CHANCERY DIVISION
Strand, London, WC2A 2LL |
||
B e f o r e :
SITTING AS A DEPUTY JUDGE OF THE HIGH COURT
____________________
JOMAST ACCOMMODATION LIMITED |
Claimant |
|
- and - |
||
G4S CARE AND JUSTICE SERVICES (UK) LIMITED |
Defendant |
____________________
Duncan McCall QC and Matthew Lavy (instructed by Clyde & Co for the Defendant)
Hearing dates: 15th, 16th, 17th, 18th, 21st and 24th November 2016
____________________
Crown Copyright ©
Ms Lesley Anderson QC :
Preliminary
a) Whether G4S is liable to Jomast in fraudulent misrepresentation as alleged in paragraphs 38 to 42 of the Particulars of Claim; and
b) Whether on the correct construction of paragraph 4.8 of Schedule 5 and having regard to the relevant surrounding circumstances or "factual matrix":
i) in circumstances where G4S itself provides services and where the actual cost to G4S of providing the services exceeds £8.10 per service user per night, G4S is liable to pay Jomast an increased sum measured by reference to the difference between £8.10 per service user per night and the cost incurred by G4S in carrying out "Compliant Services" (as that term is defined in paragraph 30.3 of the Particulars of Claim) the same or similar to those supplied by Jomast (with or without a profit margin) as alleged at paragraph 37.2.2 of the Particulars of Claim;
ii) in circumstances where G4S provides services itself which are not Compliant Services the same or similar to those supplied by Jomast, G4S is liable to pay Jomast an increased Service sum measured by reference to the difference between £8.10 per service user per night and the cost that would have been incurred by G4S in providing the services had such services been Compliant Services, as alleged at paragraph 37.3 of the Particulars of Claim;
iii) in circumstances where a sub-contractor of G4S carries out services which are not "Compliant Services" (as that term is defined in paragraph 30.3 of the Particulars of Claim) the same or similar to those supplied by Jomast, G4S is liable to pay Jomast an increased Service Charge measured by reference to the difference between £8.10 per service user per night and the price that would have been charged by G4S's sub-contractor had its services been Compliant Services" as alleged at paragraph 37.3 of the Particulars of Claim;
iv) If the answer to (ii) and/or (iii) is in the affirmative, how such cost or price of providing Compliant Services is to be ascertained?
Factual Background
"i) meet the accommodation and essential living needs of eligible asylum seekers; and
ii) have available, through appropriate contractual agreements a range of services to be provided to eligible asylum seekers;
iii) have available, through appropriate contractual agreements, a transport service available to eligible asylum seekers."
Volume of Service Users | Single SU per night | Family SU per night |
0 1000 | £9.40 | £8.84 |
1001 3000 | £9.20 | £8.63 |
3001 7500 | £9.08 | £8.50 |
7501+ | £9.00 | £8.42 |
i) Recital A was in substantively identical terms to Recital B of the COMPASS Contract;
ii) By clause 3.1 that the Agreement governs the relationship between the parties in relation to the Services provided by [Jomast] to [G4S];
iii) By clause 3.2 that [G4S] shall be entitled at any time to require the provision of any or all of the Services from [Jomast] in accordance with the SOW;
iv) By clause 3.3 that a SOW shall not enter force, be legally binding or have any other effect unless it is first signed by [Jomast] and countersigned by [G4S];
v) By clause 3.6 that [Jomast] was to provide the Services to [G4S] in accordance with the terms and conditions of the Agreement (including, without limitation, the provisions of any SOW, Schedule 2 (Statement of Requirements) and Schedule 13 (Performance Regime));
vi) By clause 3.8 that [Jomast] was to commence provision of the Services described in the SOW on the date specified in such SOW ("the Commencement Date") and from which date [G4S] was entitled to issue Accommodation Requests Orders, which are issued to [Jomast] in respect of Service Users;
vii) By clause 3.10 that if so requested by [G4S], [Jomast] would provide the Additional Services and [G4S] would pay for the same at the rates set out in the SOW;
viii) By clause 3.11 that [G4S] made no representation as to the number or type of Service Users which would be allocated to [Jomast] and [Jomast] confirmed that it had no expectation of and should have no claim against [G4S] in respect of, a minimum number of Service Users (or a particular type of Service User) to be allocated to it by [G4S] under the Agreement or any SOW. [Jomast] thereby acknowledged that the number of Service Users may increase and decrease from time to time;
ix) By clause 5.1 that in consideration of the provision of any Services by [Jomast] on the terms of the Agreement [G4S] would pay the Service Charges in accordance with the charging arrangements set out in the SOW and in Schedule 5 (Service Charges) (and for the avoidance of doubt, such Service Charges were payable during the Transaction Period where appropriate). The Service Charges were subject to adjustment as set out in such Schedule;
x) By clause 5.6 that save as expressly provided for in the Agreement, [Jomast] was not entitled to levy any charge or receive any payment in respect of its performance of the Agreement, compliance with its terms and/or costs of engaging any of its suppliers and/or its sub-contractors (including without limitation those referred to in Schedule 24 (Material sub-contractors) in connection with such performance/compliance;
xi) By clause 19.3 that save where the claim relates to the death or personal injury of any person or arises as a result of any fraud, fraudulent representation; the maximum financial liability of [Jomast] in respect of all claims (whether caused by negligence or otherwise) pursuant to the Agreement, for any breach of the Agreement or for any tort, breach of statutory duty, misrepresentation, misstatement in connection with the Agreement would in no event exceed the sum of £500,000; except where [Jomast] has valid insurance in place directly in respect of such claim in which case the liability was to be limited to the amount paid out pursuant to such insurance policy;
xii) By clause 19.4 that subject to clauses 19.5, 11.31 and 11.32 and the Service Charge provisions and notwithstanding clause 19.3, neither party would be liable to the other party for: (a) any indirect special or consequential loss or damage; (b) any loss of profits, turnover, business opportunities, damage to goodwill (whether direct or indirect) or anticipated savings;
xiii) By clause 39.1 that the Agreement constituted the entire understanding between the parties relating to the subject matter of the Agreement and supersedes all prior agreements between the parties and relating thereto;
xiv) By clause 39.2 that neither party had relied on any warranty or representation of any party (except for the Warranties) and each party irrevocably and unconditionally waived any right it might have to claim damages for any misrepresentation or breach of any warranty not contained in the Agreement and/or to rescind the Agreement unless such misrepresentation or warranty was made fraudulently.
The Witnesses
i) Stuart John Monk ("Mr Monk"), the Managing Director of Jomast, with overall responsibility for strategy and operations including the provision of asylum seeker services;
ii) Gordon Paul Greer ("Mr Greer"), a Chartered Accountant and Finance Director at Jomast, responsible for the financial management of the Jomast Group including the Agreement;
iii) Stephen Small ("Mr Small") who was employed by G4S as Managing Director of Detention & Escorting from January 2010 until June 2011 and as Managing Director of Immigration & Borders until his retirement in April 2015 and responsible for running the COMPASS Contract;
iv) Andrew David Gray ("Mr Gray") who was employed by G4S from March 2012 until June 2014 as Accommodation Director and from June 2014 to December 2015 as Partnerships Director for the COMPASS Contract;
v) Stella Margaret Gutteridge ("Ms Gutteridge") who was engaged as a consultant by G4S from December 2011 to December 2012 as Mobilisation Director for the COMPASS Contract.
i) First witness statement of Mr Monk dated 12 May 2016;
ii) Witness statement of Armel Elaudais, an associate solicitor at Clyde & Co LLP, solicitors on behalf of G4S dated 27 May 2016;
iii) Second witness statement of Mr Monk dated 10 June 2016.
