QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
SWIFT-FORTUNE LTD |
Claimant |
|
- and - |
||
MAGNIFICA MARINE S.A. |
Defendant |
|
The "Capaz Duckling" |
____________________
Bernard Eder QC (instructed by Ince & Co) for the Defendant
Hearing dates: 14th June 2007
____________________
Crown Copyright ©
Mr Justice David Steel :
Introduction
Events in Singapore
a. Addendum No. 7 was agreed on Friday 4 March. In it the parties agreed that the delivery of the vessel to the buyer and payment of the purchase price to the seller was to take place on 8 March 2005 "otherwise latest Wednesday 9 March 2005".
b. The Claimant's lawyer Mr Cumming received a signed copy of Addendum No. 7 in New York late in the afternoon New York time on Friday 4 March.
c. On receipt of Addendum No. 7 Mr Cumming instructed the Claimant to remit the balance of the purchase monies to the account provided for in Clause 3 of the MOA. This was the account of the solicitors acting for the mortgagee of the vessel (Clyde & Co) at SCB.
d. Also on 4 March Mr Cumming emailed the Defendant's lawyer Mr Plotnek requesting a draft closing memorandum and suggesting that a dry run of the closing be carried out on the day before the actual closing.
e. Mr Cumming departed New York for Singapore in the evening of Friday 4 March. On the morning of Monday 7 March Mr Cumming was advised that DNB had not yet seen all of the documents which the Claimant was to provide at the closing.
f. In the afternoon the representatives of the Claimant and the Defendant carried out a dry run of the closing. At this stage the parties were intending to complete the sale on the morning of 8 March.
g. Having not heard from the Claimant about the balance of the purchase monies by about 16.00 on Monday 7 March Mr Cumming contacted Mr Plotnek to request that the closing be postponed to Wednesday 9 March. This was agreed.
h. At about 22.00 on Monday 7 March Mr Cumming discovered that the Claimant had in fact transferred the balance of the purchase monies not to SCB but to the joint account at DNB. Mr Cumming informed Mr Plotnek of what had happened on the morning of Tuesday 8 March and Mr Plotnek made arrangements for a joint letter to be sent to DNB authorising the transfer of the sums to SCB. The monies were duly transferred in the afternoon of Tuesday 8 March.
i. DNB received the Claimant's outstanding documents some time on Tuesday 8 March and the closing duly took place on the morning of Wednesday 9 March immediately after which the Claimant served the freezing order that it had obtained from the Singapore Court on both the Defendant and SCB.
a. whether the Claimant had properly satisfied the requirements for service out of the jurisdiction;
b. whether the Claimant was guilty of bad faith or material non-disclosure or unfair presentation of law and facts;
c. whether the Claimant's motive in obtaining the injunction was to obtain security for its claim; and
d. if the freezing injunction was not set aside whether the sum frozen should be reduced.
Issues
a) the Claimant has established a real risk of dissipation in the absence of the order
b) the Claimant can establish that it is just and convenient for the freezing order to be granted.
Real risk of dissipation
a) the Defendant was a one-ship Panamanian company;
b) the Defendant has disposed of its ship: its only asset is the sum in the SCB account: it is no longer trading;
c) the Defendant has no connection with Singapore and, the monies being readily transferable, it is accepted that they will be remitted elsewhere.
d) the Defendant gives no indication as to where the monies will be transferred to or for what purpose other than to say that "ship-owners have more productive uses for their capital than leaving it in their mortgagees' lawyers' client account."
e) the fact of co-operation by the Defendant in the closing at a time when there was a rising market goes nowhere, all the more so when the sale appears to have been promoted by mortgagees.
Just and Convenient
a) the failure to draw the Court's attention to the potential difficulties in jurisdiction; and
b) the failure to make a full presentation of the English authorities relating to applications for freezing orders in the run up to a ship sale
"Injunction to retain US$2.5million in bank account.
Vera Cruz Transportation [1992] 1 W.L.R.
Accrued damages for delay.
Plaintiff there allowed to get an injunction
…………….
Notice of injunction to be given after closing."
………….. "
(1) The Assios [1979] 1 Lloyd's Rep. 331
Here the judge was not told of the plan to serve the order until after the closing. Lord Denning M.R. urged caution in the granting of injunctions in such circumstances. He expressed particular concern about the fact that the plan was not revealed to the Court but also was troubled that the buyer did not tell the sellers before the closing so as to give them opportunity to consider their position.
(2) Z Ltd v A-Z [1982] 1 Q.B. 558
Kerr LJ categorised as a potential abuse the practice of seeking a freezing order ex parte in advance of payment under a contract which order is thereafter served to freeze the sums paid over. Having referred to The Assios he said this at p. 585:
"However in my view even the disclosure of the intention should not suffice to obtain the injunction in such cases. If a person is willing to make such a payment, appreciating the implications, the courts should not assist him to safeguard the payment in advance by means of a Mareva injunction. However, this is a special type of situation, and, like all others in this field, ultimately a matter for the discretion of the judge to whom the application is made. Accordingly, I say no more about it."
