothesi contradicts the written instrument, convincing proof is required in order to counteract the cogent evidence of the parties' intention displayed by the instrument itself": Thomas Bates and Sons Ltd v Wyndham's (Lingerie) Ltd [1981] 1 WLR 505 at page 521 per Brightman LJ.
(2) Whilst it must be shown what was the common intention, the exact form of words in which the common intention is to be expressed is immaterial if in substance and in detail the common intention can be ascertained: Cooperative Insurance Society Ltd v Centremoor Ltd [1983] 2 EGLR 52 at page 54, per Dillon LJ, with whom Kerr and Eveleigh LJJ agreed.
(3) The fact that a party intends a particular form of words in the mistaken belief that it is achieving his intention does not prevent the court giving effect to the true common intention: see Centremoor at page 55 A-B and Re Butlin's Settlement Trusts [1976] Ch 251 at page 260 per Brightman J."
The Loan
"The purpose of the loan and timing I would request is as follows:
Tranche one initially £145,000 followed by £100,000 in three months. To be repaid over 10 years at a fixed rate with 12 months payment holiday. The payment holiday is requested due to the fact that we are selling enterprise level products which have a typically long sales cycle with an average of around 6 months. The fixed rate would be preferable to enable early repayment."
i) The first document is an undated file note by Mr Cheetham, which reads "Sanction As discussed with Mark Laming as per sanction and enclosed email. Confirmation of contracts of £120k required to show sufficient to service debt, before second drawdown of £145k can be released". Mr Cheetham suggested in evidence that the reference to "as per sanction" might have been to what he called an 'oral sanction', but I conclude that it is far more likely that it refers to the written sanction to which I will refer in (iii) below, while it is common ground that the email referred to is his email in (ii) below.
ii) This email, dated 17 November 2003, reads in material part:
"Have looked at the following current spend per month £5k Add interest of £2k per month.
Say allow margin of £10k spend per month £120k expenditure in first year.
All jobs start with a pilot of approx £25-30k and build up. So suggest an order for jobs to value £120k before receiving the rest of the money."
Mr Cheetham confirmed that these calculations, so as to total up to £120,000, were his own and were not discussed with the Claimant.
iii) The Sanction, an internal memo signed by Mr Laming, the Credit Risk Manager, dated 19 November 2003, reads as follows:
"I refer to your credit application requesting a Bank of Scotland approval limit of £245,000. I would advise that the status of this application is Conditional Approval.
Sanctioner's Comments
Per the terms of last sanction dated 29.10.03, noted that IBM partnership has been confirmed and that no company will provide a letter of intent confirming contract values.
Conditions
SFLGS loan to be drawn in two tranches, first one being £100k thereafter remainder to be drawn on evidence of contracts sufficient enough to serve £245k debt after all costs of business are met."
It is not suggested that this document was supplied or shown to the Claimant.
iv) The last such document is an email dated 20 November 2003. Because it is set out in a somewhat unusual way, the Claimant is dubious as to its authenticity, and, in any event, neither Mr Bate nor Ms Connelly have any recollection of seeing or receiving it at the time, before it was supplied to them under cover of the Defendant's solicitor's letter of 13 August 2004 referred to in paragraph 11 above. It reads in material part as follows:
"Subject: Re: Income needed to repay loan
His actual wording remiander [sic] to be drawn on evidence of contracts sufficient to service £245k debt after all costs of business are met. Which means I have got to decide figure
We need to ensure you have business insurance and life cover in place we can discuss at meeting."
I shall return to discuss and analyse these documents below.
"Profile: Computer Software: High Potential and dealing with large company's [sic[. Process of selling system call [sic] SmartBlobz.
Customer contact: Jo Connery [sic].
Deal: SFLG [the Scheme]: £100k now £145k in approx 3 months subject to evidence (see File)."
This seems to have accompanied a standard form "Hunter/Farmer handover sign off sheet".