The Law on Proper Construction of the Agreement
"The meaning to be given to the words used in a contract is the meaning which ought reasonably to be ascribed to those words having due regard to the purpose of the contract and the circumstances in which the contract was made".
" the exercise of construction is essentially one unitary exercise in which the court must consider the language used and ascertain what a reasonable person, that is a person who has all the background knowledge which would reasonably have been available to the parties in the situation in which they were at the time of the contract, would have understood the parties to have meant. In doing so, the court must have regard to all the relevant surrounding circumstances. If there are two possible constructions, the court is entitled to prefer the construction which is consistent with business common sense and to reject the other".
"When interpreting a written contract, the court is concerned to identify the intention of the parties by reference to 'what a reasonable person having all the background knowledge which would have been available to the parties would have understood them to be using the language in the contract to mean', to quote Lord Hoffmann in Chartbrook Ltd v Persimmon Homes Ltd [2009] UKHL 38, [2009] 1 AC 1101, para 14. And it does so by focussing on the meaning of the relevant words in their documentary, factual and commercial context. That meaning has to be assessed in the light of (i) the natural and ordinary meaning of the clause, (ii) any other relevant provisions of the [contract], (iii) the overall purpose of the clause and the [contract], (iv) the facts and circumstances known or assumed by the parties at the time that the document was executed, and (v) commercial common sense, but (vi) disregarding subjective evidence of any party's intentions ".
"17. First, the reliance placed in some cases on commercial common sense and surrounding circumstances (eg in Chartbrook, paras 16-26) should not be invoked to undervalue the importance of the language of the provision which is to be construed. The exercise of interpreting a provision involves identifying what the parties meant through the eyes of a reasonable reader, and, save perhaps in a very unusual case, that meaning is most obviously to be gleaned from the language of the provision. Unlike commercial common sense and the surrounding circumstances, the parties have control over the language they use in a contract. And, again save perhaps in a very unusual case, the parties must have been specifically focusing on the issue covered by the provision when agreeing the wording of that provision.
18. Secondly, when it comes to considering the centrally relevant words to be interpreted, I accept that the less clear they are, or, to put it another way, the worse their drafting, the more ready the court can properly be to depart from their natural meaning. That is simply the obverse of the sensible proposition that the clearer the natural meaning the more difficult it is to justify departing from it. However, that does not justify the court embarking on an exercise of searching for, let alone constructing, drafting infelicities in order to facilitate a departure from the natural meaning. If there is a specific error in the drafting, it may often have no relevance to the issue of interpretation which the court has to resolve.
19. The third point I should mention is that commercial common sense is not to be invoked retrospectively. The mere fact that a contractual arrangement, if interpreted according to its natural language, has worked out badly, or even disastrously, for one of the parties is not a reason for departing from the natural language. Commercial common sense is only relevant to the extent of how matters would or could have been perceived by the parties, or by reasonable people in the position of the parties, as at the date that the contract was made. Judicial observations such as those of Lord Reid in Wickman Machine Tools Sales Ltd v L Schuler AG [1974] AC 235, 251 and Lord Diplock in Antaios Cia Naviera SA v Salen Rederierna AB (The Antaios) [1985] AC 191, 201, quoted by Lord Carnwath at para 110, have to be read and applied bearing that important point in mind.
20. Fourthly, while commercial common sense is a very important factor to take into account when interpreting a contract, a court should be very slow to reject the natural meaning of a provision as correct simply because it appears to be a very imprudent term for one of the parties to have agreed, even ignoring the benefit of wisdom of hindsight. The purpose of interpretation is to identify what the parties have agreed, not what the court thinks that they should have agreed. Experience shows that it is by no means unknown for people to enter into arrangements which are ill-advised, even ignoring the benefit of wisdom of hindsight, and it is not the function of a court when interpreting an agreement to relieve a party from the consequences of his imprudence or poor advice. Accordingly, when interpreting a contract a judge should avoid re-writing it in an attempt to assist an unwise party or to penalise an astute party.
21. The fifth point concerns the facts known to the parties. When interpreting a contractual provision, one can only take into account facts or circumstances which existed at the time that the contract was made, and which were known or reasonably available to both parties. Given that a contract is a bilateral, or synallagmatic, arrangement involving both parties, it cannot be right, when interpreting a contractual provision, to take into account a fact or circumstance known only to one of the parties.
22. Sixthly, in some cases, an event subsequently occurs which was plainly not intended or contemplated by the parties, judging from the language of their contract. In such a case, if it is clear what the parties would have intended, the court will give effect to that intention. An example of such a case is Aberdeen City Council v Stewart Milne Group Ltd [2011] UKSC 56, 2012 SCLR 114, where the court concluded that "any approach" other than that which was adopted "would defeat the parties' clear objectives", but the conclusion was based on what the parties "had in mind when they entered into" the contract (see paras 17 and 22)".
i) Although the factual matrix surrounding the agreement of a contract can be relevant, it is the language actually used that is paramount see Lord Neuberger at [17];
ii) The admissible factual matrix consists only of facts known to both parties, and not facts known to one party alone see Lord Neuberger at [21];
iii) Although generally a court will seek to give meaning to every part of a contract or clause (the so-called presumption against superfluous language) it should not strain to do so, particularly where a contract is poorly drafted see ENER-G Holdings Plc v Hornell [2012] C.P. Rep 47, per Gross LJ at [59].
The Law on Deceit
"76. On the basis of these authorities all the appellants contend that intention to deceive is an element of the tort of deceit. The judge failed to address this element. She did not find that it had been established. On the contrary it is clear that the defendants did not have an intention to deceive.
77. I do not agree with the analysis of the authorities which the appellants advance. What the cases show is that the tort of deceit contains four ingredients, namely:
i) The defendant makes a false representation to the claimant.
ii) The defendant knows that the representation is false, alternatively he is reckless as to whether it is true or false.
iii) The defendant intends that the claimant should act in reliance on it.
iv) The claimant does act in reliance on the representation and in consequence suffers loss.
Ingredient (i) describes what the defendant does. Ingredients (ii) and (iii) describe the defendant's state of mind. Ingredient (iv) describes what the claimant does.
