QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Pioneer Freight Futures Company Limited (in liquidation) |
Claimant |
|
- and - |
||
TMT Asia Limited |
Defendant |
____________________
(instructed by Holman Fenwick & Willan LLP) for the Claimant
Jonathan Crow Esq, QC & James Leabeater Esq
(instructed by Ince & Co) for the Defendant
Hearing dates: 1st & 7th April 2011
____________________
Crown Copyright ©
Mrs Justice Gloster, DBE:
Introduction
i) there are a number of cases where similar issues arise, which are of wider importance to the market, than this case alone;ii) I was told that the appeal in Lomas was going to be heard sometime in the Michaelmas term 2011; and
iii) I had, in any event, granted TMT permission to appeal the First Judgment.
Accordingly, on 1 April 2011, I gave an immediate interim judgment in the sum of $16,557,594.10, pending argument in relation to the new point on quantification.
TMT's new point
"13A. Alternatively, the amount of the claim is in any event overstated. The contracts numbered 5, 6, 7, 8, 11, 12, 13, 15 and 16 in Schedule 1 to the Amended Particulars of Claim ('the 2008 Contracts') all terminated according to their terms at the end of December 2008. In the premises set out in paragraphs 6.6 and 6.7 above, and on the true construction of the ISDA Master Agreement –
13A.1 no Settlement Sums fell due for payment from the Defendant to the Claimant under any of the 2008 Contracts in respect of the Contract Months of November or December 2008, and
13A.2 on the termination of the 2008 Contracts, any liability on the Defendant to pay any Settlement Sums to the Claimant in respect of the 2008 Contracts was extinguished once and for all.
13B. In the premises pleaded in paragraph 13A above, the amount that should be credited to the Defendant is understated by a sum of US$4,568,754.39 in respect of November 2008 and by US$4,962,517.47 in respect of December 2008. Even if the Claimant is otherwise entitled to judgment against the Defendant, the correct sum would accordingly be US$16,557,594.10, not US$26,088,856.94."
i) First, the 2008 Contracts were not subject to Automatic Early Termination because by December 2009 they had already expired, in the sense that the last Contract Month in respect of which payments had to be made, had passed. Under section 1(c) of ISDA 92, Automatic Early Termination applies to "all outstanding Transactions"[5]. Where Transactions are no longer "outstanding" they cannot be the subject of Early Termination (whether automatic or elective).ii) Secondly, and similarly, as held by Briggs J in paragraphs 75-79 of his judgment in Lomas, where the conditions precedent to payment under section 2(a)(iii)(1) of ISDA 92 remain unsatisfied at the natural expiry of the contract, any liability to pay the Defaulting Party is extinguished.
Contract Month | Contract No | Sum ostensibly due to Pioneer $ |
November 2008 | 5 | 1,582,918.13 |
6 | 1,582,918.13 | |
11 | 1,402,918.13 | |
TOTAL | 4,568,754.39 | |
plus net amount due to TMT as per Table A of the Amended Particulars of Claim in respect of all other contracts | 5,340,359.06 |
5,340,359.06 |
Total net amount due to TMT for November 2008 | 9,909,113.45 | 9,909,113.45 |
December 2008 | 5 | 1,716,172.49 |
6 | 1,716,172.49 | |
11 | 1,530,172.49 | |
TOTAL | 4,962,517.47 | |
plus net amount due to TMT as per Table A of the Amended Particulars of Claim in respect of all other contracts | 4,799,978.76 |
4,799,978.76 |
Total net amount due to TMT for December 2008 | 9,762,496.23 | 9,762,496.23 |
The issues raised by TMT's amended quantification of its liability
i) Are payment obligations which are suspended by virtue of section 2(a)(iii) of ISDA 92 nonetheless taken into account for netting purposes under section 2(c) ("the Netting Issue")? (This first issue raises the correctness of the decision in Marine Trade).ii) Can Automatic Early Termination apply at all to an FFA after the last Contract Month specified in that FFA has passed, prior to the Automatic Early Termination date ("the AET issue")? (This second issue raises the correctness of the decisions in Lomas and COSCO.)
iii) Is a suspended debt obligation extinguished once and for all at the end of the last Contract Month specified in the relevant FFA, such that it cannot be taken into account upon Automatic Early Termination ("the Expiry Issue")? (This third issue raises the correctness of the decisions in Lomas and COSCO.)