Conditionality
i) Mr Laming, Credit Risk Manager, plainly required the "sufficient to service" condition, and it is submitted to be unlikely that Mr Cheetham, who had no authority of his own, did not comply with, and obtain agreement to, that requirement.
ii) Mr Laming had sought to impose the earlier condition of a letter of intent from one customer for a "sales order of circa £1m", which had been put to the Claimant and rejected, so that it is submitted to be wholly unlikely that Mr Cheetham did not do the same with the new and lesser requirement, which, he submits, was not rejected.
iii) As for the other two conditions precedent relied upon in the letters of 24 and 25 June, neither are in fact now relied upon to justify non-payment of a second tranche. The provision for management accounts was, on the Defendant's evidence, "standard", and would have been reasonably assumed by Mr Fulham and/or Mr Somerville to have been included in the Facility Letter, while the provision for life cover was plainly discussed (see the contested email of 20 November 2003, but also the chaser of 4 December 2003, referred to in paragraph 27 above), and, though not in fact contained in the Facility Letter, was recorded by the Defendant in the Handover sign-off sheet as having been a "Referral generated".
iv) Mr Wheeler relies particularly, in relation to the £120,000, upon Mr Cheetham's undated internal file note referred to in paragraph 26(i) above.
v) He places reliance on the fact that there was a change in the order of the first and second tranches after the meeting of 29 September 2003 and Ms Connelly's email of 1 October 2003 (referred to in paragraph 23 above), so as to have the £100,000 first and the £145,000 second, which, he submits, suggests that it was in compliance with Mr Laming's Sanction, which also contained the sufficient to service £245k condition of 19 November 2003, i.e. that that change must have been part of the imposition/agreement of the condition in the telephone conversation and/or meeting which followed after the Sanction.
vi) He relies upon Mr Cheetham's handwritten file note on transfer, set out in paragraph 30 above, to support Mr Cheetham's case that there was a condition.
vii) Finally, he relies upon what he called Mr Bate's unexpectedly 'over the top' reaction in his letter of 25 May 2004, referred to in paragraph 8 above. He submits that such reaction was only consistent with Mr Bate appreciating that there was now going to be imposed upon him a condition which he had thought he had successfully avoided once it had not been included in the Facility Letter, with which he now knew the Claimant could not comply: otherwise he would simply have asked to know what the condition was and what the unsupplied documents were, now being sought.
i) There is no record of its being accepted, required or imposed by Mr Laming. The Sanction, dated 19 November 2003, which responded to Mr Cheetham's 'suggestion' in his email to Mr Laming of 17 November 2003, of "jobs to value of £120k", makes no mention of it.
ii) It is suggested that there was must/would have been a conversation between Mr Laming and Mr Cheetham, in which there was agreement that the condition in the 19 November Sanction would be altered/ supplemented to that effect. Mr Laming has not been called. Mr Cheetham, to whose evidence I shall refer further below, has, as I have already indicated, no independent recollection; it was simply, by reference to his undated file note, that he concluded that there may have been what he called an 'oral sanction' by Mr Laming.
iii) I do not conclude that there is any basis for the suggestion by the Claimant that the 20 November 2003 email, which was originally supplied to the Claimant's solicitor by the Defendant's solicitor on 13 August 2004, is not genuine. Although neither Ms Connelly nor Mr Bate remembers receiving it, and there is no record of it on the Claimant's server, Ms Connelly did explain that a number of the Claimant's emails were lost when there was a problem with the Claimant's server, and not all emails could be recovered. On the assumption that it was sent, Mr Cheetham was passing on to the Claimant, probably after the conversation of 20 November 2003, the "actual wording", namely being that which Mr Laming had included in his Sanction of the day before, which I conclude therefore he must have mentioned to the Claimant in that telephone conversation. Mr Cheetham then continues "which means that I have got to decide a figure". This makes it clear beyond doubt in my mind that there had been no mention of, or agreement to, the £120,000 in the earlier conversation on 20 November 2003. It is simply not consistent (and, as I have indicated, is not in any way supplemented or explained by any independent evidence of Mr Cheetham) that he had already decided the figure, already mentioned it in the telephone conversation (though not in this email) and was implicitly referring to it by the email. He was, in my judgment, plainly saying that he would have (in the future) to decide the figure.