77. I do not accept that "intention to deceive" is a separate or free standing element of the tort of deceit. The phrase "intention to deceive" is merely another way of describing the mental element of the tort. It is a compendious description of ingredients (ii) and (iii) as set out in the preceding paragraph."
i) The relevant representation has to be identified with clarity, and understood in its context per Rix LJ in AIC Ltd v ITS Testing Services (UK) Ltd ("The Kriti Palm") [2007] Lloyd's Rep 555 at [252].
ii) Where a statement is capable of being understood in more than one sense, it is essential to liability in deceit that the party making the statement should have intended it to be understood in its untrue sense, or at the very least that he should have deliberately used the ambiguity for the purpose of deceiving the claimant see Clerk & Lindsell on Torts, 19th ed, 2006 at [18-25].
iii) Put another way, the requisite mental element compendiously described as "intention to deceive" and comprising elements (ii) and (iii) implies some coincidence between the knowledge on the part of the representor that the representation bears the false meaning in element (ii) and his intention that the claimant should act on it in that same sense in element (iii).
iv) The question is not whether the defendant in any given case honestly believed the representation to be true in the sense assigned to it by the court on an objective consideration of its truth or falsity, but whether he honestly believed the representation to be true in the sense in which he understood it albeit erroneously when it was made - Akerheim v Rolf de Mare [1959] AC 789 (PC) per Lord Jenkins at 805.
v) The test for dishonesty remains as set out in Derry v Peek per Lord Herschell at 374:
"First, in order to sustain an action of deceit, there must be proof of fraud, and nothing short of that will suffice. Secondly, fraud is proved when it is shown that a false representation has been made (i) knowingly, (ii) without belief in its truth, or (iii) reckless, careless whether it be true or false. Although I have treated the second and third as distinct cases, I think the third is but an instance of the second, for one who makes a statement under such circumstances can have no real belief in the truth of what he states. To prevent a statement from being fraudulent, there must, I think, always be an honest belief in its truth. Thirdly, if fraud be proved, the motive of the person guilty of it is immaterial. It matters not that there was no intention to cheat or injure the person to whom the statement was made."
vi) Knowledge for the purposes of fraud is explained in Armstrong v Strain [1951] TLR 856, per Devlin LJ:
"A man may be said to know a fact when once he has been told it and pigeon-holed it somewhere in his brain where it is more or less accessible in case of need. In another sense of the word a man knows a fact only when he is fully conscious of it. For an action of deceit there must be knowledge in the narrower sense; and conscious knowledge of falsity must always amount to wickedness and dishonesty. When Judges say, therefore, that wickedness and dishonesty must be present, they are not requiring a new ingredient for the tort of deceit so much as describing the sort of knowledge which is necessary."
vii) Recklessness is not to be equated with even an extreme form of negligence; recklessness entails having a dishonest state of mind implying a degree of moral obliquity see Angus v Clifford [1891] 2 Ch 449 per Bowen LJ at 471.
viii) Where it is alleged that a corporate entity acted fraudulently, it is necessary to identify the individual who made the representation and to establish that that individual (or, if not that individual, the person who directed or allowed the representation to be made) had a dishonest state of mind see Man Nutzfahrzeuge AG v Freightliner Ltd [2005] EWHC 2347 (Comm) per Moore-Bick LJ at [156].
ix) The representor should intend that the representation is acted upon by the claimant in the sense in which it caused damage to him (per Morritt LJ in Goose v Wilson Sandford & Co (No.2) [2001] 189 Lloyd's Rep PN 189 at [48] citing the speech of Lord Maugham in Bradford Third Equitable Benefit Building Society v Borders [1941] 2 All ER 205 at 211).
i) It is not necessary, as a matter of law, to prove that the representee believed that the representation was true. However, the representee's state of mind may be relevant to the issue of reliance. If the representee does not believe that the representation is true, he may have serious difficulty in establishing that he was induced to enter into the contract or that he has suffered loss as a result (per Lord Clarke at [18] and [40]-[42]; per Lord Toulson at [67]).
ii) Materiality is evidence of inducement because what is material tends to induce (per Lord Clarke at [29]).
iii) Where there are multiple causes, it is sufficient for the misrepresentation to be an inducing cause and it is not necessary for it to be the sole cause (per Lord Clarke at [33], citing Chitty on Contracts, 32nd ed, Vol 1 at [7-37], Barton v Armstrong [1976] AC 104, Standard Chartered Bank Ltd v Pakistan National Shipping Corp Ltd (Nos 2 and 4) [2003] 1 AC 959 at [15]-[16] and Gould v Vaggelas (1984) 157 CLR 215 (HC of Aus, Wilson J) at 236).
iv) Lord Clarke (at [32]) rejected the analysis of the Court of Appeal that for a claimant to be able to rescind a contract for misrepresentation, it must show that it was induced into making the contract by a perception that the relevant statement was true rather than false.
v) In relation to the presumption of inducement, this is not a presumption of law but an inference of fact (per Lord Clarke at [34]). The authorities were not entirely consistent as to what was required to rebut the presumption. However, it was not strictly necessary to address those differences in Hayward because, however precisely the test was worded, the presumption was not rebutted on the facts of that case (per Lord Clarke at [36]).
vi) Although the court did not need to address the issue of what is required to rebut the presumption, Lord Clarke made the obiter comment that the authorities seemed to support the conclusion that it is very difficult to rebut the presumption in cases of fraud. In his view, the orthodox view was contained in Sharland v Sharland [2015] UKSC 60, [2016] AC 871, [2015] 3 WLR 1070 where the Supreme Court held that a party who has obtained a benefit by fraud, cannot deny its materiality or that it actually played a causative part in the inducement (per Lord Clarke at [37]). That view was supported by Downs v Chappell [1997] 1 WLR 426 per Hobhouse LJ at 433D-E and BP Exploration Operating Co Ltd v Chevron Shipping Co [2003] 1 AC 197 per Lord Millett at 244H-245A (per Lord Clarke at [38]).
vii) Lord Clarke agreed with the appellant claimant (Zurich) that there is no duty upon a defrauded representee to exercise due diligence to determine whether there are reasonable grounds to believe the representations made. A representee has no duty to be careful, suspicious or diligent in research (per Lord Clarke at [28(v)] and [39]).
viii) As Zurich only suspected fraud, it was not necessary for the court to express a final view on whether it always follows from the fact that the representee knows that the representation is false that he cannot succeed. However, Lord Clarke nevertheless expressed the view that, as causation and inducement are questions of fact, it seemed to him that there may be circumstances in which a representee may know that the representation is false but may be held to rely upon the misrepresentation as a matter of fact (per Lord Clarke at [44]).
ix) Only if there had been no influence at all could the agreement have stood and the representor succeed (see Clerk & Lindsell on Torts, 21st ed, 2nd Supplement at [18-50]).
i) If a fraudulent statement is proved, there is a presumption that the statement induced the claimant to enter the contract (per Lord Clarke in Hayward at [34]).
ii) The burden of proof to rebut that presumption shifts to the defendant to prove that, on a balance of probabilities, the misrepresentation did not influence the claimant to enter the contract. It is very difficult for a defendant to rebut the presumption (per Lord Clarke in Hayward at [37]).
iii) Although the standard of proof is the same as in any civil case, where fraud is alleged, cogent evidence is needed to prove it, because the evidence must overcome the inherent improbability that people act dishonestly rather than carelessly per Lord Nicholls in Re H and Ors (Minors) (sexual abuse: standard of proof) [1996] AC 563 at 586 and per Lewison J (as he then was) in Foodco UK LLP v Henry Boot Developments Ltd [2010] EWHC 358 (Ch) at [3].
i) Neither parties to litigation, their counsel, nor judges should make serious imputations or findings unless the person against whom they are made have been given a proper opportunity of dealing with them (per May LJ in Vogon International Ltd v The Serious Fraud Office [2004] EWCA Civ 104).
ii) Any allegation of dishonestly against an individual must be put clearly and directly to that witness see Briggs J (as he then was) in Dempster v HMRC [2008] EWHC 63(Ch) at [26]:
'Secondly, it is a cardinal principle of litigation that if a serious allegation, in particular allegations of dishonesty are to be made against a party who is called as a witness they must be both fairly and squarely pleaded, and fairly and squarely put to that witness in cross-examination'.
