QUEENS BENCH DIVISION
COMMERCIAL COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
GOLDEN STRAIT CORPORATION |
Claimant/Applicant |
|
- and - |
||
NIPPON YUSEN KUBISHIKA KAISHA "The GOLDEN VICTORY" |
Defendant/Respondent |
____________________
Mr T. Young QC and Mr H. Byam-Cook (instructed by More Fisher Brown) for the Defendant/Respondent
Hearing dates: 7th –8th February 2005
____________________
Crown Copyright ©
The Hon Mr Justice Langley :
Context
The Point of Law
The Charterparty
"if war or hostilities break out between any two or more of the following countries: USA, former USSR, PRC, UK, Netherlands, Liberia, Japan, Iran, Kuwait, Saudi Arabia, Qatar, Iraq, both Owners and Charterers shall have the right to cancel this charter …."
Repudiation by NYKK
Quantum: Preliminary Issue
"Did the events (described as the outbreak of the second Gulf War) in March 2003 place a temporal limit on the recoverability of damages by the Owners for the Charterers' repudiation of the Charterparty and, if so, what limit?"
The Award
The Arbitrator's Findings
i) There was, at the time of repudiation, an available market for the chartering in of vessels such as The Golden Victory whether in terms of a spot market or a market for period chartering;ii) GSC in fact chose to trade the vessel on the spot market;
iii) The second Gulf war was "a war" within clause 33 of the Charterparty such as to give either party the right to cancel it;
iv) At 17 December 2001, a reasonably well-informed person would have considered war between the United States/United Kingdom and Iraq "merely a possibility" but not "inevitable or even probable";
v) NYKK would have cancelled the Charterparty relying on Clause 33 had the vessel remained on charter to the Company at the outbreak of the second Gulf war.
Reasons for the Award
Submissions by GSC
i) The law "prescribes a clear and long-established test" for the assessment of damages in a case of an accepted repudiation of a long-term charterparty where there is (as here there was) an "available market" at the date of repudiation.ii) The test or "rule" is that damages are to be assessed at the date of repudiation as the difference between the contract rate and the market rate for chartering a substitute ship for the balance of the charter period.
iii) The rule was established by the decision of Goff J in Koch Marine Inc v D'Amica Societa di Navigazone A.R.L. (The 'Elena d'Amico') [1980] 1 Lloyd's Rep 75. The rationale is that the innocent party's duty of mitigation requires him at the time of breach to go out into the market and obtain a substitute charter for the balance of the charter period.
iv) The only exception or qualification to this "rule" is that where the contractual rights which the innocent party has lost by reason of the repudiation were capable by the terms of the contract of being rendered less valuable or valueless in certain circumstances then the law permits the damages to be diminished or extinguished, but only if it can be proved that "those events were at the date of acceptance of the repudiation predestined to happen", or inevitably bound to happen or the rights were certain to be diminished or rendered valueless: see per Megaw LJ in Maredelanto Compania Naviera S.A. v Bergbau-Handel G.m.b.H. ("The Mihalis Angelos") [1971] 1 QB 164.
v) The justification for the rule is the need for certainty, especially in commercial matters, with the concomitant advantages of finality and encouragement of settlement. Crystallisation of the loss at the date of acceptance of repudiation enables parties to know where they are and disenables them from waiting to see if something helpful turns up.
Submissions by NYKK
i) The "general principle" for the calculation of damages is that the innocent party is to be placed, so far as money can do so, in the same position as if the contract had been performed: Lord Wilberforce in Johnson v Agnew [1980] AC 367 at 400H.ii) That principle normally leads to the assessment of damages as at the date of the breach but that is not an absolute rule: "if to follow it would give rise to injustice, the court has power to fix such other date as may be appropriate in the circumstances": Lord Wilberforce at 400H to 401A.