iv) The £120,000 does not appear in the handwritten handover note.
v) The £120,000 does not appear in either Mr Fulham's or Mr Somerville's letters of 24 and 25 June 2004, nor in the Defendant's solicitor's letter of 16 July 2004, nor their subsequent letter of 13 August 2004, which enclosed the copy of the 20 November email.
vi) Importantly, it did not surface, either in the course of, or after, the internal investigation carried on by Elaine Webster, which included her interview of Mr Cheetham, and resulted in the account in Webster para 17, which I have set out in paragraph 14 above.
vii) There was then nothing about it in his witness statement served for the purposes of this trial on 10 November 2010.
viii) It surfaced for the first time in his second witness statement, served just prior to the hearing, as set out in paragraph 17 above. When he gave his oral evidence, this is the one thing about which he professed himself to be clear. Given his acceptance of his lack of recollection of events perfectly understandable, more than seven years on it is obvious that he has drawn this conclusion (a) by reference to the undated file note set out in paragraph 26(i) above, but more significantly (b) in express response, as he said himself by way of preface to the revelatory paragraph 36 of his second witness statement, to the "EDL claim that the condition was "unworkable" as "no figure had been mentioned".
i) Going back to the wording of Mr Laming's Sanction of 19 November 2003, rather than to the two formulations of 24 and 25 June 2004, it has to be asked what is meant by "remainder to be drawn on evidence of contacts sufficient enough to service £245k debt after all costs of business are met". It is not of course the most elegant of expressions contacts is an obvious typographical error for contracts, and sufficient and enough are duplicative. But how is the sufficiency to be tested, and by whom? It is apparent that, given that the Defendant would have to be satisfied prior to payment out of the second tranche, the sufficiency, and the calculation of "all costs of business", which fell to be set off against the contracts in order to judge the sufficiency, would have to be tested after only three months of operation. But if the value of the contract is to be taken in its entirety and it might perhaps have lasted over a period then would not the costs of the business have to be off-set as against the term of the contract, rather than simply in respect of the 3-month period?
ii) In any event it would need to be clear what "costs of business" would be off-set against the value of the contract. Presumably the value of the contract would be its gross value (otherwise there would be argument as to what the value was). In that case, all the costs of performing the contract, as well as all other costs of the Claimant's business, would need to be off-set. The difficulty of this calculation becomes the more apparent from the email that Mr Cheetham sent to Mr Laming on 17 November 2003 suggesting the £120,000 (and to which suggestion, it will be recalled, Mr Laming made no reference in his response). Mr Cheetham arrived at his suggested figure of £120,000 on a very broad-brush basis, and one which he accepts that he did not discuss with Mr Bate or Ms Connelly. I have set it out in paragraph 26(ii) above. He calculated £120,000 expenditure (after allowing £3,000 per month "margin") in the first year, and therefore concluded that £120,000 would be necessary. He appears, therefore, to have been taking a 12-month period for the value of the contract, rather than the 3-month period canvassed by me above. But the significant factor appears to me to be that it is difficult to see where he got his estimates from, given the figures which the Claimant had supplied to him. Those figures included estimated expenses per month of more than £30,000. The Claimant's figure in their spreadsheets for "office" expenses was £2000, but if there is to be a genuine matching of expenses against the gross value of the contract, then all the other estimated expenses need to be taken into account, not least the costs of programmers, network purchase and operating expenses, telephone line rental and call charges, testing hardware and marketing, and this leaves aside any salary costs.
iii) Once again, as set out in paragraph 35 above, when I discussed the question of the alleged £120,000 condition, it would appear wholly unlikely that such a condition could have been consistent with the cash flow of £25,000 in the first three months, which was projected by the Claimant, as disclosed to Mr Cheetham.