The Alleged Fraudulent Misrepresentations
i) As evidenced by a series of emails dated 4 October 2011 sent to other potential sub-contractors namely: Mantel Estates Limited ("Mantel"); LMG (EM) Limited ("Live"); Leena Homes Limited ("Leena") and Transpluscare ("Transplus") G4S was very keen to win the COMPASS contract for many regions;
ii) As the successful bidder in the MEE and NEYH Regions, G4S was bound to supply services to the UKBA at its e-auction bid prices;
iii) G4S bid for, and won, the COMPASS contract without sub-contractors being bound to supply sub-contract services to it;
iv) In particular, G4S had not reached any binding agreement with any sub-contractor on the sub-contract price;
v) G4S was determined to achieve a margin (profit) of 7% on the COMPASS contract;
vi) The COMPASS contract price was hopelessly low and G4S knew (as evidenced by emails sent on 13 or 19 December 2011 to Target Housing Limited ("Target"); Horton Housing Association ("Horton"); Openmoves ("Openmoves") and Metropolitan Housing Partnership ("Metropolitan") that it might lead to them withdrawing;
vii) To achieve the margin, G4S had to drive down the sub-contract costs (ie price);
viii) G4S had no flexibility, except to reduce the sub-contract prices;
ix) This caused some sub-contractors, namely Excell Lettings & Management Limited ("Excell") to refuse to proceed, and others to withdraw, namely Metropolitan and Openmoves on 19 December 2011, and later, Leena, on the ground that the price was unworkable which left G4S with few and weak suppliers;
x) The misrepresentations were part of the strategy to engage suppliers at a low price;
xi) In particular, G4S falsely used the price it had negotiated to receive from the UKBA as a tool to drive down the sub contract price and also to bring Jomast within its supply chain;
xii) G4S's overall strategy was: (i) to win the COMPASS contract at the best price achievable; (ii) then to negotiate the sub-contract price; and (iii) to force down the sub-contract price to achieve its desired main contract margin.
i) Orally, at a meeting on 17 January 2012;
ii) In writing, in an email sent on 29 February 2012;
iii) Orally, in a telephone conversation on 21 March 2012;
iv) In writing, in an email sent on 21 March 2012;
v) In writing, in an email sent on 29 March 2012;
vi) Orally, in a meeting on 4 April 2012.
The First Representation: 17 January 2012 Meeting
The Second Representation: 29 February 2012 E-mail
"Further to our conversation yesterday as promised I attach a schedule showing the breakdown of how we (our supply chain) believe we can achieve the price we have agreed with UKBA.
You may not agree with the breakdown or see how it is achieved, but it is provided in the spirit of trying to assist and in the acknowledgment that it was your expectation from our meeting.
The rent figures are market rents and the assumption is that landlords provide furnished accommodation and a repair service for the market rent.
I have to stress again that I am sending this information in absolute confidence.
Jomast must be able to confirm that you can deliver at the price we have agreed with UKBA, how the price is broken down is for you to confirm independently".
Jomast must be able to confirm that you can deliver at the price we have agreed with UKBA, how the price is broken down is for you to confirm independently".
The Third and Fourth Representations: 21 March 2012 Telephone Call and E-mail
"Further to our telephone conversation this morning I understand that you would like to have a further meeting with G4S with the possibility that we can reach an agreement for JOMAST to be part of G4S' COMPASS Programme. The essence of that meeting would be to have a best and final offer from you on your costs to G4S.
As we have discussed, there is currently a gap of £2.70. As I noted in that call, that whilst appreciating the current situation, G4S had agreed a supply price with UKBA that we have market tested. We are not in a position to pay more than we have indicated already. On the same basis that you have clearly articulated to me, any agreement has got to make sense commercially for both parties. Just as you would not want to enter into an agreement where that means making losses, then I am sure you will appreciate that is true for G4S also.
Therefore, I would be happy for that meeting to go ahead but, only the basis that G4S have made clear the current gap between us and that you have indicated to me that you believe that JOMAST can close that gap. Clearly, if that gap cannot be closed then any meeting would not see either of us reach any better conclusion than the one we face now and therefore, be unproductive for both parties.
As I said in our call Stuart, the day to day executive running of the contract, including budgets, costs and the procurement of suppliers sits with Andrew Gray. Andrew reports into to me and whilst I have a vested interest in the decisions Andrew makes on these matters, Andrew will make the overall call and it is my job to support and guide him only. For this meeting should we agree to go ahead, I will attend as a support to Andrew.
If you are in agreement that you can close the gap, then I will ask Jenny to organise this meeting at the very earliest opportunity that suits all.
I look forward to your reply."
"Thanks for the feedback. I have no real faith that JOMAST have any ability to deliver at our price.
My main aim here is to once and for all kill of JOMAST'S continued grievances (unfounded in my view) with UKBA at senior level that we have made little effort to engage JOMAST.
I will word the email appropriately and seek his assurance that he can close the gap before the meeting takes place (I have said as much in the email thus far). Once we have his response either committing to matching our price or not, I can, with auditable evidence show any creators of noise at UKBA that we have given him every opportunity to be part of COMPASS."
The Fifth Representation: 29 March 2012 E-mail
"Further to our conversation yesterday and in advance of our meeting next week I2agreed to confirm our position on the 3 key issues.
As we discussed there are 3 issues we need finally to agree:
1. Price Our price is £7.90. To clarify once and for all at the end of the e-auction, we arrived at a price with UPM (our main supplier) based on 100% volume. In order to still have a diverse supply chain we agreed, with UPM, a compensation payment for lost volume. This is 20p. Our e-auction price with UKBA is £8.10 and therefore our other suppliers have agreed to supply at the lower £7.90 price. I am sorry if the last email gave the impression of a price of £8.00.
2. Volumes We have agreed with UKBA that the split of properties to be supplied in the North East should be around 30%. This is based on a split with the 3 LIT areas. It appears that Jomast has more than this at present closer to 45% and it would be our intention to reduce this over the term of the contract.
3. KPI's We are flowing down the KPI's under our contract directly to the supply chain. The principle we are applying is if the fault for the KPI rests with one supplier then they are responsible for the whole of the penalty, which is calculated as a percentage of the revenue for the entire NEYH region. We are still working on the final version of this and I [sic] let you have this as soon as I can.
I hope this is now absolutely clear and look forward to our meeting next week. Can you please confirm Monday or Wednesday as the date."
"The reference in the email to the "e-auction agreed price with UKBA" was a typographical error, which should have read "e-auction agreed price with UPM". UPM had been present at G4S's offices as the e-auction took place, and as the auction price decreased agreed with G4S the price per service-user per night that it would be willing to accept. That was explained in the email in the words: " at the end of the e-auction, we arrived at a price with UPM (our main supplier) based on 100% volume".
