BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
BUSINESS LIST (CH D)
Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
____________________
Barrowfen Properties Limited |
Claimant |
|
- and – |
||
Girish Patel Stevens & Bolton LLP Barrowfen Properties II Limited |
Defendants |
____________________
Roger Stewart QC, Angharad Start and Joshua Folkard (instructed by Reynolds Porter Chamberlain) for the Second Defendant
Hearing dates: 15th March 2021
____________________
Crown Copyright ©
Tom Leech QC
Monday, 15 March 2021 (10.44 am)
Tom Leech QC (sitting as a judge of the High Court, Chancery Division):
The Application
The Claims
The Amendment
"191.3.1 Stevens & Bolton will contend that in the events which happened the delay in the development of the Tooting Property has led to Barrowfen securing an increased Gross Development Value for the Tooting Property in the order of a £20m increase for which Barrowfen must give credit.
191.3.1.2 Further or alternatively, Barrowfen must give credit for an increase in the Gross Development Value pursuant to the appropriate figures in paragraph 8.0.11 of the 29 January 2021 report of Peter Clarke FRiCS for the events as found by the Court.
191.3.1.3 In the premises, it is denied that Barrowfen has made any loss and/or averred that it has made a profit.
(a) S&B's primary position is that set out in paragraph 182-190 of its Amended Defence, namely that Prashant and Suresh wished to "exit" their investment through a sale of the Tooting Property undeveloped with the benefit of planning permission at all material times. The profit made by the development in fact is in the sum of £15,891,884
(b) The measure of loss claimed is in any event denied and/or is misconceived.
(c) Further or alternatively, the profit which would have been made by the hypothetical development is in the sum of £6,479,353.
191.3.1.4 It is in any event, denied that any loss sustained by Barrowfen, which is denied, was caused by Stevens & Bolton or is loss for which Stevens & Bolton is responsible."
The Procedural Chronology
(1) On 16 September 2020 I gave directions for Barrowfen to serve Re-Amended Particulars of Claim by 3 November 2020 and for S&B to serve a Re-Amended Defence by 24 November 2020. I also gave directions for the service of expert reports by 11 January 2021 and for service of the joint statement by 19 January 2021.
(2) On 3 November 2020 Barrowfen served the Re-Amended Particulars of Claim. It made some amendments to the causation and loss allegations but none relevant to the proposed amendment.
(3) On 26 November 2020 S&B served the Amended Defence. It did not take the point that Barrowfen must give credit for the increase in capital value between the Original and the Revised Development Schemes.
(4) On 9 December 2020 Barrowfen served the Amended Reply. I should set out paragraph 58 which is relevant to this application:
"Paragraph 187 is specifically denied. As for the sub-paragraphs of paragraph 187: a. Barrowfen embarked on a different development in 2016 because by 2016 the old development was no longer viable. b. Prashant was advised by professionals that residential housing would be preferable to student accommodation in 2016. He acted on that advice. c. It is admitted that the development is not yet complete. d. The choice was made because by the time Barrowfen exited administration (an event caused entirely by the conspiracy of Stevens & Bolton, Girish and Barrowfen II) and Prashant and Suresh regained control of Barrowfen, the original development was no longer commercially viable. The delay was caused because it was necessary to obtain planning permission for a development that was commercially viable. e. Save as aforesaid the sub-paragraphs are denied."
(5) The expert issues were not agreed and at the PTR on 25 January 2021 I fixed the expert issues for trial (which are set out in the schedule to the Order). I excluded issues 10 to 12 which dealt with capital values because I accepted that they were not relevant to any pleaded allegation in the statements of case at that stage. But I ordered the experts to address the viability of the development. I also extended time for service of expert reports and the joint statement by agreement between the parties.
(6) On 29 January 2021 the parties exchanged experts' reports. Barrowfen's expert valuer, Mr Alford, approached the issue of viability which was then numbered as issue 8 by providing a general commentary on the market. Mr Clarke dealt with this issue by undertaking a series of development appraisals which he described as viability assessments, as I have already said.
(7) On 10 February 2021 the expert valuers signed the joint statement. They were not able to agree anything in relation to issue 8.