i) and
ii) Mr Cheetham consistently uses the word "discussed", not only according to Webster para 17, but also throughout his first statement and even his second statement. The first time he uses the word "agreed" is in his second witness statement at paragraph 36, and that is in relation to the agreement of the alleged figure of £120,000. There was no evidence from Mr Laming, for example, that he had an oral agreement with Mr Cheetham such as Mr Cheetham suggested might have occurred, subsequent to his written Sanction.
iii) The other two alleged conditions precedent have not been pursued, and, although both were sought to be justified as proper requirements, it has never been said, whether by reference to contemporaneous documents or otherwise, that they were either of them agreed to be conditions precedent.
iv) The undated file note may well reflect an intention to seek "confirmation of contracts of £120k required", but it does not evidence any such agreement with Mr Bate or Ms Connelly, and I have already concluded that there was none.
v) There is an issue between the parties, which I do not need to resolve, as to whether the changeover of the figures for the two tranches was raised and agreed with Mr Bate and Ms Connelly on 25 November 2003, such that they had no reason to be surprised, and were not surprised, when that was the arrangement in the Facility Letter, or whether, as they allege, they had no idea that the two figures were to be transposed until they received the Facility Letter, and were so pleased finally to receive the money that they did not complain or draw it to anyone's attention, particularly as the second tranche would so soon thereafter be forthcoming. But, in any event, I do not conclude that the transposition of these two figures has any relevance to my resolution of the issue as to whether the condition precedent was agreed. There would be as good a reason for the Bank insisting upon such a condition precedent (which was to relate to the entirety of the £245,000 debt), whichever way around the tranches were to be paid out, and it does not to my mind make it any more or less likely that the condition precedent now relied on by the Defendant was agreed on 25 November.
vi) There is no mention in the handwritten handover note of there being a particular condition precedent, not to speak of the one that is now relied upon. What is says is simply "subject to evidence (see file)". Of course, it would support the fact that Mr Cheetham believed that there was some provision or other in place, and he may well have believed that he had "imposed" (a word used in Webster para 17), but that does not mean that he did.
vii) Finally, I am not satisfied that Mr Bate went 'over the top' in his letter of 25 May 2004, for the reason that Mr Wheeler contends. I am satisfied, as Mr Price submits, and Mr Bate explained, that he was extremely angry at the yet further delay that was taking place in the provision of finance, likely to put at risk the success of his project, as he saw it. There was already delay in relation to the provision of the first tranche (which the original Scheme literature had suggested he would have in a matter of weeks, and for which delay the Claimant subsequently received an apology from the Bank as being "delay outwith normal timescales for assessment and agreement of the loan" by Mr Somerville's letter of 16 August 2004), and he was now being faced with a then unexplained delay of a further month in relation to the overdue payment of the second tranche.
Misstatement
i) As set out more than once above, Mr Cheetham has no independent recollection of what occurred. Insofar as he now makes general statements as to what he must have done or known, I do not find myself able to accept them, unless they are drawn from contemporaneous documents, of which there are, as will appear, a significant number. The most significant document from the Defendant's point of view, not of itself to establish that there has been breach of contract/warranty by the Claimant, but in order to show what the state of mind of Mr Cheetham was at the time, is an undated document prepared by him and submitted to the Bank, which has been called the "Introduction/Purpose" document. It is clear that a good deal of statements made and information given in the documents supplied by the Claimant to Mr Cheetham during the period September 2003 to February 2004 found their way into the Introduction/Purpose document, consequently relayed on to the Bank and thus relied upon. In the event, although it may be that some information supplied was inaccurately reflected in that document indeed such is almost inevitable given that Mr Cheetham, doing the best as he could, was not an expert in software and could only do his best to reflect what he had been told Mr Wheeler relies not directly upon that document, but upon the contents of the documents supplied by the Claimant.