iii) The starting point for an assessment of damages is to determine what has been "lost". In this case what GSC lost was a charterparty with a four-year period to run but subject to the War Clause and other provisions such as Clause 69. Hence the pleaded case of GSC was, for "… the hire that would have been received under and in accordance with the provisions of the charterparty but for the charterers' repudiatory breach of contract" less "the market rate".
iv) The available market (if there is one) provides the test for what is required of the innocent party by way of reasonable mitigation of his loss. It fixes the maximum claim (unless there is a claim to "special" damages). But it remains in principle founded on the requirement to mitigate the loss suffered.
v) There are countless examples in the law where the assessment of damages does take into account subsequent events and the court is exhorted not to shut its eyes to reality. There is no principled reason why damages for repudiation of a long-term contract should be different. Indeed the longer the term the more it may be appropriate to take account of such events or their probability.
vi) There is no justification on the authorities or in principle for some higher test of "predestiny" or certainty. The issue is one of causation and should be approached on normal principles of proof.
vii) Certainty and crystallisation are desirable in every case not just ones where there is an available market and not at the expense of justice. Indeed such outcomes are rarely achievable short of judgment. Thus there may be real issues even in a case such as the present concerning which party (if any) repudiated the contract, what the charter rate is (profit sharing), whether or not there is an available market and what it is, what the period of the charterparty is, and even on the limited exception acknowledged by Mr Hamblen, as to whether a war is "inevitable or predestined at the time of repudiation" and as to when it would break out and so trigger the right to cancel.
Observations
The Authorities
i) Mr Young is right in his submission that the general principle is that GSC is entitled to be put in the same position as it would have been in had NYKK not repudiated the Charterparty. This principle has been referred to as the compensatory rule.ii) Mr Hamblen is right in his submission that the general or normal rule is that damages are to be assessed at the date of breach. But the general rule must give way to the compensatory rule if assessment at a later date more accurately reflects the loss: Lord Wilberforce in Johnson v Agnew (above); Bingham LJ, in County Personnel v Alan R Pulver [1987] 1 WLR 916 at 925-6 and Lord Browne-Wilkinson in Smith New Court v Scrimgeour Vickers [1997] AC 254 at 265H to 266C. The effect, of course, can be to increase the damages as well as to decrease the damages.
iii) Mr Young is right that in the assessment of damages generally the law is not shy of looking at what has in fact happened after the relevant cause of action has arisen. Indeed the authorities are replete with observations to the effect that "facts are to be preferred to prophecies" and the like. But Mr Hamblen is right that in many of those authorities the question the court was required to ask could only be answered by an examination of future events. An example is The Bwllfa and Merthyr Dare Collieries v The Pontypridd Waterworks Companies [1903] AC 426. Another example is, I think, Aitchison v Gordon Durham & Co (unreported) 30 June 1995 (CA). On the other hand, in personal injury cases, unforeseen subsequent events have unquestionably impacted on the damages which would have been awarded had they been assessed at the date of the relevant wrong: see Curwen v James [1963] 1 WLR 748 and Baker v Willoughby [1969] 2 All ER 549
iv) In Melachrino v Nickoll [1919] 1 KB 693 the sellers of a cargo of Egyptian cotton to be shipped from Alexandria to the United Kingdom repudiated the contract before shipment. Bailhache J held (at page 699) that damages were to be assessed by reference to the market price at the time when the cotton ought to have been delivered (which resulted in no loss) not when the "anticipatory breach" occurred and was accepted (which would have resulted in a significant loss) albeit if the sellers could show that the buyer acted unreasonably in not buying in against him between repudiation and delivery date Bailhache J considered that the sellers could also have benefitted from that by way of a reduction in any damages. The significance of the latter point is that it is an example of a case where the duty to mitigate may arise at a time prior to the time of assessment of loss. It was Mr Hamblen's submission that there should be a coincidence of those dates.