"I read this email in the context of the discussion that I was told was ongoing at the time with Jomast, which was focusing on how much G4S had agreed to pay other subcontractors. I understood the email to mean that G4S's eAuction bid, as agreed with UKBA, was predicated on G4S paying its subcontractor(s) £8.10 per Service User per night in the NEYH region."
"Given the context of the email, it did not occur to me that Jomast would have understood Andrew's words "our e-auction agreed price with UKBA is £8.10" to mean that G4S was being paid £8.10 per Service User night by the UKBA" and "When I read the email, it would have been obvious to me that what Andrew was saying was that the price G4S could pay its other subcontractors was £7.90 because of the fact that it had agreed with UKBA a price which incorporated the target price to sub-contractors of £8.10".
i) Although it is common ground that the literal meaning of the e-mail was false, I am entirely satisfied that the explanation is innocent and so not fraudulent.
ii) In particular, I reject, because it is wholly implausible and contradicted by my assessment of those I heard, as honest witnesses, the implicit strand to the submissions made on behalf of Jomast that each of Mr Small, Mr Gray, Ms Gutteridge and Mr Bickers was dishonestly seeking to defraud Jomast and had colluded or conspired together for that purpose. There is simply nothing in the internal e-mail exchanges to support such a serious conclusion and much to undermine it. It is, as G4S submitted, wholly incongruous with the stated intention to avoid misleading Mr Monk.
iii) I accept the evidence of Mr Small, Ms Gutteridge and Mr Gray that, internally, the expression "e-auction agreed price with UKBA" had become a form of short-hand for the "e-auction agreed price UKBA which was predicated on what had been agreed with UPM, namely £8.10". This is consistent with the fact that, despite its flagged importance, none of them picked up the fact that it contained an error.
iv) On that basis, although I find that the false representation was made, it was not made dishonestly.
v) In any event, given Mr Monk's evidence that he needed clarity at the 4 April 2012 meeting, I am not satisfied that he relied on what had been said in this e-mail when entering into the Agreement.
The Sixth Representation: 4 April 2012 Meeting
i) In its annual accounts to 31 December 2012, Live reported net liabilities of £697,919;
ii) Mantel resigned as a sub-contractor for the MEE region on 30 January 2013 because it was unable to make a profit;
iii) On 1 July 2013, G4S took over responsibility for all of Live's previous asylum seeker accommodation services including taking a transfer of its employees.
The Warranty Claim
i) Part 1: "[G4S] warrants and acknowledges that the Service Charges per Service User per Night at least equal to the Company's other alternative subcontractors (including but not limited to [G4S] itself) of services the same or similar to the Services in any part of either Region ("Alternative Subcontractor");
ii) Part 2: "and if at any time the service charges due to any Alternative Subcontractor are higher than or increase above the Service Charges per Service User per Night, then the Service Charge per Service User per Night shall be immediately increased by an equal amount;
iii) Part 3: "[G4S] shall as soon as reasonably practicable notify [Jomast] if the service charges payable to any Alternative Subcontractor are higher than or increase above the Service Charges per Service User per night".
i) Whether the Warranty applies where it is G4S (as opposed to a third party sub-contractor) which supplies the relevant accommodation services to asylum seekers at a cost to it in excess of £8.10 PSUPN ("the Self-Delivery Issue");
ii) Whether the Warranty has the effect that if G4S or another sub-contractor delivers the relevant accommodation services to asylum seekers which are not compliant with G4S's contractual obligations to UKBA under the COMPASS Contract, Jomast is entitled to an additional payment to reflect the cost which would have been incurred by G4S or the other sub-contractor in supplying compliant services (i.e. services which would be compliant with G4S's obligations to UKBA under the COMPASS Contract) ("the Compliant Services Issue").
i) Jomast was an experienced provider of asylum-seeker accommodation which had provided services under Target between 2009 and 2012;
ii) Jomast had a suitable portfolio of properties and was well-placed to supply accommodation services to asylum seekers in the NEYH region but not in any other region;
iii) There had been an unknown bidder during the e-auction who made a bid but did not proceed which may have influenced bidding;
iv) G4S's bid to UKBA was predicated on a supply-chain model;
v) G4S had no experience of providing accommodation services to asylum seekers;
vi) Paragraph 4.2.1 of Schedule 2 of the COMPASS Contract required G4S to accommodate unlimited numbers of asylum seekers;
vii) Providing accommodation services involves elements of fixed costs;
viii) The COMPASS Contract included a performance regime based upon KPIs which, if not met, could cause G4S to incur financial penalties;
ix) The COMPASS Contract included provision for G4S to be financially responsible for the performance of its sub-contractors and for the satisfaction of the performance criteria;
x) G4S had been in negotiation with Jomast from November 2011 with a view to it being a subcontractor in the NEYH region but had been unable for some time to agree a price;
xi) In the course of the negotiations, Jomast had expressed concerns to G4S that it was not possible to supply compliant services at a price of £8.10 PSUPN;
xii) By late March 2012, G4S was intending to use a number of other sub-contractors and to compensate UPM for the loss of its 100% volume;
xiii) The withdrawal of UPM in late May 2012 had left G4S with an urgent requirement to find replacement sub-contractors for UPM;
xiv) On 25 May 2012, Jomast agreed, subject to contract, to supply sub-contract services at £8.10 PSUPN;
xv) Jomast sought confirmation, at the meetings on 30 May 2012 and 8 June 2012 and in the 6 June 2012 email that G4S would not pay any other sub-contractor more than the £8.10 PSUPN and that it would be entitled to an increased price if G4S increased the price for any other sub-contractor;
xvi) There was no discussion, whether at the meetings on 30 May 2012 and 8 June 2012 or otherwise, of G4S self-delivering accommodation services to asylum seekers;
xvii) The COMPASS Contract became operational on 18 June 2012.
i) Unless I am satisfied that they are surplusage, and I am not so satisfied, it is necessary to give some meaning to the words "the Company's other alternative subcontractors (including but not limited to [G4S] itself)" in Part 1 because the Court should give effect to the language actually used by the parties.
ii) The express inclusion of reference to G4S itself in the words in parenthesis in this part of the Warranty is a powerful indication that the parties were equating G4S with other sub-contractors and I reject as unduly semantic, G4S's suggestion that the two do not sit comfortably because G4S cannot be described as a sub-contractor of itself.
iii) I reject as implausible, G4S's submission that these words mean rather that the Warranty applies to an alternative subcontractor engaged indirectly (for example by another entity in the G4S group) as well as to one engaged directly by G4S.
iv) Although G4S is correct to point to the fact that the Warranty calls for a comparison of charges payable to Jomast with charges payable to other subcontractors and not one between charges payable to Jomast and costs incurred by G4S I do not regard this as fatal. In my view, it is tolerably clear that the clause is driving at a comparison between the respective liabilities for G4S in the case of alternative sub-contractors this refers to charges whereas in the case of self-delivery, it is referring to costs.
v) If I am wrong about this and the clause is to be regarded as ambiguous, I would accept Mr Todd QC's submission that to construe the Warranty as including self-delivery by G4S accords with common business common sense because Jomast was seeking to protect against an increase "by any mechanism" in the price from £8.10. It would significantly undermine that negotiated protection if G4S was able to self-deliver services at a price in excess of £8.10 without compensating Jomast.