Relevant terms of the FFAs and ISDA 92
"5. Contract Period
Average of all BPI Index days of the contract month(s) up to and including the settlement date(s)."
"Contract Months" are defined in a FFA as the relevant months in respect of which a party has to pay a "Settlement Sum" (as also defined in a FFA).
Issue i): the Netting Issue
Section 2 of ISDA 92 and clause 10(a) of the FFA
"2. Obligations
(a) General Conditions
(i) Each party will make each payment or delivery specified in each Confirmation to be made by it, subject to the other provisions of this Agreement.
(ii) Payments under this Agreement will be made on the due date for value on that date in the place of the account specified in the relevant Confirmation or otherwise pursuant to this Agreement, in freely transferable funds and in the manner customary for payments in the required currency. Where settlement is by delivery (that, other than by payment), such delivery will be made for receipt on the due date in the manner customary for the relevant obligation unless otherwise specified in the relevant Confirmation or elsewhere in this Agreement.
(iii) Each obligation of each party under section 2(a)(i) is subject to (1) the condition precedent that no Event of Default or Potential Event of Default with respect to the other party has occurred and is continuing, (2) the condition precedent that no Early Termination Date in respect of the relevant Transaction has occurred or been effectively designated and (3) each other applicable condition precedent specified in this Agreement.
...
(c) Netting. If on any date amounts would otherwise be payable
(i) in the same currency; and
(ii) in respect of the same Transaction,
by each party to the other, then, on such date, each party's obligation to make payment of any such amount will be automatically satisfied and discharged and, if the aggregate amount that would otherwise have been payable by one party exceeds the aggregate amount that would otherwise have been payable by the other party, replaced by an obligation upon the party by whom the larger aggregate amount over the smaller aggregate amount.
The parties may elect in respect of two or more Transactions that a net amount will be determined in respect of all amounts payable on the same date in the same currency in respect of such Transactions, regardless of whether such amounts are payable in respect of the same Transaction. The election may be made in the Schedule or a Confirmation by specifying that subparagraph (ii) above will not apply to the Transactions identified as being subject to the election together with the starting date (in which case subparagraph (ii) above will not, or will cease to, apply to such Transactions from such date). This election may be made separately for different groups of Transactions and will apply separately to each pairing of Offices through which the parties make and receive payments or deliveries." (emphasis added)
"… a net amount due will be determined in respect of all amounts payable on the same date in the same currency in respect of two or more Transactions."
The decision of Flaux J in Marine Trade
"22. I have no doubt that Mr Baker's construction of the provision in section 2(c) is the correct one. As a matter of ordinary language, 'payable' clearly means now due and owing, for immediate payment and not only payable if and when some suspensive condition for which Mr Tselentis contends is satisfied. Quite apart from the ordinary meaning of language, when the agreement is considered as a whole, the word 'payable' in section 2(c) clearly means that there is a current enforceable obligation to pay. This is clear from the fact that, having talked about 'amounts which would otherwise be payable', the provision goes on to talk about 'each party's obligation to make payment' being 'automatically satisfied and discharged' by payment of the balance after netting. However, where Pioneer is affected by an Event of Default, as a consequence of section 2(a)(iii), Marine Trade has no obligation to make payment to Pioneer at all.
23 That 'payable' connotes an immediately enforceable obligation to pay is also clear from the definition of 'Unpaid Amounts' for the purposes of the calculation of the payment due on Early Termination. This refers to such unpaid amounts being 'the amounts that became payable (or that would have become payable but for section 2(a)(iii))' which demonstrates that the effect of non-compliance with the conditions precedent in section 2(a)(iii) is that the amounts have not become payable. That is only consistent with 'payable' meaning immediately due for payment and wholly inconsistent with Mr Tselentis' construction of 'payable' as somehow covering a situation where the payment obligation has been suspended. Mr Tselentis accepted that if his construction of 'payable' was wrong (which I do consider it to be), his argument on Issue 2 could not run.
24 Given what I consider to be the clear construction of section 2(c), it is not necessary to consider in any great detail the various arguments about the commercial purpose of the provision with which Pioneer sought to bolster its construction. The main thrust of those arguments was the alleged absurdity of a situation such as would obtain if Marine Trade were right, where a Non-Defaulting Party could insist that the Defaulting Party paid sums gross to it without netting off, even if, were the Non-Defaulting Party to designate an Early Termination Date under section 6 (which ex hypothesi it would not do) the calculation of the payment on such Early Termination would result in a substantial balance in favour of the Defaulting Party, because the Settlement Sums which would have become payable to the Defaulting Party but for section 2(a)(iii) fall to be considered in arriving at the eventual figure.
