QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
TTMI Sarl |
Claimant |
|
- and - |
||
Statoil ASA |
Defendant |
____________________
Peter MacDonald Eggers (instructed by Winter Scott) for the Defendant
Hearing date: 23 March 2011
Further submissions: 24 and 25 March 2011
____________________
Crown Copyright ©
Mr Justice Beatson:
"(a) The claimant instructed shipbrokers, Galbraith's, to charter the vessel to the defendant;
(b) Galbraith's erroneously named Sempra Energy, not the claimant, as "T/C owner" in the recap email dated 26 October 2005 and timed 11:44am;
(c) Galbraith's had no instructions or authority to enter into a charter-party on behalf of Sempra Energy".
The factual background
Discussion
(a) The approach in a challenge under section 67 of the 1996 Act
(b) The issues:
(1) Did the mistake by Galbraith's in recording the identity of the chartered vessel's time chartering owner in the recap email mean that no contract was formed on or shortly before 17 October 2005 because (in the light of the third factual assumption) Galbraith's had no authority to conclude a charter-party on behalf of Sempra Energy?
(2) Did a contract between the parties come into existence by conduct because the voyage was performed by and the freight paid to TTMI, the time-chartering owners, and not the entity named in the recap email?
(3) Should the recap email be rectified to show the correct time chartering owner?
At the hearing Mr MacDonald Eggers submitted that, should I find a contract came into existence by performance, TTMI had no right to the jurisdiction of the court under section 67 of the 1996 Act because the contract was not one in or evidenced by writing and (see section 5 of the 1996 Act) Part I of the Act does not apply to it. This point was not one taken in Statoil's statement of case or its skeleton argument. Although Mr Coldrick dealt with it briefly in his reply, I gave permission for the parties to make written submissions on this point.
(1) Was a contract concluded between TTMI and Statoil on or shortly before 17 October 2005?
(2) Did a contract between the parties come into existence by conduct because the voyage was performed by and the freight paid to TTMI, the time-chartering owners, and not the entity named in the recap email?
(3) Should the recap email be rectified to show the correct time chartering owner?
Conclusion