"a) whether to allow an amendment is a matter for the discretion of the court. In exercising that discretion, the overriding objective is of the greatest importance. Applications always involve the court striking a balance between injustice to the applicant if the amendment is refused, and injustice to the opposing party and other litigants in general, if the amendment is permitted;
b) where a very late application to amend is made the correct approach is not that the amendments ought, in general, to be allowed so that the real dispute between the parties can be adjudicated upon. Rather, a heavy burden lies on a party seeking a very late amendment to show the strength of the new case and why justice to him, his opponent and other court users requires him to be able to pursue it. The risk to a trial date may mean that the lateness of the application to amend will of itself cause the balance to be loaded heavily against the grant of permission;
c) a very late amendment is one made when the trial date has been fixed and where permitting the amendments would cause the trial date to be lost. Parties and the court have a legitimate expectation that trial fixtures will be kept;
d) lateness is not an absolute, but a relative concept. It depends on a review of the nature of the proposed amendment, the quality of the explanation for its timing, and a fair appreciation of the consequences in terms of work wasted and consequential work to be done;
e) gone are the days when it was sufficient for the amending party to argue that no prejudice had been suffered, save as to costs. In the modern era it is more readily recognised that the payment of costs may not be adequate compensation;
f) it is incumbent on a party seeking the indulgence of the court to be allowed to raise a late claim to provide a good explanation for the delay;
g) a much stricter view is taken nowadays of non-compliance with the CPR and directions of the Court. The achievement of justice means something different now. Parties can no longer expect indulgence if they fail to comply with their procedural obligations because those obligations not only serve the purpose of ensuring that they conduct the litigation proportionately in order to ensure their own costs are kept within proportionate bounds but also the wider public interest of ensuring that other litigants can obtain justice efficiently and proportionately, and that the courts enable them to do so."
Objection 1: Delay
(1) Mr Stewart took me to RPC's letter dated 4 December 2020 in which S&B flagged up the amendment. Barrowfen was, therefore, aware of the amendment from that date. Mr Stewart also told me that Barrowfen had only given disclosure in relation to the Revised Development
Scheme in various tranches, the last on the day on which expert reports were exchanged.
(2) Experts' reports were not exchanged until 29 January 2021 and the joint statement was not agreed until 10 February 2021. It is difficult to see how the application could have been heard until the parties had served their experts' reports. It is unrealistic in my view to have expected S&B to object to further time for exchange of experts' reports or to insist that the Court hear the application in advance of exchange. In any event, both experts would have had to modify their development appraisals or produce new ones in the light of the very large member of agreement which they achieved in the joint statement.
(3) I heard Barrowfen's application to strike out parts of the Amended Defence in early February 2021 and handed down a reserved judgment on 5 February 2021. It is highly likely, therefore, that I would have dealt with this application at the same time if it had been made at the PTR.
(4) I heard the PTR and dealt with a number of applications on 5, 25 and 26 February 2021. I also put back that trial by a week to enable the parties to be ready. This was a particularly intense period and it was only because the parties (and I include Mr Girish Patel in this) were working so hard, combined with some flexibility from the court, that the trial did not go off altogether. In those circumstances, the opportunity to put this application before the court before the trial itself were very severely limited. I am therefore satisfied that S&B cannot be held responsible for the delay in the hearing of the application between the date of the application itself and the date of the hearing, given the applications with which the court had to deal.
Objection 2: No real prospect of success
"This court has recently had to deal with collateral benefits in a context not far removed from the present one. The general rule is that where the claimant has received some benefit attributable to the events which caused his loss, it must be taken into account in assessing damages, unless it is collateral. In Swynson Ltd v Lowick Rose LLP [2017] 2 WLR 1161 at [11] it was held that as a general rule "collateral benefits are those whose receipt arose independently of the circumstances giving rise to the loss." Leaving aside purely benevolent benefits, the paradigm cases are benefits under distinct agreements for which the claimant has given consideration independent of the relevant legal relationship with the defendant, for example insurance receipts or disability benefits under contributory pension schemes. These are not necessarily the only circumstances in which a benefit arising from a breach of duty will be treated as collateral, for there may be analogous cases which do not exactly fit into the traditional categories. But they are a valuable guide to the kind of benefits that may properly be left out of account on this basis."