ii) It is important to bear in mind that which is set out in paragraph 23 above, namely that Mr Cheetham knew that, by the very fact that the application was under the Scheme, the Claimant could not have obtained finance in the ordinary way: and at least subliminally that such inevitably more risky lending was substantially cushioned by the 75% guarantee by the Government. Mr Wheeler rightly points out that Mr Somerville gave evidence that only some one in four applicants for support under the Scheme were in fact accepted by the Bank. However, that does not mean that it is not likely, indeed probable, that, even if the 'farmer' is in the event cautious, the 'hunter' can become extremely enthusiastic about a prospect which, if ordinary lending was in issue, might well have been rejected in limine.
iii) In the event, the Claimant did supply a great deal of information between November 2003 and February 2004. This did not just consist of two Business Plans (one supplied at the first meeting on 4 September and the second sent on 8 September and re-supplied on 29 September), a three-year forecast of financial projections by way of projected earnings and expenses on a dozen or more spreadsheets, a Sales Forecast and a number of detailed notes setting out information about the Claimant, its SmartBlobz concepts, its Partners (well known computer companies such as Sun Services, IBM and InterSystems), two versions (the second an update) of an "Interesting History and Latest Developments" and an Executive Summary, but also, on a continuing basis, a number of emails showing communications between the Claimant and Sun Services, InterSystems and a number of other companies to which I shall make reference below. If Mr Cheetham had read all that documentation at the time, particularly the emails, he would have known, for example, that the actual signing of any substantial contracts was still some way off and that SmartBlobz would need to be customised, demonstrated and tested for each potential customer and so as to satisfy each customer's requirements, before any such contract was to be signed.
iv) Subject to the subsequent supply of the later emails, it is important to note that the majority of the information supplied, particularly for example the Sales Forecast, was supplied as at September 2003, when it was anticipated both that the finance from the Defendant would be forthcoming in a matter of weeks, and (prior to 29 September 2003) that it would be forthcoming in one tranche, of £250,000, rather than in two. Mr Cheetham plainly knew, as time went by, that nothing could really get started until after the first tranche, which was in the event delayed until 25 February, and inevitably that that very delay would have, and must have had, an impact upon the Claimant's prospects.
v) It is difficult if not impossible to test the accuracy of the statements as one might otherwise have done by reference to what in fact occurred, by virtue of the fact that the Claimant's business never in the event took off on the Claimant's case, because of the Defendant's failure to make the second tranche. The accuracy of the statements made has therefore to be tested only by reference to the appropriateness/ justifiability of the statement at the time. Of course that is always the test for misrepresentation, but it is usually possible at least to draw inferences from what occurred thereafter. In this case, particularly as most of the statements complained of are assertions as to future prospects, and there is no suggestion of fraud or deceit, the Defendant's case is, and has to be in most cases, that the Claimant was representing to Mr Cheetham, and through him to the Bank, that it was in a position to undertake business when it was not, and Mr Cheetham had no knowledge that such was the case.
i) that the Claimant had completed development of SmartBlobz.
ii) that it was actively marketing SmartBlobz.
iii) that it was in a position to take a significant market share.
iv) that it was very far down the path to significant contracts.
i) In Mr Cheetham's Introduction/Purpose document, he himself says at the outset:
"[EDL] was set up 3 years ago, when the project started and no income has as yet been generated (hence a start-up has only been in development stage)."
ii) The 3-year forecast, prepared in September 2003, on the basis referred to in paragraph 45(iv) above, projected earnings in the first year of £3.2m. However, the application form under the Scheme, signed by Mr Cheetham at the meeting of 25 November 2003, recorded "Turnover expected in next 12 months" as £1.3m. It may be that Mr Cheetham understood what appeared to me from Ms Connelly's oral evidence to be the case, namely that she was being over-optimistic.