i) Mr Todd QC fairly accepts that the Warranty does not provide expressly for any uplift to reflect the cost to an alternative sub-contractor of providing compliant services. The Warranty is silent on issues of quality and so rather assumes that the services supplied will be compliant services. However, I am not surprised by this as it seems to me that the core risk which the Warranty was designed to address was that Jomast should be paid at least the same rate PSUPN being paid to other sub-contractors.
ii) The Warranty refers explicitly to the provision of "services the same or similar to" the services provided by Jomast. Given that Jomast does not urge upon me a construction which has, as a premise, that it would be supplying non-compliant services, it seems to me that the comparator is also to be assumed to be providing compliant services. Unless one proceeds on this basis, the comparison is not like for like.
iii) I agree with Mr McCall QC that Jomast's construction involves reading too many words into the Warranty which are simply not there. Although this has the effect, which I accept, that Jomast is not protected from the risk that the services provided by another sub-contractor were non-compliant, I am not satisfied that a reasonable person, armed with the admissible background which I have identified, would have understood the parties to be dealing with issues of non-compliance.
iv) Not least, this is because Jomast's construction involves the comparison of the £8.10 PSUPN with a hypothetical charge representing what it would have cost the alternative sub-contractor (or G4S in light of my conclusions on self-delivery) to provide compliant services.
v) As Mr McCall QC submits, and I accept, I should be slow to accept a construction of the Warranty which countenances such an elaborate and complex exercise of comparison whenever the Warranty is engaged. Establishing the hypothetical cost of those alternative compliant services would be expensive, time-consuming and commercially unworkable especially given that, in the case of other sub-contractors, all or some of the information relating to the hypothetical additional cost would not be known to Jomast or possibly even G4S.
Conclusions on the Part 7 Claim
i) Issue 1.1 in the negative. G4S is not liable to Jomast in fraudulent misrepresentation as alleged in paragraphs 38 to 42 of the Particulars of Claim.
ii) Issue 1.2.1 in the positive. On the correct construction of paragraph 4.8 of Schedule 5 and having regard to the relevant surrounding circumstances or "factual matrix", G4S is obliged to pay an increased sum in circumstances where it self-delivers the services.
iii) Issues 1.2.2 and 1.2.3 in the negative. On the correct construction of paragraph 4.8 of Schedule 5 and having regard to the relevant surrounding circumstances or "factual matrix", G4S is not obliged to pay any compliant service uplift.
iv) Issues 1.2.4 does not arise on my findings but if am wrong and a compliant services uplift is payable, then it is a matter for expert evidence.
The Part 8 Claim
i) The target percentage of Service User nights in the NEYH Region to be allocated by G4S to Jomast under the SOW ("the Target Percentage Market Share") is 33.3% of the Individual Family Members and the Single Service Users allocated by the Defendant in the NEYH Region (paragraph 3.5 of Part H of Schedule 5 of the SOW) ("Declaration One");
ii) The number of (a) Individual Family Members and (b) Single Service Users which may be allocated to Jomast by G4S within the Target Percentage Market Share is (a) between 817 and 1,666 and (b) between 333 and 766 respectively (paragraph 14 of Part H of Schedule 5 to the SOW) ("Declaration Two");
iii) Jomast is not bound by the terms of the Agreement and the SOW to accept any allocation of Service Users by G4S in excess of Jomast's Target Percentage Market Share set out in paragraphs 3.5 and 14 of Part H of Schedule 5 of the SOW ("Declaration Three");
iv) Jomast is not bound by the terms of the Agreement and the SOW to provide any accommodation or other services to G4S in respect of Service Users allocated (or purportedly allocated) by G4S to Jomast in excess of Jomast's Target Percentage Market Share set out in paragraphs 3.5 and 14 of Part H of Schedule 5 of the SOW ("Declaration Four");
v) If G4S wishes to allocate to Jomast Service Users in excess of Jomast's Target Percentage Market Share set out in paragraphs 3.5 and 14 of Part H of Schedule 5 of the SOW, G4S is bound to invite Jomast to renegotiate Jomast's Target Percentage Market Share and the associated price for a revised volume range (paragraph 12.4 of Part H of Schedule 5 of the SOW) ("Declaration Five");
vi) If G4S wishes to allocate to Jomast Service Users in excess of Jomast's Target Percentage Market Share set out in paragraphs 3.5 and 14 of Part H of Schedule 5 of the SOW, but (i) G4S fails to invite Jomast to renegotiate Jomast's Target Percentage Market Share and the associated price for a revised volume range or (ii) Jomast and G4S fail to agree a revised Target Percentage Market Share for Jomast and/or an associated price for a revised volume range, Jomast is not bound
a) to accept any allocation of Service Users by G4S in excess of Jomast's Target Percentage Market Share set out in paragraphs 3.5 and 14 of Part H of Schedule 5 of the SOW or
b) to provide any accommodation or other services to G4S in respect of Service Users allocated (or purportedly allocated) by G4S to Jomast in excess of Jomast's Target Percentage Market Share set out in paragraphs 3.5 and 14 of Part H of Schedule 5 of the SOW
(paragraphs 12.4 and 12.7 of Part H of Schedule 5 of the SOW ("Declaration Six");
vii) If G4S wishes to allocate to Jomast Service Users in excess of Jomast's Target Percentage Market Share set out in paragraphs 3.5 and 14 of Part H of Schedule 5 of the SOW, but agreement is not reached between Jomast and G4S on a revised target market share and price
a) G4S may refer volumes of Service Users who are in excess of the Upper Limit set out in paragraph 14 to other subcontractors, alternatively to any subcontractor (including Jomast), but
b) Jomast is not bound to accept any allocation in excess of Jomast's Target Percentage Market Share set out in paragraphs 3.5 and 14 of Part H of Schedule 5 of the SOW
(paragraph 12.7 of Part H of Schedule 5 of the SOW) ("Declaration Seven");
viii) Paragraph 12.7 of Part H of Schedule 5 of the SOW does not entitle G4S to allocate to Jomast such number of Service Users in the NEYH Region as it sees fit, without agreement by Jomast ("Declaration Eight");
ix) Paragraph 12.7 of Part H of Schedule 5 of the SOW does not require Jomast to accept such number of Service Users in the NEYH Region as are referred to it by G4S, without limit ("Declaration Nine");
x) If (i) G4S allocates to Jomast Service Users in excess of Jomast's Target Percentage Market Share set out in paragraphs 3.5 and 14 of Part H of Schedule 5 of the SOW (namely, in excess of 766 Single Service Users and/or 1666 Family Member Service Users), (ii) Jomast accepts such excess allocation and provides services to G4S in respect of such Service Users, but (iii) Jomast and G4S do not agree a price for the volume of services provided
a) Jomast is entitled to payment by G4S of a reasonable fee in respect of the volume of services provided by Jomast and
b) G4S is liable to pay to Jomast a reasonable fee in respect of the volume of services provided by Jomast
on a quantum meruit basis ("Declaration Ten");
xi) By reason of paragraph 3.3 of the SOW, G4S may not require Jomast to provide services to G4S in any area other than the North East Local Immigration Team area ("Declaration Eleven").
