Mr Justice Moore-Bick:
“ Warranted London Salvage Association approval of location, fire fighting and mooring arrangements and all recommendations complied with.
Warranted no hot work”.
“Warranted London Salvage Association or London Salvage Association appointed surveyor to approve mooring and fire fighting arrangements within 14 days”.
“ 2. Any alterations in the lay up and mooring arrangements, arrival or removal of vessels in the group or any other alteration to be notified to The Salvage Association and other interests concerned so that, if necessary, a further survey may be held
. . . . . . . . . . . . . . . . . . . . .
11. No hot work to be carried out and no open flame devices to be used on board.”
“ Hot Works on decks is due to commence soon.
Underwriters agree to cover such work hereunder.
Warranted L.S.A. certificate updated & all recommendations complied with prior commencement of hot work.
All other terms, clauses and conditions remain unaltered”.
“ Warranted L.S.A. certificate updated ”.
The warranty of 6th February 1996
Earlier breaches of warranty
(i) The original warranty
(ii) The indorsement of 9th October
(iii) The indorsement of 9th January
(iv) The indorsement of 12th January
(v) Waiver