CHANCERY DIVISION
BIRMINGHAM DISTRICT REGISTRY
Bull Street, Birmingham B4 6DS |
||
B e f o r e :
____________________
Anderson Properties Ltd |
Claimant |
|
- and - |
||
Blyth Liggins (a firm) |
Defendant |
____________________
Mark Cannon QC (instructed by Reynolds Porter Chamberlain LLP) for the Defendant
Hearing dates: 27,28,31 October, 1,3,4 November 2016
____________________
Crown Copyright ©
HHJ David Cooke:
Introduction
i) It could have obtained planning permission and sold the land with the benefit of it, orii) It could have gone on to complete Phase 1 of the development and sold the land with the benefit of planning permission for Phase 2, or
iii) It could have completed the whole development itself.
The damages claimed as set out in a schedule of loss (Bundle A/p 67) are put at just under £8m. This is based on a suggested 50% chance that the claimant would have completed the whole development, 25% that it would have developed Phase 1 but not phase 2 and 25% that it would not have undertaken any development itself but sold the land with planning permission.
The contract and allegations of negligence
i) The proposed development was referred to as a "care village" and comprised three main elements:a) A 20 bedroom residential unit for adults with learning difficulties, physical disabilities and/or dementia. It was intended that the existing Newlands Hurst residents would be moved into this unit when it was completed and thereafter looked after for life by the purchaser, subject to continuing payment of fees at their existing level. This was referred to as the "Care Facility".b) An 80 bed nursing home, andc) A number, originally envisaged to be about 120, of single and double bedroom apartments to be sold to older persons on the basis that they would have available to them (for a fee) care facilities and services provided on site. These were referred to as "close care units" or "supported housing". The part of the site on which they would be built was referred to as the "Supported Housing Site".d) It was envisaged that there would be other facilities on the site, such as a GP surgery, pharmacy and communal facilities for residents of all of the parts.ii) The layout of the various elements was not specified in the contract. Mr. Jeffs was throughout the negotiations adamant in his instructions to the defendant that he required flexibility to negotiate the best arrangement he could with the local planning authority, Wychavon DC. His preference was to do this before a formal application was submitted, so that, it was hoped, the application would be agreed and supported by planning officers. He was particularly interested in obtaining permission for the greatest possible number of close care apartments, which he no doubt envisaged would be the most profitable part of the development. The contract therefore provided a mechanism by which
a) The purchaser (ie the claimant) would prepare a draft full planning application. This necessarily would show the proposed layout of the buildings roads and other facilities on the siteb) That draft would be approved by the Charity, such approval not to be unreasonably withheld or delayed, andc) The claimant would then make an application in the approved form, and have the right to pursue it to appeal and judicial review.iii) Completion would be subject to receipt of a planning permission satisfactory to the claimant, though the claimant had the right to waive this condition.
iv) On completion the Charity would transfer the whole site to the claimant, and
a) The claimant would pay £400,000, less a deposit of £10,000 paid on exchangeb) The claimant would grant a 999 year lease of "the Care Facility" to the Charity at a nominal rent, in the form attached to the contract. That form defined the area to be leased by reference to "the plan annexed". No such plan was however attached to the draft form of leasec) The Charity would immediately grant an underlease of the same premises back to the claimant, for a term just less than 999 years and again at a nominal rent.v) The claimant undertook in the contract to construct "the Care Facility" within 18 months of completion. In the meantime the Charity would continue to accommodate the residents in the existing building (and was granted a licence to occupy for that purpose) but on completion of the new Care Facility the business and assets of the Charity would be transferred to the purchaser which would thereafter accommodate the residents in the new Care Facility. Depending on the terms of the planning permission obtained, the old house would either be demolished or refurbished as part of the claimant's development (but not as part of the Care Facility).
vi) On completion of the Care Facility the claimant would pay a further £1.4m, subject to deduction of certain additional costs if incurred. This amount was referred to as "the Further Sum" and was to be secured by a legal charge over the Supported Housing Site, in the form of a draft attached to the contract, to be granted at completion. This charge also required a plan to be attached to define the land charged, but none was included in the draft.
vii) The claimant had an option, exercisable within 48 months after completion of the Care Facility, to pay a further amount of £1.7m referred to as "the Supported Housing Site Price", in which event it would retain for itself all proceeds of the development and sale of the apartments to be built on that part of the site. In default, a schedule to the contract provided for what was described as a joint venture development, but was in substance only an obligation on the claimant to pay the Charity 16.25% of the net proceeds of sale of each apartment as and when built and sold by it. If this obligation was exercised, the percentage share of proceeds was also to be secured by the legal charge.
i) The underlease back to the claimant contained a covenant to build the Care Facility in terms corresponding to the obligation in the contract. Mr. Scott said this was required so that if the claimant defaulted in completing the facility, the Charity would be able to forfeit the underlease and complete the works itself.ii) Mr. Scott advised that the retention of the Charity's limited interest in the site would enable it to say it was maintaining its charitable purpose even though it had ceased to be responsible for the residents.
"4.1 The Buyer shall as soon as reasonably practicable and in any event before 10 December 2009 [or such extended period of time as the Seller shall approve…] submit a Planning Application to the Local Planning Authority … The planning application shall first be submitted to and first approved by the Seller in draft (such approval not to be unreasonably delayed or withheld).