The Mihalis Angelos
"(7) In the present case, the finding of fact that the charterers would have cancelled the charterparty under clause 11, if the contract had not previously been determined, is irrelevant in point of law. A valid cancellation of the charterparty under clause 11 would not be a breach of contract; and since the owners have anticipated an actual breach of contract by the charterers, the latter must be regarded as though they would have committed an actual breach when the time came for them to perform.
(8) It follows that the present case must be decided on the basis that the vessel would have proceeded to Haiphong and the charterers would then in actual breach of contract, have failed to do what they then had to do. All matters relevant to the assessment of damages on this basis are relevant, but no other matters. Thus if, for example, the charterparty gave the charterers an option as to the amount of cargo to be shipped, such an option would have to be taken into account by the court in assessing damages where that breach has been anticipated. Again, any relevant event subsequent to the time of the actual breach which would have had the effect of reducing the damages which would otherwise have flowed from the actual breach (even an event which would thereafter have frustrated the adventure) must be taken into account in assessing damages where the breach has been anticipated …."
"Seeing that the renunciation itself is the breach, the damages must be measured by compensating the injured party for the loss he has suffered by reason of the renunciation. You must take into account all contingencies which might have reduced or extinguished the loss. That is made clear by the very first case in which the doctrine of anticipatory breach was established, in Hochster v De la Tour itself (1853) 2 E. & B. 678, 686-687. It follows that if the defendant has under the contract an option which would reduce or extinguish the loss, it will be assumed that he would exercise it. Again, if it is reasonable for him to take steps to mitigate his loss, he must do it. And so forth. In short, the plaintiff must be compensated for such loss as he would have suffered if there had been no renunciation: but not if he would have lost nothing.
Seeing that the charterers would, beyond doubt, have cancelled, I am clearly of opinion that the shipowners suffered no loss: and would be entitled at most to nominal damages. On this point the two experienced arbitrators (one on each side) were quite agreed. I agree with them. I would allow the appeal and restore the award, which adjudged that the claim of the owners failed."
"But the true test in a case of anticipatory breach is: "What would the position of the parties have been if the defendant had not wrongly announced his refusal to fulfill his part of the contract when the time for performance arrived?" One must look at the contract as a whole, and if it is clear that the innocent party has lost nothing, he should recover no more than nominal damages for the loss of his right to have the whole contract completed.
The assumption has to be made that, had there been no anticipatory breach, the defendant would have performed his legal obligation and no more. "A defendant is not liable in damages for not doing that which he is not bound to do": per Scrutton LJ in Abrahams v Herbert Reiach Ltd. [1922] 1 KB 477, 482, cited with approval by Diplock LJ in Lavarack v Woods of Colchester Ltd. [1967] 1 QB 278,293. In the light of the arbitrators' finding, it is beyond dispute that, on the belated arrival of the Mihalis Angelos at Haiphong, the charterers not only could have elected to cancel the charterparty, but would actually have done so. The rights lost to the owners by reason of the assumed anticipatory breach were thus certain to be rendered valueless. It follows from this that, in my judgment, the arbitrators were right in holding that, in the circumstances, the claim of the owners for damages should be dismissed."
"In my view, where there is an anticipatory breach of contract, the breach is the repudiation once it has been accepted, and the other party is entitled to recover by way of damages the true value of the contractual rights which he has thereby lost, subject to his duty to mitigate. If the contractual rights which he has lost were capable by the terms of the contract of being rendered either less valuable or valueless in certain events, and if it can be shown that those events were, at the date of acceptance of the repudiation predestined to happen, then in my view the damages which he can recover are not more than the true value, if any, of the rights which he has lost, having regard to those predestined events."
i) I do not think any of the members of the court were seeking to lay down some rule to apply in all cases of repudiation with an available market.ii) If they were, they expressed themselves in markedly different terms. Reference to "at the date of acceptance of the repudiation" appears only in the judgment of Megaw LJ. Lord Denning's words are quite general and unqualified. So, too, the words of Edmund Davies LJ.