25 However, it seems to me that there is an obvious difference between what is to happen whilst the contract is subsisting and how the parties resolve their differences on early termination by way of 'wash-out'. As Mr Baker pointed out, in what might be described as orthodox contractual analysis, if one party is in default and that amounts to a repudiatory breach of contract, the other party can accept that repudiation as bringing the contract to an end and thereby terminate any of its own obligations for the future. To that extent, some of the Early Termination provisions of the Master Agreement might be said to be unorthodox, in the sense that they seek to balance the current and future obligations of the Non-Defaulting Party under the relevant futures transactions against those of the Defaulting Party. They are no doubt designed at least in part to ensure a 'wash-out' between the parties on termination which strikes a fair balance to reflect that transactions which by definition were going to continue for some time into the future have been terminated early.
26 However, it does not seem to me that what will happen on early termination necessarily has any connection with what happens when the relevant transactions are subsisting. Where the Non-Defaulting Party has chosen (as it is perfectly entitled to do) not to elect for early termination under section 6, I can quite see the commercial sense of being able to insist on 'gross' payment by a Defaulting Party.
27 In any event, even if it could be said that the commercial balance of the argument lay in favour of Pioneer, that is not enough to gainsay the clear meaning of section 2(c) as I have held it to be. This is not a case in which Pioneer has suggested that the construction for which Marine Trade contends is so unreasonable commercially that the court should endeavour not to construe the agreements in that way, applying Lord Reid's famous dictum in Schuler v Wickman Machine Tools [1974] AC 235 at 251."
The approach taken in Lomas
Flaux J's approach to the netting issue in COSCO
"92. Briggs J in Lomas accurately summarised my conclusion as: 'His view was that the clear language, in particular of Section 2(c), meant that credit only had to be given, by way of netting, for an amount that was payable, and not for an amount that, because of an unfulfilled condition precedent under Section 2(a)(iii), was not payable.' This issue was one of the issues raised by the appeal of Pioneer in Marine Trade, which was not pursued.
93. In the present case, the issue does not arise directly, since, after November 2008, neither party made any payment, Pioneer because it did not have the financial means to do so and Cosco because it was under no obligation to do so because of Section 2(a)(iii). It follows that the question of netting did not arise after Section 2(a)(iii) took effect in November 2008. Whether netting would have been possible in other circumstances where Section 2(a)(iii) had taken effect is thus an academic question. It is of no more than marginal relevance to the issue of whether contingent payment obligations survive in the case of transactions which have reached their natural expiry.
94. In his Skeleton Argument, Mr Thanki recognised this and said that this point was not essential to his argument, but that the view of all the parties in Lomas was to be preferred. By the time of the hearing, perhaps goaded by Mr Jacobs' submissions in his Skeleton Argument as to why my decision on the point in Marine Trade was correct, Mr Thanki had put in a detailed written Supplementary Note as to why my decision was wrong. He pointed out that my analysis, that netting was only available if there was a current, enforceable obligation to pay and not if the particular Settlement Sum was not payable because of non-fulfilment of the conditions precedent in Section 2(a)(iii), had been disapproved by textbook writers.
95. He drew particular attention to the intense criticism my decision had received in Henderson on Derivatives, a textbook by Schuyler K Henderson, an eminent American academic and consultant on derivatives law. Mr Henderson describes my decision variously as 'remarkable', 'astonishing' and 'bizarre'. He suggests that the flaw in my reasoning is a failure to recognise that, because Section 2(a)(i) says that it is 'subject to the other provisions of this Agreement', one of which other provisions is Section 2(c), both Section 2(a)(iii) and Section 2(c) should be read as referring back to Section 2(a)(i) independently and there is no reason to give primacy to Section 2(a)(iii) (see para. 20.18 of the second edition at p 1074).