i) Executive Summary July 2003. This was not, as it happens, prepared by the Claimant for the Defendant, nor handed to it by the Claimant, but it was prepared for Wired Sussex (referred to in paragraph 23 above) who were to help find finance, and it would seem that it was supplied by Wired Sussex to the Defendant. The statement complained of is: "Formed in 2000, EDL has spent the last two and a half years developing a unique product set and is now in a position to take a significant market share." I do not conclude that this meant, or was to be taken as meaning, that they had concluded their development. I also conclude that it was an accurate statement of the Claimant's own belief as to the fact that it was in a position to take a significant market share because, as set out in its second Business Plan of September 2003, at p12, "EDL has the opportunity to obtain significant 'first mover' advantage with its products that will translate into future market leadership and high returns." At that stage, Ms Connelly stated in evidence, and was not challenged, there was no other similar product in the market.
ii) The second Business Plan of September 2003. Complaint is made that two particular statements were incorrect, the first two appearing under "Current Sales and Prospects", namely:
"Major Japanese bank
[EDL] has been asked to undertake a project for a large us bank This project will commence almost immediately and will provide an excellent reference for SmartBlobz Migration.
UK Stockbroker
EDL has provided migration, de-duplication and data cleansing for a project entailing the transfer of over £1.4m of mission-critical, live data records We are expecting to undertake another, larger project for the same company this autumn."
The first of them is said to be false in that "the proposed contract was with an unidentified contractor and not a major Japanese bank", and the second because "the proposed contract was with an unidentified contractor and not a UK Stockbroker". I do not conclude that either of those two aspects render either of the statements materially false. It appears that (albeit through an "unidentified contractor"), at that stage in September the Claimant was discussing a possible project with a Japanese bank, which would have used SmartBlobz, but that such project fell through, and Ms Connelly so informed Mr Cheetham in September. As for the UK Stockbroker, there was a project, which had by then been completed, for a UK Stockbroker, described in the Sales Forecast September 2003 as "test only", and it was then intended, the first project having been a success, to have a further, more substantial project for the same client, using SmartBlobz. In relation to both those projects and to a further paragraph headed "NHS", which I shall set out below, Mr Wheeler makes the general allegation, set out in paragraph 47 above, as to the Claimant asserting that it was, but in fact not being, in a position to undertake business. The NHS statement read as follows:
"IBM has recently been awarded the NHS Modernisation contract EDL is working at senior level to provide data management and information management services. We would expect a pilot to be in place by the third quarter of 2003."
Ms Connelly, as I accept, told Mr Cheetham at the meeting of 29 September, that IBM had not been granted the NHS contract, but that one of the Claimant's partner companies, InterSystems, was working on that project and the Claimant expected to be able to provide similar services to InterSystems. Email communications with InterSystems in relation to a number of possible contracts continued through until 2004, though heavily held up as a result of the delay in the financing, copies of which were supplied to Mr Cheetham. The last statement in the Business Plan complained of was under "Repayment of Loan", namely:
"[EDL] already has customers and is in dialogue with several large companies regarding the purchase of its products. These sales will generate sufficient revenue to cover our loan repayments."
It is clear to me that Mr Cheetham understood that the existing customers related to SmartBlobz data, and that the dialogue with several large companies related to SmartBlobz, and was indeed taking place, the sales projections for which appeared in the Current Sales Forecast referred to below.
iii) Brunel Report. This was a significant document for the Claimant to show the Defendant, being an analysis by Brunel University of the viability, from a technical point of view, of the Claimant's software. In the course of a factual background summary in the document, a few inaccuracies were set out with regard to the Claimant's business, as Mr Bate accepted. But I have no doubt whatever that Mr Cheetham placed no reliance on the background summary by the Appraiser, a Professor Clive Butler, when he had the information direct from the 'horse's mouth', but what he would have relied upon was the Appraiser's view. It is in my judgment significant that in the Introduction/Purpose document, compiled by Mr Cheetham, he stated:
"Below I have [a] summary of the findings of a report that was undertaken by [Brunel] University by Professor Clive Butler on 12/9/2003 which gave the Company a clean report confirming that [the] technology worked and a score of 68. Any score above 50 indicates that the technical proposal is strong and funding should be considered. SmartBlobz has many advantages over any other methods."
iv) Interesting History and Latest Developments. This was a document supplied after the meeting on 29 September 2003. Express complaint is made as to the truth of the statement under "Latest Developments" that:
"We are nearing completion of our latest project which is to publish the VCR Directory to the web via a SmartBlobz portal."