iii) References to the level to which the charterers had proved that the charterparty would have come to an end at Haiphong simply reflect the finding of the arbitrators and, no doubt, the natural concern that a party in breach who alleges the breach would have caused no loss because of some later event, should establish such a case clearly.
iv) "Predestined" is a word which could apply to subsequent events which were not even anticipated as well as to those which were. In The Mihalis Angelos, in a sense it was "predestined" that there was insufficient time for the vessel to reach Haiphong but it is less obvious that cancellation by the charterers could be so described. In this case in a sense it is now known that the second Gulf war was "predestined" but again less obviously that the charterers would then cancel.
v) As a matter of principle I can see no reason why in this limited type of claim the law should seek to set some higher or different standard of proof of what is a causation issue. Nor, as I have said, do I see any principle which would justify such a "rule" with an exception limited both by reference to the time at which what has to be proved is to be viewed and by the standard to which it has to be proved. I hope I do no injustice to Mr Hamblen's skilful and careful submissions if I say that he did not offer any such principle save perhaps the need for certainty. In this case, before the arbitrators, there was a considerable debate, with conflicting expert evidence, about the extent to which the second Gulf war was, at the time of repudiation, possible, probable or inevitable. I suspect such issues are likely to involve just as much, if not more, uncertainty as a straightforward application of the normal principles of causation of loss. More importantly I do not read any of the judgments in the Mihalis Angelos as saying otherwise. Indeed the terms of the judgments of both Lord Denning and Edmund Davies LJ are, I think, inconsistent with Mr Hamblen's submission.
The Elena d'Amico
North Sea Energy Holdings v PTT
"At the time of the repudiation found by the Judge it was predestined that without the information as to the ports of discharge no confirmation could be obtained from the original supplier. Indeed it was predestined that no oil could be delivered by MSH without the information. It was also predestined at that time that PTT would not supply that information. Only if PTT were in breach of contract for failing to do so could MSH succeed on a claim for damages.
The Seaflower
"I must follow the formulation of the majority of the Court of Appeal. In any event, I see no reason why in the case before me the approach should be constrained in the way suggested by Lord Justice Megaw. If the contract would inevitably have come to an end earlier than its due date anyway, it is right that the damages should be limited accordingly, regardless of whether or not that event was predestined at the date of repudiation. As Lord Denning said the Court "must take into account all contingencies which might have reduced … the loss".
Counsel for the owners also relied upon the fact that Lord Justice Megaw's formulation was cited with approval by Lord Justice Waller in North Sea Energy Holdings NV v Petroleum Authority of Thailand, [1999] 1 Lloyd's Rep 483 at 496, col. 2. However, on the facts of that case no issue arose as to whether or not the event was predestined, so that the Court of Appeal did not need to explore the precise ambit of the test.
I therefore ask myself the simple question, would this contract inevitably have come to an end on Feb. 26, 1998, because the owners would have lost (and been unable to regain in time) the Mobil approval? It of course goes without saying in this context that had the charterers acquired a liberty to cancel under the major approvals clause, they would have used it."
SUMMARY AND CONCLUSION
i) The conclusion accords with the basic compensatory rule for the assessment of damages in that had the Charterparty not been repudiated but been performed it would have come to an end upon the outbreak of the second Gulf War.ii) I can see no sound reason why the ordinary principles requiring a claimant to prove his loss and that it was caused by the impugned conduct of the defendant should not apply in this case nor why the "normal" approach to assessment of loss derived from the normal approach to mitigation should dictate another result.
iii) I also see no sound reason why there should be an "exception" to the rule for which Mr Hamblen contends limited only to a case where at the time of repudiation the loss is predestined to end at a date earlier than the expiry of the charter period.
iv) The desirability of certainty and crystallisation is accepted but, I think, no more obviously achievable with than without Mr Hamblen's rule and its supposed exception. The fact is that the Charterparty itself contained the uncertainty of the War Clause. That was what GSC lost. If Mr Hamblen were right GSC would recover more than the Charterparty was worth to it and do so without in fact incurring any greater loss.