BUSINESS AND PROPERTY COURTS IN WALES
COMPETITION LIST (ChD)
2 Park Street Cardiff |
||
B e f o r e :
____________________
RED AND WHITE SERVICES LIMITED | Claimant | |
- and - | ||
PHIL ANSLOW LIMITED | Defendant | |
THE PRUDENTIAL ASSURANCE COMPANY | Third Party |
____________________
8th Floor, 165 Fleet Street, London, EC4A 2DY
Tel No: 020 7404 1400 Fax No: 020 7404 1424
Web: www.epiqglobal.com/en-gb/ Email: civil@epiqglobal.co.uk
(Official Shorthand Writers to the Court)
MISS J MACLEOD (instructed by Tuppers Law) appeared on behalf of the Defendant
MR B RAYMENT (instructed by Hogan Lovells International LLP) appeared on behalf of the Defendant
____________________
Crown Copyright ©
MR JUSTICE BIRSS:
"4. PROPORTIONALITY11. As noted above, the claim now has a maximum value of £1.1 million. The total amount of the costs in the costs budgets (excluding VAT on the claimant's costs), is about £1.6 million. In other words, it will cost significantly more to fight this case than the claimant will ever recover. On that basis alone, it seems to me that the costs in the costs budgets are both disproportionate and unreasonable. During the course of his helpful submissions, Mr Wygas argued that, as a result of the comparison between the costs figure and the amount at stake, the claimant's costs were indeed disproportionate. In my view, there is insufficient difference between the two costs budgets to mean that the defendant's costs could be characterised in a different way.
12. In reaching that conclusion, I accept that a professional negligence claim of this kind can involve costs that other commercial disputes may not. For example, in a professional negligence case, expert evidence will almost always be necessary to demonstrate that a professional fell below the standard required. Furthermore, there also needs to be an allowance, in any consideration of the proportionality of costs, for the non-quantifiable, but potentially serious, damage to the defendant's professional reputation that may be caused by a claim of this kind.
13. But even making due allowance for both these factors, I do not regard the budget costs figures in this case as proportionate or reasonable, particularly given the relatively limited nature of the disputes between the parties. The individual dispute which is worth the most is the overpayment/overvaluation claim. That will involve some quantity surveying evidence, although experience of such disputes leads me to suspect that this will not necessarily be extensive: the various valuation items in issue will probably fall into a handful of types or categories, so that once an expert has addressed the leading items in each category, there will be little left for the expert to do. The defects are a relatively modest element of this claim, so that even if they required both M and E and architectural experts, the involvement of such experts ought to be relatively limited.
14. As I put to the parties during submissions, it seems to me that one test of proportionality is whether the trial is likely to be an end in itself, or merely a lesser part of the process which the parties will use in order to put themselves in the strongest position to argue that, subsequently, the other side should pay all or most of their costs. When the costs on each side are much higher than the amount claimed/recovered, the latter is almost inevitable. I have no doubt that that will be the case here. For those reasons, therefore, I conclude that the costs shown in the costs budgets are disproportionate and unreasonable."
Note added after judgment was given:
Item | C's Precedent H (11.05.2018) |
D's Precedent H (10.05.2018) |
TP's Precedent H (11.05.2018) |
Pre-Action | [1,033.50] | [10,500.00] | [87,218.90] |
Issues/SoC | Total 59,397.73 Of which incurred [39,147.73] |
41,246.60 [33,746.60] |
147,662.50 [97,557.50] |
CMC | 70,171.10 [28,876.10] |
15,847.93 [6,267.93] |
121,320.50 [55,111.50] |
Disclosure | 267,194.00 [3,194.00] |
9,375.00 | 106,794.90 [11,762.40] |
WS | 71,668.50 [53.50] |
10,875.00 | 91,729.50 [9,757.00] |
Expert Reports | 150,521.00 [1,541.00] |
25,875.00 | 190,700.00 |
PTR | 38,165.00 | 7,705.00 | 34,850.00 |
Trial Prep | 47,150.00 | 17,125.00 | 79,850.00 |
Trial | 633,335.00 | 61,698.00 | 408,625.00 |
ADR/Settlement | 47,775.50 [23,850.00] |
59,353.65 [53,103.65] |
123,276.50 [70,043.00] |
Contingencies | |||
A) Mediation | 40,078.50 [28.50] |
15,000.00 | 54,800.00 |
B) Security for costs | 47,091.50 [6,236.50] |
13,800.00 | 52,385.00 [16,792.00] |
TOTAL | £1,473,581.33 | £288,401.18 | £1,499,213.30 |
of which incurred costs = | [103,961.33] | [103,618.18] | [348,242.30] |
Epiq Europe Ltd hereby certify that the above is an accurate and complete record of the proceedings or part thereof.
165 Fleet Street, London EC4A 2DY
Tel No: 020 7404 1400
Email: civil@epiqglobal.co.uk