96. However, with respect to Mr Henderson and Mr Thanki, who adopted his reasoning, my analysis in Marine Trade did not depend upon giving Section 2(a)(iii) primacy over Section 2(c). Assuming for present purposes that Mr Thanki is right in his submission that Section 2(a)(iii) is subject to, and logically anterior to, Section 2(c), Section 2(c) still only applies where, before netting occurs, there is an amount which 'would otherwise be payable' and 'an obligation to make payment of any such amount', but for the netting process. In the light of Mr Henderson's criticisms and Mr Thanki's submissions, I have reconsidered the issue of what those phrases connote in Section 2(c).
97. Mr Thanki relied upon the definition of 'payable' in Black's Law Dictionary (9th edition 2009): '(Of a sum of money or a negotiable instrument) that is to be paid. An amount may be payable without being due. Debts are commonly payable long before they fall due.' He also submitted that 'payable' meant different things in different contexts in the ISDA Master Agreement, pointing to various references to payment being 'due' or 'due and payable' but it seems to me that he could not point to anything, at least in the 1992 Master Agreement with which the Court is concerned, which suggested that 'payable' is being used anywhere in the Master Agreement in a contingent sense of 'payable, although the payment obligation is suspended' or in the sense to which Black is referring.
98. As I said in Marine Trade, it seems to me from the internal references within Section 2(c) to 'each party's obligation to make payment' being 'automatically satisfied and discharged' by payment of the balance after netting, that 'payable' in Section 2(c) connotes an immediately enforceable obligation to pay. Furthermore, the 'Unpaid Amounts' definition, which refers to 'the amounts that became payable (or that would have become payable but for Section 2(a)(iii))', makes it clear that the effect of non-compliance with the conditions precedent in Section 2(a)(iii) is that amounts did not become 'payable' for the purposes of netting under Section 2(c). Thus, in so far as it is necessary to decide this point in the present case, I consider that, where the conditions precedent in Section 2(a)(iii) have not been satisfied, netting is not available to the Defaulting Party, for the same reasons as I gave in Marine Trade."
TMT's submissions on the Netting Issue
Pioneer's submissions on the Netting Issue
i) First, the construction supported by Pioneer was consistent with the commercial purpose of section 2(a)(iii). As was held in paragraph 69 of the First Judgment, the "commercial function or purpose of the condition precedent to payment as set out in section 2(a)(iii) is to mitigate counterparty credit risk during the currency of what may be numerous swap transactions under the umbrella of ISDA 92 and while they remain open." That commercial purpose would be entirely fulfilled if Pioneer's construction (and the common ground in Lomas) were correct. In particular, if, following the netting process, it turned out that a net sum were due to a Defaulting Party in respect of a particular Contract Month, the effect of section 2(a)(iii) was to ensure that the Non-defaulting Party did not have to pay that sum while the Event of Default was subsisting. By way of contrast, the commercial purpose could not explain or justify an interpretation of section 2 of ISDA 92 which enabled the Non-defaulting Party to claim against a Defaulting Party on a gross basis, as found by Flaux J. The effect of that construction was that the Non-defaulting Party obtained a substantial windfall as a result of the Event of Default (or Potential Event of Default) of the other party. There was no sensible commercial rationale for such a result, and clear words would be needed in order for ISDA 92 to be construed in such a way. The words of section 2(c) were nowhere near clear enough for this purpose.ii) Second, a debt could be "payable" even if it was not "due and owing for immediate payment". The word "payable" could mean different things in different contexts. Flaux J was wrong to say that it meant "now due and owing, for immediate payment" as a matter of ordinary language. Black's Law Dictionary (9th edition 2009) defines "payable" as follows:
"(Of a sum of money or a negotiable instrument) that is to be paid. An amount may be payable without being due. Debts are commonly payable long before they fall due."[12]In ISDA 92, the word "payable" meant different things in different contexts. That was no surprise. Whilst ISDA 92 was a carefully drafted agreement, it was nevertheless clear that it was not in all respects internally consistent.[13] For example, in clauses within ISDA 92 where it was critical to refer to a debt which was actually due for payment, rather than merely accrued, ISDA 92 used the language of "due", or "due and payable", rather than merely "payable": see for example: (i) sections 5(a)(i) and (ii); section 5(a)(vii)(2); and section 5(a)(vi). The above provisions indicated that at times there was a distinction within ISDA 92, between the concept of a debt being "payable" and that of a debt being "due". In particular, if the word "payable", as used in ISDA 92, meant "due and owing for immediate payment", then that word could have been used in each of the examples listed above. It was noteworthy that it was not so used.The same distinction, between a debt being "due" and a debt being "payable" was inherent in the FFABA 2007 Terms: see clause 10(a).The later 2002 ISDA Master Agreement, by section 6(f), provided that an Early Termination Amount payable by one party to the other shall be set off against "other amounts payable by the Payee to the Payer (whether or not … matured or contingent)[14]". This was a further clear indication that, in the context of ISDA, the word "payable" was not ordinarily used in the narrow sense adopted by Flaux J, but in the broader sense suggested by Pioneer.Pioneer accepted that, in the definition of "Unpaid Amounts" in ISDA 92, the term "payable" was arguably used in the sense of "due and owing". However, even if that were right, the other provisions referred to above demonstrated that the word "payable" was not always used in that narrower sense in ISDA 92. Further and in any event, it was unrealistic to suppose that these words, used in parentheses in the context of an ancillary provision in ISDA 92, could themselves control the meaning of the word "payable" throughout the Master Agreement. That would be to allow the tail to wag the dog.Once it was seen that "payable" could be interpreted narrowly or broadly, depending on context, then much of the reasoning behind Flaux J's decision on the point was undermined.iii) Third, Flaux J's approach did not take account of the way in which section 2(a)(i) and section 2(c) interrelated. That approach assumed that, in applying section 2 of ISDA 92 it was first necessary to ascertain what sums were payable under section 2(a)(i), and only then, once those payment obligations were ascertained, to apply the netting process to the sums thus payable. But, that was the wrong way around. On a proper analysis of section 2 of ISDA 92, it was clear that section 2(a)(i) was subject to, and logically anterior to, section 2(c). That was clear from the fact that section 2(a)(i) was expressed to be "subject to the other provisions of this Agreement". Those other provisions included section 2(c).
It followed that, in order to ascertain what sum was payable under section 2(a)(i) it was first necessary to apply the netting process under section 2(c). In other words, the obligation to make a payment under section 2(a)(i) was always and necessarily an obligation to pay a net amount. It also followed that, where the first limb of section 2(a)(iii) suspended an obligation to make a payment under section 2(a)(i), what was being suspended was the obligation to make a net payment, after section 2(c) had been applied.iv) Fourth, in addition, the construction adopted by Flaux J had the potential to offend the anti-deprivation rule. Thus, in holding that section 2(a)(iii) did not offend the anti-deprivation principle in Lomas, Briggs J emphasised that he might well have come to a different conclusion were it not for the common ground on the approach to netting[15]. The anti-deprivation rule could be shortly stated. House of Lords authority, as interpreted in subsequent cases such as Perpetual Trustee v BNY Corporate Trustee Services [2009] EWHC 1912 (Ch), [2009] EWCA Civ 1160, held that:
"Where the effect of a contract is that an asset which is actually owned by a company at the commencement of its liquidation would be dealt with in the way other than in accordance with [the statutory provisions for rateable distribution to creditors] then to that extent the contract as a matter of public policy is avoided."[16]The provisions relied on by TMT, assuming they are to be interpreted in the manner relied upon by Flaux J, would have the result of depriving Pioneer of US$10 million in respect of the November and December 2008 Contract Months, by reason of Pioneer's insolvency.The very fact that the decision of Flaux J, if correct, led to the risk that the provisions might be struck down as contrary to the rule, indicated that his construction was wrong. As explained by Lord Hoffmann in BCCI v Ali [2002] 1 AC 251 at 269: "… the parties are unlikely to have intended to agree to something ... legally ineffective". Reference was also made to Lewison, The Interpretation of Contracts, 7.15:"Where two constructions of an instrument are equally plausible, upon one of which the instrument is valid, and upon the other of which it is invalid, the court should lean towards that construction which validates the instrument."
Accordingly, if there were otherwise any doubt as to whether Pioneer's construction of section 2(c) were correct, the fact that the alternative construction would arguably offend the anti-deprivation principle should encourage the Court to lean in favour of Pioneer's approach.
