BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
BUSINESS LIST (ChD)
Rolls Building Fetter Lane London EC4A 1NL |
||
B e f o r e :
____________________
BRITNED DEVELOPMENT LIMITED |
Claimant |
|
- and – |
||
(1) ABB AB (2) ABB LTD |
Defendants |
____________________
Ms Sarah Ford, QC and Ms Jennifer MacLeod (instructed by Freshfields Bruckhaus Deringer LLP) for the Defendants
Hearing date: 18 October 2018
____________________
Crown Copyright ©
Mr Justice Marcus Smith:
A. INTRODUCTION
(1) The implications of BritNed's disinclination to provide an undertaking along the lines articulated in paragraphs 540 to 541 of the Judgment. This is considered in Section C below.
(2) Interest, considered in Section D below.
(3) Permission to appeal, considered in Section E below.
B. COSTS NOT ADDRESSED
C. THE UNDERTAKING
(1) Option 1: To decide the issue of the true effect of the Amended Exemption Order. I have re-visited my thinking in paragraph 540 of the Judgment. For the reasons there given, I do not consider that I can satisfactorily decide this question, in a manner that binds BritNed. The documents imposing the Regulatory Cap are binding as between BritNed and its respective UK and Dutch regulators, who are not before the court. ABB is not party to these transactions. Accordingly, there does not seem to me to be a lis before the court that entitles me to determine the issue; and, as was noted in the Judgment, were I to determine the issue, I would be doing so in the absence of the regulators who are party to these transactions. I do not consider that Option 1 is open to me.
(2) Option 2: To treat the requirement of an undertaking as the "price" for a damages award. It is trite that in the context of an application for an interim injunction, the court will generally require the applicant to provide an undertaking in damages[11] (sometimes fortified) as the "price" for granting the injunction. In such cases there is, as here, no right in the court to require the undertaking, but in most cases the court will not grant the injunction without the undertaking being proffered. I have considered whether the same course is open to me in this case. That is, to decline the remedy of damages because an undertaking, explicitly required to avoid over-compensation, has not been proferred. In many respects, this is the neatest and fairest solution. The undertaking is not, in my judgment, an onerous one; and it ensures that BritNed is not overcompensated. However, I do not consider Option 2 to be open to me:
(a) An interim injunction is a discretionary remedy, where the harm to the respondent caused by the injunction is a highly material factor. That harm can be avoided – or at least, minimised – by the undertaking in damages. The failure of an applicant to proffer the undertaking will – in many, if not most, cases – alter the balance of factors going to the court's discretion and oftentimes render the granting of the interim injunction inappropriate.
(b) By contrast, given the findings in the Judgment, BritNed is entitled to damages as a matter of law, not discretion. Self-evidently, this is not the case of an interim remedy pending trial, but a final order for damages, to which BritNed has a right.
In these circumstances, I have no right in effect to compel an undertaking that BritNed is not prepared to give by making that undertaking a precondition to damages. Rather, I must do what I sought to avoid in the Judgment: I must consider the risk of the IRR Cap being exceeded in circumstances where – if the IRR Cap is exceeded – BritNed will retain monies it is not entitled to. That brings me to the third option: adjusting the award of damages.
(3) Option 3: Adjusting the award of damages. As to this:
(a) In paragraph 542 of the Judgment, I considered (but very briefly) what my findings would have been had ABB's arguments succeeded. Had ABB's arguments succeeded, then even if the IRR Cap applied, and BritNed was obliged to use the excess in the manner described in paragraph 522 of the Judgment, the amount representing x in Figure 2 at paragraph 525 of the Judgment would still represent over-compensation. In these circumstances, and given the size of the award of damages, I would have made only a nominal deduction in BritNed's damages.[12]
(b) The present case is rather different: I consider, and it is the basis for my rejection of ABB's argument, that the Exemption Condition described in paragraph 522 applies but, for the reasons given in paragraph 15(1) above, I am precluded from making a holding in this regard. BritNed clearly does not consider that damages awarded in this action will go towards the calculation of whether the IRR Cap is breached and so will side-step the Exemption Condition. That, to my mind, is the only explanation for BritNed's disinclination to engage on this point[13] and, indeed, for BritNed's disinclination to provide an undertaking. Clearly, then, there is a risk of overcompensation to BritNed that must be reflected in the award of damages.
(c) Given the uncertainties referred to in paragraph 542(2) of the Judgment, and the fact that the damages I am minded to award are small compared to the overall costs and revenues (see paragraph 542(3) of the Judgment), the adjustment to the award should not be large. But it cannot be nominal. The question I considered in paragraph 542 was the alternative question assuming ABB's contentions (contrary to my findings in the Judgment) were right. The present question arises out of an explicit assumption that I made in rejecting ABB's contentions. If that assumption is wrongly founded – as clearly it may be – the risk of over-compensation to BritNed is patent, and the rule described in paragraph 12(9) of the Judgment is engaged. I remind myself: where a court is compelled to use a broad brush in the absence of precision in the evidence of the harm suffered by a claimant, it should err on the side of under-compensation, so as to (i) reflect the uncertainty as to the loss actually suffered and (ii) to give the defendant the benefit of any doubts in the calculation.
(d) In my assessment of quantum, I have been using a broad brush and I have sought to ensure that BritNed is fully compensated according to law, but not over-compensated. The assumption in paragraph 538 of the Judgment was a material part of that approach. In light of the present position, that assumption may very well not hold good. In these circumstances, once-again wielding a broad brush, I consider that the award of €13,009,568 must be reduced by 10% to reflect the risk of over-compensation and the need to give ABB the benefit of any doubts in my calculation of damages generally.
For these reasons, the damages described in paragraph 550(1) of the Judgment are reduced by 10% (€1,300,956.80) from €13,009,568 to €11,708,611.20.
