CHANCERY DIVISION
BRISTOL DISTRICT REGISTRY
2 Redcliff Street, Bristol, BS1 6GR |
||
B e f o r e :
(sitting as a Judge of the High Court)
____________________
Mark Richmond |
Claimant |
|
- and - |
||
Selecta Systems Ltd |
Defendant |
____________________
Stewart Chirnside (instructed by Shakespeare Martineau) for the Defendant
Hearing dates: 20-23 March, 9 May 2018
____________________
Crown Copyright ©
HHJ Paul Matthews :
Introduction
Procedure
Civil decision-making
Witnesses
Facts found
Law
"45. The general principles are not in doubt. Whether there is a binding contract between the parties and, if so, upon what terms depends upon what they have agreed. It depends not upon their subjective state of mind, but upon a consideration of what was communicated between them by words or conduct, and whether that leads objectively to a conclusion that they intended to create legal relations and had agreed upon all the terms which they regarded or the law requires as essential for the formation of legally binding relations. Even if certain terms of economic or other significance to the parties have not been finalised, an objective appraisal of their words and conduct may lead to the conclusion that they did not intend agreement of such terms to be a pre-condition to a concluded and legally binding agreement."
"(1) In order to determine whether a contract has been concluded in the course of correspondence, one must first look to the correspondence as a whole...
(2) Even if the parties have reached agreement on all the terms of the proposed contract, nevertheless they may intend that the contract shall not become binding until some further condition has been fulfilled. That is the ordinary 'subject to contract' case.
(3) Alternatively, they may intend that the contract shall not become binding until some further term or terms have been agreed...
(4) Conversely, the parties may intend to be bound forthwith even though there are further terms still to be agreed or some further formality to be fulfilled...
(5) If the parties fail to reach agreement on such further terms, the existing contract is not invalidated unless the failure to reach agreement on such further terms renders the contract as a whole unworkable or void for uncertainty.
(6) It is sometimes said that the parties must agree on the essential terms and it is only matters of detail which can be left over. This may be misleading, since the word 'essential' in that context is ambiguous. If by 'essential' one means a term without which the contract cannot be enforced then the statement is true: the law cannot enforce an incomplete contract. If by 'essential' one means a term which the parties have agreed to be essential for the formation of a binding contract, then the statement is tautologous. If by 'essential' one means only a term which the Court regards as important as opposed to a term which the Court regards as less important or a matter of detail, the statement is untrue. It is for the parties to decide whether they wish to be bound and if so, by what terms, whether important or unimportant. It is the parties who are, in the memorable phrase coined by the Judge [at page 611] 'the masters of their contractual fate'. Of course the more important the term is the less likely it is that the parties will have left it for future decision. But there is no legal obstacle which stands in the way of the parties agreeing to be bound now while deferring important matters to be agreed later. It happens every day when parties enter into so called 'heads of agreement'."
"the more complicated the subject matter the more likely the parties are to want to enshrine their contract in some written document to be prepared by their solicitors. This enables them to review all the terms before being committed to any of them. The commonest way of achieving this ability is to stipulate that the negotiations are 'subject to contract'."
"(1) Any provision in an agreement (whether a contract of employment or not) is void in so far as it purports–
(a) to exclude or limit the operation of any provision of this Act, or
(b) to preclude a person from bringing any proceedings under this Act before an industrial tribunal.
(2) Subsection (1)–
[ … ]
(f) does not apply to any agreement to refrain from instituting or continuing before an industrial tribunal any proceedings within section 18(1)(d) (proceedings under this Act where conciliation available) of the Industrial Tribunals Act 1996 if the conditions regulating compromise agreements under this Act are satisfied in relation to the agreement.
(3) For the purposes of subsection (2)(f) the conditions regulating compromise agreements under this Act are that–
(a) the agreement must be in writing,
(b) the agreement must relate to the particular complaint,
(c) the employee or worker must have received independent legal advice from a qualified lawyer as to the terms and effect of the proposed agreement and, in particular, its effect on his ability to pursue his rights before an industrial tribunal,
(d) there must be in force, when the adviser gives the advice, a policy of insurance covering the risk of a claim by the employee or worker in respect of loss arising in consequence of the advice,
(e) the agreement must identify the adviser, and
(f) the agreement must state that the conditions regulating compromise agreements under this Act are satisfied.
[ … ]."
"there is a cause of action in tort whether or not [a carbon emission allowance known as a European Union Allowance, or EUA] is regarded as 'intangible property'."
"if and where legal title remains with the claimant, a proprietary restitutionary claim at common law is available in respect of receipt by the defendant of a chose in action or other intangible property."
Even so, I do not see how this is relevant to the facts of the present case.
"It would seem that there is in some cases a sui generis action, distinct from conversion, for knowing misdealings with intangible assets of value, which cause loss to those entitled to the benefit of those intangibles."
For this proposition, the learned editors refer to the decision in Armstrong. However, in the written submissions of the claimant, nothing further is said as to how this relates to the facts of the present case. I will consider this claim further in applying the law to the facts of the case.
"The parties were agreed that the authorities disclose three tests which have been used in deciding whether a defendant sued as causing pure economic loss to a claimant owed him a duty of care in tort. The first is whether the defendant assumed responsibility for what he said and did vis-à-vis the claimant, or is to be treated by the law as having done so. The second is commonly known as the threefold test: whether loss to the claimant was a reasonably foreseeable consequence of what the defendant did or failed to do; whether the relationship between the parties was one of sufficient proximity; and whether in all the circumstances it is fair, just and reasonable to impose a duty of care on the defendant towards the claimant (what Kirby J in Perre v Apand Pty Ltd [1999] HCA 36, (1999) 198 CLR 180, para 259, succinctly labelled 'policy'). Third is the incremental test, based on the observation of Brennan J in Sutherland Shire Council v Heyman (1985) 157 CLR 424, 481, approved by Lord Bridge of Harwich in Caparo Industries Plc v Dickman [1990] 2 AC 605, 618, that
'It is preferable, in my view, that the law should develop novel categories of negligence incrementally and by analogy with established categories, rather than by a massive extension of a prima facie duty of care restrained only by indefinable 'considerations which ought to negative, or to reduce or limit the scope of the duty or the class of person to whom it is owed'."
Discussion
Conclusion