Decision to determine the Netting Issue notwithstanding settlement
Analysis of the Netting Issue
"In Charter Reinsurance Lord Mustill underlined the danger of focusing too narrowly on a critical phrase (in that case, a phrase defining the term 'net loss' as meaning 'the sum actually paid by the Reinsured in settlement of claims'), saying, at p.384G-H that:
'This is … an occasion when a first impression and simple answer no longer seem the best, for I recognise that the focus of the argument is too narrow. The words must be set in the landscape of the instrument as a whole. Once this is done the shape of the policy and the purpose of the terms … become quite clear'
Adopting that approach, the House concluded that the words "actually paid" were in context not intended to introduce a pre-condition of pre-payment by the insurer to the original insured, but to ensure that the reinsurers' liability was measured precisely by reference to any settlement of liability as between the insurer and insured. Later (at p.387D) Lord Mustill said that the principle that the liability of a reinsurer is wholly unaffected by whether the insurer has in fact satisfied the claim under the inward insurance is one which
'can undoubtedly be changed by express provision, but clear words would be required; and it would to my mind be strange if a term changing so fundamentally the financial relationship were to be buried in a provision such as clause 2, concerned essentially with the measure of indemnity, rather than being given a prominent position on its own.'"
"… what will happen on early termination necessarily has any connection with what happens when the relevant transactions are subsisting …"[21]
I disagree. In my view, it is much more likely that, given the commercial background, where, typically, there will at any one time be a number of open Transactions between the parties, the scheme was intended to be a cohesive one, governing the entire period of the relationship of the parties.
"… the commercial function or purpose of the condition precedent to payment as set out in Section 2(a)(iii) is to mitigate counterparty credit risk during the currency of what may be numerous swap transactions under the umbrella of ISDA 92 and while they remain open."
i) Assume A and B have five open FFAs in sterling where settlement sums are payable monthly on the same date.ii) Assume that on the Settlement Date[23], say 30 November, A is in the money if the net position under all five contracts is struck. Under each of contracts 1 - 4, the Settlement Sum[24] which B is obliged to pay to A is £3 million (£12 million in total). Under contract 5, the Settlement Sum which A is obliged to pay to B is £5 million.
iii) Two days later, on 2 December, A presents its invoice to B, which, in compliance with clause 10(a) of the FFA and section 2(c) of ISDA 92, determines the net amount due to A on the due payment date in respect of all five transactions, namely £7 million.
iv) Thus, on 7 December (five London Business Days after the Settlement Date) B is prima facie obliged to pay A £7 million. However, on 7 December, a Potential Event of Default occurs in relation to A; this occurs under section 5(a)(v) of ISDA 92[25], because A has defaulted under a Specified Transaction[26], although there has, as yet, been no liquidation or acceleration of obligations under, or an early termination of, that transaction, since the applicable notice period has not expired.
v) B does not pay the £7 million to A on 7 December, because of the potential Event of Default, relying on section 2(a)(iii).
vi) A pays the gross sum of £5 million to B on 10 December to minimise any obligation to pay Default Interest under section 2(e) of the FFA.
vii) Twenty days later, on, say, 27 December, the Potential Event of Default in relation to A is cured, because, for example, A's creditor in relation to the Specified Transaction waives the event of default, or A pays the amount due thereunder.
viii) One day later on, say, 28 December, administrators are appointed in respect of B, which is insolvent.
i) A was under an obligation on 7 December to pay B a gross sum of £5 million in respect of contract 5, without any netting off.ii) The automatic netting provisions of section 2(c) never kicked in to discharge A's obligation under contract 5 to pay to B the aggregate amount of £5 million. Nor would they have kicked in when A cured its potential Event of Default, because the sums were no longer payable on the same day.
iii) If A had indeed discharged the asserted obligation to pay £5 million gross to B, it would have been faced with subsequently proving for £12 million in B's insolvent administration or subsequent liquidation.
iv) Even if, in the above example, B had not become insolvent, A would have been exposed to a credit risk in respect of B in relation to £12 million gross during the period pending the resolution of A's Potential Event of Default and B's actual payment of the £12million.
v) Further, although this point strictly arises in relation to Issues ii) and iii), if TMT were correct in its submissions on those issues, once the final Contract Month (or the payment date in respect of such month) had passed in respect of a contracts 1-4, A would have lost forever its right to claim the £12 million, because the section 2(iii) condition precedent was not satisfied at the "natural expiry" of the contract.
i) to make the payment specified in each Confirmation (i.e. FFA) andii) to make it subject to the other provisions of "this Agreement" (ISDA 92).
i) a non-automatic consideration of whether there has been the occurrence of an Event of Default or Potential Event of Default; followed byii) no automatic netting off of aggregate amounts, but simply an ascertaining or taking account of the aggregate gross amount due to the Non-defaulting Party.