1.33 'Planning Application' means an application for the Planning Permission
1.35 'Planning Permission' means full planning permission for the construction of a care village on the Property retaining the existing principal house (at least until the Care Facility is constructed) including the Care Facility
1.9 'the Care Facility' means a new residential care facility for persons with physical and learning disabilities capable of delivering at least similar services to those presently offered by the Seller in accordance with CSCI NHS Trust and all other statutory requirements at the date of completion
2.2 The sale and purchase of the Property… is conditional upon:
2.2.1 the Unconditional Date occurring prior to the Termination Date…
2.4 Unless the Unconditional Date has occurred this agreement shall automatically determine upon the Termination Date …
1.52 'the Unconditional Date' means three months after the grant of the Satisfactory Planning Permission …
1.40 'a Satisfactory Planning Permission' means a Planning Permission which is not subject to an Unreasonable Condition [defined in clause 5]
1.51 'Termination Date' means 6 March 2011 unless on that date … the Planning Application has not yet been decided … when the Termination Date shall be extended until the expiry of three months from the issue of the decision by the Local Planning Authority…
2.3 The Buyer has the sole benefit of the condition referred to in clause 2.2.1 above and made by written notice given at any time prior to the Termination Date unilaterally waive the condition and upon the giving of notice to that effect the Unconditional Date shall be deemed to have occurred."
The allegations of negligence
i) There was uncertainty as to the land to be comprised in the lease, underlease and Seller's Charge over the Supported Housing Site, by reason of the absence of plans when the contract was executed,ii) The schedule providing for joint venture development of "close care housing" as part of the "care village" on the Supported Housing Site did not define these terms.
(see paras 31-2 of the Particulars of Claim at A/11).
"Even when a document (or relevant part of a document) is intended by the parties to be legally binding, there are circumstances in which it may be regarded as too uncertain to be enforceable by a court. Such a conclusion should, however, be one of last resort. English law aims to uphold and give effect to the intentions of the parties, not to defeat them. As Lord Tomlin observed in Hillas & Co Ltd v. Arcos Ltd (1932) 43 Ll.L.Rep. 359, 364, the aim of the court 'must always be so to balance matters that, without violation of essential principle, the dealings of men may as far as possible be treated as effective, and that the law may not incur the reproach of being the destroyer of bargains.' Accordingly, where the court is satisfied that the parties intended that their bargain should be enforceable, it will strive to give effect to that intention by construing the words used in a way which gives them a practical meaning: see e.g. Brown v. Gould [1972] Ch. 53, 56-58; BJ Aviation Ltd v Pool Aviation Ltd [2002] EWCA Civ 163, [2002] 2 P. & C.R. 25, para 23; Maple Leaf Macro Volatility Master Fund v. Rouvroy [2009] EWHC 257 (Comm), [2009] 1 Lloyd's Rep 475, para 235; Barbudev v. Eurocom Cable Management Bulgaria EOOD and others [2012] EWCA Civ 548, para 32."
"In my judgment the following principles relevant to the present case can be deduced from these authorities, but this is intended to be in no way an exhaustive list:
Each case must be decided on its own facts and on the construction of its own agreement. Subject to that:
1. Where no contract exists, the use of an expression such as 'to be agreed' in relation to an essential term is likely to prevent any contract coming into existence, on the ground of uncertainty. This may be summed up by the principle that 'you cannot agree to agree'.
2. Similarly, where no contract exists, the absence of agreement on essential terms of the agreement may prevent any contract coming into existence, again on the ground of uncertainty.
3. However, particularly in commercial dealings between parties who are familiar with the trade in question, and particularly where the parties have acted in the belief that they had a binding contract, the Courts are willing to imply terms, where that is possible, to enable the contract to be carried out.
4. Where a contract has once come into existence, even the expression 'to be agreed' in relation to future executory obligations is not necessarily fatal to its continued existence.
5. Particularly in the case of contracts for future performance over a period, where the parties may desire or need to leave matters to be adjusted in the working out of their contract, the Courts will assist the parties to do so, so as to preserve rather than destroy bargains, on the basis that what can be made certain is itself certain. Certum est quod certum reddi potest.
6. This is particularly the case where one party has either already had the advantage of some performance which reflects the parties' agreement on a long term relationship, or has had to make an investment premised on that agreement.
7. For these purposes, an express stipulation for a reasonable or fair measure or price will be a sufficient criterion for the courts to act on. But even in the absence of express language, the Courts are prepared to imply an obligation in terms of what is reasonable."
i) That the size, design, layout, position and specification of the care facility, including the decision as to what ancillary land should be included, were essentially to be determined by the purchaser subject only to the requirement that it be capable of delivering services at least similar to the old facilityii) That subject to that requirement being satisfied the Charity had little real interest in the precise boundary of the land to be leased. Once the facility was built the Charity would hold only a largely notional intermediate reversion entitling it to possession for a brief period in 999 years time. In the event it sought to forfeit the underlease and build the facility itself it would be able to do so as long as the land demised included the building area and any surrounding land reasonably necessary for operation of the facility
I have no doubt the court would strive to uphold the enforceability of the contract. It would be able to do so, for instance, by finding that there was an implied term that the land to be demised would include the relevant buildings and such surrounding land as was reasonably necessary to be occupied exclusively for the operation of the care facility, and that the parties were under an obligation to agree a plan identifying such land, in default of which the court could do so, applying objective standards.
Causation and loss
Could the claimant company have obtained the funds to complete?
Could the claimant have funded any part of the development?
Could the land have been sold at a profit?
Other participants
Conclusion