a) Where the total number of Service Users per night that G4S is required to accommodate in the NEYH Region pursuant to the COMPASS Contract exceeds the Service User Volume Threshold Upper Limit and the parties reach no agreement to the contrary, (i) the target market share does not apply to the excess Service User Volumes and (ii) G4S is entitled to allocate as few or as many of the excess Service Users to Jomast as it sees fit ("G4S Declaration One"); and
b) Jomast has an absolute obligation to provide accommodation services to all Service Users that G4S refers to it within the NEYH Region ("G4S Declaration Two").
i) Schedule 2 Statement of Requirements;
ii) Schedule 5 - Service Charges;
iii) Schedule 13 Performance Measurement.
i) By paragraph 3.1 that [UKBA] will not commit to specific volumes of Service Users and therefore [G4S] is unable to commit specific volumes to [Jomast];
ii) By paragraph 3.2 that [G4S] will use reasonable endeavours to allocate a target percentage of Service User nights in the Specified Region to [Jomast]. This target will be measured periodically and will endeavour to be within a "percentage points" tolerance of that will be agreed periodically at the Contract Management Group meetings;
iii) By paragraph 3.3 that [G4S] requires [Jomast] to deliver the Services in the following LIT area: North East;
iv) By paragraph 3.4 that [Jomast] shall allocate Service Users to properties within the LIT areas with due consideration of:
a) The target proportional allocation of Service Users between the LIT areas, as defined by [G4S] periodically [3.4.1];
b) Limits defined by [G4S] for Service Users within Local Authority Cluster Areas or within specific post codes [3.4.2];
c) Any Service User geographical requirements defined by [G4S] [3.4.3].
v) By paragraph 3.5 that it is at the discretion of [G4S] to allocate Service User referrals to [Jomast], which will be made taking account of:
a) Specific requirements made by [UKBA] to [G4S] in relation to the particular Service User(s) [3.5.1];
b) The location of existing Service Users and therefore accommodation availability as well as capacity in specific Local Authority Cluster Areas, specified sub-regions and the Specified Region as a whole [3.5.2];
c) [G4S] being able to balance the allocation of Service User nights across its Service Subcontractor portfolio through allocating Service User referrals [3.5.3].
vi) There is then a Table which provides that Jomast's Target % Market Share (Service User Nights) is 33.3% Individual Family Members and 33.3% Single Service Users. Although the relevant box marked "Specified Region" is empty it is common ground that it relates to the NEYH region.
vii) By paragraph 3.6 that the target market share allocation may be suspended where any of the following events occur:
a) During any periods of transition where Service Users are transferred between Incoming and Outgoing subcontractors within the Specified Region and for a period of up to 3 months before and after such transition period to allow [G4S] to balance the market share across the Specified Region [3.6.1];
b) During periods of remedial action or default (clauses 16 and 17 of the Agreement) [3.6.2];
c) In the event of outgoing KPI failure by [Jomast] (Schedule 13) [3.6.3];
d) During periods leading to termination (clause 21 of the Agreement) [3.6.4];
e) Where [Jomast] is otherwise in breach of the Agreement [3.6.5].
i) At paragraph 4.2.1 under the headings "Accommodation Services" and "Requirements" that [Jomast] shall provide serviced accommodation for Service Users within the Specified Region;
ii) At paragraph 4.2.1 under the heading "Related Information" that the serviced accommodation shall be within the Specified Region [1.a];
iii) At paragraph 4.2.1 under the heading "Volume of service" that [Jomast] shall be able to provide sufficient accommodation for Service Users as is required by [G4S] [1];
iv) At paragraph 4.2.1 under the heading "Performance Standards" that each Service User is accommodated within the time-scales defined in Annex A to this Schedule [1].
i) At paragraph 12.1 that the market size for the entire Specified Region shall be measured periodically and quantified in terms of the numbers and types of Service Users receiving the Services;
ii) At paragraph 12.2 that the target market share percentage offered to [Jomast] by [G4S] and the price agreed by [Jomast] for single and individual family member Service Users shall remain in force within the specified Service User volume thresholds, subject to indexation adjustments (Schedule 5) and efficiency adjustments (Schedule 6);
iii) At paragraph 12.3 that the volume threshold is stated in terms of the Service User numbers relating to the whole of the Specified Region, and not just the volume relevant to [Jomast] (although this is provided as a memo in paragraph 14);
iv) At paragraph 12.4 that where the overall market size for the Specified Region is outside of the Service User volume threshold range in paragraph 14, [G4S] will invite [Jomast] to renegotiate the target market share and the associated price for a revised volume range. Paragraphs 12.5 to 12.7 set out the scenarios where agreement is reached and where it is not reached;
v) At paragraph 12.5 that where an agreed target market share and price has been reached for the new volume threshold range that will take effect from the point of agreement;
vi) At paragraph 12.6 that where agreement of target market share and price has not been reached and the overall Service User volumes are less than the lower limit set out in paragraph 14 [G4S] will continue to honour the existing target market share and [Jomast] agrees to continue to deliver at the existing agreed price;
vii) At paragraph 12.7 that where agreement of target market share and price has not been reached and the overall Service User volumes are higher than the upper limit set out in paragraph 14 [G4S] will continue to honour the existing target market share up to the upper limit and [Jomast] shall continue to deliver at the existing agreed price. [G4S] reserves the right to refer any volumes over the upper limit to subcontractors at its discretion.
viii) At paragraph 14 for a "Pricing and Volume Table" as follows:
Market Size Payment | Single Service User | Individual Family Member Service User |
Price per night | £8.10 | £8.10 |
Specified Region Service User Volume Threshold Upper Limit |
2,300 Single Service Users per night | 5,000 Family Member Service Users per night |
Specified Region Service User Volume Threshold Lower Limit |
1,000 Single Service Users per night | 2,450 Family Member Service Users per night |
Memo Only indicative Service User numbers at [Jomast's] target market share | From 333 to 766 | From 817 to 1,666 |
i) 333 represents 33.3% (Jomast's Target Percentage Market Share) of the 1,000 lower limit in the case of Single Service Users and 766 represents 33.3% of the 2,300 upper limit in the case of Single Service Users; and
ii) Although the figure is slightly too high, 817 represents 33.3% (Jomast's Target Percentage Market Share) of the 2,450 lower limit in the case of Family Member Service Users and 1,666 represents 33.3% of the 5,000 upper limit in the case of Family Member Service Users.
i) There has been an increase in the number of asylum seekers in the UK who need to be accommodated by G4S pursuant to its obligations to UKBA under the COMPASS Contract.
ii) G4S has required Jomast to accommodate asylum seekers in greater numbers than the upper threshold limits set out in paragraph 14 of Schedule 5 to the SOW and, subject to my ruling, intends to do so in the future.
iii) On 23 February 2016, G4S invited Jomast to re-negotiate the target market share and the associated price for an increased volume range. Although a meeting took place on 2 March 2016, the parties have been unable to agree on either.
iv) Jomast has (it contends without any obligation to do so) accommodated additional asylum seekers when requested by G4S when it has had the capacity in its portfolio of properties to do so.
v) Jomast has not had the capacity to accommodate all the additional asylum seekers which G4S has sought to allocate to it.
vi) G4S claims to have suffered losses as a result of having to accommodate in hotel accommodation service users which were not accepted by Jomast.