This was the Claimant's second project, after the Stockbrokers, and the Claimant was then nearing the end of that project. They had used SmartBlobz Data, and Ms Connelly gave evidence that they were, at that stage, still intending to use SmartBlobz to complete the project. Mr Wheeler marshals his general allegation, set out in paragraph 47 above, against the following passages in which there is reference to AEA Technology, Alcatel and InterSystems:
"AEA Technology, which we have been working with for a few months, have now asked us to provide 'proof of concept' for a project to collate the sensor data from the railways, trains and rail systems around the UK. This is a substantial project and SmartBlobz is currently in the lead for this contract.
On a similar theme, we have been in discussion with Alcatel for around 4 months and we are now starting to move forward. They are interested in SmartBlobz for two projects.
Our Partnership with InterSystems is also progressing well and InterSystems have identified several projects where they believe SmartBlobz will be available. [EDL] is working on a 'proof of concept' project for this company."
It is clear to me from the documents which I have seen, and which were supplied to Mr Cheetham, that, as at October 2003, the Claimant did indeed believe that it had a good chance of using SmartBlobz on projects with AEA, Alcatel and InterSystems. The correspondence with AEA, supplied to Mr Cheetham, was primarily in October 2003, and then seems to have gone cold (Ms Connelly says because of the delay in obtaining the finance from the Defendant), but was revived in February 2004. InterSystems similarly. The communications with Alcatel in September/October 2003 unfortunately ran into the sand, and could not be revived, but in the Current Sales Forecast, whereas Ms Connelly included a 75% chance of a contract with AEA by February 2004 and an 80% chance of a contract with InterSystems by November/December 2003, Alcatel was not included as a prospect. Again it seems to me important to note that in his Introduction/Purpose document, Mr Cheetham reported to the Bank that:
"These areas are currently being explored with Motorola, Sun and Alcatel. These sales may be a year in the future but the revenue would be very substantial for the Company."
v) Essentially Different Ltd Pricing and Sales. The complaint made is as to the words "[EDL] is making and will continue to make and service a number of direct sales, which will generate significant income". There is no doubt that Mr Cheetham knew that all there had been to date were the UK Stockbroker and VCR contracts, of which only the UK Stockbroker involved any "service", and that was only a test contract. The Claimant however did expect to make and service a number of significant direct sales contracts. Once again it is important to refer to Mr Cheetham's opening words in the Introduction/Purpose document, namely "No income has yet been generated".
vi) The Current Sales Forecast. This contained in draft form the Claimant's expectations as at September 2003 upon the assumptions referred to in paragraph 45(iv) above. I have already referred to AEA and InterSystems, and the Claimant's expectations, and their disclosure to Mr Cheetham of continuing correspondence. With regard to Sun Services, what was anticipated by the Claimant in that graph was a 75% chance of a contract as from January 2004. There were, and were disclosed to Mr Cheetham, continuing communications between the Claimant and Sun from October 2003 through to February 2004. I do not conclude that it was a false statement, as at September 2003, with the expectation that £250,000 would be coming in by way of finance in the very near future that (as it was put in the document) the "graphic illustrated the potential sales achievable from the sample of [EDL's] current, qualified sales prospects". Again, I return to the Introduction/ Purpose document where Mr Cheetham said "Although [they] have know [sic] signed contracts, I have seen various documents and emails to show the parties are very interested".
vii) Supporting Information for Bank of Scotland November 2003. The statement complained of is that "We are in the later stages of discussion with two senior directors of the rail division of AEA Technology. They have identified several projects in the next 3 months for which budgets have been assigned for SmartBlobz. These projects could lead to a national railway project". This is again said to be false, on the basis that it indicates that the Claimant was in a position to undertake business with SmartBlobz. I do not conclude that this is a false statement. I have referred to the communications with AEA above, from which Mr Cheetham could have appreciated, indeed it is clear from his own Introduction/Purpose document that he did appreciate, that there was still considerable work needed down the line by way of customisation and demonstration before it would be possible for the Claimant to sign a contract with AEA.