(3) The Niedersachsen [1983] 2 Lloyd's Rep. 600
Here an application was made prematurely in the sense that the relevant cause of action for damages could not arise until delivery. However the planned trap as such was revealed to the Court. When in due course the application was renewed, Mustill J made these general observations:
"While I see the logic of this, it is not compelling. There is something unattractive about the idea of a buyer, who is ostensibly paying the full price of a chattel, preparing himself behind the seller's back to deprive him of part of the price. This gives the buyer the best of both worlds. He is spared the awkward decision whether to reject the res vendita, with the possible commercial loss to himself from not having the chattel, coupled with the risk of an action by the seller for non-acceptance. Instead, he gets the res vendita, avoids an action, and can secure himself for a cross-claim in damages pursued in his own good time. I am very doubtful whether this is a proper use of the Mareva jurisdiction. On the other hand, how is the Judge to identify the cases where relief should refused? I believe that the answer may- and I emphasis "may"- be that it will normally be an abuse of procedure for a seller to restrain the disposal of the purchase price where - (a) the claim upon which the injunction is founded is itself based on the contract of sale and (b) the Court can infer that the seller knows of the facts upon which his claim is based before the sale is completed. In the event, however, it is not necessary to express a concluded view on this point, since I propose to set aside the injunction on other grounds. "
In the event the Court of Appeal, while expressing broad agreement with this critique, laid down no guidelines.
(4) A v B [1989] 2 Lloyd's Rep. 423
Whilst this was a further example of an application being made prior to the cause of action accruing, Saville J was disposed to grant a conditional freezing order - coming into effect when and if delivery took place. The decision was later not followed by the Court of Appeal (see below) but notably, in any event, the apparent ex parte application was in fact on notice to both the defendants and their mortgagees.
(5) Great Marine No. 1 [1990] 2 Lloyds Rep. 245
The issue here centred on whether, in circumstances when following payment a freezing order was obtained, the sellers would be entitled to cancel the contract. That specific submission failed. But Leggatt J made more general observations at p.250:
"The sellers in this case have an understandable sense of disappointment, if not of grievance, that having been led to believe that they would receive an unfettered right to deal with the whole of the purchase monies as they saw fit, they found themselves deprived of the right to deal with $400,000 of it. But if I am right, that occurred, not through breach of contract, but through the imposition of the Mareva injunction. If, when application is made for such an injunction, the Court is not told of the intention to use it to block payment of purchase money, any injunction granted will be discharged for non-disclosure. Provided that the Court is told the facts, it can then decide whether to grant an injunction subject to an undertaking that notice of the intention to serve it will be given to the sellers before completion of the sale so that they may consider, before there are assets of theirs within the jurisdiction to which the injunction can apply, whether there are grounds open to them for not completing the sale.
Though such an order may be appropriate in some cases, in others it may seem more just to allow the trap to be laid so that a one-ship foreign company is not enabled to divest itself not only of the ship but also of the proceeds of sale before a bona fide claim advanced it can be satisfied. "
(6) The Vera Cruz [1992] 1 Lloyd's Rep. 353
It was held that a claimant could not before delivery freeze part of purchase monies in respect of a claim for defects which it was feared would be present on delivery. In so doing the Court of Appeal expressly disapproved of the conditional order granted by Saville J in A v B. Further the Court expressed no disagreement on the view of the judge below that there had been no reason to proceed ex parte:
"That the plaintiff had shown no good reason for applying to the Court ex parte as opposed to proceeding on notice. He rejected the plaintiff's contention that, if notice had been given, the defendant would simply have declined to deliver the vessel altogether and "torn up the agreement". The Judge described this as an important and potentially fundamental point."
(7) The "P" [1992] 1 Lloyd's rep. 470
This was another example of a freezing order obtained prematurely. In addition, the application having been made ex parte, Evans J commented:
"Why then were the defendants' solicitors not informed? The plaintiff's solicitor gives the reason. There was concern lest the defendants might refuse delivery of the ship if they became aware of the injunction, although the plaintiffs were advised that the defendants were not entitled to refuse delivery on this ground. Thus, the defendants were deprived altogether of their right to delay or withhold delivery, if they had such a right and I would add, to question whether the Mareva order was appropriate in the present case, before the order took effect. Lord Denning, M.R. in The Assios thought that the defendants would be entitled in such a case at least to delay delivery to some extent: see [1979] 1 Lloyd's Rep. at p.333. Conversely, if the defendants were not entitled to delay delivery, then by definition the plaintiffs had nothing to lose by giving advance notice. It was even to their advantage to have this issue, if it was to be raised, decided before delivery took place.
I shall say no more in open Court about the facts of the present case, save that in my judgment the plaintiffs were not justified in making the application ex parte, for the reasons I have indicated above. Having taken it upon themselves to make the application without notice to the defendants, the plaintiffs' solicitors undertook a heavy duty of disclosure, one which in my judgment must be stringently enforced."
a) whether the Court had jurisdiction to entertain the application;
b) whether it was appropriate for the application to be made ex parte;
c) whether it was appropriate to permit the creation of the "trap" in circumstances in which the co-operation of the sellers to ensure completion before the cancelling date had been duly forthcoming; and
d) whether it was appropriate to require notice to be given prior to completion.
a) The authorities referred to are not obscure: they are of some antiquity and are referred to in the leading text books
b) The submission that there is no obligation to disclose relevant legal principles is not well founded: see Memory Corp v Sidhu (No. 2) 1 W.L.R. 1443.
"94. If the original application had been made to the English Court, with all the material facts and relevant authorities being put before the English judge, it is submitted that the application would either have been refused outright, on the basis that it was unjust for the Buyer to encourage the Seller to complete and take advantage of the Seller's co-operation to enable completion, while at the same time setting a 'trap', or (at the very least) the Buyer would have been obliged to notify the Seller immediately and before completion took place, in order that the Seller might properly consider the options available to it before walking into this 'trap'.95. Equally, if the initial application had been made in England, and the non-` disclosures discussed above had been before an English judge, it is submitted that this alone would have justified any injunction which had been granted without notice being set aside once these non-disclosures came to light."