vii) G4S claims it is entitled to withhold by way of set-off sums otherwise due to Jomast pursuant to the Agreement which Jomast has threatened to seek to restrain by interim injunction.
i) As to market size, this was to be measured periodically and quantified in numbers and types of Service Users receiving the Service see paragraph 12.1 of Part H of Schedule 5 to the SOW. There would be no need for this provision if Jomast's contractual obligations were limited to the upper and lower volumes in paragraph 14 of Part H of Schedule 5 to the SOW.
ii) As to market share, G4S made no representation as to the number or type of Service Users which would be allocated to Jomast and Jomast was not entitled to any minimum number or types of Service User see clause 3.11 of the Agreement and clause 3.1 of the SOW.
iii) G4S is entitled, at its discretion to allocate Service Users to Jomast after taking into account the factors in paragraphs 3.5.1, 3.5.2 and 3.5.3 of the SOW see paragraph 3.5 of the SOW.
iv) The volume thresholds relate to the numbers of Service Users in the whole of the Specified Region (ie NEYH) and not just to the volumes relevant to Jomast see paragraph 12.3 of Part H of Schedule 3 to the SOW.
v) Jomast's Target Percentage Market Share is 33.3% for Individual Family Members and 33.3% Single Service Users see the table at the end of paragraph 3.5 of the SOW. Some meaning must be given to the description of these percentage shares as "targets".
vi) Save in circumstances where it is entitled to suspend it in the specific circumstances set out in paragraph 3.6 of the SOW (which are all circumstances where G4S are likely to want to allocate numbers in lower numbers to Jomast), G4S was obliged to use reasonable endeavours to allocate the Jomast Target Percentage Market Share (ie 33.3%) of the total volume of Service Users in the NEYH region to Jomast see paragraph 3.1 of the SOW.
vii) Some meaning must also be given to the use in paragraphs 12.3 and 14 of Part H of Schedule 5 to the SOW of the words "memo" and "indicative Service User numbers". In my judgment, they mean to illustrate but not to define, the number of Service Users that would be allocated to Jomast if overall Specified Region Service User volumes are at the Upper Limit and the Lower Limit and Jomast is allocated 33.3%.
viii) Subject to the indexation adjustments in Schedule 5 and the efficiency adjustments in Schedule 6, the Jomast Target Percentage Market Share was to remain in force within the Specified Region Service User Volume Thresholds (being those set out in paragraph 14 of Part H of Schedule 5 to the SOW) see paragraph 12.2 of Part H of Schedule 5 to the SOW.
ix) G4S required Jomast to deliver services in the North East LIT area see paragraph 3.3 of the SOW. However, this does not mean that Jomast is only obliged to deliver in the North East LIT because the obligation was for Jomast to provide serviced accommodation in the NEYH region see paragraph 4.2.1 of Schedule 2. Jomast had to deliver the services in the NEYH region but not necessarily all in the North East LIT.
x) Where the overall market size for the NEYH region falls outside the Service User Volume Thresholds in paragraph 14 of Part H of Schedule 5 to the SOW, the regime in paragraphs 12.4 to 12.7 of Part H of Schedule 5 to the SOW applies in relation to Jomast's market share. The mechanism is one to renegotiate Jomast's Target Market Percentage Share and the associated price - see paragraph 12.4 of Part H of Schedule 5 to the SOW.
xi) If agreement is then reached between Jomast and G4S as to both agreed target market share (effectively in substitution of the final row in paragraph 14 of Part H of Schedule 5 of the SOW) and price (in substitution for the first row in paragraph 14 of Part H of Schedule 5) then it takes effect from the point of agreement see paragraph 12.5 of Part H of Schedule 5 to the SOW.
xii) If no agreement of target market share and price has been reached and the overall Service User volumes are below the lower limit set out in paragraph 14, G4S is still obliged to honour Jomast's existing Target Percentage Market Share (ie to use its reasonable endeavours to allocate 33.3% of the Service Users in the NEYH region) and Jomast is obliged to deliver at the existing price (ie £8.10 PSUPN) see paragraph 12.6 of Part H of Schedule 5 to the SOW.
xiii) If no agreement of target market share and price has been reached and the overall Service User volumes are above the upper limit set out in paragraph 14, G4S is obliged to continue to honour Jomast's existing Target Percentage Market Share (ie to use its reasonable endeavours to allocate 33.3% of the Service Users in the NEYH region) up to the upper limits of 766 and 1,666 and Jomast is obliged to deliver at the existing price (ie £8.10 PSUPN) see paragraph 12.7 of Part H of Schedule 5 to the SOW.
xiv) This means that above those upper limits, G4S was no longer obliged to use its reasonable endeavours to allocate 33.3% of the Service Users in the NEYH Region to Jomast.
xv) If no agreement of target market share and price has been reached and the overall Service User volumes are above the upper limit set out in paragraph 14, G4S was entitled to refer volumes over the upper limit to any subcontractors at its discretion see paragraph 12.7 of Part H of Schedule 5 to the SOW.
xvi) However, Jomast was obliged to provide sufficient accommodation for Service Users as required by G4S see paragraph 4.2.1 of Schedule 2 to the SOW. If G4S elected to refer volumes over the upper limit to Jomast, then, absent any contrary agreement, it was obliged to provide the services at £8.10 PSUPN see paragraph 12.7 of Part H of Schedule 5 to the SOW.
xvii) It follows, in my judgment, notwithstanding that Part H of Schedule 5 of the SOW is headed "Market Size, Market Share and Pricing" its real thrust is to preserve and protect Jomast's share of the overall market in the NEYH region.
xviii) On this view, there is no scope for the operation of any quantum meruit in the manner suggested on behalf of Jomast.
i) Declaration One is no more than a re-statement of the relevant provision in the SOW and was not controversial. I am content to make the declaration but only on that basis.
ii) I decline to make Declarations Two, Three, Four, Six, Eight, Nine and Ten because they are contrary to my findings as to the proper construction or interpretation of the SOW.
iii) I decline to make Declaration Five in the terms sought because part of it is contrary to my findings as to the proper construction or interpretation of the SOW. It is uncontroversial that the effect of paragraph 12.4 of Part H of Schedule 5 of the SOW is that there is an obligation to re-negotiate the target market share and the associated price for a revised volume range where the overall market size for the NEYH is outside the Specified Region Service User Volume Threshold range in paragraph 14 of Part H of Schedule 5 of the SOW and I am prepared to make a declaration in those terms if the parties wish me to do so but it seems to me in doing so I am doing no more than re-stating the relevant provision.
iv) I decline to make Declaration Seven in the terms sought because they are contrary to my findings as to the proper construction or interpretation of the SOW. However, shaved of the preamble, it seems to me that sub-paragraph 7(a) is both uncontroversial and correct.
v) In their opening Skeleton Argument at [120.2] Counsel for G4S indicated that Declaration 11 was pointless because it was uncontroversial. In fact, in his oral closing submissions Mr McCall QC argued, and I have accepted, that G4S has a discretion to allocate Service-Users within the NEYH region as a whole, not just to the North East LIT and that Jomast is then obliged to accept them. I decline to make Declaration Eleven on the basis that it is contrary to my findings as to the proper construction or interpretation of the SOW.
vi) The two declarations sought by G4S reflect these findings.