i) I do not conclude that the Claimant represented, or that Mr Cheetham believed, that development of SmartBlobz was completed. The 1 October 2003 email requested £50,000 for "set up of infrastructure necessary to support customers" and £10,000 for "set up of demonstration and test environments to enable us to fully demonstrate our product to potential customers" and, in the second tranche, £50,000 for "set up of a small consulting team to implement our technology". The "Purpose of Facility" was described in the Facility Letter itself as "Setting up infrastructure, employing staff and consultancy team, set up office and equipment and working capital". But above all, from the emails themselves, Mr Cheetham must have understood that work was still necessary on SmartBlobz before it could be connected up to, and synchronised with, the systems of the various companies with whom contracts were in the pipeline.
ii) It was not a misrepresentation to state that the Claimant was indeed actively marketing. They had no sales person or sales team yet hence the need, provided for by way of £15,000 in the first tranche in the email of 1 October 2003, for "appointment on a part time and partial contingency basis of Les Line as Head of Sales and Marketing": but there was no doubt that the Claimant was actively marketing, and the passages I have quoted above from the Introduction/Purpose document show that Mr Cheetham well understood that, even though "no income has yet been generated".
iii) It was also not a misrepresentation to state that the Claimant was in a position to take a significant market share. Given that they were the only product in the field at that stage and, as the Business Plan stated, had "significant 'first mover' advantage", such representation, insofar as it can be spelt out from what was said in all the information supplied to Mr Cheetham, was not a misrepresentation.
iv) Finally, the Claimant did make sufficient disclosure to Mr Cheetham to show him that Ms Connelly and Mr Bate were indeed on the path to significant contracts, albeit that, as he said in his Introduction/Purpose document "these sales may be a year in the future".
Conclusions on the Defendant's Counterclaim
Causation
i) When the first tranche came through, the Claimant took the opportunity to pay its Directors their unpaid salaries of some £25,000. Whether or not that was to be equated, as Mr Bate suggested, to the figure in tranche 1 allowed for "operating cost £25k", it meant that, in fact, there was that much less to be spent on further developing the project, and in any event, by June 2004, there was still some £35,000 approximately unspent in the bank. There were thus no reasons why the Claimant could not have continued with that money, expending it on a programmer and/or development or connectors and demonstrations for at least one of the potential targets of the Claimant company.
ii) In fact, as is common ground, the Alcatel project had come to nothing and, although there was some communication with InterSystems, AEA and Sun Services, there were no demonstrations prepared for any of them. By June 2004, Mr Wheeler effectively submits, there was, in any event, no future for the SmartBlobz project.
i) The expenses which, in its forecast given to Mr Cheetham, the Company had anticipated in order to generate the business which the £245k was intended to engender, were estimated at some £30,000 per month (as referred to in paragraph 39(ii) above). Even assuming that that was an over-estimate, and that a lesser sum would be needed to start with, there is little doubt that £35,000 would not have lasted very long.
ii) They were now back in the position they were, save for the amount left in the bank, prior to September 2003, when they were not in a position to fund what was necessary to secure what they saw to be exciting and profitable business. There had already been the delay between September 2003 and February 2004, which had lost them Alcatel, and which no doubt had lost them some credibility with those proposed customers or partners, particularly Sun Services, InterSystems and AEA, with whom they managed to pick up again in February 2004. Once again they were back in a position in which they were unlikely to be able to fund very much going forward, by way of satisfying clients through demonstrations and pilots. Although I must judge the situation as at June 2004, another factor to be borne in mind when considering what actually happened is that the Claimant was in fact unable to obtain any other financing, both by virtue of the provisions of Clause 9.02 of the Facility Letter preventing them from borrowing further without the Defendant's prior written consent, and against the background of the Debenture granted to the Defendant, and soon against the background of the threatened litigation with a major bank.