BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
7 Rolls Buildings, London, EC4A 1NL |
||
B e f o r e :
____________________
(1) INEOS UPSTREAM LIMITED (2) INEOS 120 EXPLORATION LIMITED (3) INEOS PROPERTIES LIMITED (4) INEOS INDUSTRIES LIMITED (5) JOHN BARRIE PALFREYMAN (6) ALAN JOHN SKEPPER (7) JANETTE MARY SKEPPER (8) STEVE JOHN SKEPPER (9) JOHN AMBROSE HOLLINGWORTH (10) LINDA KATHARINA HOLLINGWORTH |
Claimants |
|
- and - |
||
(6) JOSEPH BOYD (7) JOSEPH CORRÉ |
Defendants |
____________________
BLINNE NÍ GHRÁLAIGH KC AND JENNIFER ROBINSON (instructed by Leigh Day) for the Sixth Defendant
STEPHEN SIMBLET KC (instructed by Bhatt Murphy) for the Seventh Defendant
____________________
Crown Copyright ©
Master Kaye :
i) The claimants had agreed that they should pay the Costs of the Remitted Costs but on the standard basis subject to detailed assessment. The remaining issue between the parties was whether the costs should be paid on an indemnity basis.
ii) D6 no longer sought pre-judgment interest on its costs.
iii) The claimants agreed in principle that they would pay pre-judgment interest on D7's costs but the date from which that interest was to be paid, the costs to which it should be applied, and the rate of interest remained in dispute.
iv) The position in relation to the amount of the interim payments on account of costs was as follows:
a) D6 said his overall costs were a total of £699,243.70 and sought an interim payment on account of 50%, £349,621.70. The claimants offered nothing.
b) D7 said his overall costs were a total of approximately £330,000. He sought an interim payment on account of £220,000, approximately two thirds. The claimants offered approximately 50% or £167,500.
Conclusions
i) The claimants shall pay the defendants' Costs of the Remitted Costs on a standard basis to be assessed if not agreed, save for the period August 2021 to 25 March 2022, during which period the costs should be assessed on an indemnity basis;
ii) The claimants shall pay an interim payment on account of D6's costs of £200,000;
iii) The claimants shall pay an interim payment on account of D7's costs of £167,500;
iv) Judgment rate interest at 8% will run post-judgment from the dates on which the relevant costs orders were made in the usual way; and
v) Pre-judgment interest in relation to D7's costs will accrue at 2% over base from the date on which the liability to pay the costs accrued.
Indemnity Basis
D6
i) The claimants' unreasonable negotiating position and overall approach to settlement (including not replying to an offer to participate in a costs mediation) and in particular their rejection of D6's offers to settle before the CMC in July 2022 and in September 2022;
ii) Generally, the claimants' unreasonable conduct and in particular their refusal to agree to the claim being struck out earlier; and
iii) The length of the claimants' submissions and the size of the bundle.
D6 Negotiations/Settlement
D7
D7 Negotiations/Settlement
Other Conduct
Discussion
Interim Payments
Interest
Post-Judgment Interest
Pre-Judgment interest
Pre-judgment interest rate