D. INTEREST
(1) An award of interest is not punitive and the use to which the party paying interest would have put the funds (and the returns that such party may or may not have made) is irrelevant.[15]
(2) There is a convention that at least the starting point for the award of simple interest (at least where the award is in £ sterling) is Bank of England base rate plus 1%.[16] However, where the award is in another currency, like US$, the US$ Prime Rate plus 1% will be used as the starting point.[17]
(3) This conventional rate will, usually, be less than what a claimant would have to pay as a borrower, but more than a claimant could earn as a lender. The appropriate benchmark, however, is not to regard the claimant as the lender of monies (inferentially, to the defendant), but rather as having had to borrow money in order to fund the loss that has been vindicated by the award of damages in the judgment.[18] It is this that informs the court's departure from the conventional starting point: the overall aim is to determine a fair rate to compensate the claimant.[19]
(4) When considering the departure from the conventional starting point, a broad brush approach must be taken. In Fiona Trust, Andrew Smith J put the point as follows:[20]
"A "broad brush" is taken to determine what rate of interest is just and appropriate: it would be neither practical nor proportionate (even in a case involving as large sums as these) to attempt a minute assessment of what will precisely compensate the recipient. In particular, the courts do not have regard to the rate at which a particular recipient of compensation might have borrowed funds. This policy is adopted in order to control the extent of the inquiry to ascertain an appropriate rate…The court will, however, consider the general characteristics of the recipient in order to decide whether to assess interest at a rate that is higher or lower than is conventional."
(5) Specific evidence (eg as to the claimant's borrowing rates) may be adduced to support a particular departure from the conventional rate or as regards the particular circumstances of the claimant.[21]
(1) The period will run from the date the contract between BritNed and ABB was concluded, which was 21 May 2007.[22] This is the date on which BritNed's cause of action accrued.[23] Interest should run to the date of this Supplemental Judgment, which is 31 October 2018.
(2) The rate of interest will be EURIBOR plus 1%. I consider this to be a fair rate in all the circumstances:
(a) BritNed itself incurred no borrowing costs. It was a joint venture funded by its two parents, National Grid and TenneT. To the extent the parents' position is relevant – and I frankly do not consider that it is – these are large commercial organisations. There would be no reason to increase the rate because these are "small businessmen" who have been kept out of their money.[24] However, the key point, to my mind, is that because BritNed incurred no borrowing costs, there is really nothing to justify a substantial move away from the conventional rate, either way.
(b) I appreciate that because BritNed paid the purchase price for the Interconnector in tranches, the rate I have ordered is actually materially higher than EURIBOR plus 1%. I am satisfied that it is fair to apply the rate of EURIBOR plus 1% to the full €11,708,611.20 from 21 May 2007: that is the date on which BritNed committed to pay an inflated price, and it will have had to be assured at that time that it had funds available from that date to pay for the Interconnector. Consistently with my broad brush approach, I am satisfied that this award is fair.
E. PERMISSION TO APPEAL
Note 1 See paragraph 550(4) of the Judgment. [Back] Note 2 See paragraph 550(1) of the Judgment. [Back] Note 3 These were sent to the court in advance of BritNed’s written submissions. [Back] Note 4 See Mr O’Donoghue QC’s email of 3 October 2018. [Back] Note 6 See paragraph 538 of the Judgment. [Back] Note 7 See paragraph 539 of the Judgment. [Back] Note 8 See paragraph 539 of the Judgment. [Back] Note 9 Transcript, p.4. [Back] Note 10 Made in paragraph 8 of BritNed’s note. [Back] Note 11 Ie, to hold the respondent harmless against any loss sustained through the granting of the injunction, should it prove to be the case that the interim injunction was “wrongly” granted. [Back] Note 12 See paragraph 542. [Back] Note 13 See paragraph 538 of the Judgment. [Back] Note 14 The point was made by BritNed that the payment of interest constitutes an essential component of compensation, and that this held good for competition claims. I accept this as a proposition, but do not consider (and do not understand BritNed to contend) that the principles of equivalence and effectiveness in relation to EU law require any departure from, or augmentation of, the rules regarding section 35A interest. That seems to be confirmed – in the distinct area of repayments of VAT – by the decisions of the European Court of Justice and the UK Supreme Court inLittlewoods v. Revenue and Customs Commissioners. See, generally, the Supreme Court’s decision at [2017] UKSC 70. [Back] Note 15 Fiona Trust & Holding Corporation v. Privalov [2011] EWHC 664 (Comm) at [13]; Sycamore Bidco Ltd v. Breslin [2013] EWHC 174 (Ch) at [6]. [Back] Note 16 Shearson Lehman Hutton Inc v. Maclaine Watson & Co Ltd [1990] 3 All ER 723 at 733; Fiona Trust at [14], [15]. [Back] Note 17 Fiona Trust at [15]. [Back] Note 18 Fiona Trust at [14]; Reinhard v. ONDRA [2015] EWHC 2943 (Ch) at [31]. In the latter case, Warren J differentiated between cases such as this, where money has been lost by the claimant which might have to be replaced by borrowing; and cases unlike this where the award is an accretion to the claimant’s assets. [Back] Note 19 Fiona Trust at [25]. [Back] Note 20 At [16]. See also Ahmed v Jaura [2002] EWCA Civ 210 at [20] and [26]; Sempra Metals v.IRC [2006] QB 37 at [47] (in the Court of Appeal); Reinhard at [9].
[Back] Note 21 Fiona Trust at [25]. [Back] Note 22 See paragraph 169 of the Judgment. [Back] Note 23 See paragraph 428 of the Judgment. [Back] Note 24 See the consideration in Fiona Trust at [16]. [Back]