Non-determination of the AET Issue and the Expiry Issue
i) Pioneer and TMT settled this action prior to hand-down of this judgment;ii) I have determined the first issue, viz the Netting Issue, in Pioneer's favour and my decision on this issue would have been outcome-determinative of the case in Pioneer's favour in any event, if there had been no settlement;
iii) the fact that the AET Issue and the Expiry Issue are likely to be considered by the Court of Appeal on the Lomas and COSCO appeals in any event;
iv) the work pressures on the Commercial Court in relation to on-going cases are considerable;
I do not consider it appropriate, notwithstanding that I heard argument on the matters, to express my views in relation to the AET and Expiry Issues. However, it should not be assumed, from the fact that I have not done so, that I agree with the conclusions reached, by Briggs J in Lomas, or Flaux J in Marine Trade and COSCO, on, or in relation to these issues.
Conclusion
Note 1 [2011] EWHC 778 (Comm). [Back] Note 2 Due to my other commitments, it was not possible to list that case in front of me, although attempts were made to do so. [Back] Note 3 See on a similar point The Queen, on the application of Stamford Chamber of Commerce v The First Secretary [2010] EWCA Civ 992. [Back] Note 4 Contracts 5, 6 and 11. [Back] Note 5 See also paragraphs 36-37 of the First Judgment. [Back] Note 6 The due date for payments is stated to be on “… the later of two (2) London business days after presentation of payee’s invoice (with complete payment instructions) or five (5) London business days after the Settlement Date and for this purpose a ‘London business day’ means a day (other than Saturday or Sunday) on which commercial banks are open for business in London. The Settlement Sum will be deemed “paid” when it has been received into the bank account designated by the payee.” [Back] Note 7 In my First Judgment I held that clauses 10 and 21 of the FFABA 2007 terms applied to FFAs originally concluded on FFABA 2005 terms. Contracts 5, 6 and 11 were all originally concluded on FFABA 2005 terms. [Back] Note 8 See paragraphs 60 - 65 of Briggs J’s judgment. [Back] Note 9 See paragraph 64,ibid. [Back] Note 10 See paragraph 64,ibid. [Back] Note 11 See paragraph 93 of the judgment in COSCO. [Back] Note 12 Emphasis added. [Back] Note 13 See e.g. per Flaux J in Britannia Bulk plc v Pioneer Navigation Ltd [2011] EWHC 692 (Comm) at paragraph 43. [Back] Note 14 Emphasis added. [Back] Note 15 See paragraph 115 of his judgment. [Back] Note 16 British Eagle v Air France [1975] 1 WLR 758 as applied in Carreras Rothmans Ltd v Freeman Matthews Treasure Ltd [1985] 1 Ch 207 at 226E-F, approved by the Master of the Rolls, Lord Neuberger in Perpetual at paragraph 48. [Back] Note 17 See, for example, the definitions of Loss, Market Quotation, Set Off, Settlement Against Unpaid Amounts, etc. [Back] Note 18 See paragraph 62 of the First Judgment, and more generally paragraphs 47-108. [Back] Note 19 See paragraphs 109-188. [Back] Note 20 See per Moore-Bick J (as he then was) in Peregrine Fixed Income v Robinson Department Store plc [2000] CLC 1328 at 1336H - 1137B. [Back] Note 23 The last Baltic Exchange Index publication day of each Contract Month: see clause 6. [Back] Note 24 As defined in clause 8 of the FFA. [Back] Note 25 This provides, inter alia, that an event of default occurs if “the party … defaults under a Specified Transaction and after giving effect to any applicable notice requirement or grace period, there occurs a liquidation of, an acceleration of obligations under, or an early termination, of that Specified Transaction”. [Back] Note 26 As defined in Clause 14. or in the Schedule to ISDA 92. Such an agreement might be between the same parties to the FFA, or might be one, for example, between the Defaulting Party and a funder of the Non-defaulting Party. In fact, these cross-default provisions are very wide and permit a wide variety of transactions to be specified in the Schedule to ISDA 92. [Back] Note 27 See per Lord Mustill in Charter Re (supra) at 3849G-H. [Back] Note 28 Op cit at 1074. [Back] Note 29 See, for example, paragraph 98 of his judgment inCOSCO. [Back]