"The essential question is whether there is a sufficiently close link between the two and not whether they are similar in nature. The relevant link is causation. The benefit to be brought into account must have been caused either by the breach of the charterparty or by a successful act of mitigation much."
"First the relevant question is whether the negligence which caused the loss also caused the profit, in the sense that the latter was part of the continuous transaction of which the former was the inception. The second question is primarily one of fact."
Objection 3: Prejudice
(1) Expert valuation evidence: Ms Hilliard relied on the fact that it will be necessary to obtain expert evidence Mr Alford and vary the list of issues. Based on the current timetable, the experts will give evidence on 24 March 2021 (i.e. in ten days) and I am satisfied that it is possible for Barrowfen to obtain the necessary evidence from Mr Alford and serve a reply to Mr Clarke's report within that time. As I have stated, most of the inputs are agree and Mr Alford should have access to a development appraisal model which would enable him to produce the appraisals and to discuss them with Mr Clarke. Quite properly, Ms Hilliard did not suggest that it was impossible for him to prepare and serve a supplemental report.
(2) Further disclosure: Ms Hilliard submitted that it will be necessary to obtain further disclosure relating to the valuation of the Tooting property and, in particular, valuations obtained during the negotiations for funding with Barclays Bank. Given the level of agreement between the experts about their rental valuations, I am not satisfied that any historic valuations prepared for the purposes of applications for finance will assist me to determine what the capital values of the Tooting Property were at the relevant times. However, if Ms Hilliard wishes to put in historic valuations prepared for Barclays to Mr Clarke, I consider that she has sufficient time to locate and disclose them before he gives his evidence. Indeed, Barrowfen has pleaded a positive case that it is entitled to recover the professional costs of Lambert Smith Hampton and Savills and ought therefore to be able to disclose their original reports and might well have done so in order to make good the case that those costs are recoverable.
(3) Amendment: Ms Hilliard also submitted that it would be necessary to re-amend the Particulars of Claim to advance a case that Barrowfen would have re-invested the rental income from the original development scheme if it had received it at an earlier time. I disagree. It already forms part of Barrowfen's case that it lost the opportunity to re-invest and generate a return on the profit which had would have made from renting out the property during the earlier period of 39 or 55 months as the case may be. See, in particular, responses 49 and 52 to which I have referred (above). This response was not withdrawn when Barrowfen chose to amend to withdraw its claim for developer's profit. It relates to the additional interest or opportunity costs which Barrowfen would have been able to earn on the rent which it would have received earlier.
(4) Expert accountancy evidence: Ms Hilliard also submitted that it would be necessary to obtain accountancy evidence about the present value of the future interest burden of the additional borrowing which Barrowfen had to take in order to complete the Revised Development Scheme. I am not satisfied that it would be impossible for the expert valuers to provide this evidence in their development appraisals and Mr Stewart took me to the relevant parts of Mr Clarke's development appraisals in which he had included finance costs. But even if it is necessary to obtain expert accountancy on this issue, this is not in my judgment a sufficient reason to justify refusing the amendment by itself. If the experts cannot deal with this issue, then it can be dealt with as part of the consequential matters following judgment. Parties often adduce evidence of their finance costs after judgment to justify a claim for interest, whether for statutory interest or interest as damages and, if necessary, I can direct an enquiry on this issue should it arise.
(5) Factual evidence: Finally, Ms Hilliard submitted that it would be necessary to call factual evidence on the negotiations with Barclays and in relation to the lost opportunity to re-invest. Again, I am not satisfied that this is a sufficient reason to disallow the amendment. It has been part of Barrowfen's case that it lost the opportunity to re-invest the rental income or the net rental income from the original development scheme since least 11 September 2020. If it wanted to call evidence on this issue, it should have done so to support its case. Moreover, as I have already stated above, I am not satisfied that factual evidence in relation to negotiation for Barclays has any real relevance to the capital value of the Tooting Property subject to the Revised Development Scheme. Nevertheless, if she does wish to adduce any further evidence in order to deal with these issues, I will permit her to do so.